Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Parsa East and Kanta Basan Opencast Mine and Pit Head Coal Washery expansion from 15 MTPA to 21 MTPA
(b)Name of the Company / Organisation RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LIMITED
(c)Registered Address Vidyut Bhawan, Janpath, Jyoti Nagar, Jaipur,,Jaipur,Rajasthan-302005
(d)Legal Status of the Company State PSU
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Arvind Kumar Agrawal
(b)Designation (Owner/ Partner/ CEO) Addl. Chief Engineer (Fuel)
(c)Address NIL
(d)Pin code 302005
(e)E-mail fuel.rvun@gmail.com
(f)STD Code. 141(f)Telephone No. 2744927
(g)Fax No. 1412744927
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity2(a) Coal washeries
1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/CG/CMIN/235298/2021
(d)Master Proposal Number(Single Window) SW/235297/2021
(e)EAC concerned (for category A Projects only) NIL
(f)Project Type Expansion under para 7(ii)
4.
Location of the Project:
(a)Plot/Survey/Khasra No. The block is covered in the Survey of India topo s
(b)Pincode 497116
(c)Bounded Latitudes (North)
From
Degree 22
Minutes 47
Second 39
From
Degree 22
Minutes 51
Second 12
(d)Bounded Longitudes (East)
From
Degree 82
Minutes 46
Second 38
From
Degree 82
Minutes 50
Second 51
(e)Survey of India Topo Sheet No. 64J/13
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 569
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)ChhattisgarhSurgujaAmbikapurSalhi, Hariharpur, Ghatbarra, Parsa, Kente, Parogiya and Basan
6.
Details of Terms of Reference (ToR)/EC: Not Applicable
4.
Whether the Project Exempted from Public Hearing? Details Not Applicable
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Raipur
(iii)Letter No. EC 3-3/2012(Env)/7566
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit Nov 25 2020 12:00AM
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal UnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)RoM (Coal)15000000600000021000000.000Tons per Annum(TPA)Rail,Conveyor Belt
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Opencast mining15 MTPA6 MTPA21 MTPAWashery expansion through Separate application.
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 25 Nov 2021
(iv)Valid Upto 30 Nov 2024
(v)File No. 5986/TS/CECB/2021
(vi)Application No. 7837909
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 2369
(b) Funds Allocated for Environment Management (Capital) (in Crores) 10
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 5.50
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Explosives23630Tons per AnnumAuthorized VendorRoad50 LinkageCopy of Linkage
(2.)Diesel106Kilo Litre per DayOpen MarketRoad20 Open MarketCopy of Linkage
16.
Baseline Data Not Applicable
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 18.08 To 7.70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.70 To 5.80
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. 21-4(44)/NCCR/CGWA/2009-763
(f)Date of Issue 05 Sep 2019
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater6151.2Copy of Permission LetterPipelineTube Well21-4(44)/NCCR/CGWA/2009-76305 Sep 2019615
(2.)GroundWater125803.2Copy of Permission LetterPipelineOthersMine water21-4(44)/NCCR/CGWA/2009-76305 Sep 201912580
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)ETP1020ETPReuse within the Plant & Recycling,OthersGreenbelt100
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 10
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 10
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Washery RejectOthersWashery Reject4725000Tons0Road,RailOthersSell to Nearby users
(2.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)77Kilolitre0RoadAuthorized Recyclers
(3.)Overburden in cubic meterOthersOverburden in cubic meter113000000Tons0RoadOthersBackfilling within ML area
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)NOxMicrogram per Meter Cube29.40.50029.4080
(2.)SO2Microgram per Meter Cube23.100.50023.1080
(3.)PM10Microgram per Meter Cube69.400.417.1376.53100
(4.)PM2.5Microgram per Meter Cube40.10.412.8742.9760
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Nil000OthersNil0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 15000
(b)Source CSPDCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 100 KVA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 1871.118
(b)Private Land (ha.) 701.786
(c)Government Land (ha.) 109.952
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 2682.856
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 701.786
(b)Waste/Barren Land (ha.) 0
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 1871.118
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Government Land 109.952
    Total (ha.) 2682.8560
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)OB Dump Area112.655External
(2.)Quarry Area2388.247Excavation Area
(3.)OthersCHP, Washery, Infrastructure, greenbelt etc.181.954CHP, Washery, Infrastructure, greenbelt etc.
Total (ha.) 2682.856
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone0None
(2.)ESZsNone0None
(3.)WLSNone0None
(4.)NPANone0None
(5.)ESAsNone0None
(6.)CorridorsNone0None
(7.)Wildlife CorridorsNone0None
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestPhatepur PF0Within ML
(2.)OthersForestMatringa PF0Within ML
(3.)Archaeological SitesNone0None
(4.)Defence InstallationsNone0None
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 368.19
(b)Land yet to be acquired(Ha) 333.6
(c)Status of Land acquisition if not acquired In progress
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Atem River
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 2.7
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 500
(b)Permanent Employment-During Operation 1000
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 368
(e)No. of working days 330
(f)Total Manpower 2168
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt297.921999.752297.67
(2.)Percentage of Total Project Area11.1074.585.6
(3.)No. of Plants80913448775915686725
(4.)Funds Allocated150200350
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalProject will result into Greenbelt Development within mining lease area as well as Compensatory Afforestation over double degraded forest land. Moreover, Rain water harvesting measures will result into ground water recharge.
(2.)SocialProject will result into overall development of the area and quality of life of the stakeholders including infrastructure development, improvement in education status, livelihood development, employment, health and sanitation etc.
(3.)FinancialProject will result into revenue to State as well as Central Government. Power Supply to State Government will result into saving public exchequer.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
2.
Mine Capacity in ROM (Run of Mine) 21 MTPA
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 34011/18/2016-CPAM
(b)Date of Approval 12 Aug 2016
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Coal
(e)Approved Mining Lease Area 2682.856
(f)Approved Capacity 21
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 516.40
(b)Mineable Reserves (Million Ton) 452.46
(c)Extractable Reserves(Million Ton) 452.46
(d)Percent(%) of Extraction 87.62
(e)Grade of Coal /Ore /Mineral F
(f)Stripping Ratio 5.24 : 1
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 4
(i)Mining Method Opencast
(j)Life of Mine (Years) 19
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area Yes
(b)Beneficiation / Washing Technology Wet Washing
(c)Capacity 21
(d)Whether it is proposed to install crusher within the mining lease area Yes
(e)No. of crushers 3
     6.1.    Details of crusher:
S. No.Crusher ID Capacity (in PH)Remarks
(1.)11700 Existing
(2.)21200 Existing
(3.)3700 Proposed
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 3
(c)Thickness of seams to be worked on 1
(d)Maximum Thickness of Seams (metres) 9.72
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 2388.525
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 19 Apr 2017
(iii)Validity of LOI 30
(iv)Reference No. of LOI Nil
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 2388.525
(iii)Validity of the lease deed From : 01 Apr 2017 To : 01 Apr 2047
(iv)Date of Execution of Mining Lese 19 Apr 2017
(v)Reference Number Nil
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Lease deed still valid
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 2
(ii)Total Area (in Hectare) 112.655
(iii)Height (in meter) 60
(iv)Quantity (in Million Cubic meter) 52.07
(v)No. of year back fill up 3
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 2
(ii)Total Area (in Hectare) 1059.092
(iii)Height (in meter) 60
(iv)Quantity (in Million Cubic meter) 2316.65
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 230.687
(b)Depth (in meter) 30
(c)Volume (in Million Cubic meter) 0
12.
Details of Quarry:
(a)Final Void of 230.687 (hectare) at a Depth of 30 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 2328.247
13.
Details of Transportation:
(a)In Pit/Underground to Surface Conveyor
(b)Surface to Siding/Loading Conveyor
(c)Transportation / Conveyor Details Train
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)OTHERS(Specify)Government109.9520109.952
(2.)AGRICULTURE LAND701.7860701.786
(3.)FOREST LAND1871.11801871.118
(4.)SURFACE WATER BODIES000
(5.)WASTE LAND000
(6.)GRAZING LAND000
(7.)SETTLEMENTS000
TOTAL2682.85602682.856
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXTERNAL OB DUMPS112.65500112.655
(2.)TOP SOIL STORAGE5005
(3.)BUILT UP AREA (COLONY/OFFICE)0000
(4.)GREEN BELT0000
(5.)EXCAVATION/QUARRY2127.555260.69202388.247
(6.)ROADS13.7440123.691137.435
(7.)INTERNAL OB DUMPS0000
(8.)VIRGIN AREA35.93103.58839.519
TOTAL2294.885260.692127.27902682.856
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 112.655
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 2127.555
(d)Safety Zone(in hectare) 0
(e)Final Void of 260.692 (hectare) at a Depth of 30 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 54.675
(h)Total afforestation plant (in hectare) 2294.885
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20161010106.210
(2.)2021151515150
(3.)201310220.290
(4.)2020151515150
(5.)2014101051.200
(6.)20151010103.440
(7.)20171010108.270
(8.)2019151515150
(9.)20181010108.330
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court Supreme Court of India
(c)Case No. Civil Appeal 4395/2014
(d)Orders/Directions of the court ,if any and its relevance with the proposed project Stay on NGT Judgment
(e)Case Details NGT suspended Forest Clearance. However, Supreme C
(f)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0166(Rev.01)
(ii)Name of the EIA Consultant Vardan Environet
(iii)Address Plot No. 82 A , Sector-5 , IMT Manesar
(iv)Mobile No. 9953147268
(v)Landline No. 0124434375
(vi)Email Id info@vardanenvironet.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 06 Nov 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File NA
(h)Uploaded Proposal Presentation (To be given in EAC meeting) Copy of Uploaded Proposal Presentation
            Essential Detail Sought:
Sno. EDS Letter Remarks Date of EDS
1.NA1. Please clarify whether this application for expansion is being requested for mining or washery or mine plus washery. As per the OM dated 15.09.2017 the expansion is applicable for mine production only. In case washery expansion to be requested with mine enhancement then the application of TOR may be applied for such expansion. 2. In case of seeking enhancement of mine production, the detailed report vis-a vis with points laid down in OM dated 15.09.2017 in tabular form may be furnished. 3. Revised mine plan for enhanced production capacity may be attached 4. Whether any forest land is involved for enhanced production. Please provide the details of forest land, its status of permission, etc. 5. Proper KML file with pin drop needs to be attached. 6. Please attach legible copy of last EC obtained for 15 MTPA production capacity. 7. Please attach a full certified compliance report with all annexures as the same is not attached fully. 09 Nov 2021
2. Eds Reply LetterEDS Reply has been uploaded for consideration of proposal for expansion of coal mine only excluding coal washery. 12 Jan 2022
      Additional Detail Sought : NIL
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantArvind Kumar Agrawal
DesignationAddl. Chief Engineer (Fuel)
Name of Company (Applicant Name should not be given here)RAJASTHAN RAJYA VIDYUT UTPADAN NIGAM LIMITED
AddressVidyut Bhawan, Janpath, Jyoti Nagar, Jaipur