1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of Existing Sponge Iron Plant from 1,00,000 to 4,50,000 TPA, Steel Melting Shop from 47,000 to 5,42,000 TPA, Rolling Mill from 72,000 to 4,02,000 TPA and Captive Power Plant from 10 to 34 MW | (b)Name of the Company / Organisation | VRKP SPONGE AND POWER PLANT LLP | (c)Registered Address | Sy. No. 229, 288 & 289, Halakundi village, Bellary Taluk and district, Karnataka-583102,,Bellary,Karnataka-583102 | (d)Legal Status of the Company | Private | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Prateek Agarwal | (b)Designation (Owner/ Partner/ CEO) | Partner | (c)Address | Sy.No. 229, 288 and 289, Halakundi village, Bellary taluk and district, Karnataka,,Bellary,Bellary,Karnataka-583102 | (d)Pin code | 583102 | (e)E-mail | ea@vsp.vrkp.in | (f)STD Code. | 40(f)Telephone No. | 23717213 | (g)Fax No. | 22227106 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 3(a) Metallurgical industries (ferrous & non ferrous)
| Minor Activity | 1(d) Thermal Power Plants
| (b)Category | A | (c)Proposal Number | IA/KA/IND/116324/2017 | (d)Master Proposal Number(Single Window) | SW/191624/2021 | (e)EAC concerned (for category A Projects only) | Industrial Projects - 1 | (f)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Sy. No. 219, 229, 288, 289, 299, 304, 305, 307, 31 | (b)Pincode | 583102 | (c)Bounded Latitudes (North) | | From | | Degree | 15 | Minutes | 3 | Second | 89 | From | | Degree | 15 | Minutes | 4 | Second | 76 | (d)Bounded Longitudes (East) | | From | | Degree | 76 | Minutes | 51 | Second | 48 | From | | Degree | 76 | Minutes | 52 | Second | 17 | (e)Survey of India Topo Sheet No. | 57 A/16 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 500 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Karnataka | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Karnataka | Bellary | Hadagalli | Halakundi | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | SEIAA: 31: IND: 2007 | (b)Date of Apply of TOR | 11 Oct 2017 | (c)Date of Issue of TOR / Standard ToR | 29 Nov 2017 | (d)Date of Apply of EC | 23 Aug 2016 | (e)Date of Issue of EC | 23 Dec 2016 | (f)Previous TOR Letter | Copy of Previous TOR letter | (g)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 20 Feb 2019 | Distance of Public Hearing Venue from the Proposed Project : | 0 |
| Proposed Project Site | State : | Karnataka | District : | Bellary | Tehsil : | Bellary | Village : | Halakundi |
| 190 | Total 69 participants have given their opinion about the proposed expansion project. Out of that 56 belongs to Halakundi village, 3 from Honnahalli village, 3 from Honnahalli Tanda, one from Mincheri | Others | Additional Deputy Commissioner | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bangalore | (iii)Letter No. | EP/12.1/SEIAA/143/KAR | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | Dec 20 2019 12:00AM | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Rolled Products/TMT Bars/Hot Strips/Coils | 72000 | 330000 | 402000.000 | Tons per Annum(TPA) | | Conveyor Belt | | (2.) | Hot Billets/Steel Billets | 47000 | 495000 | 542000.000 | Tons per Annum(TPA) | | Conveyor Belt | | (3.) | Electricity | 10 | 24 | 34.000 | Mega Watt(MW) | | Others | Transmission | (4.) | Sponge Iron | 90000 | 350000 | 440000.000 | Tons per Annum(TPA) | | Conveyor Belt | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Rolling Mill | 72,000 TPA | 3,30,000 TPA | 4,02,000 TPA | Nil | (2.) | Captive Power Plant | 10 MW (WHRB: 6 MW & AFBC: 4 MW) | 24 MW (WHRB) | 34 MW (WHRB: 30 MW & AFBC: 4 MW | Nil | (3.) | DRI Plant | 90,000 TPA (3x100 TPD) | 3,50,000 TPA (3x350 TPD) | 4,40,000 TPA (3x100 TOD + 3x350 TPD) | Nil | (4.) | Induction Furnace with CCM | 47,000 TPA (1x12 T) | 4,95,000 TPA (3x40 T) | 5,42,000 TPA (1x12 T + 3x40 T) | Nil | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 16 Aug 2021 | (iv)Valid Upto | 30 Jun 2026 | (v)File No. | AWH-326208 | (vi)Application No. | 11769 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 570 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 45.72 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 2.85 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 5.55 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 660000 | (b)Existing quantity of raw material/fuel | 220000 | (c)Total quantity of raw material/fuel | 880000 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Iron Ore | 700000 | Tons per Annum | | NMDC Ltd. Donimalai, BMM Ispat Ltd. Bellary | Road | | 100 | Open Market | | Copy of Linkage | (2.) | LDO/LSHS | 8320 | Others | KL | Local Market | Road | | 100 | Open Market | | Copy of Linkage | (3.) | Scrap | 70000 | Tons per Annum | | (Purchased from Local Area + in-house) | Road | | 100 | Open Market | | Copy of Linkage | (4.) | Iron ore pellets | 490000 | Tons per Annum | | NMDC Ltd. Donimalai, BMM Ispat Ltd. Bellary | Road | | 100 | Open Market | | Copy of Linkage | (5.) | Dolomite | 17500 | Tons per Annum | | Local Market | Road | | 100 | Open Market | | Copy of Linkage | (6.) | Indian Coal | 455000 | Tons per Annum | | Open Market | Road | | 300 | Open Market | | Copy of Linkage | (7.) | Sponge Iron | 70250 | Tons per Annum | | Nearby plants in Bellary | Road | | 100 | Open Market | | Copy of Linkage | (8.) | Pig Iron | 50000 | Tons per Annum | | Local Market | Road | | 100 | Captive | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Dec 2017 To 28 Feb 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 42.9 | 22.9 | 42.8 | 60 | (2.) | Others | CO | Micro Gram per Meter Cube | 1028 | 514 | 1025 | 2000 | (3.) | PM10 | | Micro Gram per Meter Cube | 75.3 | 40.6 | 75.1 | 100 | (4.) | SO2 | | Micro Gram per Meter Cube | 28.9 | 12.4 | 28.9 | 80 | (5.) | NOx | | Micro Gram per Meter Cube | 25.6 | 12.8 | 25.5 | 80 | |
14.2. No. of Ground Water monitoring locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 8.22 | 7.28 | 6.5 | 8.5 | (2.) | Total Hardness | | | mg/l | | 458 | 279 | 300 | 600 | (3.) | TSS | | | mg/l | | 0.72 | 0.3 | 1.0 | 1.5 | (4.) | TDS | | | mg/l | | 889 | 586 | 500 | 2000 | (5.) | Chlorides | | | mg/l | | 458 | 322 | 250 | 1000 | (6.) | Fluoride | | | mg/l | | 1.2 | 0.85 | 1.0 | 1.5 | (7.) | Heavy Metals | | Iron | mg/l | | 0.25 | 0.11 | 0.3 | 1.0 | |
14.3. No. of Surface Water monitoring locations : 2 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 5.1 | 3.9 | A | (2.) | BOD | | mg/l | | 3.3 | 2.6 | A | (3.) | COD | | mg/l | | 16.5 | 10.4 | A | (4.) | pH | | NA | | 7.7 | 7.2 | A | |
14.4. No. of Ambient Noise monitoring locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 61.5 | 35.4 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 70.6 | 46.1 | 75 | |
14.5. No. of Soil Sample Monitored locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 7.94 | 7.22 | (2.) | K(Potassium) | Kilogram per hectare | | 391 | 229 | (3.) | P(Phosphorus) | Kilogram per hectare | | 39 | 14 | (4.) | N(Nitrogen) | Kilogram per hectare | | 414 | 115 | (5.) | Electric Conductivity | Others | µS/cm | 459 | 219 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 3.68 To 32.51 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.27 To 34.56 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 1552.5 | 4.8 | Copy of Permission Letter | Pipeline | | Intake Well | | KGWA/GW/NOC/13/2020-21/2467 | 08 Dec 2020 | 1552.5 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | D.M. plant regeneration water | 66 | 66 | ETP | Others | 66 | 66 | 0 | (2.) | Sanitary Wastewater | 22 | 22 | ETP | Others | STP | 22 | 0 | (3.) | Induction Furnace | 19 | 19 | ETP | Others | DUST SUPPRESSION | 19 | 0 | (4.) | Rolling Mill | 27 | 27 | ETP | Others | for Ash handling | 27 | 0 | (5.) | Cooling Tower blowdown | 151 | 151 | ETP | Others | for Greenbelt development | 151 | 0 | (6.) | Boilers blowdown | 192 | 192 | ETP | Others | for Dust Suppression | 192 | 0 | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 477 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 477 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Mill scales from Rolling Mill | Industrial Waste | | 6600 | Tons | 100 | Road | given to nearby Sinter Plants / Ferro Alloy units. | Others | given to nearby Sinter Plants / Ferro Alloy units. | (2.) | End cuttings from Rolling mill | Industrial Waste | | 9900 | Tons | 0 | Others | Reused In SMS | Others | Reused In SMS | (3.) | Ash from DRI | Industrial Waste | | 63000 | Tons | 0 | Others | Own Brick Making Plant. | Others | Own brick making plant | (4.) | Dolochar | Industrial Waste | | 70000 | Tons | 0 | Others | used in AFBC power plant | Others | used in AFBC power plant | (5.) | Kiln Accretion Slag | Industrial Waste | | 3150 | Tons | 0 | Others | Own Brick Making Unit. | Others | Own brick making plant | (6.) | SMS Slag | Industrial Waste | | 49500 | Tons | 0 | Others | Own Brick Making Plant. | Others | Own brick making plant | (7.) | Wet Scraper Sludge | Industrial Waste | | 16100 | Tons | 0 | Others | Own Brick Making Plant. | Others | Own brick making plant | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM2.5 | | Microgram per Meter Cube | 42.9 | 1.3 | 0.92 | 43.82 | 60 | (2.) | SO2 | | Microgram per Meter Cube | 28.9 | 2.0 | 7.37 | 36.27 | 80 | (3.) | Others(Specify) | CO | Microgram per Meter Cube | 1028 | 1.4 | 3.56 | 1031.56 | 2000 | (4.) | PM10 | | Microgram per Meter Cube | 75.3 | 1.3 | 1.54 | 76.84 | 100 | (5.) | NOx | | Microgram per Meter Cube | 25.6 | 1.4 | 10.23 | 35.83 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | DRI kiln with WHRB (1 x 350 TPD) | Coal | 72 | 2.5 | Others | PM, SO2, NOx. | 1.45 g/s, 63.2 g/s, 9.6 g/s | (2.) | Induction Furnace (3x 40 T) | Electricity | 45 | 2.1 | Others | PM, NOx. | 1.2 g/s, 8.2 g/s | (3.) | DRI kiln with WHRB (2 x 350 TPD) | Coal | 88 | 2.5 | Others | PM, SO2, NOx. | 1.45 g/s, 63.2 g/s, 9.6 g/s. | (4.) | Re-heating furnace attached to 1000 TPD | LDO | 58 | 1.7 | Others | PM, SO2, NOx. | 0.7 g/s, 30.6 g/s, 4.5 g/s. | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 61500 | (b)Source | Captive Power Plant & State grid | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 1000 KVA | (e)Stack Height (in m) | 7 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 0 | (b)Private Land (ha.) | 88.15 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 0 | Total Land (ha.) | 53.4 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 17992.2 | (b)Waste/Barren Land (ha.) | 3768 | (c)Grazing/ Community Land (ha.) | 0 | (d)Surface Water Bodies (ha.) | 1538.6 | (e)Settlements (ha.) | 2072.4 | (f)Industrial (ha.) | 1224.6 | (g)Forest (ha.) | 4207.6 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Mining area | 596.6 | Total (ha.) | 31400.0000 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Green belt | | 29.38 | | (2.) | Main Plant | | 55.94 | Storage area, Internal Roads, parking area others | (3.) | Water Reservoir | | 2.83 | Water Reservoir & RWH | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | Nil | 0 | Nil within 10 Km radius | (2.) | ESAs | Nil | 0 | Nil within 10 Km radius | (3.) | Wildlife Corridors | Nil | 0 | Nil within 10 Km radius | (4.) | Corridors | Nil | 0 | Nil within 10 Km radius | (5.) | WLS | Nil | 0 | Nil within 10 Km radius | (6.) | ESZs | Nil | 0 | Nil within 10 Km radius | (7.) | NPA | Nil | 0 | Nil within 10 Km radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Bellary RF | 0.6 | Nil | (2.) | Archaeological Sites | | Bellary Fort | 9.0 | Nil | (3.) | Defence Installations | | Nil | 0 | Nil within 10 Km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 88.15 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Completed | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 0 | (f)Status of R&R | NA | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Tungabhadra High level canal | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 4.8 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 40 | (b)Permanent Employment-During Operation | 791 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 333 | (f)Total Manpower | 831 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 0 | 29.38 | 29.38 | (2.) | Percentage of Total Project Area | 0 | 33 | 33 | (3.) | No. of Plants | 14255 | 60000 | 74255 | (4.) | Funds Allocated | 0 | 1.2 | 1.2 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Environmental | Environmental: Greenbelt development
Social: Employment, Infrastructural facilities
Financial: Generation of income to the Government in the form of taxes; income generation to stake holders | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 1 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/ EIA/ 1922/ SA 0148 | (ii)Name of the EIA Consultant | M/s. Pioneer Enviro Laboratories & Consultants Pri | (iii)Address | Plot No. B15 & 16, Industrial Estate, Sanath Nagar, Hyderabad - 500 018, Telangana | (iv)Mobile No. | 9440677333 | (v)Landline No. | 0402311427 | (vi)Email Id | pelcpl@yahoo.co.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 1 | (ix)Validity of Accreditation | 21 Sep 2022 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Proposal is returned due to the following shortcomings:
• Column no.6 in Form II regarding existing EC details shall be furnished.
• RO certified report is of June, 2018 which is more than a year old. Recent RO report shall be submitted.
• Water source is mentioned as municipal wastewater. Relevant permission copy from the Competent Authority shall be furnished. | 13 Sep 2019 | 2. | NA | The correction have been made as per the instruction received | 13 Mar 2020 | 3. | NA | Proposal is returned due to the following:
Form 2:
• In s.no. 9, certified compliance report is of June 2018 which more than one year old. Fresh report from RO is required.
EIA report:
• In the declaration part by the consultant, it is mentioned that period of involvement of the consultant for the preparation of report is mentioned as 10 days to 2 months only which may please be explained by the PP and the consultant.
. Water withdrawal permission may please be submitted. | 27 Mar 2020 | |
Additional Detail Sought : NIL |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Prateek Agarwal | Designation | Partner | Name of Company (Applicant Name should not be given here) | VRKP SPONGE AND POWER PLANT LLP | Address | Sy. No. 229, 288 & 289, Halakundi village, Bellary Taluk and district, Karnataka-583102 |
|