Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Molasses based Distillery from 75 to 110 KLPD for Ethanol production by using C / B Heavy Molasses/ Cane Syrup with 3 MW Captive Power Plant (CPP) including expansion of cane crushing from 10,000 to 12,000 TCD along with Co-generation Plant from 20 to 30 MW by Shri Dudhganga Vedganga Sahakari Sakhar Karkhana Ltd (SDVSSKL) At: Bidri (Mouninagar), Tal.: Kagal, Dist.: Kolhapur, MS.
(b)Name of the Company / Organisation SHRI DUDHGANGA VEDGANGA SAHAKARI SAKHAR KARKHANA LIMITED
(c)Registered Address Bidri (Mouninagar), Tal. Kagal, Dist. Kolhapur,,Kolhapur,Maharashtra-416208
(d)Legal Status of the Company Others
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Krishna S Chaugale
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address Bidri, Mouninagar, Tal. Kagal, Dist. Kolhapur,,Kagal,Kolhapur,Maharashtra-416208
(d)Pin code 416208
(e)E-mail purchase.bidri@yahoo.in
(f)STD Code. 2325(f)Telephone No. 254922
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity5(g) Distilleries
Minor Activity5(j) Sugar Industry
(b)Category B2
   Reason for Applying at Ministry Other
   Other Reason for Applying at Ministry Project to be appraised as B2 as per Notification S.O. 980 (E) 02.03.2021 under EBP program
(c)Proposal Number IA/MH/IND2/231257/2021
(d)Master Proposal Number(Single Window) SW/231256/2021
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Gat No. 1042, 1043, 1044, 1045, 1050, 1051/1, 1051
(b)Pincode 416208
(c)Bounded Latitudes (North)
From
Degree 16
Minutes 25
Second 30.15
From
Degree 16
Minutes 25
Second 53.35
(d)Bounded Longitudes (East)
From
Degree 74
Minutes 7
Second 59.70
From
Degree 74
Minutes 8
Second 59.03
(e)Survey of India Topo Sheet No. 47L2, 47L3
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 568
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 0.5
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraKolhapurKagalBidri (Mouninagar)
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. EC-1247/RON/2020-NGP/7596
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Oct 15 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Electric Power from Incineration Boiler033Mega Watt(MW)OthersGrid
(2.)Electricity201030Mega Watt(MW)OthersGrid
(3.)CO2 gas168010502730OthersMT/MOthersCylinder
(4.)Ethanol (Sugarcane Syrup)0110110Kilo Litre per Day(KLD)Pipe Conveyor
(5.)Pressmud12000240014400OthersMT/MRoadGrid
(6.)RS/ENA (B & C Heavy Molasses)75075Kilo Litre per Day(KLD)Road
(7.)Ethanol (B & C Heavy Molasses)7535110Kilo Litre per Day(KLD)Road
(8.)Molasses12000240014400OthersMT/MRoadGrid
(9.)Bagasse9000018000108000OthersMT/MConveyor BeltGrid
(10.)Sugar36000720043200OthersMT/MRoadGrid
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Ditsillery75 KLPD35 KLPD110 KLPDExpansion of Molasses based Distillery from 75 to 110 KLPD for Ethanol production
(2.)Sugar Factory10000 TCD2000 TCD12000 TCDExpansion of cane crushing from 10,000 to 12,000 TCD
(3.)Co-generation Plant20 MW10 MW30 MWExpansion of Co-gen Power Plant from 20 to 30 MW
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 05 Nov 2020
(iv)Valid Upto 31 Jul 2021
(v)File No. Format1.0/CAC/UAN No. MPCB-CONSENT-0000093042/CR-2
(vi)Application No. MPCB-CONSENT-0000093042
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 50
(b) Funds Allocated for Environment Management (Capital) (in Crores) 4.30
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.44
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 12210
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 12210
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Sugar cane360000OthersMT/MNear by FarmRoad40 Open MarketCopy of Linkage
(2.)Lime660OthersMT/MNear by MarketRoad25 Open MarketCopy of Linkage
(3.)Sulfur216OthersMT/MNear by MarketRoad25 Open MarketCopy of Linkage
(4.)Sugarcane for Juice47130OthersMT/MOwn factory/ outside purchasePipe Conveyor0 Open MarketCopy of Linkage
(5.)Yeast14.67OthersMT/MLocal vendorRoad30 Open MarketCopy of Linkage
(6.)Urea3.67OthersMT/MLocal vendorRoad30 Open MarketCopy of Linkage
(7.)Bagasse60120OthersMT/MOwn Sugar FactoryConveyor Belt0 CaptiveCopy of Linkage
(8.)De-Foaming Oil10.27OthersMT/MLocal vendorRoad30 Open MarketCopy of Linkage
(9.)molasses12210OthersMT/MOwn factory/ outside purchaseRoad20 Open MarketCopy of Linkage
(10.)Lubricant50.4OthersMT/MNear by MarketRoad25 OthersAgreementCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1 To 16.28
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1 To 8
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface4550.5Copy of Permission LetterPipelineJack Well46822 Jul 20211636
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic (Sugar, Cogen & Distillery2525Proposed STPReuse within the Plant & Recycling25
(2.)Industrial (Distillery Raw Spentwash)8801000Raw Spentwash shall be conc. in Multi Effect Evaporator (MEE). Conc. Spentwash shall be burnt in existing 30 TPH incineration boilerOthersIncinerate in incineration boiler8800
(3.)Other Effluent (Distillery)9021000Proposed CPUReuse within the Plant & Recycling902
(4.)Industrial Effluent (Sugar & Co-gen)7131200Existing ETP which is recently upgradedGreen Belt Renewal Plant713
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 2520
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 2520
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Yeast SludgeIndustrial Waste7590Tons0RoadOthersBurnt in Incineration Boiler
(2.)CPU SludgeIndustrial Waste308Tons0RoadOthersBurnt in Incineration Boiler
(3.)ETP SludgeIndustrial Waste126Tons0RoadOthersUsed as Manure
(4.)Boiler Ash (Bagasse)Bottom Ash9000Tons0RoadOthersUsed as Manure
(5.)Boiler Ash (Spentwash+Coal)Bottom Ash16830Tons0RoadOthersBrick making
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube30.141.986.9337.0880
(2.)NOxMicrogram per Meter Cube34.711.965.0039.7280
(3.)PM2.5Microgram per Meter Cube24.571.951.0625.6460
(4.)PM10Microgram per Meter Cube34.711.953.3438.06100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)120 TPH (Existing Boiler)Bagasse803.4PM100
(2.)60 TPH (Proposed Boiler)Bagasse802.6PM100
(3.)30 TPH (Existing incineration boiler)Spentwash + Coal711.2PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20000
(b)Source Own Co-gen Plant & CPP
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) DG Sets 1500 KVA (2 Nos)+ 250 KVA (1 No)
(e)Stack Height (in m) 0.15
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 72.60
(c)Government Land (ha.) 0
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 72.60
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 8489
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 310
(e)Settlements (ha.) 1638
(f)Industrial (ha.) 0
(g)Forest (ha.) 1290
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Scrub Land, Maning Area, Fallow land 19688
    Total (ha.) 31415.0000
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Built Up Area6.39
(2.)Green belt23.96
(3.)OthersOpen Area42.25Open + Parking+Road
Total (ha.) 72.6
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)ESZsRadhanagari Wildlife Sanctuary9.9Project site is located at 9.9 Km from ESZ of Radhanagari Wildlife Sanctuary
(2.)NPANil0There is no presence of NPA's in 10 Km radius of project
(3.)Wildlife CorridorsNil0There is no presence of Wildlife Corridors in 10 Km radius of project
(4.)Critically Polluted AreaNil0There is no presence of CPA's in 10 Km radius of project
(5.)WLSRadhanagari Wildlife Sanctuary12.2Project site is located at 12.2 Km from extremeboundary of Radhanagari Wildlife Sanctuary
(6.)ESAsNil0There is no presence of any ESAs in 10 Km radius of project
(7.)CorridorsNil0There is no presence of Corridors in 10 Km radius of project
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0There is no presence of Archaeological sites in 10 Km radius of project
(2.)Defence InstallationsNA0There is no presence of defense installation in 10 Km radius of project
(3.)ForestReserve Forest1.54.11 % of total studyarea s under reservedforest scatteredaround the projectsite.
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 72.60
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Industry already owned the land
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Dudhganga River (0.7 Km) & Vedganga River (5.8 Km)
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 5.8
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 34
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 34
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt9.4414.5223.96
(2.)Percentage of Total Project Area132033
(3.)No. of Plants347352517859913
(4.)Funds Allocated5050100
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialAbout 34 no of workers would be appointed under Expansion of distillery unit. Preference will be is given to persons from local area thereby creating better employment opportunities
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/RA0135
(ii)Name of the EIA Consultant Equinox Environments (I) Pvt. Ltd.
(iii)Address F-11, Namdev Nest, 1.160 ā€˜E’ ward, Opp. Kamala College, Sykes Extension, K
(iv)Mobile No. 9657865122
(v)Landline No. 0231253123
(vi)Email Id projects@equinoxenvi.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 21 Oct 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) Copy of Uploaded Proposal Presentation
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NAName of applicant, authorizing person and authorized person are all different. Kindly clarify and resubmit. Land use break up of study area shall be corrected and filled in Hectares not percentage. Radhanagari Wildlife Sanctuary is falling beyond 10 km. submit final notification for ESZ and google earth map showing position of plant site and ESZ of sanctuary. Also submit undertaking that no sanctuary is lying in study area. Accreditation of consultants is going to expire in this month only. Submit extension certificate while applying for EDS reply. Submit plagiarism certificate in EIA. Self certified affidavit shall be submitted in compliance to Notification dated 16th June, 2021. 04 Oct 2021
2. Eds Reply LetterThe correction have been made as per the instruction received 06 Oct 2021
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterADS reply has been submitted. 01 Feb 2022
2. ADS Raise LetterFactual Report is to be submitted as per attachment pl. 01 Feb 2022
3. ADS Reply LetterADS reply has been submitted. 31 Jan 2022
4. ADS Raise LetterFactual report required from IRO for further n/a. 27 Dec 2021
5. ADS Reply LetterADS reply has been submitted. 22 Dec 2021
6. ADS Raise LetterPl see the attachment sent to IRO for information. 29 Nov 2021
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantKrishna S Chaugale
DesignationMD
Name of Company (Applicant Name should not be given here)SHRI DUDHGANGA VEDGANGA SAHAKARI SAKHAR KARKHANA LIMITED
AddressBidri (Mouninagar), Tal. Kagal, Dist. Kolhapur
Print