Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Building Stone, Khanda & Gitti, Boulder Mining Project for Capacity Expansion
(b)Name of the Company / Organisation SMT. NIRAJ YADAV
(c)Registered Address R/o- village chhikhara, hal ghandinagar, district mahoba,,Mahoba,Uttar Pradesh-210427
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant niraj yadav
(b)Designation (Owner/ Partner/ CEO) proponent
(c)Address R/o- village chhikhara, hal ghandinagar, district mahoba,Mahoba,Uttar Pradesh-210427
(d)Pin code 210427
(e)E-mail yadavniraj1974@gmail.com
(f)Telephone No. 522-4078000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B1
(d)Proposal Number SIA/UP/MIN/67127/2019
(e)Master Proposal Number(Single Window) SW/227035/2021
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. GATA NO. 721
(b)Pincode 210427
(c)Bounded Latitudes (North)
From
Degree 25
Minutes 20
Second 14.19
From
Degree 25
Minutes 20
Second 12.88
(d)Bounded Longitudes (East)
From
Degree 79
Minutes 58
Second 22.16
From
Degree 79
Minutes 58
Second 21.52
(e)Survey of India Topo Sheet No. 54O/15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 188.8
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshMahobaMahobaDAHARRA
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 1234
(b)Date of Apply of EC 25 Oct 2019
(c)Date of Issue of EC 31 Dec 1899
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :10 Sep 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :14 Oct 2020
Distance of Public Hearing Venue from the Proposed Project :4.2
MEETING HALL IN TEHSIL-MAHOBA,DISTRICT MAHOBA,U.P.
State :Uttar Pradesh
District :Mahoba
Tehsil :Mahoba
Village :DAHARRA
21ISSUES WERE RAISED REGARDING POLLUTION,WATER SCARCITY,DEVELOPMNT,ETC.Others
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By CPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on NIL
(iii)Letter No. 00
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)40000CUM/YEAR;0.647470004000087000OthersCUMRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)NANANANANA
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 19 Aug 2021
(iv)Valid Upto 30 Aug 2021
(v)File No. 00
(vi)Application No. 00
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 1
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.3437
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 00
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 00
(e) Funds Allocated for Environment Management Capital(%) 34.37
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 00
(b)Existing quantity of raw material/fuel 00
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building Stone, Khanda, Gitti, Boulder40000OthersCUBIC METERBUILDING STONERoad0.00 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 21 Oct 2019 To 14 Jan 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube42.3937.1042.3960
(2.)SO2Micro Gram per Meter Cube13.8910.313.8980
(3.)NOxMicro Gram per Meter Cube23.6619.0323.6680
(4.)PM10Micro Gram per Meter Cube89.9577.489.95100
    14.2.     No. of Ground Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l9147135002000
(2.)Heavy MetalsLEADmg/l0.0010.00010.0100
(3.)Chloridesmg/l140.89135.122501000
(4.)pHNA7.627.166.58.5
(5.)Total Hardnessmg/l452348200600
(6.)TSSmg/l00000000
(7.)Fluoridemg/l0.890.5711.5
    14.3.     No. of Surface Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l0000B
(2.)BODmg/l13.59.5B
(3.)pHNA7.87.23B
(4.)DOmg/l7.36.8B
    14.4.     No. of Ambient Noise Monitoring Locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))60.648.165
(2.)Leq(Night)A-weighted decibels(dB(A))41.434.945
    14.5.     No. of Soil Sample Monitored Locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Milligram per Kilogram0000
(2.)Electric ConductivityMillisiemens per Centimetre346.2290.6
(3.)P(Phosphorus)Milligram per Kilogram73.1757.77
(4.)K(Potassium)Milligram per Kilogram188.4999.69
(5.)pH7.887.15
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 186.80 To 177.10
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 186.80 To 210.14
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTANKERS6.3200 Not Appliacble modeOthersROADOthersFROM LOCAL VENDORS0030 Aug 20216.32
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)00000000Discharge into Surface Water Body,Discharge into Seawater Body00
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)NO SUCH WASTE TO BE GENERATEDMunicipal Solid Waste00Tons00RoadOthersNA
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube00000000CPCB
(2.)PM2.5Microgram per Meter Cube00000000CPCB
(3.)PM10Microgram per Meter Cube00000000CPCB
(4.)SO2Microgram per Meter Cube00000000CPCB
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)00000000PM1000
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 00
(b)Source 00
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 00
(e)Stack Height (in m) 00
20.
Land Ownership Pattern:
(a)Forest Land 00
(b)Private Land 00
(c)Government Land 00
(d)Revenue Land 00
(e)Other Land 0.647
    Total Land 0.647
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 00
(b)Waste/Barren Land 0.647
(c)Grazing/ Community Land 00
(d)Surface Water Bodies 00
(e)Settlements 00
(f)Industrial 00
(g)Forest 00
(h)Mangroves 00
(i)Marine Area 00
(j)Others : 00 00
    Total 0.647
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersNA00NA
Total 0
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted Area000000
(2.)ESZs000000
(3.)WLS000000
(4.)NPA000000
(5.)ESAs000000
(6.)Wildlife Corridors000000
(7.)Corridors000000
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Forest000000
(2.)Defence Installations000000
(3.)Archaeological Sites000000
(4.)OthersNa000000
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 00
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired 00
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in Rs) 00
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 22
(b)Permanent Employment-During Operation 00
(c)Temporary Employment- During Construction 00
(d)Temporary Employment- During Operation 00
(e)No. of working days 300
(f)Total Manpower 22
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt000000
(2.)Percentage of Total Project Area00000
(3.)No. of Plants00300300
(4.)Funds Allocated003300033000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmental300 SAPLINGS WILL BE PLANTED
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)BUILDING STONEMinor
2.
Mine Capacity in ROM (Run of Mine) 20
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. Directorate of Geology and Mines, Lucknow vide Let
(b)Date of Approval 04 Sep 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Atomic
(e)Approved Mining Lease Area 0.647
(f)Approved Capacity 40000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 293132
(b)Mineable Reserves (Million Ton) 40000
(c)Extractable Reserves(Million Ton) 47000
(d)Percent(%) of Extraction 0
(e)Grade of Coal /Ore /Mineral 00
(f)Stripping Ratio 00 : 00
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) 00
(h)Average Gradient(Degree) 00
(i)Mining Method Opencast
(j)Life of Mine (Years) 20
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 0.647
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 19 Jun 2019
(iii)Validity of LOI 20
(iv)Reference No. of LOI 917
(c)Whether Lease Deed Executed ? No
(i)Reason thereof LEASE NOT STARTED YET
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof NA
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 00
(ii)Total Area (in Hectare) 00
(iii)Height (in meter) 00
(iv)Quantity (in Million Cubic meter) 00
(v)No. of year back fill up 00
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 00
(ii)Total Area (in Hectare) 00
(iii)Height (in meter) 00
(iv)Quantity (in Million Cubic meter) 00
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 00
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 00
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 00
11.
Details of Final Mine Void:
(a)Area (in Hectare) 00
(b)Depth (in meter) 00
(c)Volume (in Million Cubic meter) 00
12.
Details of Quarry:
(a)Final Void of 00 (hectare) at a Depth of 00 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 00
13.
Details of Transportation:
(a)In Pit/Underground to Surface 00
(b)Surface to Siding/Loading 00
(c)Transportation / Conveyor Details 00
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND00000
(2.)SETTLEMENTS00000
(3.)OTHERS(Specify)NA00000
(4.)AGRICULTURE LAND00000
(5.)FOREST LAND00000
(6.)GRAZING LAND00000
(7.)SURFACE WATER BODIES00000
TOTAL000
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)TOP SOIL STORAGE0000000
(2.)GREEN BELT0000000
(3.)EXTERNAL OB DUMPS0000000
(4.)ROADS0000000
(5.)BUILT UP AREA (COLONY/OFFICE)0000000
(6.)EXCAVATION/QUARRY0000000
(7.)VIRGIN AREA0000000
(8.)OtherNA0000000
(9.)INTERNAL OB DUMPS0000000
TOTAL00000
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 00
(b)Internal Dump(in hectare) 00
(c)Quarry(in hectare) 00
(d)Safety Zone(in hectare) 00
(e)Final Void of 00 (hectare) at a Depth of 00 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 00
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 00
(h)Total afforestation plant (in hectare) 300
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan 00
Total Area Excavated (in hectare) 0.647
Total Area Backfilled after Excavation (in hectare) 00
Total Area Reclaimed (in hectare) 00
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA/0200
(ii)Name of the EIA Consultant ENVIRONMENTAL RESEARCH AND ANALYSIS
(iii)Address FLAT NO. 203 YASH SILVER HEIGHT,SECOND FLOOR,BADSHAHNAGAR,LUCKNOW,U.P.
(iv)Mobile No. 7232999911
(v)Landline No. 0522407800
(vi)Email Id eraenvcle@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 30 Dec 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)06/09/2021Please submit the TOR copy.
(2.)07/09/2021The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of Applicantniraj yadav
Designationproponent
Name of Company (Applicant Name should not be given here)SMT. NIRAJ YADAV
AddressR/o- village chhikhara, hal ghandinagar, district mahoba
Print