1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Establishment of new natural and synthetic surfactant chemical manufacturing unit Mouza Kulepairi, P.S. Bagnan, Dist-Howrah, West Bengal by M/s Detergeo Chem (EAST) Private Limited (DCEPL) | (b)Name of the Company / Organisation | M/S DETERGEO CHEM (EAST) PRIVATE LIMITED (DCEPL) | (c)Registered Address | A-29, Block B1 Ext., Mohan co-operative industrial Estate, New Delhi,,New Delhi,Delhi-110044 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Raman Arora | (b)Designation (Owner/ Partner/ CEO) | Owner | (c)Address | A-29, Block B1, Ext., Mohan co-operative industrial Estate, New Delhi,,Chanakya Puri,New Delhi,Delhi-110064 | (d)Pin code | 110064 | (e)E-mail | detergeo2020@gmail.com | (f)STD Code. | 11(f)Telephone No. | 40664444 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| Minor Activity | | (b)Category | A | (c)Proposal Number | IA/WB/IND3/256360/2020 | (d)Master Proposal Number(Single Window) | SW/256322/2022 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 3 | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Dag No. 42, 44, 45, 46, 52, 53, 54, 55, 131, 132, | (b)Pincode | 711303 | (c)Bounded Latitudes (North) | | From | | Degree | 22 | Minutes | 31 | Second | 50.466 | From | | Degree | 22 | Minutes | 31 | Second | 50.993 | (d)Bounded Longitudes (East) | | From | | Degree | 87 | Minutes | 55 | Second | 52.718 | From | | Degree | 87 | Minutes | 55 | Second | 52.695 | (e)Survey of India Topo Sheet No. | 73N/14, 73N/15, 79B/2 & 79B/3 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 5 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 2 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | West Bengal | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | West Bengal | Howrah | Bagnan - I | Kulepairi | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | IA-J-11011/1/2020-IA-II(I) | (b)Date of Apply of TOR | 03 Jan 2020 | (c)Date of Issue of TOR / Standard ToR | 10 Mar 2020 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 23 Aug 2021 | Distance of Public Hearing Venue from the Proposed Project : | 3 |
| Sri Krishna Bhawan, Bagnan, Mukunda Dighi Khalna More, PS- Bagnan, Howrah, West Bengal | State : | West Bengal | District : | Howrah | Tehsil : | Bagnan - I | Village : | Kulepairi |
| 75 | 5 | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Neutralization Unit | 5000 kg/hr | 1 | (2.) | Weigh Bridge | 100 MT | 1 | (3.) | Flaker | 1500 kg/hr | 1 | (4.) | Screw Chiller | 100 TR | 2 | (5.) | Reactors with Agitators | 15 KL | 4 | (6.) | Film Sulphonation/Sulphation Reactor | 5000 kg/hr | 1 | (7.) | Water Purification Plant | 10 kl/hr | 1 | (8.) | Waste Heat Recovery Boiler | 850 Kg/hr | 1 | (9.) | Electricity Generator | 1000KW | 1 | (10.) | Pumps | As Per Requirements | | (11.) | Water Hydrants System | As Per Requirements | | (12.) | LABSA 90% Seperator | 35 KL | 1 | (13.) | Nitrogen Generator | 200 Nm3 | 1 | (14.) | Sulfur Trioxide Gas Generation Plant | 1250 kg/hr | 1 | (15.) | Vent Gas Treatment System with ESP | 6000 CMPH | 1 | (16.) | Oil Based Boiler | 2000 kg/hr | 1 | (17.) | Air Drying Unit | 9000 CMPH | 1 | (18.) | Cooling Tower | 700 m3/hr (Total) | 3 | (19.) | LABSA 90% Batch Reactor | 35 KL | 1 | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Linear Alkyl Benzene Sulphonic Acid 90% | 12000 | Others | MTA | Others | MS Tanker | (2.) | Sodium Lauryl Sulphate | 6000 | Others | MTA | Others | SS Tanker | (3.) | Cocoamidopropyl Betaine | 3000 | Others | MTA | Others | Truck | (4.) | Ethylene Glycol Distearate | 3000 | Others | MTA | Others | Truck | (5.) | Sodium Sulphate | 400 | Others | MTA | Others | Tanker | (6.) | Linear Alkyl Benzene Sulphonic Acid 96% | 12000 | Others | MTA | Others | MS Tanker | (7.) | Ethylene Glycol Monostearate | 3000 | Others | MTA | Others | Truck | (8.) | Sodium Lauryl Ether Sulphate | 24000 | Others | MTA | Others | SS Tanker | (9.) | Cocamide Monoethanolamide | 3000 | Others | MTA | Others | Truck | (10.) | Cocamide Diethanolamide | 3000 | Others | MTA | Others | Truck | (11.) | Dilute Sulphuric Acid | 12000 | Others | MTA | Others | MS Tanker | (12.) | Alpha Olefin Sulphonate | 1000 | Others | MTA | Others | SS Tanker | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 20 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 1.51 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 0.03 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0.19 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 67320 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 67320 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Coconut Fatty Acid | 5028 | Others | MTA | Import | Others | ISO Tank | 500 | Open Market | | Copy of Linkage | (2.) | Monochloroacetic acid | 243 | Others | MTA | Domestic | Others | Truck | 500 | Open Market | | Copy of Linkage | (3.) | Sulphuric Acid (98%) | 12000 | Others | MTA | Domestic | Others | MS Tanker | 50 | Open Market | | Copy of Linkage | (4.) | Caustic Soda | 4052 | Others | MTA | Domestic | Others | MS Tanker | 10 | Open Market | | Copy of Linkage | (5.) | Stearic Acid | 5490 | Others | MTA | Import | Others | ISO Tank | 500 | Open Market | | Copy of Linkage | (6.) | Lauryl Alcohol | 3150 | Others | MTA | Import | Others | ISO Tanks | 50 | Open Market | | Copy of Linkage | (7.) | Alpha Olefin | 560 | Others | MTA | Import | Others | ISO Tanks | 500 | Others | Open market | Copy of Linkage | (8.) | Monoethanolamine | 732 | Others | MTA | Domestic | Others | ISO Tank | 50 | Open Market | | Copy of Linkage | (9.) | Lauryl Ether | 13200 | Others | MTA | Import | Others | ISO Tanks | 500 | Others | Open market | Copy of Linkage | (10.) | Sulfur | 3487 | Others | MTA | Domestic/import | Others | Truck | 10 | Open Market | | Copy of Linkage | (11.) | Dimethylaminopropylamine | 264 | Others | MTA | Import | Others | ISO Tank | 500 | Open Market | | Copy of Linkage | (12.) | Ethylene Glycol | 870 | Others | MTA | Domestic | Others | MS Tanker | 50 | Others | Open market | Copy of Linkage | (13.) | Linear Alkaline Benzene (LAB) | 17215 | Others | MTA | Import | Others | MS Tanker | 500 | Open Market | | Copy of Linkage | (14.) | Di Ethanolamine | 1029 | Others | MTA | Domestic | Others | ISO Tank | 50 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2019 To 31 Dec 2019 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 55 | 27 | 54.08 | 60 | (2.) | NOx | | Micro Gram per Meter Cube | 28 | 12 | 27.08 | 80 | (3.) | SO2 | | Micro Gram per Meter Cube | 16 | 4 | 15.54 | 80 | (4.) | Others | CO | Mili Gram per Meter Cube | 0.97 | 0.58 | 0.95 | 02 | (5.) | PM10 | | Micro Gram per Meter Cube | 98 | 52 | 96 | 100 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.71 | 6.73 | 6.5 | 8.5 | (2.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | Total Hardness | | | mg/l | | 458 | 224 | 200 | 600 | (4.) | Fluoride | | | mg/l | | 1.15 | 0.33 | 1 | 1.5 | (5.) | TDS | | | mg/l | | 838 | 409 | 500 | 2000 | (6.) | Chlorides | | | mg/l | | 262 | 111 | 250 | 1000 | |
14.3. No. of Surface Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 7.1 | 5.9 | A | (2.) | COD | | mg/l | | 166 | 86 | A | (3.) | pH | | NA | | 7.48 | 6.80 | A | (4.) | BOD | | mg/l | | 28 | 16 | A | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 58.4 | 37.8 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 68.4 | 42.3 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Others | mg/100gm | 24.2 | 18.4 | (2.) | Electric Conductivity | Others | micro mhos/cm | 386 | 246 | (3.) | K(Potassium) | Others | MG/100gm | 2.9 | 0.9 | (4.) | pH | | | 7.91 | 7.18 | (5.) | P(Phosphorus) | Others | mg/100gm | 0.96 | 0.76 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.4 To 18.69 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 0.39 To 14.75 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | Water tanker/Ground water | 203 | 5 | Copy of Permission Letter | modeOthers | water tanker | Others | bore well/water tanker | 123 | 14 Feb 2022 | 203 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Cooling Tower Blowdown | 3 | 11 | ETP | Others | Reused for Scrubber and gardening purpose | 3 | 0 | (2.) | RO Reject | 4 | 11 | ETP | Others | Reused for Scrubber and gardening purpose | 4 | 0 | (3.) | Equipment Wash | 0.7 | 11 | ETP | Others | Reused for Scrubber and gardening purpose | 0.7 | 0 | (4.) | Boiler Blow down | 2 | 11 | ETP | Others | Reused for Scrubber and gardening purpose | 2 | 0 | (5.) | Softner Regeneration | 1 | 11 | ETP | Others | Reused for Scrubber and gardening purpose | 1 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 10.7 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 10.7 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Industrial waste | Others | ETP Sludge (Category 35.3) | 1.0 | Tons | 100 | Road | | Others | Give to TSDF | (2.) | Industrial Waste | Others | Spent Oil(Category 5.1) | 0.02 | Kilolitre | 180 | Road | | Others | Sell to authorized oil reclamation plant | (3.) | Industrial Waste | Others | Sulphur Ash | 1.0 | Tons | 140 | Road | | Others | Sell to fertilizer industry | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 60 | (2.) | PM10 | | Microgram per Meter Cube | 98 | 2.9 | 0.00 | 98.00 | 100 | (3.) | NOx | | Microgram per Meter Cube | 28 | 2.8 | 0.04 | 28.04 | 80 | (4.) | SO2 | | Microgram per Meter Cube | 16 | 3 | 0.00 | 16.00 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | PM10 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 1000 | (b)Source | West Bengal State Electricity Distribution Company | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 2 No. of DG sets each of capacity 910 KVA, 500 KVA | (e)Stack Height (in m) | 11 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 1.3260 | Total Land (ha.) | 1.3260 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 22796 | (b)Waste/Barren Land (ha.) | 406 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 2523 | (e)Settlements (ha.) | 6970 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 0 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Vegetation | 688 | Total (ha.) | 33383.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Built Up Area | | 0.4358 | Production Shed, Tank Farm, DG Room, etc | (2.) | Green belt | | 0.6602 | Green Belt & Roads | (3.) | Others | Others(Future Projects) | 0.2300 | For future development | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | None | 0 | None | (2.) | Wildlife Corridors | None | 0 | None | (3.) | ESAs | None | 0 | None | (4.) | NPA | None | 0 | None | (5.) | Corridors | None | 0 | None | (6.) | WLS | None | 0 | None | (7.) | ESZs | None | 0 | None | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Defence Installations | | None | 0 | None | (2.) | Forest | | None | 0 | None | (3.) | Archaeological Sites | | None | 0 | None | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 1.33 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | None | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | | (b)No. of Households | | (c)No. of PDFs (Project Displaced Families) | | (d)No. of PAFs (Project Affected Families) | | (e)Funds Allocated for R&R(in INR) (in Lacs) | | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Gaighata Khal | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 1.1 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 0 | (b)Permanent Employment-During Operation | 40 | (c)Temporary Employment- During Construction | 160 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 245 | (f)Total Manpower | 200 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 0.46 | (b)Percentage of Total Project Area | 34.69 | (c)No. of Plants to be Planted | 690 | (d)Funds Allocated for Plantation | 1600000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Greenbelt development have been proposed in 34.71% of plot area. | (2.) | Social | 1. Total 200 people are expected to be employed directly and indirectly from this project. Out of which 40 will be permanent employee.
2. A provision of Rs. 3 lakhs has been made under Public Hearing Budget towards provision of scheme of Zero Liquid Discharge (ZLD) (1 lakhs) and for awareness and training programme for local employment (2 lakhs) based on the commitment made under Public hearing meeting held on 23.08.2021 | (3.) | Financial | There will be economic development because of this project. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Industrial Projects - 3 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/2023/RA0205 | (ii)Name of the EIA Consultant | Mantec Consultants Pvt Ltd Noida | (iii)Address | D-36,Industrial Area, Udhyog Marg, E Block, Sector 6, Noida, U.P-201301 | (iv)Mobile No. | 9312284682 | (v)Landline No. | 0120421500 | (vi)Email Id | envmantec@yahoo.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 3 | (ix)Validity of Accreditation | 20 Apr 2023 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Your proposal has been examined and following are the deficiencies needs to be rectified and to be uploaded/submitted on Parivesh Portal:
(i) In Form 2 at S.No.15(i), PP has not uploaded the CGWA application, however it is mentioned that the CGWA will be taken before the commencement of the Unit. Since the Unit is not in Industrial Estate, PP needs to apply first the CGWA application. It is also not clear that PP got TOR in March 2020 and still they had not applied for Water Approval.
(ii) Details of land conversion document for industrial purpose needs to be uploaded on parivesh portal as the instant Unit is not in notified industrial area.
(iii) Details of PH proceedings is not legible which were uploaded at S.No. 7.1 of Form 2. Please resubmit the same with legible copy alongwith all the documents. Also upload the Action Plan with budgetary provisions and time lines on the issues raised during PH.
(iv) Details of onsite/offsite emergency plan/DMP and its approval needs to be submitted. PP in chapter 7, has submitted very generic DMP. Please revise accordingly.
(v) Copy of undertaking w.r.t. not proposing any banned products, needs to be submitted.
(vi) Details of court cases and SCN issued by the SPCB, if any, needs to be submitted.
(vii) As per s.no. 39 of form 2, presentation is not uploaded as per template provided by the EAC. Please revise the same.
(viii) Details of Raw material and its linkage and its mitigation measure during transportation needs to be submitted at S. No. 13.1 of Form 2.
(ix) Membership of TSDF please upload on portal.
(x) All old CTEs/CTOs/ HW Authorization to be uploaded to verify the violation, if any. The details of products need to be submitted in tabular form showing its details of CTO/EC vis-à-vis production capacity.
(xi) It is mentioned that the processing of EC proposal, in the Ministry, is through Parivesh Portal only, therefore providing the requisite information/documents shall be in compliance as per Form 2 and accordingly the PP/Consultant are kindly requested to revise the application in the Form 2 alongwith EIA/EMP Report and resubmit the same. The EIA/EMP Report shall match with the information as filled in Form 2 for further appraisal by the EAC. It is also mentioned that after acceptance the Proposal, EIA/EMP report/Form 2 can not be revise. Therefore, PP/Consultant is requested to kindly do needful. | 21 Feb 2022 | 2. | Eds Reply Letter | Letter for relisting of the project has been uploaded. | 07 Feb 2024 | 3. | NA | It is noted that PP has not submitted the information desired on 21.02.2022. Please submit the same.
As per OM dated 8.06.2022, PP should submit the latest baseline data for 3 months to be submitted.
Accordingly, Please comply with the above observations. | 21 Feb 2024 | 4. | Eds Reply Letter | The EDS is attached with the EIA Report and uploaded as additional documents. | 09 Mar 2024 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Raman Arora | Designation | Owner | Name of Company (Applicant Name should not be given here) | M/S DETERGEO CHEM (EAST) PRIVATE LIMITED (DCEPL) | Address | A-29, Block B1 Ext., Mohan co-operative industrial Estate, New Delhi |
|