APPENDIX I
(See Paragraph-6)
CATEGORY - B
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
Whether proposal involved violation of EIA notificationNA
Weather Consent to Establishment ObtainedNA
Upload copy of CTE NA
1.Name of the Project “Construction of 2 x2 lane bridge across river Ganga between Sultanganj and Aguwani ghat with approach road connecting NH 80 and NH” 31
Proposal No SIA/BR/NCP/34926/2019
2.Project Sector INFRA-1
3.Location of the project Khagaria district is surrounded by Saharsa in north, Munger & Begusarai in South, Bhagalpur and Madhepura in east and Begusarai & Samastipur in west. The proposed alignment is 3160 m long consisting 2 x 2 lane. The Ganges forms the southern boundary of the district in its entire length.
4.
Shape of the project landStrip
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
5.Brief summary of projectAnnexure-Brief summary of project
6.State of the projectBihar
Details of State of the project
S.no State Name District Name Tehsil Name
NIL
7.Town / VillageKhirarahi- 1 km from Bridge Site Tilakpur- 1 km from Bridge Site Afzuganj- 1.5 km from Bridge Site Karna- 3 km from Bridge Site Baisa - 5 km from Bridge Site Bhagalpur District is surrounded by 1
8.Plot/Survey/Khasra No.NA
9.S. No. in the schedule8(b) Townships and Area Development projects.
10. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 161.66HA ha.
11.
New/Expansion/ModernizationNew
12. Category of project B
13. Does it attract the general condition? If yes, please specify No
15. Does it attract the specific condition? No
16.Is there any litigation pending against the project?No
17. Nearest railway station along with distance in kms. Sultanganj Railway Station, 1.7 Km km
18. Nearest airport along with distance in kms Patna Airport, 210.00 Km km
19. Nearest Town/City/District Headquarters along with distance in kms Parbatta (Block HQ , 3.00 km from Bridge site km
20. Distance of the project from nearest Habitation Khirarahi , Khirarahi km
21.
Details of alternative sites examined shown on a toposheetNo
22.
Whether part of interlinked projects?No
23.
Whether the proposal involves approval/clearance under the Forest (Conservation)Act,1980?No
24.
Whether the proposal involves approval/clearance under the wildlife (Protection)Act,1972?Yes
StatusApplication for Wildlife Clearance yet to be submitted
25.Whether the proposal involves approval/clearance under the C.R.Z notification,2011?No
26.
Whether there is any Government Order/Policy relevent/relating to the site?No
27.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
28. Project Cost(in Lac.) 85900
30. Whether the proposed project/activity located in notified Industrial area(Yes/No) N/A
Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes Temporary There are temporary change in land use during construction phases for establishment of labor camps, construction yards, storage areas and borrow areas. Permanent There will be permanent change in the land use as construction of 4 lane Ganga Bridge between two districts.
1.2 Clearance of existing land, vegetation and buildings? No Yes, trees and structures falling along the road side within proposed Right of way are required to be cleared for construction of bridge.
1.3 Creation of new land uses? Yes Yes, agriculture, barren land will be converted for construction of approach road.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Preconstruction investigation like Soil testing etc has been carried out. Pre-construction Geo-technical investigations were carried out. Report is enclosed as Annexure-V.
1.5 Construction works? Yes Partial construction completed balance Construction will be done for bridge and Approach roads. Proposed Bridge site is Length of bridge (Including Viaduct portion) 3160 m No. of spans 30 No. Maximum Span length 270 m Northern Approach 20 kmportion Southern Approach Road 4 km Footpath Width (Both Sides) 1.5 m Type of construction Cantilever construction, cast in situ,segmental, cable stayed
1.6 Demolition works? No NA
1.7 Temporary sites used for construction works or housing of construction workers? Yes Temporary sites are used for Construction Yard, Labor Camps, and Construction Camps which will be restored after the construction activities are over.
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations Yes The construction of temporary structures for staff, cross-drainage structures and cutting/filling/excavation of earth all such activities is involved in improvement of project road.
1.9 Underground works including mining or tunneling? No NA
1.10 Reclamation works? Yes The reclamation work includes ? Development of areas disturbed due to construction activities ? Development of areas used temporarily for establishment of labor camps, construction yards, storage areas and borrow areas.
1.11 Dredging? No NA
1.12 Offshore structures? No NA
1.13 Production and manufacturing processes? No NA
1.14 Facilities for storage of goods or materials? Yes During construction phase the construction material is being stored in Construction camps or at construction sites.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Construction Stage Liquid effluent The liquid effluent is generated from labor and construction camps, the waste generated is being treated in Septic Tank / Sedimentation Tank before diverting it to soak pit. Mobile toilets, if required, is also being provided. Solid Waste The solid waste generated from labor and construction camps is segregated at source only. Organic Waste is being treated at site and inorganic waste is disposed as per guidelines. The recyclable waste is being sold to re
1.16 Facilities for long term housing of operational workers? No About 290 people including engineers and skilled labour during the construction period. The construction camp is being established during construction phase for construction workers which are temporary and will be removed after completion of construction activity.
1.17 New road, rail or sea traffic during construction or operation? No Temporary diversion road provided during Construction of bridge. No new rail or sea traffic shall be proposed. Existing transportation facilities will be used during construction or operation phase.
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No No, existing road is used for transportation of material to the construction site.
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? Yes Temporary diversions is being provided at required location to avoid traffic congestion during construction period.
1.20 New or diverted transmission lines or pipelines? Yes The transmission lines and pipelines coming within the construction of bridge proposals is shifted after taking prior approval with concerned departments.
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No NA
1.22 Stream crossings? Yes Bridge is crossing Ganga river Bihar
1.23 Abstraction or transfers of water from ground or surface waters? Yes Water required for construction activities will be sourced from both surface and ground water resources, depending on the availability. Prior permission will be taken from concerned department before abstraction/withdrawal.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? Yes The runoff will increase due to creation of paved area and surfaces. The river flow at bridge site is being channelized due to construction of bridge.
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes During construction period: Construction materials are transported from different sources and labors from nearby villages is being hired and brought to the construction site.
1.26 Long-term dismantling or decommissioning or restoration works? No NA
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No NA
1.28 Influx of people to an area in either temporarily or permanently? Yes Yes there is temporary influx of people to the area as labors and other people who are involved directly or indirectly in the construction of bridge. However preference is given to the local people in the employment.
1.29 Introduction of alien species? No NA
1.30 Loss of native species or genetic diversity? No NA
1.31 Any other actions? No NA
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes Total Land area required for the project is 161.66 ha including 40.6 ha in Sultanganj district and 121.06 ha in Khagaria district. Major land use along the existing road is agricultural, though built-up areas were also observed along the approach road to the ghats.
2.2 Water (expected source & competing users) unit: KLD Yes The quantity of water required for construction activities is being sourced from both surface and ground water abstraction depending on the availability.
2.3 Minerals (MT) No NA
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes The major materials required for construction of the project are as follows: Cement Aggregates Sand Steel Earth work Granular sub base Base course Bituminous work
2.5 Forests and timber (source – MT) No NA
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes 105 KW Power will be required and supply will be met through North and South Bihar Power Distribution Company Ltd.
2.7 Any other natural resources (use appropriate standard units) No NA
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Spent oil from DG sets will be stored temporarily at site and later will be disposed of through govt. approved vendors.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Suitable drainage and waste management measures is being adopted in the construction phase and same will be maintained in operational phase.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes During Construction phase: This project is providing employment to about 290 local labours during construction phase.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. Yes There will be positive impact on Vulnerable Group due to improved connectivity as travelling to educational institutions and health care facilities at the faster and easier.
3.5 Any other causes No NA
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No There will be positive impact on Vulnerable Group due to improved connectivity as travelling to educational institutions and health care facilities at the faster and easier.
4.2 Municipal waste (domestic and or commercial wastes) Yes Construction Phase: Domestic waste is being produced from labour camps which is being disposed as per established rules. Operation Phase: The domestic / commercial waste will be generated during operation phase from bridge which will be handled as per established rules.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes Used oil and lubricants is being produced which is being temporarily stored and sold to the authorized recycler.
4.4 Other industrial process wastes No NA
4.5 Surplus product No NA
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge is produced. Soak pit type arrangementsis being done for disposing the sewage.
4.7 Construction or demolition wastes Yes Construction waste is being used for construction & embankment filling.
4.8 Redundant machinery or equipment No NA
4.9 Contaminated soils or other materials No All required precaution is being taken to avoid or minimize contamination of soils.
4.10 Agricultural wastes No Not Applicable
4.11 Other solid wastes Yes Top Soil, is being stored and reused for median filling and on slopes upto the extent possible.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes During Construction emissions is being generated from the Vehicles transporting Construction Materials, Machineries involved in the construction. DG Sets are used as power back up. During Operations the emissions will be from the mobile sources as vehicles running on Road and from DG sets to be used as power back up at bridge.
5.2 Emissions from production processes No NA
5.3 Emissions from materials handling including storage or transport Yes During Construction emissions are resulting from transportation, loading and unloading and Storage of construction material. Construction material is being transported in covered trucks. Water sprinkling is being done for dust suppression. Material has been stored under Tarpaulin cover.
5.4 Emissions from construction activities including plant and equipment Yes There is emission from, Hot Mix Plant, Batching Plant and other Machineries installed for production of concrete etc. The movement of construction vehicles, clearing and grubbing of ground, earth work and other related activities are also resulting in emissions.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes There is dust generation during different construction activities particularly earthwork, loading and unloading of construction materials and disposal of construction waste.
5.6 Emissions from incineration of waste No NA
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No NA
5.8 Emissions from any other sources No NA
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes During Construction Period noise is being generated from equipment, machinery and, crushers plants
6.2 From industrial or similar processes No NA
6.3 From construction or demolition Yes Noise and Vibrations is being generated due to demolition of structures, Construction activities and due to operation of Machineries and Plant.
6.4 From blasting or piling No NA
6.5 From construction or operational traffic Yes The heavy vehicles engaged in construction work and slow movement of traffic may increase noise and vibration during construction phase. However, due to smooth running of vehicles on construction of bridge in operation phase, the ambient noise levels and emissions are expected to come down.
6.6 From lighting or cooling systems No NA
6.7 From any other sources No NA
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials Yes Temporary storage of HSD has been provided for DG sets and construction machineries which will be removed after completion of construction work.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Discharge of sewage in septic tank through temporary labour camp. The temporary toilets will be removed after completion of construction.
7.3 By deposition of pollutants emitted to air into the land or into water Yes Air emission is being generated by construction DG set, Batch mix plant and use of construction machineries. These will be removed after completion of construction.
7.4 From any other sources No NA
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No NA
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes There may be accidental spillage. Required Precaution is being taken in Storage, Handling of Hazardous Materials and accidental spillage of hazardous materials.
8.2 From any other causes No During Construction Phase all the labors are being provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Training and awareness about the safety norms are being provided to all supervisors and labors involved in construction activity.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No As per the Seismic Zoning Map of India (IS: 1893-2002), the proposed project area falls under Zone-IV which is a high damage risk zone and an earthquake up to a magnitude of 8.0 on Richter scale has the potential to hit the area.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes ? Improved access will lead to development of other industries and business enterprises in the area. ? During construction, construction material will be supplied from nearby vendors. ? The project will also result in development of supporting infrastructures like towns, shops, community facility in the vicinity of the project. Such induced development is not likely to cause any adverse impact on environment.
9.2 Lead to after-use of the site, which could have an impact on the environment Yes Temporary land-use sites like labour camps, construction camp sites etc, if enhanced/ redeveloped in consultation with owner/community to which land belongs, may have some positive impact on the environment.
9.3 Set a precedent for later developments Yes The proposed project will set precedent for future development in the area as it is planned to be developed in the environment friendly and sustainable manner.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No NA
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes The project road passes through Vikramshila Gangetic Dolphin protected wildlife sanctuary within the project influence area which is located in Bhagalpur District of Bihar. The sanctuary is a 50 km stretch of the Ganges River from Sultanganj to Kahalgaon. 8.61 ha. Forest area is also passes through the project site
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes The proposed bridge is on Ganga River
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No NA
4 Inland, coastal, marine or underground waters Yes Underground water structures like well, Hand pumps are present at various locations along the project road.
5 State, National boundaries Yes NA
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes Apart from Existing NH-30 and NH 81 other PWD road of 30 km from Maheshkunth via Gogari- Parvatta to Aguwani Ghat (Project site) is used for access in the area.
7 Defence installations No NA
8 Densely populated or built-up area Yes Sultanganj and Aguwani Ghat, near to the project site
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes 1. Primary School Navtol Borne, N (13.9 Km) 2. Shakund Degree College, SE (10.5 Km) 3. Ajgaivinath Dham ,W (1.2 Km) 4. Bari Durga Mandir Kalyanpur ,W (12.1 Km) 5. Advance ENT Hospital, E (13.9 Km) 6. Sultanganj Station, (1.7 Km)
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) Yes Ganga River
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No NA
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects Yes As per the Seismic Zoning Map of India (IS: 1893-2002), the proposed project area falls under Zone-IV which is a high damage risk zone and an earthquake up to a magnitude of 8.0 on Richter scale has the potential to hit the area.
(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
5 Uploaded Form-1A Annexure-Form-1A
6 Uploaded Conceptual Plan Annexure-Conceptual Plan
ADDITIONAL MULTIPLE ENTERIES
Sr. no. Remarks Uploaded Additional Attachments
1 Dolphin letter Annexure-Additional Attachments
2 EDS REPLY LETTER Annexure-Additional Attachments
3 Brief Summary Annexure-Additional Attachments
4 Google map Annexure-Additional Attachments
5 cover letter Annexure-Additional Attachments
(V) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge
V.(i)
NameM/S BIHAR RAJYA PUL NIRMAN NIGAM LIMITED
DesignationEngineer
Company M/S BIHAR RAJYA PUL NIRMAN NIGAM LIMITED
Address7, sardar Patel Nagar , Patna Bihar - 800015
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)29/04/2019Vide your letter no. BRPNNL/912 dated. 30/03/2019. You are already committed violation but in online application you have mentioned no violation clarify immediately. Your application shall be processed further only after receipt of your clarification and if possible by a site visit.
(2.)29/04/2019Vide your letter no. BRPNNL/912 dated. 30/03/2019. You are already committed violation but in online application you have mentioned no violation clarify immediately. Your application shall be processed further only after receipt of your clarification and if possible by a site visit.
(3.)25/06/2019The corrections have been made as per the instruction received.
(4.)25/06/2019The corrections have been made as per the instruction received.
(5.)25/06/2019The corrections have been made as per the instruction received.
(6.)25/06/2019The corrections have been made as per the instruction received.
(7.)25/06/2019The corrections have been made as per the instruction received.
(8.)25/06/2019The corrections have been made as per the instruction received.
(9.)21/05/2020Decision of SEIAA attached in pdf file.EDS Letter
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
           Transferred Details(Category A To B)
S. No.Category A(Proposal No)Category B(Proposal No)Transferred DateReasonLetter
NO Record