Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of M.S. Ingots, MS TMT Bars/Angles/Channels
(b)Name of the Company / Organisation SHRI PRITHVI ALLOYS PVT LTD
(c)Registered Address
(d)Legal Status of the Company
2.
Address for the correspondence:
(a)Name of the Applicant sudesh sharma
(b)Designation (Owner/ Partner/ CEO) director
(c)Address E-154 to E-157, Riico industrial area bagru extansion phase -II, Jaipur,Jaipur,Rajasthan-303007
(d)Pin code 303007
(e)E-mail prithvialloys2021@gmail.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/RJ/IND/60730/2021
(e)Master Proposal Number(Single Window) SW/207983/2021
(f)EAC concerned (for category A Projects only) Industrial Projects - 1
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. E-154 to E-156, E-157, RIICO Industrial A
(b)Pincode 303007
(c)Bounded Latitudes (North)
From
Degree 26
Minutes 48
Second 23.94
From
Degree 26
Minutes 48
Second 26.64
(d)Bounded Longitudes (East)
From
Degree 75
Minutes 34
Second 7.25
From
Degree 75
Minutes 34
Second 15.15
(e)Survey of India Topo Sheet No. 45 N/9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 351
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.3
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanJaipurJaipurBagru
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 542
(b)Date of Apply of TOR 02 Mar 2021
(c)Date of Issue of TOR / Standard ToR 04 Jun 2021
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :02 Dec 2021
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :03 Jan 2022
Distance of Public Hearing Venue from the Proposed Project :3
Government Senior Secondary School, Bagru (In front of the office of Sub-Tehsil Bagru)
State :Rajasthan
District :Jaipur
Tehsil :Jaipur
Village :Bagru
34environment pollution, manpower, greenbelt etcOthersAdditional District Collector City (North), District- Jaipur
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Expansion of M.S. Ingots, MS TMT Bars/Angles/ChannelsMS Ingots from 28,800 TPA to 60,000 TPA and MS TMT Bars/Angles/Channels from 28,800 TPA to 1,00,000 TPA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)MS Ingots60000Tons per AnnumRoad
(2.)MS TMT Bars/Angles/Channels100000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 24 Feb 2020
(iv)Valid Upto 30 Sep 2021
(v)File No. F(HDF)/JAIPUR(Sanganer)/1746(1)/2019-2020/5277-527
(vi)Application No. 11103
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 28.83
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.925
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.28
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.145
(e) Funds Allocated for Environment Management Capital(%) 3.21
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 90
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 90
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal27900Tons per AnnumNARoad60 Open MarketCopy of Linkage
(2.)MS Ingots103000Tons per AnnumNARoad50 Open MarketCopy of Linkage
(3.)Steel Scrap & CI / Pig Iron48906.02Tons per AnnumNARoad30 Open MarketCopy of Linkage
(4.)sponge Iron12540Tons per AnnumNARoad30 Open MarketCopy of Linkage
(5.)Ferro Silicon1253.98Tons per AnnumNARoad40 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2021 To 29 May 2021
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube57.5631.7057.0860
(2.)NOxMicro Gram per Meter Cube24.805.1324.7980
(3.)OthersCOMili Gram per Meter Cube0.660.300.652
(4.)PM10Micro Gram per Meter Cube111.1060.96110.07100
(5.)SO2Micro Gram per Meter Cube12.476.1812.4680
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA8.067.156.58.5
(2.)TSSmg/l0000
(3.)TDSmg/l48937635002000
(4.)Total Hardnessmg/l1849.9480.87200600
(5.)Fluoridemg/l0.680.181.01.5
(6.)Othersmgmg/l201.699.7230100
(7.)Heavy Metalsleadmg/l0.010.010.010.05
(8.)Chloridesmg/l2145.2172.632501000
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l00C
(2.)BODmg/l00C
(3.)CODmg/l00C
(4.)pHNA00C
(5.)OthersnoneNA00C
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))70.153.875
(2.)Leq(Night)A-weighted decibels(dB(A))52.541.170
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Percent0.0270.019
(2.)K(Potassium)Milligram per Kilogram1.320.80
(3.)pH6.956.45
(4.)P(Phosphorus)Percent0.0230.018
(5.)Electric ConductivityOthersmS/ cm1602.211371.41
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 65 To 70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 60 To 65
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater300Copy of Permission LetterPipelineOthersBorewell 1 noNone03 Mar 202230
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)domestic waste water4.86STP based on Automatic Control Airlift Crossflow MBR followed by Ozonator technologyOthersgreen belt40.8
16.1.
(a)Total Waste Water Generation 4.8
(b)Total Discharged Water 0.8
(c)Total Reused Water 4
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)iron dustIndustrial Waste3410Tons10RoadOthersSold to Traders
(2.)domestic solid wasteMunicipal Solid Waste9Tons5RoadOthersWill be handled by Municipal Corporation, Jaipur
(3.)ashIndustrial Waste12Tons10RoadOthersSent to cement/brick manufacturing units
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube111.100.22.96114.06100
(2.)PM2.5Microgram per Meter Cube57.560.21.1858.7460
(3.)SO2Microgram per Meter Cube12.470.22.531580
(4.)NOxMicrogram per Meter Cube24.800.222.7747.5780
(5.)Others(Specify)COMicrogram per Meter Cube6600467062000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)induction furnace - 4 TPH and 8 TPH(2 nos)electricity300.775PM100.711
(2.)Reheating furnace - 20 TPH (1 no)coal300.975SO22.142
(3.)DG set - 380 kVA - 1 noHSD100.1SO20.002
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9900
(b)Source JVVNL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 380
(e)Stack Height (in m) 10
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 1.72
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.72
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 7518
(b)Waste/Barren Land 12267
(c)Grazing/ Community Land 4548
(d)Surface Water Bodies 0
(e)Settlements 1838
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Un-cultivated crop land 5244
    Total 31415
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant0.91NA
(2.)Green belt0.57NA
(3.)OthersOpen Area, Road/Paved Area0.24NA
Total 1.72
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone15None
(2.)NPANone15None
(3.)CorridorsNone15None
(4.)Wildlife CorridorsNone15None
(5.)ESAsNone15None
(6.)Critically Polluted AreaNone15None
(7.)ESZsNone15None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Otherswater bodySadriya Nadi (seasonal river)0.5None
(2.)ForestMuhana R.F.13.3None
(3.)Defence InstallationsNone15None
(4.)Archaeological SitesNone15None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.72
(b)Land yet to be acquired(Ha) 1.72
(c)Status of Land acquisition if not acquired ownership
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pavo cristatus (Indian peafowl)
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made 280000
(iii)Period of Implementation 3 years
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area sadriya nadi, which is a seasonal river
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 0.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 50
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 310
(f)Total Manpower 200
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.570
(b)Percentage of Total Project Area 33.14
(c)No. of Plants to be Planted 560
(d)Funds Allocated for Plantation 1120000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Social150 persons will be get employed
(2.)SocialA total number of 150 persons will be employed directly and indirectly. Preference will be given to the local people for employment based on their qualification and eligibility.
(3.)Financial• Narrowing down and demand supply gap. • Revenue to State and Central exchangers
(4.)Environmental• 33% of plant area will be under green belt development after expansion. This will help in attenuation of noise, air pollution and adds to the aesthetics of the place.
(5.)Environmental33% of plant area will be under green belt development after expansion.
(6.)Others• A periodic health check-up camp will be arranged for the workers in the plant.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/2023/RA0192 (Rev.01) dated 16.07.2021
(ii)Name of the EIA Consultant Gaurang Environmental Solutions Pvt. Ltd.
(iii)Address #102, SNG, Shree Ratna Apartment, Peetal Factory, Jhotwara road, Bani Park, Jaipur-302016
(iv)Mobile No. 9782074776
(v)Landline No. 0141402911
(vi)Email Id gaurangenviro@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 19 Jan 2023
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC meeting) Copy of Uploaded Proposal Presentation
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)14/06/2022please also submit the Form 1 .
(2.)21/06/2022The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicantsudesh sharma
Designationdirector
Name of Company (Applicant Name should not be given here)SHRI PRITHVI ALLOYS PVT LTD
AddressE-154 to E-157, Riico industrial area bagru extansion phase -II, Jaipur