Minutes of
the 35th Meeting of the Expert Appraisal Committee (Industry-1) held
during 26th & 27th
April, 2012 at IOCL Conference Room, 5th Floor, Core 6, Scope
Complex, Lodhi Road, New Delhi -110003.
35.0 Opening Remarks of the Chairman
At the outset, Chairman welcomed the members of the Expert Appraisal
Committee (Industry-1). Thereafter, agenda items were taken up for discussion.
35.1 Confirmation
of the Minutes of the 34th Meeting of the Expert Appraisal Committee
(Industry-1) held on 29th - 30th March, 2012.
The Minutes of the 34th Meeting of the Expert Appraisal
Committee (Industry-1) held on 29th - 30th March, 2012
were confirmed.
35.2.0 Consideration of the Projects
26th April, 2012
Proposals
for Environmental Clearance
35.2.1
Integrated Aluminium Complex (Aluminium
Smelter, 0.175 MTPA) and Captive Power Plant (4x120 MW) at Villages Markata,
Kadua, Mahupal, Bhagirathpur Sajan, Samatangi, Manjakana, Malapura,
Balabhadrapurpatna, Analabareni, Tehsil Kamakhyanagar, District Dhenkanal in
Orissa by M/s RSB MetalTech Pvt. Limited
- regarding Environmental Clearance
The project
authorities and their consultant, M/s Vimta Labs, Hyderabad gave
a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken as per Terms
of Reference (ToRs) awarded during the 9th Meeting of the
Expert Appraisal Committee (Industry-1) held on 7th - 8th
April, 2010 for preparation of EIA/EMP Report. All the Aluminium
Smelters are listed at S. No. 3(a) under Primary Metallurgy Industry
of the Schedule of EIA Notification 2006 under Category ‘A’ and appraised by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s RSB Metaltech Pvt. Ltd have proposed for
an Integrated Aluminium Complex (Aluminium Smelter, 0.175 MTPA) and Captive
Power Plant (4x120 MW) at Village Markata, Kadua, Mahupal, Bhagirathpur Sajan,
Samatangi, Manjakana, Malapura, Balabhadrapurpatna, Analabareni, Tehsil
Kamakhyanagar, District Dhenkanal, Orissa. Total land requirement is 1541.53
acres and green belt will be developed in 33% area. Orissa Industrial
Infrastructure Development Corporation (IDCO) is the nodal agency for procuring
land for the project. Out of the total area, 519.62
acres is revenue forest land, the
clearance for which is under process and Stage-I forest clearance is not yet
obtained. 54 families will be displaced and 339 families will be land losers.
Socio-economic survey report has been submitted to DC, Dhenkanal along with the
proposed R&R plan. RPDAC will finalize the R&R policy. Nearest village is
Biladihi (0.3 Km) and nearest town is Kamakhyanagar (5.6 Km). Reserve forests
are located within 10 km and no protected area/national parks/ sanctuaries are
located within 15 km. Total project cost is Rs. 6,180.98 Crores. Rs. 482.56 Crores
and Rs. 18.35 Crores are the capital and recurring cost per annum towards
environment and protection measures.
Following are the details of proposed facilities
and their production capacity:
S. No. |
Units |
Production Capacity |
1 |
Aluminium
Smelter |
0.175
Million TPA |
2 |
CPP |
4x120 MW |
Aluminium smelter produces primary aluminium by electrolytic reduction of
alumina and the process is commonly known as Hall-Heroult Process using point
feed pre-bake technology. CPP uses pulverised coal fired boilers.
C.P. Coke (0.062 MTPA), Alumina (0.336 MTPA),
Pitch (0.011 MTPA), Aluminium Fluoride (0.003 MTPA), Fuel Oil (8,750 KLA), LDO (1,750
KLA) will be used as raw materials for the Smelter. Coal (2.76 MTPA) and Fuel
oil (21,900 KLA) will be used as raw materials for CPP. Coal will be sourced
from Talcher Coal Fields, Ib Valley. Total power requirement is 339.37 MW,
which will be sourced from CPP. Pre-braked Point Feeding Technology will be
used in the smelter and Pulverized Fuel Boilers will be used in the CPP.
Ambient air
quality monitoring was carried within the study area
for PM10, SO2, NOx,
Flourides and PAH. The maximum values of these parameters are 46.9 µg/m3, 9.0 µg/m3,
9.9 µg/m3, <0.01
µg/m3 and <0.01 µg/m3 respectively. The predicted incremental ground level
concentrations (GLCs) due to the proposed project are 1.07 µg/m3, 25.2 µg/m3,
10.07 µg/m3, 0.21 µg/m3 and <0.01 µg/m3 respectively. The resultant
concentrations of these parameters are within the prescribed standards. ESP will be installed as
pollution control device. Highly efficient bag filters will be used in FTP and
GTC to remove suspended particulates below 100 mg/m3 but committee insisted for 50 mg/m3. Particulate
matter emissions from anode brake oven will be controlled below 50 mg/m3 as per CREP guidelines. Twin flue stack
(220 m high) to captive power plant and 50 m high stack will be provided to
bake oven. Stack (80 m.) will be provided in gas treatment centre. Truck
mounted heavy suction arrangement will be provided for dust extraction system.
Hooded cells will be used to reduce fugitive emissions. Advance dry scrubbing
system will be used in FTP. Computerized fire control system will be provided
in baking furnace. Fluoride emissions will be kept below 0.8 kg/ton of
Aluminium production. Hyper Dense phase system will be provided for dust free
transfer for Alumina. Raw material handling
section will be provided with dust suppression (DS) and dust extraction (DE)
systems.
Total water requirement is 3,280 m3/hr,
which will be sourced from River Brahmani. Full fledged water treatment plant
with adequate sludge removing arrangement will be installed. Effluent treatment
plant will be installed for the treatment of trade effluent. Neutralization
pond will be created for DM plant effluent and cooling tower/boiler blow down.
Sewage treatment plant will be installed for treatment of domestic sewage.
Plant will be operated on ‘zero’ discharge except the rain water. A reservoir
in 140 acres has been created for rainwater harvesting. Storm water during
rainy season will be collected in guard pond and will be monitored for fluoride
level and if required will be treated for fluoride removal through
de-fluorination unit. Oil and Grease removal
will be provided.
Spent pot lining material will be used in
the steel and cement industry as fuel as per CREP recommendations. Unutilized
SPL will be disposed off in secured landfill as per CPCB guidelines. Anode
butts will be recycled in anode plant. Fly ash & bottom ash will be
collected in dry form and used in cement manufacturing/ sent to ash dyke by
HCSD system. MoU has been signed with M/s A.M Enterprises for supply of 0.99
MTPA of fly ash. Sludge of WTP and STP will be used as manure for green belt
development. Used oil and used batteries will be sold only to authorized
recyclers. Alumunium dross will be sold to authorized secondary metal
processing units. Enclosures will be provided at blowers/compressors and noise
prone equipments to reduce noise transmission. Silencer will be provided in
noise generating machines to control noise pollution. Ear muff/plugs will be
provided for employees.
Public
hearing/Public consultation was conducted by the Odisha State Pollution
Control Board on 24.1.2011. The issues raised in the public hearing were
regarding provision of sewage treatment system in the area, pollution control
measures, employment to local people, CSR activities etc. which have been
addressed in the final EIA/EMP report.
The
proponent informed that out of 1541.53 acres of land, 250 acres is for
downstream facilities under the SEZ scheme. The Committee informed that
proposal for seek separate approval for SEZ. The proponent also informed that
they have applied for coal linkage. However, they have signed 3 MOUs for supply
of coal from various sources in case the linkage is delayed.
After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to submission of revised layout plan and land requirement after excluding the downstream
facilities since the downstream facilities are going to be part of SEZ, R
&R plan submitted to the State Govt., Management plan for SOx and NOx
reduction and the stipulation of following specific conditions along
with other environmental conditions:
i.
Ministry
of Environment and Forests shall regularly be informed about the source and
quantity of Alumina procured from captive/indigenous/imported sources.
ii.
Alumina
shall be obtained only from those refineries, which have been accorded
environmental clearance by the Ministry of Environment and Forests.
iii.
The
gaseous emissions (PM, SO2, NOX, PAH, HC, VOCs and
Fluoride) from various process units shall conform to the standards prescribed
by the concerned authorities from time to time. The OSPCB may specify more
stringent standards for the relevant parameters keeping in view the nature of
the industry and its size and location. At no time, the emission levels shall
go beyond the prescribed standards. In the event of failure of any pollution
control system adopted by the unit, the respective unit shall not be restarted
until the control measures are rectified to achieve the desired efficiency. The
particulate emissions from the bake oven plant shall not exceed 50 mg/Nm3.
iv.
Particulate
fluoride emissions shall not be more than 0.65 mg/Nm3 and fugitive
particulate fluoride emissions from pot room shall not be more than 1.85 mg/Nm3.
v.
FGD shall be provided
for smelter
vi.
The
poly-aromatic hydrocarbons (PAH) from the carbon plant (anode bake oven) shall
not exceed 2 mg/Nm3. The data on PAH shall be monitored quarterly
and report submitted regularly to the Ministry/Regional Office at Bhubaneswar
and SPCB.
vii.
In-plant
control measures like fume extraction and dust extraction system for
controlling fugitive emissions from all the material handling/transfer points
shall be provided to control dust emissions. Fugitive Fluoride emissions from
the pot room and in the forage around the smelter complex shall be monitored
and data submitted regularly to the Ministry’s Regional Office at Bhubaneswar
and SPCB. Further dry scrubbing system to control the emissions from the pot
lines shall be provided.
viii.
High
efficiency Electrostatic precipitator (ESP) shall be provided to Captive Power
Plant (CPP) to control emissions below 50 mg/Nm3. The company shall
provide bag-filters, dry scrubbing system and dust suppression system to
control the all the emissions including fluoride emissions from all melting and
casting units. Tar, dust and fluoride in the fumes shall be controlled in
baking furnace by providing dry scrubber. The emissions shall conform to the
standards prescribed by the Ministry/CPCB/SPCB whichever is more stringent.
ix.
Fluoride
consumption shall be less than 10 kg/ton of Aluminium produced as specified in
the CREP guidelines.
x.
Anode
butts generated from the pots shall be cleaned and recycled to the Anode Plant.
The spent pot lining generated from the smelter shall be properly treated in
spent pot lining treatment plant to remove fluoride and cyanide and disposed
off in secured landfill. The location and design of the landfill site shall be
approved by the OSPCB as per Hazardous Wastes (Management and Handling) Rules,
2003. Leachate collection facilities
shall be provided to the secured landfill facility (SLF). The dross shall be
recycled in the cast house. STP sludge
shall be utilized as manure for green belt development. All the used oil and batteries shall be sold
to the authorized recyclers/ reprocessors.
xi.
Integrated
Ash Management Plan shall be prepared for the utilization of fly ash as per Fly
Ash Notification, 1999 as amended in 2003 and 2009 implemented. A copy of the
plan shall be submitted to the Ministry’s Regional Office. Fly ash shall be
collected pneumatically in silos and used by cement and brick manufacturers for
further utilization. Bottom Ash shall be disposed off in ash pond using high
concentrated slurry disposal method.
xii.
As
proposed, spent pot lining waste shall also be provided to cement and steel
industries for further utilization.
xiii.
Regular
ground water monitoring shall be carried out by installing Peizometers all
around the secured landfill site in consultation with the SPCB, Central Ground
Water Authority and State Ground Water Board and data submitted to the
Ministry’s Regional Office and SPCB.
xiv.
Total
water requirement shall not exceed 3,280 m3/hr
and prior permission shall be obtained from the concerned department
before commissioning of the plant. All
the effluent including from cooling tower and de-mineralization plant shall be treated
in the effluent treatment plant and treated effluent shall be recycled /
reutilized in the process in the smelter and CPP and also for fire protection,
dust suppression, green belt development etc.
Domestic effluent shall be treated in Sewage Treatment Plant (STP) and
treated domestic wastewater will be used for green belt development.
xv.
No
effluent shall be discharged outside the premises during the non-monsoon period
and shall be discharged during the monsoon period only after proper treatment and
meeting the norms of the OSPCB/CPCB.
xvi.
Green
belt of adequate width and density around the project site shall be developed
in 33 % area in consultation with the DFO as per the CPCB guidelines having
density of 2,000 trees/ha.
xvii.
Occupational
Health Surveillance of the workers should be done on a regular basis and
records maintained as per the Factories Act.
xviii.
The
company shall develop rainwater structures to harvest the run off water for
recharge of ground water in consultation with the Central Ground Water
Authority/Board.
xix.
Rehabilitation
and Resettlement (R & R) Plan prepared and submitted to the State Govt.
shall be implemented as per the R & R Policy of the State Government. All
the recommendations mentioned in the R & R Plan shall be strictly followed
including suitable employment and other facilities to all the oustees.
xx.
All
the recommendations made in the Charter on Corporate Responsibility for
Environment Protection (CREP) for the Aluminium sector shall be strictly
implemented.
xxi.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 24th
January, 2011 should be satisfactorily
implemented and a separate budget for implementing the same should be allocated
and information submitted to the Ministry’s Regional Office at Bhubaneswar.
xxii.
At least 5 % of the total cost of the project
shall be earmarked towards the Enterprise Social Commitment based on Public
Hearing issues and item-wise details along with time bound action plan should
be prepared and submitted to the Ministry’s Regional Office at Bhubaneswar.
Implementation of such program should be ensured accordingly in a time bound
manner.
xxiii.
The company shall provide housing for
construction labour within the site with all necessary infrastructure and facilities
such as fuel for cooking, mobile toilets, mobile STP, safe drinking water,
medical health care, crèche etc. The housing may be in the form of temporary
structures to be removed after the completion of the project.
35.2.2
Ferro Alloy Manufacturing Unit (4 x 9 MVA / 2 x 18
MVA Submerged Arc Furnace) for production of Silico Manganese-58,320 TPA; Ferro
Manganese-81,230 TPA; Ferro Silicon-25,272 TPA and 3 x 300 TPD Manganese ore
Sinter Plant at Mahuroomkala Village, Khairagarh Tehsil, Rajnandgaon District,
Chhattisgarh by M/s. Sarita Steels & Power Ltd. - regarding Environmental
Clearance
The
project proponents and their consultant, M/s Ramky Enviro Engineers
Limited, Hyderabad gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per Terms
of Reference (ToRs) awarded during the 25th Meeting of the
Expert Appraisal Committee (Industry-1) held on 29th-30th
June, 2011 for preparation of EIA/EMP Report. All the Ferro alloy plants
are listed at S. No. 3(a) under Primary Metallurgy Industry of the Schedule of
EIA Notification 2006 under Category’ A’ and appraised by
the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Sarita Steels & Power Ltd.
have proposed for a Ferro Alloy
Manufacturing Unit (4 x 9 MVA/ 2 x
18 MVA Submerged Arc Furnace) at Mahuroomkala village, Khairagarh Tehsil,
Rajnandgaon District, Chhattisgarh. The total land acquired is 40.27
acres of which 14.5 acres will be developed under green belt. Nearest
habitation is Mahuroomkala village at 0.5 Km N and nearest town is Rajnandgaon
at 20 Km SE. No national park/wild life sanctuary/reserve forest is
located within 10 km radius of the project site. Total cost of the
project is Rs. 297.54 Crores of which Rs. 29.75 Crores and Rs. 2.97 Crores
will be earmarked towards total capital cost and recurring cost/annum for
environmental pollution control measures.
The details of the products along with their capacity are
given below:
S. No. |
Type of the product |
Capacity (TPA) |
1 |
Ferro Alloys - 4x9 / 2x18 MVA Submerged Arc
Furnace |
|
Silicon Manganese-Si-Mn |
58,320 |
|
Ferro Manganese-Fe-Mn |
81,230 |
|
Ferro Silicon-Fe-Si |
25,272 |
|
Total |
1,64,822 |
|
2 |
3 x 300 TPD Manganese ore Sinter Plant |
2,97,000 |
The production capacity of the combined Ferro Alloy
products will not exceed 1,64,822 TPA. Ferro
Manganese, Silico Manganese and Ferro Silicon will be produced in submerged arc
furnace (SAF). The raw materials will be thoroughly mixed and charged into the
furnace. The charge will enter the smelting zone, smelted at 1200-13000C
and the alloy formed being heavy, settle at the bottom and will be cast in
dressed beds. After solidification, the cakes will be broken
manually to required lump size. The Manganese Ore Sinter is produced in Sinter
plant. The raw materials will be thoroughly mixed and charged into the furnace
(Rotary drum), the temperature of furnace is 900-10000C, the
manganese ore sinter is crushed and screened to required size. Power (60 MW)
will be sourced from Chhattisgarh State Power Distribution Co. Ltd. D.G. set
(1x500 KVA) will be installed for emergency power supply.
Ambient air
quality monitoring was carried within the study area
for PM, SO2 and NOx. The maximum
values of these parameters are 70 µg/m3,
17.9 µg/m3 and 27.1 µg/m3 respectively. The predicted maximum incremental
ground level concentrations (GLCs) due to the proposed project are 4.07 µg/m3, 0.5 µg/m3
and 2.37 µg/m3 respectively.
The resultant concentrations of these parameters are within the prescribed
standards. Dust and fume
extraction system with cyclone followed by bag filters will be provided to the
submerged arc furnaces. ESP will be installed to control the emissions from the
Sinter Plant. The emissions will be dispersed through a chimney of adequate
height (Submerged arc furnace 30 m, Sinter plant 40 m). Fugitive emissions due
to transportation will be controlled by water sprinkling on the roads. Raw
materials and products will be kept in covered sheds.
Total fresh water requirement is 558 m3/day,
which will be sourced from the ground water within plant premises and mainly
used in cooling purpose. The treated effluent (cooling tower 84 m3/day)
will be used for slag cooling and dust suppression. Domestic effluent (20 m3/day)
will be treated in septic tank followed by soak pit or STP and the treated
water is used for greenbelt development. No effluent will be discharged outside
the premises and zero discharge will be adopted.
Solid waste like bag filter dust will be reused in process.
The slag generated from the production of Si-Mn (56,450 TPA); Fe-Mn (75,108
TPA) and Fe-Si (30,540 TPA) will be used for construction of roads, brick
manufacturing, designer tiles and load bearing tiles. Waste oil and used
batteries will be sold to authorized recyclers /reprocessors. Acoustic
enclosures will be provided to D.G. sets to control noise.
The
Committee deliberated on the issues raised during the Public Hearing / Public
Consultation meeting conducted by the Chhattisgarh Environment Conservation
Board on 5th January, 2012. The issues raised in the public hearing
were regarding provision of employment to local people, pollution control measures,
depletion of ground water, local development, etc. which were addressed in the
EIA/EMP report.
The
Committee desired the information regarding major raw materials analysis,
revised layout plan with area break up and details regarding water reservoir
and rain water harvesting. The requisite information has been furnished.
After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to stipulation of following specific conditions along with
other environmental conditions:
13. At
least 5 % of the total cost of the project should be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and
item-wise details along with time bound action plan should be prepared
and submitted to the Ministry’s Regional Office at Bhopal. Implementation of
such program shall be ensured accordingly in a time bound manner.
35.2.3
Proposed expansion of Ferro Alloy
Manufacturing Unit (Existing: 1x6 & 1x9 MVA and Proposed: 2 x 12 MVA
Submerged Electric Arc Furnaces) to manufacture 66,660 TPA Ferro Manganese/53,790
TPA Silico Manganese/63,030 TPA Ferro Chrome/27,390 TPA Ferro Silicon at
Ravivalasa Village, Tekkali Mandal, Srikakulam District in Andhra Pradesh by M/s
Cronimet Alloys India Limited - regarding Environmental Clearance.
The
project authorities and their consultant, M/s Sri Sai Manasa Nature Tech Pvt.
Ltd., Hyderabad gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (ToRs) awarded during the 17th Meeting of
the Expert Appraisal Committee (Industry-1) held on 13th -14th
December, 2010 for preparation of EIA/EMP. The Ferro alloy plants are listed at S.
No. 3(a) under Primary Metallurgy Industry of the Schedule of EIA Notification
2006 under Category’ A’ and appraised by the Expert
Appraisal Committee (Industry-1) of MoEF.
M/s. Cronimet Alloys
India Limited has proposed
for expansion of Ferro Alloys Manufacturing Unit (2 X 12 MVA, SEAF for manufacture of 46,860 TPA Ferro Manganese/33,990 TPA
Silico Manganese/ 38,280 TPA Ferro Chrome,/16,500 TPA Ferro Silicon) at Survey No.: 62, 63, 64 Ravivalasa Village, Tekkali
Mandal of Srikakulam District in Andhra Pradesh. The land acquired for proposed
expansion is 14.57 acres of which green
belt will be developed in 6.76 acres. Total land acquired including existing and proposed expansion
is 22.02 acres of which green belt will be developed in 7.28 acres. The PP iinformed that the Telineelapuram bird sanctuary located
within 10 km is not a notified bird sanctuary Total cost of the proposed
expansion project will be Rs. 71 Crores, out of which Rs. 7.18 Crores is
allocated for EMP.
Following are
the existing and proposed facilities & products:
S. No. |
Facility |
Plant configuration |
Product |
Production Capacity |
||
Existing (TPA) |
Proposed (TPA) |
TOTAL (TPA) |
||||
1 |
Submerged Electric Arc furnaces |
Existing : 1 x 6 MVA, 1 x 9 MVA Proposed : 2 x 12 MVA |
Ferro Manganese |
19,800
|
46,860 |
66,660
|
2. |
Silico Manganese |
19,800 |
33,990
|
53,790
|
||
3. |
Ferro Chrome |
24,750
|
38,280
|
63,030
|
||
4. |
Ferro Silicon |
10,890 |
16,500 |
27,390 |
The Compliance to the conditions
stipulated in the NOC from SPCB has been submitted and found to be
satisfactory. Manganese ore, coal/coke, Dolomite,
quartz, Fe.
Mn Slag, carbon paste, Dry Briquetes, Cr.
Ore, Magnesite, MS rounds, Mill scale, casting sheets will be used as raw
materials. Manufacturing process involves smelting of charge materials in
submerged arc furnace. Total power requirement of 132 KVA will be met from the
substation. Noise absorbing materials will be used in the construction of
buildings etc. and less noise generating machinery will be installed.
Ambient air
quality monitoring was carried within the study area
for PM, SO2 and NOx. The maximum
values of these parameters are 56.3 µg/m3, 9.7 µg/m3 and 22.7 µg/m3 respectively. The predicted maximum incremental
ground level concentrations (GLCs) due to the proposed project are 0.69 µg/m3, 1.71 µg/m3
and 0.96 µg/m3 respectively.
The resultant concentrations of these parameters are within the prescribed
standards. Dust extraction
system with Jet Pulse bag filters and furnace hoods will be provided to
submerged arc furnace. Water sprinkling system will be provided to control
fugitive dust emissions from material handling.
Total water requirement of 152 m3/day (Existing
52 KLD and 100 KLD for proposed) will be met from ground water through bore
wells. The fresh water requirement will be 67 m3/day. No process
wastewater will be generated. Maximum recycling of wastewater will be done
after proper treatment. Domestic wastewater will be sent to septic tank
followed by dispersion trench. Wastewater generated from Jigging machine will
be recycled and when it becomes non-recyclable with contamination of sand soil,
it will be discharged. Zero effluent discharge will be maintained.
Ferro-Manganese slag will be reused in Silico-Manganese
manufacture. Silico Manganese and Ferro Silicon slag will be used in construction
works. Ferro Chrome slag will be sent for Toxic Chemical Leachability Potential
(TCLP) test for the Chrome content in the slag. If Cr2O3 content is less
than 0.2%, slag will be used in construction and infrastructure developmental
activities. If Cr2O3 content
is greater than 0.2%, slag will be sent to Cr. Recovery Plant. AFPL proposes to
setup a chrome recovery plant for recovering the chrome content in the slag.
Waste slag after chrome recovery will be disposed for filling low lying areas. Bag
filter dust will be sent to fly ash brick manufacturing units. Domestic and
commercial solid waste will be collected, segregated and disposed for reuse and
to dumping yard.
Public hearing/public consultation was conducted by the
Andhra Pradesh Pollution Control Board on 14th July 2011. The issues
raised in the public hearing meeting were regarding provision of employment to
locals, pollution control measures, drinking water facilities, development of
School, green belt development, etc. which have been addressed and included in
the EIA/EMP report.
After detailed deliberations, the Committee recommended the
proposal for environmental clearance subject to stipulation of the following
specific conditions along with other environmental conditions:
5. The total water requirement shall not exceed
152m3/day. ‘Zero’ effluent discharge shall be strictly followed and
no wastewater should be discharged outside the premises.
13. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
based on Public Hearing issues and item-wise details along with time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bangalore. Implementation of such program shall be ensured accordingly in a
time bound manner.
35.2.4
Grinding unit of Cement of 200 TPD at Sy. No.
181/1, Village Peradam, Sathyavedu Mandal, Distt. Chittoor, Andhra Pradesh - by
M/s. Vishnu Maya Cements (P) Ltd. - regarding Environmental Clearance
The
proponent informed that they will not be able to attend the meeting. The
Committee decided to consider the project as and when requested by the
proponent.
35.2.5
Expansion of Integrated Steel Plant from
0.075 MTPA to 0.425 MTPA and Captive Power Plant of 76 MW (FBC- 60 MW & WHRB - 16 MW) at
Kulei, Parajang, Dhenkanal, Orissa by
M/s Rana Sponge Limited - regarding
Environmental Clearance
The project authorities and their consultant,
M/s Global Experts, Bhubaneswar gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (ToRs)
awarded during the 90th Meeting of the Expert Appraisal Committee
(Industry-1) held on 6th-8th January, 2009 for
preparation of EIA/EMP. The Integrated Steel Plants are listed at S.
No. 3(a) under Primary Metallurgy Industry of the Schedule of EIA Notification
2006 under Category’ A’ and appraised by the Expert
Appraisal Committee (Industry-1) of MoEF.
M/s Rana Iron and Power Ltd. (formerly M/s Rana Sponge Limited) have proposed for expansion of Integrated Steel Plant from 0.075 MTPA to 0.425
MTPA at Kulei, Parajang, Dist Dhenkanal, Odisha. The company has acquired 263.0 acres of land
through IDCO, in which various process units, raw material & solid waste
storage units, rain water harvesting facility etc. would be set up. About 88 acres
(33% of total land area) of land has been ear marked for development of green
belt all around the project area. No National Parks / Wildlife Sanctuaries/ Biosphere
Reserves are located within 10 km radius of the project area. The total project
cost is Rs. 778.7 Crores and the cost
allocated towards pollution control and environmental protection measures will
be Rs. 31 Crores.
Following will be the plant configuration and product
mix:
UNIT |
CAPACITY |
PRODUCT |
PRODUCTION
in TPA |
END USE |
Existing
Plant Facilities |
||||
DRI kiln |
1 x 100
TPD 1 x 350
TPD |
Sponge
iron |
1,35,000 |
SMS |
SMS-IF |
2X 10 T |
Billets |
75,000 |
Sale/SMS |
Rolling
Mill |
2500
MT/Month |
MS Angles |
30,000 |
Sale |
FBC CPP |
4
MW |
Power |
4 MW |
Internal
Use |
WHRB CPP |
8
MW |
Power |
8 MW |
Internal
Use |
Producer
gas plant |
25
TPD |
Producer
gas |
|
Use in RHF |
Proposed Expansion (Phase 1) |
||||
DRI kiln |
1 x 100
TPD 2 x 350
TPD |
Sponge
iron |
240,000 |
SMS –I SMS- II |
SMS-I |
||||
IF |
7 X 10 T |
Billets |
187,000 |
Rolling
Mill 1 |
LRF |
Matching |
|||
CCM |
Matching |
|||
RM- I |
0.25 MTPA |
Rolled
Product |
2,50,000 |
Sale |
Coal
Washery |
0.9 MTPA |
Washed
Coal |
495,000 |
DRI kilns |
Middling |
3,15,000 |
FBC CPP |
||
Reject |
85,000 |
Sale |
||
FBC CPP |
1X
30 MW |
Power |
60 MW |
Internal
Use |
WHRB CPP |
16
MW |
Power |
16 MW |
Internal
Use |
Phase-II |
||||
Sinter |
1
X 30 m2 |
Sinter |
2,94,000 |
MBF |
MBF |
1
X 250 m3 |
Hot Metal Pig iron |
1,80,000 30,000 |
SMS-II SMS |
SMS- II |
||||
EAF |
1 X 50T |
Billets |
2,62,000 |
Rolling
Mill I & II |
LRF |
Matching |
|||
CCM |
Matching |
|||
RM-II |
0.25 MTPA |
Rolled
Product |
2,50,000 |
Sale |
Fe-Mn |
1 X 16.5
MVA |
Fe-Mn |
25,000 |
Sale |
Si-Mn |
1 X 16.5
MVA |
Si-Mn |
25,000 |
Sale |
Saleable
product after complete expansion |
||||
Rolling
Mill |
0.5 MTPA |
Rolled product |
500,000 |
Sale |
Fe-Mn |
1 X 16.5
MVA |
Fe-Mn |
25,000 |
Sale |
Si-Mn |
1 X 16.5
MVA |
Si-Mn |
25,000 |
Sale |
CPP |
64 MW FBC 24 MW WHRB |
Power |
88 |
Internal
consumption |
The PP
informed that the proposal
for pulp and paper mill as part of the expansion is dropped. Iron
Ore-10,13,000 TPA, Coal-11,50,000 TPA, Dolomite-45,000 TPA, Lime Stone–70,000 TPA,
Manganese – 1,37,000 TPA are the major raw materials. Iron ore & Manganese
will be sourced from Joda/Barbil and coal will be sourced from nearest coal
mine & local dealers. The total power requirement is 154 MW of which 88 MW will
be met from the CPP and the rest will be met from the State grid.
It is
proposed to install a IF and LF to produce billets to be used in rolling mills
to produce 0.5 MTPA Rolled product. The IF -LF-CCM route with optimum feed
combination of sponge iron and hot metal/pig iron feed for the production of
high quality steel billet/bloom will be used. A waste heat boiler to produce 88 MW power utilizing
hot flue gas from DRIs and CFBC to utilize DRI char and middlings from coal
washery will be installed.
Ambient air
quality monitoring was carried within the study area
for PM, SO2 and NOx. The maximum
values of these parameters are 102.3 µg/m3, 12.8 µg/m3 and 14.3 µg/m3 respectively. The predicted maximum incremental
ground level concentrations (GLCs) due to the proposed project are 18.58 µg/m3, 12.49 µg/m3
and 8.3 µg/m3 respectively.
Dust extraction system with adequate capacity bag house followed by tall
stack and water sprinkling system will be provided for the raw material
handling system and material transfer points. Dust extraction system with pulse
jet type bag filter will be provided to Blast Furnace stock house and wet
scrubber will be provided for Blast Furnace. Fume extraction system with
adequate capacity bag house will be provided for EAF-GCP. Water sprinkling will
be done in coal washery and ash handling.
The water
requirement of 16,910 m3/day will be sourced from River Brahmani. The
water consumption will be minimized by rain water harvesting. No effluent will
be discharged outside the plant premises. The wastewater generated in the
process will be treated and reused in the process. The iron ore fines,
limestone fines, dolomite fines, MBF dust, Rolling mill scale & coke fines
will be used in the sinter unit. The granulated MBF slag will be sold to cement
plants. The coal fines and DRI Kiln will be used in the FBC boiler. The SMS and
RM scrap will be reused in SMS. The coking coal fines and sinter fines will be
recycled. The Fe-Mn slag will be used in the manufacture of Si-Mn. The SMS
slag, Si-Mn slag etc. will be used for road making.
Public Hearing/public consultation was conducted by the Odisha
State Pollution Control Board on 18h May 2011. The issues raised in
the public hearing meeting were regarding provision of employment to local
people, pollution control measures, green belt development, rain water
harvesting, CSR activities etc. which have been addressed and included in the EIA/EMP
report.
The
Committee after detailed deliberations sought the following information for
reconsideration:
· Documents regarding name change of company from Rana
Sponge to Rana Iron & Power Ltd.
· Photographs of the existing and
proposed plant area.
· Copy of environmental clearances obtained for the
existing units and the dates of commissioning of various units.
· Compliance
to the conditions stipulated in the environmental clearance
/ NOC granted by the SPCB.
· Recent
monitoring report from the SPCB, which shall include data on AAQ, water
quality, solid waste etc. shall be submitted.
· Has the unit received any notice under
the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air
and Water Acts? If so, compliance to the notice(s)
· Copies of Firm
Coal linkages
· Ambient air
quality at 8 locations covering the study area of 10 km., aerial coverage from
project site with one AAQMS in downwind direction. measures of mitigation of SO2
and NOx.
· Impact of water drawl on River Brahmani
· Ground water analysis for all the 34 parameters as
per IS10500
· Details regarding reuse of wastewater in various
processes etc.
· Action plan for 100% utilization of fly ash and MoUs
with cement plants etc.
· Management plan for toxic metal mitigation
· Action plan for the implementation of
OHS standards as per OSHAS/USEPA
· Plan and
fund allocation to ensure the occupational health & safety of all contract
and sub-contract workers.
35.2.6
Proposed 3 X 9 MVA Submerged Arc Furnace (Fe-Mn : 55,440 TPA / Si-Mn : 39,600 TPA / Fe-Si : 19,800 TPA or Product mix of all) at Mouza & Village Maheshpur, P.O. & P.S.: Salanpur, District Burdwan, West Bengal by M/s Padma Iron Products Private Limited
- regarding Environmental Clearance
The project authorities and
their consultant, M/s
Environ India, Kolkata gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (TORs) awarded during the 26th
Meeting of the Expert Appraisal Committee (Industry-1) held during 22nd
– 23rd July, 2011 for preparation of EIA/EMP report. The Ferro
Alloy Plants are listed at S. No. 3(a) under Primary Metallurgy Industries
under Category A of the Schedule of EIA Notification 2006 and appraised by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Padma Iron Products Private Limited have proposed to set up a 3 X 9 Submerged Arc Furnace at Mouza & Village : Maheshpur, P.O. & P.S. :
Salanpur, District : Burdwan, West Bengal. Total land for the proposed project is 9.86 acres
and green belt will be developed in 3.26 acres of area. No R & R is
involved. No National Park/Wild Life Sanctuary/Reserve Forest is located
within 10 km radius of the project site. Total cost of the proposed
project is Rs. 60.0 Crores. Rs. 4.5 Crores and Rs. 45 Lakhs/Annum will be
earmarked towards total capital cost and recurring cost for environmental
pollution control measures.
Following will be the facilities
and products from the proposed plant:
Main
Plant |
Submerged Arc Furnace (SAF) |
3 X 9 MVA |
Installed
Capacity |
Ferro
Manganese |
55,440 TPA |
Silico
Manganese |
39,600 TPA |
|
Ferro Silicon |
19,800 TPA |
Manganese ore, Fe-Mn slag, coke
breeze, quartz, dolomite, iron scrap and pet coke will be used as raw
materials. Power requirement (27.75 MVA) will be met by Damodar Valley
Corporation. The manufacturing of ferro alloys
will be carried out in submerged arc furnace and the process involves feeding
the raw materials into the furnace. In nature, the elements are available in
the form of oxides. These oxides along with carbon will be fed to the furnace.
After attaining favourable temperatures in the furnace, carbon will react with
oxide and will remove it from element or metal. The metal will
be tapped at regular intervals and collected in pans/moulds. After
solidification of the metal, the same will be broken to required sizes and
delivered to customers.
Ambient air quality monitoring
has been carried at 8 locations during the period from March 2011 to May 2011
and the average data indicate PM10 (36-72 µg/m3), PM2.5
(22-40 µg/m3), SO2 (6-12 µg/m3) and NOx
(17-35 µg/m3) are within the permissible limits. Prediction of Ground
Level Concentrations (GLCs) due to proposed project has been made by Industrial
Source Complex, Short Term (ISCST3) as per CPCB guidelines and the average data
indicated an incremental PM10 of 3.1 µg/m3. Similarly, average incremental PM2.5 emission
is 2.6 µg/m3. The smoke and fumes collected from SAF by the hood
will be passed through bag filter before discharging through a stack of
adequate height. Fugitive emissions from the raw material handling section will
be suppressed by dry fogging system / water sprinkling.
Total water requirement of 30 m3/day
will be sourced from borewell / rainwater harvesting pond. Maximum recycling of
wastewater will be done after treatment to achieve zero discharge. Treated
waste water will be used for dust suppression and green belt development.
Effluent streams such as cooling tower blow down, floor washings, etc. will be
used for fugitive dust suppression, water sprinkling etc. Plant sewage will be
treated in septic tank. Fines and bag
filter dust will be recycled in the process. Slag from Si-Mn production will be
used in land / road / area development / manufacturing of coloured
glass/insulated bricks. Slag from Fe-Si production will be used in the cupola
furnace as raw material. All pumps and motors
will be selected from less noise generating types. Ear plugs will be provided
to employees working in high noise prone areas. DG
sets of capacity 2 X 125 KVA & 1 X 250 kVA will be installed and used during power
failure only. DG sets will be
provided with silencer.
Public hearing/Public
consultation meeting was conducted by the West Bengal Pollution Control
Board on 18.1.2012. The main issues raised in the public hearing meeting
were w.r.t. proper pollution control measures, local employment, proper
wages to workers, plantation programmes etc. and have been addressed and
included in the EIA/EMP.
After
detailed deliberations, the Committee has recommended the proposal for
environmental clearance subject to submission of trace
element analysis of raw materials in absolute values & if the values are
more than the standards, shall submit a management plan and stipulation of following specific
conditions along with other environmental conditions:
13. At
least 5 % of the total cost of the project should be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and
item-wise details along with time bound action plan should be prepared
and submitted to the Ministry’s Regional Office at Bhubaneswar. Implementation
of such program shall be ensured accordingly in a time bound manner.
35.2.7
Expansion of
Induction Furnace (Billets: 49,200 TPA), Rolling Mill (Hot-rolled strips/
sheet/ coil: 49,200 TPA) and Oxygen plant (600 m3/hr) in the
existing plant premises at Plot No. 30, APIIC Industrial Park Gollapuram
(Phase-3), Village Gollapuram, Mandal Hindupur, District Ananthapur in Andhra
Pradesh by M/s Vedik
Ispat Private Limited- regarding Environmental Clearance
The
project authorities and their consultant, M/s Pioneer Enviro Laboratories &
Consultants Pvt. Ltd., Hyderabad gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken as per Terms of Reference (ToRs) awarded during the 28th Meeting
of the Expert Appraisal Committee (Industry-1) held during 26th
- 27th September, 2011 for preparation of EIA/EMP. The
Induction Furnace (>30,000 TPA) are listed at S. No. 3(a) in Secondary Metallurgy
Industries under Category ‘B’ of the amendment to Schedule of EIA Notification
2006 and appraised
by the SEIAA/SEAC. However, due to location of the project within 10 km of the
interstate boundary of Karnataka, the proposal was kept in Category ‘A’ and appraised by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Vedik Ispat Pvt. Ltd. have proposed for expansion of
Induction Furnace & Rolling Mill in the existing plant premises at Plot No.
30, APIIC Gollapuram Industrial Park (Phase-3), Gollapuram Village, Hindupur
Mandal, Ananthpur District, Andhra Pradesh. The project site is located in
Gollapuram Industrial area, which is a notified industrial area. Green belt
will be developed in 33% (inclusive of existing) of the total plant area. Penneru
River is flowing at a distance of 3.0 Kms. from the site and State highway no. 9
is at a distance of 2.0 Kms from the site. No National Park / Wild life
sanctuary / Reserved forest is located within 10 km radius of the
project site. Total cost of the expansion project is Rs. 25.4 Crores. Rs. 1
Crores and Rs. 10 lakhs/annum will be earmarked towards capital cost and
recurring cost for environmental pollution control measures.
Following is the plant configuration:
S.No. |
Units |
Product |
Existing configuration As per E.C. accorded in 2010 |
Additional Capacity Proposed |
Total capacity after the proposed
additional capacity
|
1. |
Induction Furnace with C.C.M with
AOD |
Billets |
68,400 TPA * (In operation since October, 2011) |
49,200TPA |
1,17,600 TPA** |
2. |
Rolling Mill |
Hot-rolled Strips/sheet/coil |
68,400 TPA |
49,200TPA |
1,17,600 TPA*** |
3. |
Oxygen plant |
Oxygen |
- |
600 m3/hr |
600 m3/hr |
*1X25 MT Induction Furnace is in operation from October,
2011.
** The production of 1,17,600 TPA will be achieved in the
same existing Induction Furnace by considering 12 heats per day and the raw
scrap will be melted of in AOD.
*** A single Rolling mill of 1,17,600 TPA will be installed
(As already permitted 68,400 TPA of is yet to be installed.)
The sponge iron will be fed to Induction furnace to make
ingots / billets which will be casted in rolling mill in form of steel i.e. TMT
bars / Structural Steel. Power requirement for the proposed plant will be met
from Grid. Ambient air quality monitoring was carried out at 8 locations during
September 2010 to November 2010 and the submitted data indicated the value of
PM2.5 (14.7- 20.9 µg/m3),
PM10 (25.3 – 34.9 µg/m3), SPM (79.2 – 96.7 µg/m3), SO2 (6.0- 8.4 µg/m3) and NOx (7.0 – 9.5 µg/m3). The submitted data indicated the incremental value of PM10
(0.9 µg/m3), SO2 (7.5 µg/m3) & NOx (8.5 µg/m3)
which is within the permissible limit. Fume extraction system with bag
filters will be provided to Induction Furnace, LRF and CCM. Bag filters will be
provided to Rolling Mill.
Total water required for the proposed expansion project is
65 m3/day. The water requirement for the proposed expansion project
will be supplied by APIIC. No wastewater will be generated from the proposed
expansion project, as closed circuit cooling system will be adopted. Domestic
wastewater will be disposed off into the soak pit via septic tank. Zero
discharge will be maintained in the proposed plant. Slag generated from SMS
will be crushed and after iron recovery, the inert material will be used in brick
manufacturing units. Mill scale from Rolling mill will be reused in SMS.
Public
hearing is not required as the unit is located in notified industrial area.
After detailed deliberations, the Committee has recommended the proposal
for environmental clearance subject to stipulation of following specific
conditions along with other environmental conditions:
i.
Compliance
to all the specific and general conditions stipulated for the existing plant by
the Central and State Government shall be ensured and regular reports submitted
to the Ministry’s Regional Office at Bangalore and SPCB.
ii.
The company shall install wet
scrubber and bag filters etc. to control the particulate emissions below 50
mg/Nm3.
iv.
Gaseous emission levels including
secondary fugitive emissions from all the sources shall be controlled within
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008 and regularly monitored. Guidelines / Code of
Practice issued by the CPCB should be followed.
vii.
Risk and Disaster Management
Plan along with the mitigation measures shall be prepared and a copy submitted
to the Ministry’s Regional Office at Bangalore,
APPCB and CPCB within 3 months of issue of environment clearance letter.
viii.
As proposed, green belt shall be developed in
33 % of the plant area. Selection of plant species shall be as per the CPCB
guidelines in consultation with the DFO.
ix.
At least 5 % of the total cost of the project
shall be earmarked towards the Enterprise Social Commitment based on locals
need and item-wise details along with time bound action plan should be prepared
and submitted to the Ministry’s Regional Office at Bangalore. Implementation of
such program should be ensured accordingly in a time bound manner.
35.2.8
Expansion of Ferro
Alloy Plant from 27 TPD to 54 TPD by installation of 1X6 MVA Submerged Arc Furnace at Sarandi Industrial Growth Centre, Tehsil Waraseoni, District Balaghat in Madhya Pradesh by M/s Ramnik Power & Alloys (P) Limited -
regarding Environmental
Clearance
The project authorities and their consultant, M/s Creative Enviro Services, Bhopal gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded during the
22nd Meeting of the Expert Appraisal Committee
(Industry-1) held on 18-19 April, 2011 for
preparation of EIA/EMP report. All the Ferro Alloy plants are listed at S.No. 3(a)
in primary metallurgical industry under Category-A of the Schedule of the EIA notification 2006 and appraised by the Expert Appraisal Committee (Industry-1) in the MoEF.
M/s Ramnik Power & Alloys Pvt. Ltd have proposed for the
expansion of existing Ferro Alloys Plant at Sarandi Industrial Growth Centre,
Sarandi, Tehsil Waraseoni, District Balaghat in Madhya
Pradesh.
The proposed expansion will be carried in the already acquired land of
10 acres within the existing plant premises, of which 33% area will be
developed under green belt. No National Park / Wildlife Sanctuary is located
within 10 km radius of the project site. One reserve forest, G F Sonawani is
located at 6 km away from the project site. Chandan River is flowing at
around 0.2 km from the project site. Waraseoni town is around 5 km from the
project site. Total cost of the proposed project is Rs.
12 Crores and total project cost for existing and proposed project is Rs 48.83 Crores.
Rs. 2.5 Crores and Rs. 1.07 Crores will be earmarked towards the total capital
cost and recurring cost/annum for environmental pollution control measures.
Following are the existing units:
Sl. No. |
UNIT |
CAPACITY |
1 |
Ferro Alloys Plant 1x6 MVA
SAF Captive Power plant Biomass
Based |
27 TPD of
Ferro Manganese and Silico Manganese 6 MW |
Following units will be
installed:
Sl. No. |
UNIT |
CAPACITY |
1 |
Ferro Alloys Plant 1x6 MVA
SAF |
27 TPD of
Ferro Manganese and Silico Manganese |
Manganese ore, Dolomite, Pet coke, Carbon paste will be used
as the major raw materials in the plant process. The estimated power
requirement for the proposed project is 12 MVA and 5.2 MW will be sourced
through captive power plant and 4.2 MW which will be sourced from the Madhya Pradesh
State Electricity Board. Raw materials and products will be transported
in covered trucks. All the trucks for raw materials and finished products
transportation will comply with the applicable environmental norms.
Ambient air quality monitoring was carried out within the study area for PM10, PM2.5,
SO2 and NOx. Values of these parameters were found ranging from
28-92 µg/m3, 5.6-18.4 µg/m3, 3-8 µg/m3 and 5-13 µg/m3 respectively. The
predicted incremental ground level concentration (GLC) due to the proposed
project for PM is 2.20 µg/m3, which is within the prescribed standards. There will be emissions during handling of raw materials and
products, which will be controlled by dust suppression system. The emissions from the production processes
will be passed through Bag filters to retain flue dust particles. The cleaned gases will be
discharged to the atmosphere through stack of adequate height of 30 mt.
Total water requirement for the proposed
expansion including domestic requirement is about 37 m3/d, which will be sourced through
bore well. The required permission has been obtained from CGWB. All the
discharges will be treated and reused in the plant resulting in Zero Discharge.
The slag generated in silico-manganese plant will be used for roads and
building construction and as filler material for fly ash bricks. Flue dust will
be sold to brick manufacturers.
The public hearing was exempted for the proposed project as
per para 7(i) III Stage (3) of EIA Notification 2006 due to the location of the
project in Notified Sarandi Industrial Growth Centre by Directorate of Industries, Govt. of Madhya
Pradesh .
The
committee was informed that SPCB has issued closure notice to the unit for
operating without environmental clearance. The PP informed that the Hon’ble
High Court of MP has stayed the said notice in the WP No. 20579/2011.
After detailed deliberation, the
Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions
along with other environmental conditions:
1. The environmental clearance is subject
to the outcome of Writ Petition No. 20579 of 2011 in the matter of M/s Ramnik
Power & Alloys (P) Ltd. vs. Union of India & Ors. in the Hon’ble High
Court of Madhya Pradesh.
2.
Compliance
to all the specific and general conditions stipulated for the existing plant by
the Central/State Government shall be ensured and regular reports submitted to
the Ministry’s Regional Office at Bhopal/SPCB.
14. At
least 5 % of the total cost of the project should be earmarked towards the Enterprise
Social Commitment based on locals need and item-wise
details along with time bound action plan should be prepared and
submitted to the Ministry’s Regional Office at Bhopal. Implementation of such
program shall be ensured accordingly in a time bound manner.
Proposals for TORs
35.2.9
Proposed Iron Ore Beneficiation (10,00,000
TPA), Iron Ore Pelletization (6,00,000 TPA), Sponge Iron (3,00,000 TPA),
Billets (3,60,000 TPA), TMT/Wire Rod Mill (2,25,000 TPA), Structural Mill
(1,20,000 TPA) along with Power Plant
(WHRB- 16 MW and FBC - 20 MW) at Sy nos. 224, 227, 231, 232, 233, 423, 424,
430, 431, 432, 452, 453, 454, 455, 457, 458, 459, 461, 462, 463, 468, 474, 475
& 476, Village Mudumalagurthy, Mandal Kodumur, District Kurnool in Andhra
Pradesh by M/s MPL Mineral Processing Pvt. Limited - regarding TORs
The project authorities
and their consultant, M/s Pioneer Enviro Laboratories & Consultants Pvt.
Ltd., Hyderabad gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP report. All the steel plants are listed at S.No. 3(a) in primary metallurgical
industry under Category-A of the Schedule of EIA Notification, 2006 and appraised by the Expert Appraisal
Committee (Industry-1) in the MoEF.
M/s
MPL Mineral Processing Pvt. Ltd. has proposed to set up a Steel Plant at
Village Mudumalagurthy, Mandal Kodumur, District Kurnool in Andhra Pradesh. The
total land envisaged for the proposed project is 150 acres and green belt will
be developed in 50 acres of plant area. No National Parks / Wild Life
Sanctuaries / Reserve Forests / Bird Sanctuaries / Eco Sensitive Areas / Tiger
Reserves/ Elephant Corridors are situated within 10 km radius of the project
site. Nearest village is Krishnapuram at 1.5 km. Hagari River (non-perennial) flows
at a distance of 0.6 Km. from the project site. A runoff drain is passing
through the site in the South East corner. No forest land is involved in the
proposed site. No litigation or court case is in pending against the project
and/or land.
Following
is the plant configuration:
S.No.
|
UNIT
|
CONFIGURATION
|
CAPACITY
|
|
1. |
Iron
Ore Beneficiation |
1
x 10,00,000 TPA |
10,00,000
TPA |
|
2. |
Iron
Ore Pelletization |
1
x 6,00,000 TPA |
6,00,000
TPA |
|
3. |
Sponge
iron (pre
Heating Technology) |
2
x 350 TPD |
3,00,000
TPA |
|
4.
|
Billets |
3
x 40 MT |
3,60,000
TPA |
|
5.
|
TMT/Wire
Rod Mill |
1
x 2,25,000 TPA |
2,25,000TPA |
|
6.
|
Structural
Mill |
1
x 1,20,000 TPA |
1,20,000
TPA |
|
7. |
Power
Generation |
WHRB
|
2
x 8 MW |
16
MW |
FBC
|
1
x 20 MW |
20
MW |
||
Total
|
36
MW |
Iron ore fines, bentonite,
limestone & coal fines for beneficiated iron ore & pelletisation &
pellet plant, coal, dolomite for sponge iron plant, sponge iron, scrap, ferro
alloy for MS billets, billets for TMT / wire rod mill and structural mill &
dolochar, coal & fines for power plant will be used as raw materials. Power requirement
will be sourced from captive power plant. DG sets will be installed. Iron ore fines will be
grinded in ball mills. The concentrate will be fed to thickener and
subsequently to filtering unit. The filter cake will be sent to pellet plant
comprising of Rotary grate kiln. Green pellets will be produced from this
process. Sponge Iron will be manufactured in coal based Direct
Reduction (DR) kilns. Billets will be manufactured by melting in
Induction furnace and casting in continuous casting machine. Rolled products
will be manufactured in TMT / wire rod mill and structural mill. Waste Heat Recovery
Boiler (WHRB) and FBC boiler will be installed.
Electrostatic precipitator will be provided to Pellet plant, DRI kiln and FBC
boiler to control particulate emissions within 50 mg/Nm3. Bag
filters will be installed to control emissions from induction furnace and
rolling mill. Flue gases for DRI plant will be utilized in Waste Heat Recovery
Boiler (WHRB) and passed through ESP and then into atmosphere through ID fans
and chimney. Hot gases from DRI plant will pass through dust settling
chamber (DSC) and after burning chamber (ABC), WHRB and stack. Fume extraction
system with ID fan will be provided to IF. Dust suppression (chemical and dry
fog type) will be provided to control emissions. Bag filters will be
provided to material handling areas, coal handling areas, crusher, stock house,
cooler discharge area, screening area etc.
Total water
required for the proposed project will be 2,593 m3/day, which will
be sourced from ground water and Hagari River. Closed loop system will be
adopted so that no effluent is discharged from the proposed plant. Only make up
water will be fed into the plant. Acidic and alkaline effluent from cation and
anion units of DM Plant will be neutralized in neutralization tank. Boiler
blow down will be neutralized in the neutralization tank before mixing with
other effluent streams. After neutralization, these two effluents will be
mixed with cooling tower blow down in a guard pond. The treated effluent will
be used for ash conditioning, dust suppression and green belt development.
Service water will be passed through oil separator to remove oil content in the
effluent. Domestic effluent will be treated in septic tank followed by
soak pit. No effluent will be discharged outside the premises and Zero
discharge will be adopted. Rain water harvesting structure will be
constructed.
Tailings from the beneficiation plant will be given to ceramic industries /
Cement Plants / other mineral based industries. Char from DRI process will be
used in FBC boiler as fuel. Dust from air pollution control devices
(APCD) will be partly used and/or in abandoned mines filling. Slag will be
crushed and after iron recovery, the inert material will be used given to brick
manufacturers. Ash from Sponge iron plant and FBC power plant will be sold
to brick manufacturers and cement units. Waste oil and used batteries
will be sold to authorized recyclers/re-processors.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study.
1.
Executive
summary of the project.
2.
Photographs
of the proposed plant area
3.
Revised
plant lay out by excluding part of the project site so that no natural drainage
passes through the project site
4.
A
line diagram/flow sheet for the process and EMP
5.
A
copy of the mutual agreement for land acquisition signed with land oustees. Break up of small, medium and large farmers
from whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
6.
Firm
Coal linkages should be submitted along with the EIA report
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
8.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
9.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
10. Location of national parks / wildlife
sanctuary / reserve forests within 10 km. radius should specifically be
mentioned. A map showing land use/land cover, reserved forests, wildlife
sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
11. Project site layout plan using AutoCAD
showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
12.
Coordinates
of the plant site as well as ash pond with topo sheet co-ordinates of the plant
site as well as ash pond with topo sheet should also be included.
13. Details and classification of total
land (identified and acquired) should be included.
14. Rehabilitation & Resettlement (R
& R) should be as per policy of the State Govt. and a detailed action plan
should be included.
15. Permission from the tribals, if tribal
land has also to be acquired along with details of the compensation plan.
16. Permission and approval for the use of
forest land, if any, and recommendations of the State Forest Department. .
17. A list of industries containing name
and type in 25 km radius should be incorporated.
18. Residential colony should be located
in upwind direction.
19. List of raw material required from
coal linkage, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
20. Petrological and Chemical analysis and
other chemical properties of raw materials used (with GPS location of source of
raw material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.), if applicable, should also be
included..
21.
Petrography,
grain size analysis and Major element analysis of raw material and soil from
project site and raw material should be done on the same parameters along with
analysis for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
22. If the rocks, ores, raw material has
trace elements their petrography, ore microscopy, XRD, elemental mapping EPMA,
XRF is required to quantify the amount present in it and hence future risk
involved while using it and management plan.
23. Action plan for excavation and muck
disposal during construction phase.
24. Studies for fly ash, muck, slurry,
sludge material disposal and solid waste generated, if the raw materials used
has trace elements and a management plan should also be included.
25. Manufacturing process details for all
the plants should be included.
26. Mass balance for the raw material and
products should be included.
27. Energy balance data for all the
components of steel plant including proposed power plant should be
incorporated.
28. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall should be collected.
29. Data generated in the last three years
i.e. air, water, raw material properties and analysis (major, trace and heavy
metals), ground water table, seismic history, flood hazard history etc.
30.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
31. Ambient air quality at 8 locations
within the study area of 10 km., aerial coverage from project site with one
AAQMS in downwind direction should be carried out.
32. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
33. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
34. Air quality modeling for steel plant
for specific pollutants needs to be done. APCS for the control of emissions
from the kiln and WHRB should also be included to control emissions within 50
mg/Nm3.
35. Action plan to follow National Ambient
Air Quality Emission Standards issued by the Ministry vide G.S.R. No. 826(E)
dated 16th November, 2009 should be included.
36. Ambient air quality monitoring
modeling along with cumulative impact should be included for the day (24 hrs)
for maximum GLC along with following :
i)
Emissions (g/second) with and without the air
pollution control measures
ii)
Meteorological inputs (wind speed, m/s), wind
direction, ambient air temperature, cloud cover, relative humidity & mixing
height using SODAR) on hourly basis
iii)
Model input options for terrain, plume rise,
deposition etc.
iv)
Print-out of model input and output on hourly
and daily average basis
v)
A graph of daily averaged concentration (MGLC
scenario) with downwind distance at every 500 m interval covering the exact
location of GLC.
vi)
Details of air pollution control methods used
with percentage efficiency that are used for emission rate estimation with
respect to each pollutant
vii)
Applicable air quality standards as per LULC
covered in the study area and % contribution of the proposed plant to the
applicable Air quality standard. In case of expansion project, the contribution
should be inclusive of both existing and expanded capacity.
viii) No. I-VII
are to be repeated for fugitive emissions and any other source type relevant
and used for industry
ix)
Graphs of monthly average daily concentration
with down-wind distance
x)
Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi)
Fugitive dust protection or dust reduction
technology for workers within 30 m of the plant active areas.
37. A plan for the utilization of
waste/fuel gases in the WHRB for generating power have to be set out.
38. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided. The alternate method of raw material and end product
transportation should also be studied and details included.
39. One season data for gaseous emissions
other than monsoon season is necessary.
40. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
41. Presence of aquifer(s) within 1 km of
the project boundaries and management plan for recharging the aquifer should be
included.
42. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included. Information regarding surface hydrology and water
regime should be included.
43. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
44. Ground water modeling showing the
pathways of the pollutants should be included
45.
Column
leachate study for all types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
46.
Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
47. Permission for the drawl of water from
the State Irrigation Department or concerned authority and water balance data
including quantity of effluent generated, recycled and reused and discharged is
to be provided. Methods adopted/to be adopted for the water conservation should
be included.
48. A note on the impact of drawl of water
on the nearby River during lean season.
49. Surface water quality of nearby River
(60 m upstream and downstream) and other surface drains at eight locations must
be ascertained.
50. If the site is within 10 km radius of
any major river, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency.
51. A note on treatment of wastewater from
different plants, recycle and reuse for different purposes should be included.
52. Provision of traps and treatment
plants are to be made, if water is getting mixed with oil, grease and cleaning
agents.
53. If the water is mixed with solid
particulates, proposal for sediment pond before further transport should be
included. The sediment pond capacity should be 100 times the transport
capacity.
54. Wastewater characteristics (heavy
metals, anions and cations, trace metals, PAH) from any other source should be
included.
55. The pathways for pollution via
seepages, evaporation, residual remains are to be studied for surface water
(drainage, rivers, ponds, lakes), sub-surface and ground water with a
monitoring and management plans.
56. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and Geo-hydrological
status of the study area are essential as also.
Ecological status (Terrestrial and Aquatic) is vital.
57. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources, char and fly ash. Copies of MOU regarding utilization of ash should
also be included.
58. Details of evacuation of ash, details
regarding ash pond impermeability and whether it would be lined, if so details
of the lining etc. needs to be addressed.
59. A note on the treatment, storage and
disposal of all type of slag should be included. Identification and details of
land to be used for SMS slag disposal should be included. Details of secured
land fill as per CPCB guidelines should also be included.
60. End use of solid waste and its
composition should be covered. Toxic
metal content in the waste material and its composition should also be
incorporated particularly of slag.
61. All stock piles will have to be on top
of a stable liner to avoid leaching of materials to ground water.
62. Action plan for the green belt
development plan in 33 % area i.e. land with not less than 1,500 trees per ha.
giving details of species, width of plantation, planning schedule etc. should
be included. The green belt should be around the project boundary and a scheme
for greening of the travelling roads should also be incorporated. All
rooftops/terraces should have some green cover.
63. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
64. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
65. Occupational health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
d)
Action plan for the implementation of OHS
standards as per OSHAS/USEPA.
e)
Plan and fund
allocation to ensure the occupational health & safety of all contract and
sub-contract workers.
66.
Details regarding infrastructure facilities such
as sanitation, fuel, restroom etc. to be provided to the labour force during
construction as well as to the casual workers including truck drivers during
operation phase.
67.
Impact
of the project on local infrastructure of the area such as road network and
whether any additional infrastructure needs to be constructed and the agency
responsible for the same with time frame.
68. Environment Management Plan (EMP) to
mitigate the adverse impacts due to the project along with item wise cost of
its implementation. Total capital cost and recurring cost/annum for
environmental pollution control measures should be included.
69. Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular
chart.
70. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
public hearing issues and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
71. Plan for the implementation of the
recommendations made for the steel plants in the CREP guidelines must be
prepared.
72. A note on identification and
implementation of Carbon Credit project should be included.
73. Any litigation pending against the
project and/or any direction/order passed by any Court of Law against the
project, if so, details thereof should also be included.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents provided are in a
language other than English, an English translation should be provided. The
draft EIA/EMP report shall be submitted to Andhra Pradesh Pollution Control
Board for public hearing. The issues emerged and response to the issues shall
be incorporated in the EIA report. The
final EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs
prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports along with public hearing proceedings.
35.2.10
Proposed expansion of Asbestos Cement
Corrugated & Plain Sheets from 200 TPD to 340 TPD at Trilokpur Road,
Village Kheri, Kala Amb, Tehsil Nahan, District Sirmour in Himachal Pradesh by M/s
Vardhman Roofing Pvt. Limited - regarding TORs
The project authorities
and their consultant, M/s Ascenso Management
and Consulting Services, Delhi gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft TORs for preparation of EIA/EMP. All the Asbestos milling and
asbestos based products are listed at S.No. 4(c) under
category-A of
the Schedule of EIA notification 2006 and appraised
by the Expert Appraisal Committee (Industry-1) in the MoEF.
M/s Vardhman Roofing Pvt. Limited have proposed for expansion of Asbestos Cement
Corrugated & Plain Sheets from 200 TPD to 340 TPD at Trilokpur Road,
Village Kheri, Kala Amb, Tehsil Nahan, District Sirmour in Himachal Pradesh. The
environmental clearance for the existing unit was accorded on 10.5.2011. The
total existing project area is 41,000 Sq.Yards and the expansion will be done
in the existing premises. The interstate boundary of Haryana is at a distance
of 5 kms.
Raw
asbestos, cement and fly ash are the raw materials that will be used. Asbestos
fiber of different grades will be imported and received in pressure packed
condition in impermeable bags in pelletized form. The existing power
requirement is 900 KW which is sourced from HPSEB and there is no increase in
power requirement for the proposed expansion. 2 nos of DG sets of capacity 250
KVA each are provided for power back up. Automatic bag opening device will be
provided. Dust collectors will be provided to various unit operations. The
water requirement for the proposed expansion is 102 KLD, which will be sourced
from ground water.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study.
1 Executive Summary of the project.
2 Photographs of the existing and
proposed plant area.
3 Compliance
to the conditions stipulated in the Environmental
Clearance / NOC granted by the SPCB. Recent monitoring report from SPCB, which
shall include data on AAQ, water quality, solid waste etc. shall be
submitted.
4 Has the unit received any notice under
the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air
and Water Acts? If so, compliance to the notice(s)
5 If the project site is located within
10 kms of Kala Amb, a severely
polluted area, the comments from Member Secretary, SPCB shall be obtained.
6 A line diagram/flow sheet for the
process and EMP
7
Modern
up-to-date Asbestos plant with automatic bag opening devices should be
installed.
8 The safety measures adopted during
import and transport of Asbestos from Canada or any other country should be
included.
9 Present land use of study area for 10
Km radius should be included. Detailed topographical map indicating drainage
pattern and other features of the area should also be included.
10 Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land viz. allotment letter should be
included.
11
High-resolution satellite image data having
1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for
the 10 km radius area from proposed site should be incorporated. The same should be used for land used /land-cover
mapping of the area.
12
Project site layout plan to scale using
AutoCAD, raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 Km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
13
Cumulative data base of last 2 yrs. for
emissions e.g. aerosols size, optical depth, CO, CO2, surface and
air temperature, NO, CH4, anions/cations/trace metals as given below
in surface/subsurface water with present GW level and its fluctuation for last
5-10 yrs from CGWB as may be applicable.
14
For the project location within 10 km radius
of any major river, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency.
15
Geo-technical data by a bore hole of upto 40
mts. in every One sq. km area such as ground water level, SPTN values, soil
fineness, geology, shear wave velocity etc. for liquefaction studies. This will
help making a future Seismic Hazard and Earthquake Risk Management area.
16 Site-specific micro-meteorological
data including inversion height and mixing height should be included
17 Details of the other industries
located in 10 km radius should be included
18 One season base line data on air,
water, soil & noise etc. should be included
19 A chapter on chemistry of asbestos,
handling of asbestos material, precautions proposed for the direct contact,
arrangements made for storage and monitoring of asbestos fibres etc. other
details as per given below:
i. Size of silica
sand, transportation, storage, spillway of melt and temperature management for
float glass and mirror Industry along with silicosis management and toxicity
studies and management for Ag etc.
ii. Source and
location of Asbestos (GPS) even if imported, size in F/ml, levels in
environment, Chemical composition of raw material as especially amount of
Tremolite, Crocidolite, Amosite and other amphiboles, Hexavalent chromium in
raw material especially in serpentine, talc and chrysotile, Electron
microscopy, XRD and Raman Spectra studies.
iii. Health
Management Plan for Mesothalmia, Lung cancer and Asbestosis related problems in
asbestos industries.
20 Petrological and Chemical analysis and
other chemical properties of raw materials used (with GPS location of source of
raw material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc.
Presence of radioactive elements (U, Th etc.),
21 Petrography, grain size analysis and
Major element analysis of raw material and soil from project site and raw
material should be done on the same parameters along with analysis for SiO2,
Al2O3, MgO, MnO, K2O, CaO, FeO, Fe2O3,
P2O5, H2O, CO2.
22 If the rocks, ores, raw material has
trace elements their petrography, ore microscopy, XRD, elemental mapping EPMA,
XRF is required to quantify the amount present in it and hence future risk
involved while using it and management plan.
23 Mode of transport of raw materials
from sources are to be shown. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”
24 Studies are also required for management
of muck disposal, slurry, sludge material and solid waste generated if the raw
materials used has trace elements and a management plan.
25 Air quality modeling for the Asbestos
handling system. Ambient air quality monitoring modelling along with cumulative
impact. Following are to be included as an annexure for the day (24 hrs)
considered for maximum GLC:
i. Emissions
(g/second) with and without the air pollution control measures
ii. Meteorological
inputs (wind speed, m/s), wind direction, ambient air temperature, cloud cover,
relative humidity & mixing height) on hourly basis
iii. Model input options for terrain, plume rise, deposition
etc.
iv. Print-out of
model input and output on hourly and daily average basis
v. A graph of
daily averaged concentration (MGLC scenario) with downwind distance at every
500 m interval covering the exact location of GLC.
vi. Details of
air pollution control methods used with percentage efficiency that are used for
emission rate estimation with respect to each pollutant
vii. Applicable
air quality standards as per LULC covered in the study area and % contribution
of the proposed plant to the applicable Air quality standard. In case of
expansion project, the contribution should be inclusive of both existing and
expanded capacity.
viii. No. I-VII
are to be repeated for fugitive emissions and any other source type relevant
and used for industry
ix. Graphs of
monthly average daily concentration with down-wind distance
x. Specify when
and where the ambient air quality standards are exceeded either due to the
proposed plant alone or when the plant contribution is added to the background
air quality.
xi. Fugitive
dust protection or dust reduction technology for workers within 30 m of the
plant active areas.
xii. Existing
stack emission data and fibre concentration in the work zone.
26 Sources of secondary emissions, its
control and monitoring as per the CPCB guidelines and latest notification vide
G.S.R. 414(E) dated 30th May, 2008 should be included.
27 Chemical characterization of RSPM and
incorporation of RSPM data. Location of one AAQMS in downwind direction.
28 Action plan to follow National Ambient
Air Quality Emission Standards issued by the Ministry vide G.S.R. No. 826(E)
dated 16th November, 2009 should be included.
29 Action plan for rainwater harvesting
measures at plant site should be submitted to harvest rainwater from the roof
tops and storm water drains to recharge the ground water and also to use for
the various activities at the project site to conserve fresh water and reduce
the water requirement from other sources.
Rain water harvesting and groundwater recharge structures may also be
constructed outside the plant premises in consultation with local Gram
Panchayat and Village Heads to augment the ground water level. Incorporation of
water harvesting plan for the project is necessary, if source of water is bore
well.
30 Actual source and permission for the
drawl of water from bore well from the SGWB/CGWA or concerned authority and
water balance data including quantity of effluent generated, recycled and
reused and discharged is to be provided. Methods adopted/to be adopted for the
water conservation should be included
31 Ground water monitoring minimum at 8
locations should be included.
32 Scheme for proper storage of asbestos
fibres and disposal of solid/hazardous waste should be included.
33
Presence of aquifer/aquifers within 1 km of
the project boundaries should be included. Management plan for recharging the
aquifer should be given so as to limit the water extraction within permissible
limit of CWC or CGWB should be included.
34
Source of surface/ground water level, site
(GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used along with a Piper and Piper Duro-V diagram. If surface water is used from
river, rainfall, discharge rate, quantity, drainage and distance from project
site should also be included.
35
Ground water analysis with bore well data,
litho-logs, drawdown and recovery tests to quantify the area and volume of
aquifer and its management should be included.
36
Ground water modeling showing the pathways of
the pollutants should be included
37
Column leachate study for all types of
stockpiles or waste disposal sites, at 20oC-50oC should
be conducted and included.
38
All samplings for water have to be done
during the peak summer time (Sampling number, dates and standard deviation
should be included.
39
Incorporation of water harvesting plan for
the project is necessary, if source of water is bore well should be ensured.
40
Provision of traps and treatment plants are
to be made, if water is getting mixed with oil, grease and cleaning agents
should be included.
41
If the water is mixed with solid
particulates, proposal for sediment pond before further transport should be
included. The sediment pond capacity
should be 100 times the transport capacity.
42
Wastewater characteristics (heavy metals,
anions and cations, trace metals, PAH) from asbestos bearing effluent should be
included.
43
The pathways for pollution via seepages,
evaporation, residual remains are to be studied for surface water (drainage,
rivers, ponds, lakes), sub-surface and ground water with a monitoring and
management plans should be included.
44
All stock piles should be on top of a stable
liner to avoid leaching of materials to ground water.
45
The green belt should be around the project
boundary in 33 % area and a scheme for greening of the traveling roads should
also be incorporated. All rooftops/terraces should have some green cover.
46 Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
47 Occupational health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
d)
Action plan for the implementation of OHS
standards as per OSHAS/USEPA.
e)
Plan and fund
allocation to ensure the occupational health & safety of all contract and
sub-contract workers.
48 Detailed action plan for compliance of
the directions (including the recent Kalyaneswari case) of the Hon’ble Supreme
Court of India regarding occupational health and safety measures in asbestos
industries should be included.
49 Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
50 Compliance to the recommendations
mentioned in the CREP guidelines should be included.
51 An action plan on entire operation
should be automatic and closed system for all operations for fibre handling and
processing should be included.
52 Details of arrangement for measurement
and monitoring of asbestos fibre (Phase contrast microscope) should be
included.
53 Detailed Environment management Plan
(EMP) with specific reference to details of air pollution control system water
& wastewater management, monitoring frequency, responsibility and time
bound implementation plan for mitigation measure should be provided.
54 EMP should include the concept of waste-minimization,
recycle/reuse/recovery techniques, Energy conservation, and natural resource
conservation.
55 EMP should include a clear map for
plantation/green belt.
56
Commitment
that laboratory for monitoring asbestos fibres will be established at the site.
57
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
58 At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
Public Hearing issues and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
59
Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It
was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the
documents provided are in a language other than English, an English translation
should be provided. The draft EIA/EMP report shall be submitted to H.P
State Pollution Control Board for public hearing. The issues emerged and
response to the issues shall be incorporated in the EIA report. The
final EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed shall be valid
for a period of two years for submission of the EIA/EMP reports, after public
consultation.
35.2.11
Proposed modernization of existing Coke Oven
Plant at Dag No. 122 & 123, Patta No. 3&9, 12th Mile, G.S.
Road, N.H. No. 40, Village Ambher, Taluk Sonapur District Kamrup in Assam by M/s
Pride Coke Pvt. Limited - regarding TORs
The project
authorities and their consultant, M/s. Kalyani Laboratories Pvt. Ltd.,
Bhubaneswar gave a detailed presentation on the salient features of the project
and proposed environmental protection measures to be undertaken along with the
draft TORs for preparation of EIA/EMP. The proposed project is a Category (B)
project as per the Schedule of the EIA notification 2006, but due to absence of
SEIAA/SEAC for Assam, the proposal has been appraised by the Expert Appraisal
Committee (Industry-1) in the Ministry.
M/s Pride Coke Pvt. Ltd. have proposed for modernization of
existing Coke Oven Plant by installing coal washing facility of 25 TPH (1,20,000
TPA) capacity considering two shift working at Dag No. 122 & 123 of Patta
No. 3 & 9, 12th Mile, G. S. Road, N. H. 40, Village, Ambher,
Taluka Sonapur, District Kamrup, Assam. No additional land will be
acquired for the proposed modernization. Existing project area is 10,063.90
sq.m. No Defense Installation, Biosphere Reserve, National Park/Wild
Life Sanctuary, Ecologically Sensitive Area exists within 10 km radius. The total
cost of the project will be Rs. 534.0 Lakhs. Rs. 10 Lakhs and Rs. 2 Lakhs will
be earmarked towards total capital cost and recurring cost/annum for
environmental pollution control measures. The project site is in Seismic
Zone-V.
In the existing coke oven plant, to manufacture 60,000 TPA
of coke (finished product) 1,20,000 MTPA of raw coal will be required. To
produce 1,20,000 MT of washed coal additional 36,000 MT of raw coal will be
required. Input coal would be obtained by trucks from privately owned mines
located in Meghalaya. The technology
used for the coal washing will be wet process technology using self generated
slurry as a media. About 36,000 TPA of rejects would be sold to local coal supplier for the use as a fuel of FBC based power
plants. An estimated 16 m3/d of water is required for the washing
unit. Manpower requirement is 12 no. Coal transportation would be by road. No
industrial wastewater shall be generated due to proposed project and the plant
would operate on a zero-discharge concept.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive summary of the project.
2. Photographs
of the existing and proposed plant area.
3. Compliance
to the conditions stipulated for existing capacity in the environmental
clearance or NOC obtained from the SPCB.
4. A line diagram/flow sheet for the
process and EMP
5.
Coal linkage documents
6. Plan for utilization of Coke oven gas
7.
Has the unit received any notice under the
Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air and
Water Acts? If so, compliance to the notice(s).
8. Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land should be included.
9.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
10. Present land use should be prepared
based on satellite imagery. High-resolution satellite image data having 1m-5m
spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the
10Km radius area from proposed site. The same should be used for land
used/land-cover mapping of the area.
11. Location of national parks / wildlife
sanctuary / reserve forests within
12. A list of industries within 10 km
radius of the plant area.
13. Details and classification of total
land (identified and acquired) should be included.
14. Project site layout plan showing raw
materials and other storage plans, bore well or water storage, aquifers (within
15. List of raw material required and
source along with mode of transportation should be included. All the trucks for
raw material and finished product transportation must be “Environmentally
Compliant”.
16. Quantification & Characterization
of solid /hazardous waste & its action plan for management should be
included.
17. Mass balance for the raw material and
products should be included.
18. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall is necessary.
19. Ambient air quality at 8 locations
within the study area of
20. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
21. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
22. Ambient air quality as per National
Ambient Air Quality Emission Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be included.
23. Air Quality Impact Predication
Modelling based on ISCST-3 or the latest
models.
24. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided.
25. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
26. Presence of aquifer/aquifers within
27. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included.
28. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
29. ‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
30. A note on the impact of drawl of water
on the nearby River during lean season.
31. Action plan for rainwater harvesting
measures.
32. Surface water quality of nearby River
(
33. If the site is within
34. Pretreatment of raw water, treatment
plant for waste water should be described in detail. Design specifications may
be included.
35. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
36. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources should also be included.
37. Identification and details of land to
be used for all type of slag disposal in the secured land fill as per CPCB
guidelines should be included.
38. End use of solid waste and its
composition should be covered. Toxic
metal content in the waste material and its composition should also be
incorporated particularly of slag.
39. Provision of Toxic Chemical
Leachability Potential (TCLP) test for the slag and its end use should be
included.
40. Action plan for the green belt
development plan in 33 % area should be included.
41. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
42. Geo-technical data by a bore hole of
upto 40 mts. in every One sq. km area such as ground water level, SPTN values,
soil fineness, geology, shear wave velocity etc. for liquefaction studies and
to assess future Seismic Hazard and Earthquake Risk Management in the area and
impacts due to land slides.
43. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
44. Occupational health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
45. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
Public Hearing proceedings and item-wise details along with time bound action
plan should be included. Socio-economic development activities need to be
elaborated upon.
46. Total capital cost and recurring
cost/annum for environmental pollution control measures should also be
included.
47. Public hearing issues raised and
commitments made by the project proponent on the same should be included
separately in EIA/EMP Report in the form of tabular chart with financial budget
for complying with the commitments made.
48. Any litigation pending against the
project and / or any direction / order passed by any Court of Law against the
project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents provided are in a
language other than English, an English translation should be provided. The
draft EIA/EMP report shall be submitted to Pollution Control Board, Assam for
public hearing. The issues emerged and response to the issues shall be
incorporated in the EIA report. The final EIA report shall be submitted to the
Ministry for obtaining environmental clearance.
The TORs prescribed shall be valid for a period of two
years for submission of the EIA/EMP reports, after public consultation.
35.2.12
Proposed 4.0 MTPA Cement Grinding Unit under
“Ash Utilization Plan” within the premises of 3X660 MW Thermal Power Plant at
Village Jodh Khansemra, Tehsil Bara, District Allahabad in Uttar Pradesh by M/s
Prayagraj Power Generation Company Limited - regarding TORs
The
project authorities and their consultant,
M/s Vimta Labs, Hyderabad, gave
a detailed presentation on the salient features of the project and proposed environmental protection measures to be
undertaken along with the draft TORs for preparation of EIA/EMP
report. All the stand alone cement grinding units are covered under
Category ‘B’ as per para 3(b) of the Schedule of the EIA notification 2006, but
due to the location of project site within 10 km of interstate boundary, the
proposal has been appraised by the Expert Appraisal Committee (Industry-1) in
the Ministry.
M/s Prayagraj Power Generation Company Limited have proposed for 4.0 MTPA
Cement Grinding Unit under “Ash Utilization Plan” ” within the premises of
3X660 MW Thermal Power Plant at Village Jodh Khansemra, Tehsil Bara, District
Allahabad in Uttar Pradesh. The environmental clearance for the 3X660 MW
Thermal Power Plant was accorded on 8.9.2009. In order to productively utilize fly ash from the power plant, 4.0 MTPA
Cement Grinding Unit is proposed to be set up. The total land requirement is 20.0 ha which is part
of 773.10 Ha of land available with power plant and is under possession. No
additional land is proposed to be acquired. No ecologically sensitive areas
such as National Park/Sanctuary/Biosphere Reserve/Historical monuments, defence
installations, etc. exist within 10 km radius of the Plant site. There is no litigation/pending case against the proposal. Cost of
project is Rs.
450.0 crores.
Two sets of high pressure roller press with ball mills would be installed
in the grinding unit to produce Portland Pozzolona Cement. The main raw
material clinker will be sourced from Jaypee group’s existing plants at Rewa /
Bela / Sidhi / Dalla. Gypsum will be sourced from Rajasthan. Proposed grinding
unit requires about 30 MW of power which will be sourced from 3x660 MW power
plant. 700 m3/day of water is required for the proposed project,
which will be sourced from the water allocated for the thermal power plant from
River Yamuna . No additional allocation of water is required.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1. Executive summary of the project.
2. Photographs of the proposed plant
area.
3. A line diagram/flow sheet for the
process and EMP
4.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
5.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
6.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
7.
Break up of small, medium and large farmers from
whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
A
list of industries within 10 km radius of the plant area.
10.
Details
and classification of total land (identified and acquired) should be included.
11.
Project
site layout plan to scale using AutoCAD showing raw materials and other storage
plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing through the project
site should be included.
12.
List
of raw materials required and source along with mode of transportation should
be included. All the trucks for raw material and finished product
transportation must be “Environmentally Compliant”.
13.
Chemical and Trace Element Analysis of coal and fly
ash
14.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
15.
Mass
balance for the raw material and products should be included.
16.
Energy
balance data for all the components of plant should be incorporated.
17.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
18.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
19.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
20.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
21.
Air
quality modeling for specific pollutants needs to be done. APCS for the control of emissions should also
be included to control emissions within 50 mg/Nm3.
22.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
23.
Air
Quality Impact Prediction Modeling based on ISCST-3 or the latest models. Mixing height shall be estimated using SODAR.
24.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
25.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
26.
Presence
of aquifer/aquifers within 1 km of the project boundaries and management plan
for recharging the aquifer should be included.
27.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used along
with a Piper and Piper Duro-V diagram.
If surface water is used from river, rainfall, discharge rate, quantity,
drainage and distance from project site should also be included.
28.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
29.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
30.
A
note on the impact of drawl of water on the nearby River during lean season.
31.
Action
plan for rainwater harvesting measures.
32.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
33.
If
the site is within 10 km radius of any major river, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency and a management plan.
34.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
35.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
36.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
37.
Action
plan for the green belt development plan in 33 % area should be included.
38.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
39.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
40.
Occupational
health:
a) Details of existing Occupational &
Safety Hazards. What are the exposure levels of above mentioned hazards and
whether they are within Permissible Exposure level (PEL). If these are not
within PEL, what measures the company has adopted to keep them within PEL so
that health of the workers can be preserved,
b) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical examinations
give the details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c) Annual report of heath status of
workers with special reference to Occupational Health and Safety.
d) Plan and fund allocation to ensure the occupational health & safety
of all contract and sub-contract workers.
41.
At
least 5 % of the total cost of the project should be earmarked towards the
Enterprise Social Commitment based on locals need and item-wise details along
with time bound action plan should be included. Socio-economic development
activities need to be elaborated upon.
42.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
43.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee (Industry-1) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents
provided are in a language other than English, an English translation should be
provided. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance. The proposal
is exempted from public hearing as per
Para 7(II) of EIA Notification 2006 due to no
additional land and water allocation requirement, use of energy efficient
technology, no clinker manufacturing at the proposed site, no sensitive area
within 10 km. radius, ‘zero’ effluent discharge, utilization of all the solid
waste in the process itself including utilization of fly ash etc. The public
hearing for the Thermal Power Plant was held on 30.5.2008.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP report.
35.2.13
Proposed 2100 TPA Low Carbon Ferro Alloy
Plant at Village Kharmangi, Tehsil Darpani District Jajpur in Odisha by M/s
National Ispat & Power Pvt. Limited - regarding TORs
The
proponent informed that they will not be able to attend the meeting. The
Committee decided to consider the project as and when requested by the
proponent.
35.2.14
Proposed 50 TPD Stand alone Clinker Grinding
Unit at plot no. G-27, RIICO Industrial Area, Village Sotanala, Tehsil Behror,
District Alwar in Rajasthan by M/s Jai Shree Krishna Cements- regarding TORs
The project authorities gave
a detailed presentation on the salient features of the project and proposed environmental protection measures to be
undertaken along with the draft TORs for preparation of EIA/EMP
report. All the stand alone cement grinding units are covered under
Category ‘B’ as per para 3(b) of the Schedule of the EIA notification 2006, but
due to the location of project site within 10 km of interstate boundary, the
proposal has been appraised by the Expert Appraisal Committee (Industry-1) in
the Ministry.
M/s Jai Shree Krishna Cements have proposed for 50 TPD Stand
alone Clinker Grinding Unit at plot no. G-27, RIICO Industrial Area, Village
Sotanala, Tehsil Behror, District Alwar in Rajasthan. The project area is 1,500
sq.m and green belt will be developed in 496.7 sq.m. There is not litigation
pending against the project. River Sabi Nadi, a seasonal River flows at a
distance of 5 km from the site. The project cost is Rs. 64.5 lakhs.
Clinker, Fly ash and Gypsum are the raw materials that
will be used. The power requirement is 200 KVA, which will be sourced from
J.V.V.N.L. Since the manufacturing process is a dry process, no water is
required for the process. The water requirement is 3 KLD for domestic use and
green belt development which will be met from RIICO water supply. The entire
process of clinker grinding is a closed loop process and there would be no
solid waste generation from the process. The dust collected from bag houses
will be reused in the process. Water sprinkling would be done on roads and raw
material handling areas.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project.
2.
Photographs
of the proposed plant area.
3.
A
copy of the Gazette Notification for the Industrial Area.
4.
A
line diagram/flow sheet for the process and EMP
5. Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land should be included.
6. A site location map on Indian map of
1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with
at least next 10 Kms of terrains i.e. circle of 10 kms and further 10 kms on
A3/A2 sheets with proper longitude/latitude/heights with min. 100/200 m.
contours should be included. 3-D view i.e. DEM (Digital Elevation Model) for
the area in 10 km radius from the proposal site.
7. Present land use should be prepared
based on satellite imagery. High-resolution satellite image data having 1m-5m
spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the
10Km radius area from proposed site. The same should be used for land
used/land-cover mapping of the area.
8. Break up of
small, medium and large farmers from whom the land is being acquired. If small
farmers are involved, a detailed R&R plan.
9. Location of national parks / wildlife
sanctuary / reserve forests within 10 km. radius should specifically be
mentioned. A map showing land use/land cover, reserved forests, wildlife
sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
10. A list of industries within 10 km
radius of the plant area.
11. Details and classification of total
land (identified and acquired) should be included.
12. Project site layout plan to scale
using AutoCAD showing raw materials and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
13. List of raw materials required and
source along with mode of transportation should be included. All the trucks for
raw material and finished product transportation must be “Environmentally
Compliant”.
14. Quantification & Characterization
of solid /hazardous waste & its action plan for management should be
included.
15. Mass balance for the raw material and
products should be included.
16. Energy balance data for all the
components of plant should be incorporated.
17. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall is necessary.
18. Ambient air quality at 8 locations
within the study area of 10 km., aerial coverage from project site with one AAQMS
in downwind direction should be carried out.
19. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
20. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
21. Air quality modeling for specific pollutants
needs to be done. APCS for the control
of emissions should also be included to control emissions within 50 mg/Nm3.
22. Ambient air quality as per National
Ambient Air Quality Emission Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be included.
23. Air Quality Impact Predication
Modeling based on ISCST-3 or the latest
models.
24. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided.
25. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
26. Presence of aquifer/aquifers within 1
km of the project boundaries and management plan for recharging the aquifer
should be included.
27. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included.
28. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
29. ‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
30. A note on the impact of drawl of water
on the nearby River during lean season.
31. Action plan for rainwater harvesting
measures.
32. Surface water quality of nearby River
(60 m upstream and downstream) and other surface drains at eight locations must
be ascertained.
33. If the site is within 10 km radius of
any major river, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency and a management plan.
34. Pretreatment of raw water, treatment
plant for waste water should be described in detail. Design specifications may
be included.
35. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
36. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources should also be included.
37. Action plan for the green belt
development plan in 33 % area should be included.
38. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
39. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
40. Occupational health:
a) Details of existing Occupational &
Safety Hazards. What are the exposure levels of above mentioned hazards and
whether they are within Permissible Exposure level (PEL). If these are not
within PEL, what measures the company has adopted to keep them within PEL so
that health of the workers can be preserved,
b) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical examinations
give the details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c) Annual report of heath status of
workers with special reference to Occupational Health and Safety.
d) Plan and fund allocation to ensure the occupational health & safety
of all contract and sub-contract workers.
41. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
locals need and item-wise details along with time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
42. Total capital cost and recurring
cost/annum for environmental pollution control measures should also be
included.
43. Any litigation pending against the
project and / or any direction / order passed by any Court of Law against the
project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee (Industry-1) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents
provided are in a language other than English, an English translation should be
provided. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance. The proposal
is exempted from public hearing by categorizing in B-2 category due to use of
energy efficient technology, no clinker manufacturing at the proposed site, no
sensitive area within 10 km. radius, ‘zero’ effluent discharge, utilization of
all the solid waste in the process itself including utilization of fly ash etc.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP report.
35.2.15
Proposed 0.1 MTPA Tunnel Kiln DRI, 4x8 T IF,
0.05 MTPA TMT Bar and 3x4500 Nm3/hr Producer Gas Plant at Village
Badapokhari, Tehsil Tangi, District Cuttack in Odisha by M/s Kashvi Power
& Steel Pvt. Limited - regarding TORs
The project authorities and their consultant, M/s Visiontek
Consultants, Bhubaneswar gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP report. All the steel plants are listed at S.No. 3(a) in
primary metallurgical industry under Category ‘A’ of
the Schedule of EIA notification 2006 and appraised
by the Expert Appraisal Committee
(Industry-1) in the MoEF.
M/s. Kashvi Power and Steel Pvt. Ltd.
has proposed for 0.1 MTPA DRI Through Tunnel Kiln, 0.1 MTPA MS Ingots, 0.05 MTPA
TMT Bars and 3x4500 M3/Hr Producer Gas Plant at Village Badapokhari,
Tehsil -Tangi, District- Cuttack, Odisha.
Total land required for the proposed plant is 16.0 acres, which is
already in the possession of the project proponent and green belt will be developed in 33% of the total plant area. The
project is located at a distance of 17.0 KM from Cuttack Town. No national
Park/wild life sanctuary is located within 10 km radius of the
project site. Total cost of the project is Rs. 74.43 Crores. Rs. 4.16 Crores
and Rs. 0.832 Crores will be earmarked towards capital cost and recurring cost per
annum for environmental pollution control measures. It
was confirmed that no litigation/court case is pending against the proposal.
Following are the details of the proposed
plants:
Sl. No. |
Unit |
Capacity |
1. |
Tunnel Kiln (3 Nos.) for production of DRI |
3 X 100 TPD ~ 0.1 MTPA |
2. |
Producer Gas Plant |
3x4500 Nm3/Hr |
3. |
M.S Ingot Plant (4x8T
IF) |
0.1 MTPA |
4. |
TMT Bar Plant (6 mm to 32
mm dia.) |
0.05 MTPA |
DRI will be manufactured
through Tunnel Kiln Technology. Producer Gas will be used as fuel in Tunnel
Kiln for sponge iron production. Iron Ore fines, Coal, Limestone and Bentonite
are the major raw materials used in the plant process. Power (17 MVA) will be
sourced from OTPCL/CESCO. The unit’s saleable product will be TMT Bars and MS
Ingots.
Major air emissions are anticipated
from operations of Furnaces & Tunnel Kiln. Bag Filter will be installed at
screen, transfer point and product screen to control fugitive dust emission.
Exhaust gas from Tunnel Kiln will pass through the Bag filter and to atmosphere
through stack. Kiln is air cooled. Re-circulated phenol water will be used for
scrubbing gas from producer gas unit which separates out the Tar in liquid form
which can burn in furnace as FO. Bag filter will be provided for coal handling
and feeding section. Bag filter will be provided at the stacks attached to
induction furnace to control PM. The plant systems
will be designed suitably to keep stack emissions to levels well below Board’s
stipulated norms.
Total water requirement
for the proposed project is of 192 m3/day. Settling tank will
be installed for the treatment of wastewater generated from different units and
the treated water will be used for dust suppression, plantation etc. There will be no
waste water from Tunnel Kiln & SMS unit. The hot water from DRI and SMS units after cooling will
be recycled to corresponding units with required quantum of makeup water.
Domestic Effluent will be treated in STP & treated water will be reused for
green belt with the help of sprinklers or water sprayers.
Char generated from Tunnel Kiln will
be reused in process and CSR. Ash from producer gas will be sold to fly ash
brick manufacturers. Slag from induction furnace shall be utilized for making
and strengthening roads both internal/external and building material. Waste
from TMT bar mill will be recycled in the process. STP sludge will be used as
manure for green belt development. Ear muffs/ear
plugs will be provided to workers working in high noise prone areas.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study.
1.
Executive
summary of the project.
2.
Photographs
of the proposed plant area
3.
A
line diagram/flow sheet for the process and EMP
4.
A
copy of the mutual agreement for land acquisition signed with land oustees. Break up of small, medium and large farmers
from whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
5.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
6.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
Project
site layout plan using AutoCAD showing raw materials, fly ash and other storage
plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing through the
project site should be included.
10. Coordinates of the plant site as well
as ash pond with topo sheet co-ordinates of the plant site as well as ash pond
with topo sheet should also be included.
11.
Details
and classification of total land (identified and acquired) should be included.
12.
Rehabilitation
& Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
13.
Permission
from the tribals, if tribal land has also to be acquired along with details of
the compensation plan.
14.
Permission
and approval for the use of forest land, if any, and recommendations of the
State Forest Department. .
15.
A
list of industries containing name and type in 25 km radius should be
incorporated.
16.
Residential
colony should be located in upwind direction.
17.
List
of raw material required from coal linkage, analysis of all the raw materials
and source along with mode of transportation should be included. All the trucks
for raw material and finished product transportation must be “Environmentally
Compliant”.
18.
If
the rocks, ores, raw material has trace elements their petrography, ore microscopy,
XRD, elemental mapping EPMA, XRF is required to quantify the amount present in
it and hence future risk involved while using it and management plan.
19.
Action
plan for excavation and muck disposal during construction phase.
20.
Studies
for fly ash, muck, slurry, sludge material disposal and solid waste generated,
if the raw materials used has trace elements and a management plan should also
be included.
21.
Manufacturing
process details for all the plants should be included.
22.
Mass
balance for the raw material and products should be included.
23.
Energy
balance data for all the components of steel plant including proposed power
plant should be incorporated.
24.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
25.
Data
generated in the last three years i.e. air, water, raw material properties and
analysis (major, trace and heavy metals), ground water table, seismic history,
flood hazard history etc.
26. One season site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall and AAQ data (except monsoon) should be collected. The monitoring
stations should take into account the pre-dominant wind direction, population
zone and sensitive receptors including reserved forests.
27.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
28.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
29.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
30.
Air
quality modeling for steel plant for specific pollutants needs to be done. APCS
for the control of emissions from the kiln and WHRB should also be included to
control emissions within 50 mg/Nm3.
31.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
32.
Ambient
air quality monitoring modeling along with cumulative impact should be included
for the day (24 hrs) for maximum GLC along with following :
i)
Emissions (g/second) with and without the air
pollution control measures
ii)
Meteorological inputs (wind speed, m/s), wind
direction, ambient air temperature, cloud cover, relative humidity & mixing
height using SODAR) on hourly basis
iii)
Model input options for terrain, plume rise,
deposition etc.
iv)
Print-out of model input and output on hourly
and daily average basis
v)
A graph of daily averaged concentration (MGLC
scenario) with downwind distance at every 500 m interval covering the exact
location of GLC.
vi)
Details of air pollution control methods used
with percentage efficiency that are used for emission rate estimation with
respect to each pollutant
vii)
Applicable air quality standards as per LULC
covered in the study area and % contribution of the proposed plant to the
applicable Air quality standard. In case of expansion project, the contribution
should be inclusive of both existing and expanded capacity.
viii)
No. I-VII are to be repeated for fugitive
emissions and any other source type relevant and used for industry
ix)
Graphs of monthly average daily concentration
with down-wind distance
x)
Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi)
Fugitive dust protection or dust reduction
technology for workers within 30 m of the plant active areas.
33.
A
plan for the utilization of waste/fuel gases in the WHRB for generating power
have to be set out.
34.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided. The alternate method of raw
material and end product transportation should also be studied and details
included.
35.
One
season data for gaseous emissions other than monsoon season is necessary.
36.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
37.
Presence
of aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
38.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
39.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
40.
Ground
water modeling showing the pathways of the pollutants should be included
41. Column leachate study for all types of
stockpiles or waste disposal sites at 20oC-50oC should be
conducted and included.
42. Action plan for rainwater harvesting
measures at plant site should be submitted to harvest rainwater from the roof
tops and storm water drains to recharge the ground water and also to use for
the various activities at the project site to conserve fresh water and reduce
the water requirement from other sources.
Rain water harvesting and groundwater recharge structures may also be
constructed outside the plant premises in consultation with local Gram
Panchayat and Village Heads to augment the ground water level. Incorporation of
water harvesting plan for the project is necessary, if source of water is bore
well.
43.
Permission
for the drawl of water from the State Irrigation Department or concerned
authority and water balance data including quantity of effluent generated,
recycled and reused and discharged is to be provided. Methods adopted/to be
adopted for the water conservation should be included.
44.
A
note on the impact of drawl of water on the nearby River during lean season.
45.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
46.
If
the site is within 10 km radius of any major river, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency.
47.
A
note on treatment of wastewater from different plants, recycle and reuse for
different purposes should be included.
48.
Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents.
49.
If
the water is mixed with solid particulates, proposal for sediment pond before
further transport should be included. The sediment pond capacity should be 100
times the transport capacity.
50.
Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from any
other source should be included.
51.
The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans.
52.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
53.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
54.
Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
55.
A
note on the treatment, storage and disposal of all type of slag should be
included. Identification and details of land to be used for SMS slag disposal
should be included. Details of secured land fill as per CPCB guidelines should
also be included.
56.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
57.
All
stock piles will have to be on top of a stable liner to avoid leaching of
materials to ground water.
58.
Action
plan for the green belt development plan in 33 % area i.e. land with not less
than 1,500 trees per ha. giving details of species, width of plantation,
planning schedule etc. should be included. The green belt should be around the
project boundary and a scheme for greening of the travelling roads should also
be incorporated. All rooftops/terraces should have some green cover.
59.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
60.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
61.
Occupational
health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
d)
Plan and fund
allocation to ensure the occupational health & safety of all contract and
sub-contract workers.
62.
Details regarding infrastructure facilities
such as sanitation, fuel, restroom etc. to be provided to the labour force
during construction as well as to the casual workers including truck drivers
during operation phase.
63. Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure needs to be constructed and the agency responsible for the same
with time frame.
64.
Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
65.
Public hearing issues raised and commitments made by
the project proponent on the same should be included separately in EIA/EMP
Report in the form of tabular chart.
66.
At
least 5 % of the total cost of the project should be earmarked towards the
Enterprise Social Commitment based on public hearing issues and item-wise
details along with time bound action plan should be included. Socio-economic
development activities need to be elaborated upon.
67.
Plan
for the implementation of the recommendations made for the steel plants in the
CREP guidelines must be prepared.
68.
A
note on identification and implementation of Carbon Credit project should be
included.
69.
Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents provided are in a
language other than English, an English translation should be provided. The
draft EIA/EMP report shall be submitted to Odisha State Pollution Control Board
for public hearing. The issues emerged and response to the issues shall be
incorporated in the EIA report. The
final EIA report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs
prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports along with public hearing proceedings.
Any
Other Item
35.2.16
Proposed
55,000 TPA High Carbon Ferro-Chrome Plant, 4,00,000 TPA Rebar Mill &
Desalination Plant at Gopalpur Villages
Chamkhandi, Sindhigaon Jagannathpur, Tehsil Chatrapur, District Ganjam, Odisha
by M/s Tata Steel
Limited - regarding Reconsideration
for EC
The above proposal was considered
and discussed in the 31st Meeting of the Expert Appraisal Committee (Industry-1)
held during 22nd & 23rd December, 2011. After
detailed deliberations, the Committee sought the following information for
re-consideration and deferred the proposal.
·
Information regarding source of coal.
·
CRZ clearance for the intake and outfall of
the sea water
·
Revised plant layout after relinquishing the
project area through which the nallah is flowing
·
Environmental Health Risk Assessment around
10 km radius as per the guidelines of OSHAS/USEPA including Hexavalent Chromium
and other toxic metals
·
Piper diagram for the surface water quality
·
Commitment for a separate truck parking area
in the plant. Measures for control of fugitive emissions due to trucks.
·
Trace Element analysis of Raw Materials. If
concentration of trace metal analysis is more, a management plan should be
submitted.
·
Disaster Management Plan for Tsunami
The above information
was submitted by the PP. The project proponent and their consultant, M/s Vimta
Labs, Hyderabad also made a presentation before EAC. After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to submission of Trace Element analysis of Raw Materials in
ppbs & Management Plan for Trace Elements in Air & Water, Environmental Health Risk Assessment around 10
km radius based on primary data and the stipulation of following specific
conditions along with other environmental conditions:
5. The total water requirement shall not
exceed 5.5 MLD. ‘Zero’
effluent discharge shall be strictly followed and no wastewater should be
discharged outside the premises.
12. At least 5 % of the total
cost of the project should be earmarked towards the Enterprise Social Commitment based on
based on Public Hearing issues and item-wise details
along with time bound action plan should be prepared and submitted to the
Ministry’s Regional Office at Bhubaneswar. Implementation of such program shall be ensured accordingly in a time
bound manner.
35.2.17
Expansion of Sponge
Iron Plant (0.39 to 0.84 MTPA) and Co-generation Power Plant ( 26 MW to 63 MW)
at Joda, Bileipada, Barbil, District Keonjhar in Orissa by M/s Tata Sponge Iron Limited - regarding
extension of validity of environmental clearance
The above proposal was considered and discussed in the 31st
Meeting of the Expert Appraisal Committee (Industry-1) held during 22nd
& 23rd December, 2011. After detailed deliberations, the
Committee sought the details regarding the Steel Plant which is being proposed
in another location to which the sponge iron will be sent. The above information was submitted by the PP.
After detailed deliberations, the committee has recommended the extension
of validity period of environmental clearance by a period of five years w.e.f 11.4.2012
subject to the specific and general environmental conditions.
35.2.18
Proposed Ferro
Alloys manufacturing unit (4x9 MVA) submerged Electric Arc Furnace for
production of 51,022 TPA of Silico-Mn, 70, 974 TPA of Ferro-Mn, 57,222 TPA of
Ferro-Chrome and 24,842 TPA of Ferro-Silicon at Sy. No. 61, 63, 67 & 68,
Village Penubarthi, Mandal Gurla, District Vizianagaram, Andhra Pradesh by M/s
Astra Ferro - Tech Pvt. Limited- regarding Reconsideration for EC
The
above proposal was considered
and discussed in the 32nd Meeting of the Expert Appraisal
Committee (Industry-1) held during 27th & 28th
January, 2012. The Committee after detailed
deliberations sought the following information for reconsideration:
·
Revised lay out plant showing the slag process area and
with water harvesting pond.
·
Chemical and Trace element analysis of Raw Materials from
Source.
·
Management plan for slag
·
Plan for Rain water harvesting for 2-3 months
·
Detailed action plan for Enterprise Social Commitment
The above information
was submitted by the PP. The project proponent and their consultant, M/s Sri Sai
Manasa Nature Tech Pvt. Ltd., Hyderabad also made a presentation before EAC. After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to submission of Management Plan for Trace Elements in Air & Water and the stipulation of
following specific conditions along with other environmental conditions:
5. The total water requirement shall not
exceed 160 KLD. ‘Zero’
effluent discharge shall be strictly followed and no wastewater should be
discharged outside the premises.
13. At least 5 % of the total
cost of the project should be earmarked towards the Enterprise Social Commitment based on
based on Public Hearing issues and item-wise details
along with time bound action plan should be prepared and submitted to the
Ministry’s Regional Office at Bangalore. Implementation of such program shall be ensured accordingly in a time
bound manner.
35.2.19
Proposed Ferro Alloy Unit (4 MVA SEAF for
production of 4,000 TPA Fe-Si or 8,000 TPA Si-Mn) along with 3.8 MW Gas based
Captive Power Plant at Dag No. 103, Village Chalakotoki, Kathalguri Panchayat, near Duliajan District
Dibrugarh, Assam by M/s Gasgen Ferro Alloys LLP- regarding Reconsideration for EC
The
above proposal was considered
and discussed in the 33rd Meeting of the Expert Appraisal
Committee (Industry-1) held during 27th & 28th
February, 2012. The Committee after detailed
deliberations sought the following information for reconsideration:
· Revised
layout plan to scale using AutoCAD with 33% green belt
· A
copy of Gazette Notification for the Notified Industrial Area
· Trace
element management plan in the solid waste
·
Flood
Hazard and Dam breakage Zonation Mapping at 1:5000 to 1;10,000 scale indicating
the peak and lean river discharge as well as flood occurrence frequency.
·
Geo-technical
data by a bore hole of upto 40 mts. in every One sq. km area such as ground
water level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies and to assess future Seismic Hazard and Earthquake Risk
Management in the area and impacts due to landslides.
The above information
was submitted by the PP. The project proponent and their consultant, M/s. Envision Enviro Engineers Pvt. Ltd., Surat also made a presentation before EAC. After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to stipulation of the following specific conditions along
with other environmental conditions:
12. At least 5 % of the total
cost of the project should be earmarked towards the Enterprise Social Commitment based on locals
need and item-wise details along with time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Shillong. Implementation of such program shall be ensured accordingly in a
time bound manner.
35.2.20
Expansion of existing induction furnace (from
40 TPD to 250 TPD/90,000 TPA ingots/ billets) along with installation of 9 MVA
SAF for manufacture of ferro Alloys 54 TPD/19,440
TPA (Ferro Manganese/Silico Manganese) at Sy. No. 439/2 & 440/2, Village
Wadiyaram, District Medak in Andhra Pradesh by M/s Mohan Steels (India) Pvt.
Ltd. - regarding Reconsideration for EC
The
above proposal was considered
and discussed in the 33rd Meeting of the Expert Appraisal
Committee (Industry-1) held during 27th & 28th
February, 2012. The Committee after detailed
deliberations sought the following information for reconsideration without
calling the Project Proponent:
·
Trace element analysis of raw materials
·
Ground water analysis after verification
·
Slag utilization Plan
·
Management plan for trace metal in the solid waste
The above information
was submitted by the PP. The project proponent and their consultant, M/s Consafe Science (India), Hyderabad
also made a presentation before EAC. After
detailed deliberation, the Committee recommended the project for environmental
clearance subject to stipulation of the following specific conditions along
with other environmental conditions:
12. At least 5 % of the total
cost of the project should be earmarked towards the Enterprise Social Commitment based on locals
need and item-wise details along with time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bangalore. Implementation of such program shall be ensured accordingly in a
time bound manner.
35.2.21
Cement Grinding
Unit (500 TPD) at Dag No. 267, 268 & 269, Patta No.38, 77, Village
Hathigaon, Mouza Borbhogia, Gaon Panchayat Kuwaritol, District Nagaon, Assam by M/s
Aditi Industries - regarding amendment
in Environmental Clearance
Environmental clearance to the above proposal was accorded
by MoEF vide letter no. J-11011/735/2009-IA II (I), dated 29th
September 2010. The PP has requested for the following amendments in the above
EC. The PP and their consultant, M/s Envision Enviro Engineers Pvt. Ltd., Surat
have also made a presentation before the committee.
1. Specific condition no. I, which
reads as under:
“Continuous stack monitoring facilities to
monitor emissions from all the stacks shall be provided. Particulate emission
shall be controlled within 50 mg/Nm3 by installing adequate air
pollution control system viz. Bag Filter and stacks of adequate height etc.
Data on ambient air, fugitive and stack emission shall be submitted to the
Ministry’s Regional Office at Shillong, Assam State Pollution Control Board
(ASPCB) and CPCB Regularly.”
It is requested to amend the condition as under.
“Particulate
emission shall be controlled within 50 mg/Nm3 by installing adequate
air pollution control system viz. Bag Filter and stacks of adequate height etc.
Data on ambient air quality, fugitive and stack emission shall be submitted to
the Ministry’s Regional Office at Shillong, Assam State Pollution Control Board
(ASPCB) and CPCB Regularly.”
The justification
for above is that, the company has proposed close circuit ball mill (C.C.B.M.)
with reverse pulse jet type bag filters at various stages of production and all
other pollution control equipments which are necessary for maintaining the
emission from the stacks are below the prescribed limits. Moreover, the unit is
very small and non polluting unit with approximate cost of Rs. 9.7 Crores at an
area of around 13,075 Sq.Mt. only and therefore continuous online stack
monitoring system for all the stacks would be very difficult and is not economically feasible.
However, the company has already implemented a periodical monitoring scheme for
regular monitoring of the stack emission by appointing a third party. Results
will be analyzed and proper action will be taken on time to time if found
necessary.
2. General Condition no. x,
which reads as under:
“As
proposed, Rs 131.71 Lacs and Rs. 42.00 Lacs shall be earmarked towards capital
cost and recurring cost/annum for environment pollution control measures to
implement the conditions stipulated by the Ministry of Environment and Forests
as well as the State Government. An implementation schedule for implementing
all the conditions stipulated herein shall be submitted to the regional office
of the Ministry at Shilong. The funds so provided shall not be diverted for any
other purpose”.
It is requested to amend the condition as under.
“As proposed, Rs 35.0 Lacs and Rs. 5.65 Lacs
shall be earmarked towards capital cost and recurring cost/annum for
environment pollution control measures to implement the conditions stipulated
by the Ministry of Environment and Forests as well as the State Government. An
implementation schedule for implementing all the conditions stipulated herein
shall be submitted to the regional office of the Ministry at Shilong. The funds
so provided shall not be diverted for any other purpose.”
The project proponent had only proposed Rs. 35.00 Lacs as capital cost for
environment pollution control measures and Rs. 5.65 Lacs towards recurring
cost/annum in all the documents submitted and the figures mentioned in the
condition is a typographical error.
After detailed deliberations, the committee has recommended for
the above amendments.
35.2.22
Expansion of Ferro
Alloy Plant (Fe-Si: 7200 TPA; Si-Mn: 17,640 TPA; Fe-Mn: 22320 TPA), Pig Iron
(25440 TPA), Ferro Chrome (16200 TPA) at Sy. No. 515/A, 516/A, 521 & 523,
Bhimaraopally Road, Village Reddipally, Mandal Chegunta, District Medak in
Andhra Pradesh by M/s GSN
Ferro Alloys Pvt. Limited- regarding amendment in environmental clearance
Environmental clearance to the above proposal was accorded
by MoEF vide letter no. J-11011/465/2009-IA II (I), dated 13th May,
2011. The PP has requested for amendments in the above EC for inclusion of 100
TPD Sinter Plant. The PP and their consultant, Global
Enviro Labs, Hyderabad have also made
a presentation before the committee.
It is submitted that the
main aim of installation of the proposed sintering plant is to utilize the
manganese fines and other solid wastes like coke fines, coal fines, lime fines
& bag filter dust etc. generated from the existing ferro alloy plant. The
additional land, water and power requirement would be 0.7 acres, 8 KLD and 500
KVA respectively. The cost for installation of the sinter plant would be Rs. 80
Lakhs. One pulse jet bag filter would be installed for the sinter plant and the
dust from bag filter will be reused in the sintering process. The flue gases
would be let out through tall chimney. The water would be used only for
maintaining the moisture and there would be no generation of wastewater.
After detailed deliberations, the committee sought the
following information for reconsideration without calling the project
proponent.
·
Exit gas analysis
·
Existing vs. new
pollution load.
·
Stack height for
sinter plant
27th April, 2012
Proposals
for Environmental Clearance
35.3.1
Expansion of Ferro Alloy Plant (Fe-Mn
& Si-Mn) by installing 5.5 MVA SAF at Mouza Nakrajoria, P.S. Salanpur,
Dist. Burdwan, West Bengal by M/s. Hira Concast Limited - regarding
Environmental Clearance
The project authorities and
their consultant,
M/s Environ India, Kolkata gave a detailed presentation on the salient features
of the project and proposed environmental protection measures to be undertaken
as per Terms of Reference (TORs) awarded during the 10th
Meeting of the Expert Appraisal Committee (Industry-1) held during 17th
– 18th May, 2010 for preparation of EIA/EMP report. The
Ferro Alloy Plants are listed at S. No. 3(a) under Primary Metallurgy
Industries under Category A of the Schedule of EIA Notification 2006 and
appraised by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Hira
Concast Limited have proposed to
expand its existing plant by installing 1 X 5.5 MVA Ferro Alloy Plant at Mouza : Nakrajoria, P.S. : Salanpur, District
: Burdwan in West Bengal. The expansion will be carried out within the existing plant
premises of 6.68 acres and green belt
will be developed in 2.20 acres. No R & R is involved. No National
Park/Wild Life Sanctuary/Reserve Forest is located within 10
km radius of the project site. Total cost of the proposed project is Rs.
10.63 Crores. Rs. 80.0 Lakhs and Rs. 10.0 Lakhs/Annum will be earmarked towards
total capital cost and recurring cost for environmental pollution control
measures. The compliance
to the conditions stipulated in the environmental clearance accorded for
existing plant on 11.12.2008 is submitted and found to be satisfactory.
Following are the details of
existing facilities and proposed facilities to be installed :
|
Units |
Existing |
Additional |
Main Plant |
Submerged Arc Furnace (SAF) |
1 X 7.5 MVA |
1 X 5.5 MVA |
Induction Furnace |
2 X 7 T |
- |
|
Installed
Capacity |
Ferro Manganese |
15,225 TPA |
12,330 TPA |
Silico Manganese |
11,455 TPA |
9,280 TPA |
|
Ingots |
53,000 TPA |
- |
Manganese ore, Fe-Mn slag, coke
breeze, quartz & dolomite will be used as raw materials. Power
requirement (Existing:14 MVA; Additional : 5.5 MVA) will be met from Damodar
Valley Corporation. DG set of capacity 1 X 250 kVA
will be installed and used during power failure only. The
manufacturing of ferro alloys will be carried out in submerged arc furnace and
the process involves feeding the raw materials into the furnace. The oxides
along with carbon will be fed to the furnace. After attaining favourable
temperatures in the furnace, the carbon will react with oxide and will
remove it from element or metal. The metal will be tapped at regular intervals
and collected in pans/moulds. After solidification of the metal, the same will
be broken to required sizes and delivered to customers.
Ambient air quality monitoring
has been carried out at 8 locations during the period March 2011 to May 2011
and the average data submitted indicate PM10 (36-72 µg/m3),
PM2.5 (22-40 µg/m3), SO2 (6-12 µg/m3) and NOx
(17-35 µg/m3) are within the permissible limits. Prediction of
Ground Level Concentrations (GLC’s) due to existing and proposed expansion has
been made by Industrial Source Complex Short Term (ISCST3) as per CPCB
guidelines and the average data submitted indicated an incremental PM10
of 1.7 µg/m3. Similarly,
average incremental PM2.5 is 1.5 µg/m3. The smoke and
fumes collected from SAF by the hood will be passed through bag filter before
discharging through a stack of adequate height. Fugitive emissions from raw
material handling section will be suppressed by dry fogging system / water
sprinkling.
Total water requirement for the
proposed plant will be 4 KLD in addition to existing consumption of 24 KLD
which will be sourced from borewell/rainwater harvesting pond. Maximum
recycling of wastewater will be done after proper treatment towards zero
discharge. Treated wastewater will be used for dust suppression and green belt
development. Effluent streams such as cooling tower blow down, floor washings,
etc. will be used for fugitive dust suppression, water sprinkling etc. Sewage
will be treated in septic tanks. Fines
and Bag Filter dust will be recycled in the process. Fe-Mn slag will be
utilized in Si-Mn production. Slag from Si-Mn production will be used in land /
road / area development / manufacturing of coloured glass / insulated bricks. All pumps and motors will be selected from less noise
generating types. Ear plugs will be provided to employees working in high noise
prone areas. DG set will be provided
with silencer.
Public hearing/Public
consultation meeting was conducted by the West Bengal Pollution Control
Board on 17.11.2011. The main issues raised in the public hearing meeting
were w.r.t. proper pollution control measures, local employment, proper
wages to workers, plantation programmes etc. which have been addressed and
included in the EIA/EMP.
After detailed deliberations, the
Committee has recommended the proposal for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
13.
At least 5 % of the total cost of
the project should be earmarked towards the Enterprise Social Commitment based on
Public Hearing issues and item-wise details along
with time bound action plan should be prepared and submitted to the
Ministry’s Regional Office at Bhubaneswar. Implementation of such program shall
be ensured accordingly in a time bound manner.
35.3.2
Expansion of the existing unit by installation of 2 X 7.5 MVA Ferro
Alloys Plant & 1 X 300 TPD Sinter Plant to manufacture Ferro Alloys and
Manganese Ore Sinter at Mouza : Nakrajoria, P.S. : Salanpur, District : Burdwan
in West Bengal by M/s Impex Steel Limited- regarding Environmental Clearance
The project authorities and
their consultant, M/s Environ
India, Kolkata gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded during the 24th Meeting of
the Expert Appraisal Committee (Industry-1) held during 19th &
20th May, 2011 for preparation of EIA/EMP. All the Ferro
Alloy Plants are listed at S. No. 3(a) under Primary Metallurgy Industries
under Category A of the Schedule of EIA Notification 2006 and appraised by
the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Impex Steel Limited have
proposed to expand its existing plant by installing 2 X 7.5 MVA Ferro Alloys Plant & 1 X 300
TPD Sinter Plant at Mouza
: Nakrajoria, P.S. : Salanpur, District : Burdwan in West Bengal. The expansion will be carried out
within the existing plant premises of 10.46 acres. Green belt will be developed
in 3.46 acres, out of total plant area of 10.46 acres. An
additional land of 2.8 acres has been taken on lease for Rainwater Harvesting
Pond & Labour Hutment. No R & R is involved. No National Park/Wild Life
Sanctuary/Reserve Forest is located within 10 km radius of the
project site. Total cost of the proposed project is Rs. 101.10 Crores. Rs. 4.2
Crores and Rs. 45 Lakhs/Annum will be earmarked towards total capital cost and
recurring cost for environmental pollution control measures.
Following are the details of
existing facilities and proposed facilities to be installed :
Main Plant |
Units |
Existing |
Additional |
Submerged Arc Furnace |
2
X 7.5 MVA |
2 X 7.5 MVA |
|
Induction Furnace |
2
X 7 T |
- |
|
Sinter Plant |
- |
1 X 300 TPD |
|
Installed Capacity |
Items |
Existing |
Additional |
M.S. Ingots |
53,004 TPA |
- |
|
Ferro Manganese
|
17,076 TPA |
31,500 TPA |
|
Silico Manganese |
11,394 TPA |
22,500 TPA |
|
Ferro Silicon |
- |
9,000 TPA |
|
Mn Ore Sinter |
- |
90,000 TPA |
Manganese ore, Fe-Mn slag, coke breeze,
quartz, dolomite, iron scrap and pet coke will be used as raw
materials. Total power requirement of 38.5 MW will be met by Damodar
Valley Corporation (DVC). DG set of capacity 1 X 250
kVA will be installed and used during power failure only. Manufacturing
of manganese Ore Sinter will be carried out in Sinter Plant. Ferro alloys will
be manufactured in submerged arc furnace and the process involves feeding the
sintered raw materials into the furnace. The oxides along with carbon will be
fed to the furnace. After attaining favourable temperatures in the furnace,
carbon will react with oxide and will remove it from element or metal. The
metal will be tapped at regular intervals and collected in pans/moulds. After
solidification of the metal, the same will be broken to required sizes and
delivered to customers.
Ambient air quality monitoring
has been carried out at 8 locations during the period March 2011- May 2011 and
the average data submitted indicate PM10 (36-72 µg/m3),
PM2.5 (22-40 µg/m3),
SO2 (6-12 µg/m3) and NOx (17-35 µg/m3)
are within the permissible limits. Prediction of Ground Level Concentrations
(GLC’s) due to existing and proposed expansion has been made by Industrial
Source Complex, Short Term (ISCST3) as per CPCB guidelines and the average data
submitted indicated an incremental PM10 of 3.4 µg/m3. Similarly, average incremental PM2.5
emission is 2.7 µg/m3. The smoke and fumes collected from SAF and
Sinter Plant by the hood will be passed through bag filter before discharging
through a stack of adequate height. Fugitive emissions from raw material
handling section will be suppressed by dry fogging system/water sprinkling.
Total water requirement for the
proposed plant will be 45 m3/day in addition to existing consumption
of 22 m3/day which will be sourced from bore well/rainwater
harvesting pond. Maximum recycling of wastewater will be done after treatment to
achieve zero discharge. Treated waste water will be used for dust suppression
and green belt development. Effluent streams such as cooling tower blow down,
floor washings, laboratory effluent etc. will be used for fugitive dust
suppression, water sprinkling etc. Plant sewage will be treated in septic
tanks. Bag filter dust will be recycled
in the process. Fe-Mn slag will be utilized in Si-Mn production. Slag from
Si-Mn production will be used in land / road / area development / manufacturing
of insulated bricks & coloured glass. Fe-Si slag will be utilized in cupola
furnace as raw material. All pumps and motors
will be selected from less noise generating types. Ear plugs will be provided
to employees working in high noise prone areas. DG set will be provided with silencer.
Public hearing/Public
consultation meeting was conducted by the West Bengal Pollution Control
Board on 16.11.2011. The main issues raised in the public hearing meeting
were w.r.t. proper pollution control measures, supply of drinking water,
local employment, plantation etc. which have been addressed and included
in the EIA/EMP.
After detailed deliberations, the
Committee has recommended the proposal for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
13.
At least 5 % of the total cost of
the project should be earmarked towards the Enterprise Social Commitment based on
Public Hearing issues and item-wise details along
with time bound action plan should be prepared and submitted to the
Ministry’s Regional Office at Bhubaneswar. Implementation of such program shall
be ensured accordingly in a time bound manner.
35.3.3
Expansion of integrated cement
plant (Clinker from 8.0 MTPA to 10.4 MTPA), Cement 8.8 MTPA, CPP: 180 MW, Waste
Heat Recovery Power: 35 MW to 45 MW along with Nimbeti Limestone Mining (750
ha, 14.4 MTPA to 17.2 MTPA) situated near Village Ras, Tehsil Jaitaran,
District Pali, Rajasthan by M/s Shree Cement Ltd. – regarding Environmental
Clearance
The project
authorities and their consultant, M/s. J.M. EnviroNet Pvt. Ltd.,
Gurgaon gave a detailed presentation on the salient features of the project and
proposed environmental protection to be undertaken as per the Terms of Reference (TORs) accorded
during the 14th
Meeting of the Expert Appraisal Committee (Industry-1) held during 23rd –
25th September, 2010 for preparation of EIA/EMP report. The
Cement Plants with production capacity > 1.0 MTPA and limestone mining projects with mining area > 50 ha are listed
at S. No. 3 (b) and 1(a) respectively under Category “A” of the Schedule of EIA
Notification 2006 and appraised by the Expert Appraisal Committee
of MoEF.
M/s Shree Cement Ltd. have
proposed for expansion of integrated cement plant (Clinker from 8.0 MTPA to
10.4 MTPA), Cement 8.8 MTPA, CPP: 180 MW, Waste Heat Recovery Power from 35 MW
to 45 MW along with Nimbeti Limestone Mining (750 ha, 14.4 MTPA to 17.2 MTPA)
situated near Village Ras, Tehsil Jaitaran, District Pali, Rajasthan. Total project area is
977.56 ha, including the existing plant area i.e. 187.56 ha,
existing ML area i.e. 750 ha & proposed colony area of 40.0 ha. No eco-sensitive areas like National Park, Wildlife Sanctuary, Biosphere
Reserve and Reserved Forest/Protected Forest exist within 10 km radius study
area of project site. The proposed expansion will be within the existing plant premises and no
additional land will be required for the proposed expansion project. Total cost
of the project is Rs. 1,230 Crores. Capital cost for environmental protection measures
is Rs. 60 Crores and Recurring Cost is Rs. 0.5 Crores/annum. The compliance to the
conditions stipulated in the environmental clearance accorded for existing
plant on 27.2.2010 is submitted and found to be satisfactory.
Details of the products along with their production capacity are given
below:
S.
No. |
Unit |
Existing EC Granted
Capacity |
Existing
Operation Capacity |
Proposed
Additional Capacity |
Total
capacity after
Expansion |
1. |
Clinker Production (MTPA) |
8.0 |
6 Units X 1.2 = 7.2 |
2 Units X 1.6 = 3.2
or 1 X 3.2= 3.2 |
10.4 |
2. |
Cement Production(MTPA) |
8.8 |
2 Units X 2.2 = 4.4 |
Nil |
8.8 |
3. |
Thermal Power Generation (MW) |
180 |
180 |
Nil |
180 |
4. |
Waste heat recovery Power Generation (MW) |
35 |
30 |
15 |
45 |
5. |
Nimbeti Limestone Mining (MTPA) |
14.4 |
12.4 |
4.8 |
17.2 |
Method of
mining is mechanized open cast involving drilling and blasting. Limestone is
transported to cement plant by Covered conveyor belt. Elevation range is 360
mRL to 440 mRL and ultimate working depth will be 75 m RL. The cement plant is based on the dry process technology for
cement manufacturing with pre-heater and pre-calciner technology. Major raw
material required for the proposed expansion of cement plant is limestone,
which will be sourced from the captive limestone mine. Other raw materials are
Gypsum & Fly ash, which are sourced from Nagaur in Rajasthan and
Suratgarh/Kota Thermal Power Plant/Chabra etc. and Pet Coke /Coal &
Laterite or Lead Zinc Slag from refinery and Chittorgarh, Bhilwara respectively
by road/rail. Existing power consumption is 80.5 MW and additional 19.9 MW
power will be required for proposed expansion and residential colony. The power
requirement will be met from the already installed 180 MW Captive Thermal Power
Plant in existing cement plant premises.
The baseline study was conducted for the project for the Post monsoon season,
2010. As per the Ambient Air Quality Monitoring carried out, in Core Zone, PM2.5
& PM10 ranges between 24.70 to 38.30 mg/m3 and 52.89 to 79.45 mg/m3, respectively. Whereas, in Buffer
Zone, PM2.5 & PM10 ranges between 18.34 to 36.12 mg/m3 and 45.98 to 75.34 mg/m3, respectively. In Core Zone, SO2
& NOx concentrations were found in the range of 6.25 to 9.23 mg/m3 and 15.20 to 19.18 mg/m3, respectively and in Buffer Zone, SO2
& NOx concentrations were found in the range of 6.12 to 9.12 mg/m3 and 13.56 to 19.12 mg/m3, respectively. Max incremental GLC for particulate
matter for proposed expansion will be 1.29 µg/m3 and the
resultant concentration is within the permissible limit.
Controlled
drilling and blasting technique is being/will be used to avoid dust generation.
Use of pollution control equipments like ESP, Bag houses and Bag filters will
maintain the dust concentration well within the prescribed CPCB Norms. All material
transfer points have been provided with bag filters to control the particulate emissions
at the source itself. Clinker & fly ash will be stored in silo
and gypsum in covered yard. Mining will
be carried above the water table and the impact on water regime is not
anticipated. There will be no discharge of mine water. There is no perennial water body within the
lease area to have any adverse impact due to the project activities.
Water requirement after proposed expansion will be 43 m3/day
(Existing 3,000 m3/day & additional 1300 m3/day) will
be sourced from ground water & mine sump. Necessary clearance has been
obtained for the same. No industrial wastewater will be generated in
the Cement Plant. Domestic wastewater generated from the Cement Plant will be
treated in the STP. The treated water will be utilized for greenbelt
development.
No solid
waste will be generated in the cement manufacturing process. Dust collected
from the various pollution control equipments will be recycled back to the
process. STP Sludge will be utilized as manure for green belt development
within the plant premises. At the
conceptual stage, total excavated area will be 425.0 ha, part of which will be
backfilled with sand/waste & will be reclaimed by plantation and rest of
the area will be converted into water reservoir.
Public hearing meeting was
conducted by the Rajasthan State Pollution Control Board on
31.1.2012. The main issues raised in the public hearing meeting were regarding pollution
control measures including noise pollution, local employment etc. which
have been addressed and included in the EIA/EMP report.
After detailed deliberations, the
Committee has recommended the proposal for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
i). The gaseous and particulate matter
emissions from various units shall conform to the standards prescribed by the
SPCB. At no time, particulate emissions from the cement plant including kiln,
coal mill, cement mill, cooler and captive power plant (CPP) shall not exceed
50 mg/Nm3.
ii).
Continuous
on-line monitors for particulate emissions shall be installed. Interlocking facility shall be provided in
the pollution control equipment so that in the event of the pollution control
equipment not working, the respective unit (s) is shut down automatically.
iii).
Data
on ambient air quality (PM10, SO2, NOx) shall be
regularly submitted to the Ministry including its Regional office located at
Lucknow and the State Pollution Control Board / Central Pollution Control Board
once in six months. Further, quality of
discharged water shall also be monitored [(TDS, DO, pH) and total Suspended
solids (TSS)]. The monitored data shall be uploaded on the website of the
company as well as displayed on a display board at the project site at a
suitable location near the main gate of the company in public domain.
iv).
Secondary
fugitive emissions shall be controlled within the prescribed limits and
regularly monitored. Guidelines / Code of Practice issued by the CPCB in this
regard shall be followed.
v).
The National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 shall be
followed.
vi).
Efforts
shall be made to reduce impact of the transport of the raw materials and end
products on the surrounding environment including agricultural land. All the
raw materials including fly ash shall be transported in the closed containers
only and shall not be overloaded.
Vehicular emissions should be regularly monitored.
vii).
The
company shall make the efforts to utilize the high calorific hazardous waste in
the cement kiln and necessary provisions shall be made accordingly. The company
shall keep the record of the waste utilized and shall submit the details to
Ministry’s Regional Office at Lucknow, CPCB and SPCB.
viii).
Rainwater
harvesting measures shall be adopted for the augmentation of ground water at
cement plant, colony including check dams at mine site. The company must also
collect rain water in the mined out pits of captive lime stone mine and use the
same water for the various activities of the project to conserve fresh water
and reduce the water requirement from the ground water. An action plan shall be
submitted to Ministry’s Regional Office at Lucknow within 3 months from date of
issue of this letter. Efforts should be made to make use of rain water
harvested. If needed, capacity of the reservoir should be enhanced to meet the
maximum water requirement. Only balance water requirement shall be met from
other sources.
ix).
Total
water requirement for the proposed expansion shall not exceed 1300
m3/day. The
water stored in the artificial reservoir made in the mine pit shall be used
maximum to reduce ground water consumption. No effluent should be discharged
from the mine to any water body or nearby River.
x).
IBM
approval for mine plan shall be submitted to
the Ministry of Environment & Forests and
its Regional Office, Lucknow
xi).
Top
soil, if any, shall be stacked with proper slope at earmarked site(s) only with
adequate measures and shall be used for reclamation and rehabilitation of mined
out areas.
xii).
The
project proponent shall ensure that no natural water course shall be obstructed
due to any mining and plant operations. The company shall make the plan for
protection of the natural water course passing through the plant and mine area
premises and submit to the Ministry’s Regional Office at Lucknow.
xiii).
The
inter burden and other waste generated shall be stacked at earmarked dump
site(s) only and shall not be kept active for long period. The total height of
the dumps shall not exceed
xiv).
The
void left unfilled shall be converted into water body. The higher benches of
excavated void/mining pit shall be terraced and plantation to be done to
stabilize the slopes. The slope of higher benches shall be made gentler for
easy accessibility by local people to use the water body. Peripheral fencing
shall be carried out along the excavated area.
xv).
Catch
drains and siltation ponds of appropriate size shall be constructed for the
working pit, inter burden and mineral dumps to arrest flow of silt and
sediment. The water so collected shall be utilized for watering the mine area,
roads, green belt development etc. The drains shall be regularly desilted,
particularly after monsoon, and maintained properly.
xvi).
Garland
drain of appropriate size, gradient and length shall be constructed for both
mine pit and inter burden dumps and sump capacity shall be designed keeping 50%
safety margin over and above peak sudden rainfall (based on 50 years data) and
maximum discharge in the area adjoining the mine site. Sump capacity shall also
provide adequate retention period to allow proper settling of silt material.
Sedimentation pits shall be constructed at the corners of the garland drains
and desilted at regular intervals.
xvii).
Dimension
of the retaining wall at the toe of inter burden dumps and inter burden benches
within the mine to check run-off and siltation shall be based on the rain fall
data.
xviii).
Regular
monitoring of ground water level and quality shall be carried out by
establishing a network of existing wells and constructing new piezometers at
suitable locations by the project proponent in and around project area in
consultation with Regional Director, Central Ground Water Board. The frequency
of monitoring shall be four times a year- pre-monsoon (April / May), monsoon
(August), post-monsoon (November), and winter (January). Data thus collected
shall be sent at regular intervals to Ministry of Environment and Forests and
its Regional Office at Lucknow, Central Ground Water Authority and Central
Ground Water Board.
xix).
Wet
drilling sequential and controlled blasting method and provision for the
control air emissions during blasting using dust collectors etc. shall be used.
The mitigative measures for control of ground vibrations and to arrest fly
rocks and boulders shall be implemented.
xx).
Bench
height, width and slope for individual bench shall be properly assessed and
implemented. Adequate measures should be adopted to stabilize the slope before
abandonment. The fencing around the reservoir should be provided to prevent
accidents.
xxi).
Action
plan for the mining, management of over burden (removal, storage, disposal
etc.), reclamation of the mined out area and mine closure should be submitted
to the Ministry and its Regional Office at Lucknow.
xxii).
As
proposed, green belt shall be developed in 33% of the plant and mine area as
per the CPCB guidelines in consultation with DFO.
xxiii). All the recommendations of the
Corporate Responsibility or Environmental Protection (CREP) for the cement
plants shall be strictly followed.
xxiv).
Vehicular
emissions shall be kept under control and regularly monitored. Measures shall
be taken for maintenance of vehicles used in mining operations and in
transportation of mineral.
xxv).
Risk
and Disaster Management Plan along with the mitigation measures should be
prepared and a copy submitted to the Ministry’s Regional Office at Lucknow,
SPCB and CPCB within 3 months of issue of environment clearance letter.
xxvi).
Final
Mine Closure Plan along with details of Corpus Fund shall be submitted to the
Ministry of Environment & Forests 5 years in advance of final mine closure,
for approval.
xxvii).
The
company shall comply with the commitments made during public hearing held on 31st
January, 2012 and a separate budget for implementing the same shall be
allocated and information submitted to the Ministry’s Regional Office at
Lucknow.
xxviii).
At
least 5 % of the total cost of the project should be earmarked towards the Enterprise
Social Commitment based on Public Hearing issues and item-wise details along with time bound action plan
shall be prepared and submitted to the Ministry’s Regional Office at Lucknow.
Implementation of such program should be ensured accordingly in a time bound
manner.
xxix).
Provision
shall be made for the housing of construction labour within the site with all
necessary infrastructure and facilities such as fuel for cooking, mobile
toilets, mobile STP, Safe drinking water, medical health care, crèche etc. The
housing may be in the form of temporary structures to be removed after the
completion of the project
35.3.4
Expansion of Polyester Chips manufacturing
from 36,000 MTPM to 49,500 MTPM and captive power generation from 4.5 MW to
10.7 MW at Plot no. 11 & 215 to 231, GIDC Estate, Sarigam, Tehsil Umargaon,
District Valsad in Gujarat by M/s JBF Industries Limited - regarding Environmental Clearance
The project authorities and their consultant,
M/s. Precitech
Laboratories, Gujarat gave a detailed presentation on the salient
features of the project and proposed environmental protection to be undertaken as per
the Terms of Reference (TORs) accorded during the 14th Meeting of the
Expert Appraisal Committee held during 16th – 17th September,
2010 for preparation of EIA/EMP report. The manmade fibres
manufacturing other than rayon are listed at S. No. 5 (d) under Category “B” of the Schedule of EIA
Notification 2006 and appraised by the SEIAA/SEAC. However, due to location of the project within 10 km of the
interstate boundary of Dadra Nagar Haveli, the proposal was kept in Category
‘A’ and appraised
by the Expert Appraisal Committee of MoEF.
M/s.
JBF Industries Ltd. have proposed for expansion
of Polyester Chips manufacturing (36,000 MTPM to 49,500 MTPM) and captive power
generation from 4.5 MW to 10.7 MW at Plot no. 11 & 215 to 231, GIDC Estate,
Sarigam, Tehsil Umargaon, District Valsad in Gujarat. The existing
plots are taken on lease from the GIDC and proposed expansion will be done on
existing land. No additional land will be required .The total plot area of the
unit is 40,867.55 M2 out of which 5,582.74 M2 will be
allotted for green belt area. The total cost of proposed project will be Rs.
43.25 crores out of which Rs. 3.02 Crores will be allocated for EHS. A
budgetary provision of Rs. 2.79 Crores per annum will be made for EHS expenses.
The Products
and Production Capacity are as follows:
Sr.
No. |
Product
Name |
Existing
Qty |
Proposed
Qty |
Total
Qty |
1. |
Polyester
Chips of various types & grades |
36,000
TPM |
13,500
TPM |
49,500
TPM |
2. |
Power
Generation for Captive requirement |
*4.5
MW |
**4.2
MW |
**8.7
MW |
*Existing
installed capacity includes 4.5 MW through gas turbine – in continuous
operation. **Proposed
installed capacity will include 2 MW Gas Engine to be in continuous
operation. The 2.2 MW FO fired Gensets will only act a standby arrangement |
The company
has 3 Nos of Thermic Fluid Heaters (TFH) each having capacity of 10 M.KCal/Hr
with 1 No of Steam Generator of 2 TPH steam generation capacity (Standby
facility), attached as an excess heat recovery system to the TFHs. It also has
installed a Gas based Turbine of 5 MW
rated capacity, with waste heat recovery (WHR) based steam generator of
capacity 4.3 TPH. Natural gas is used as a fuel in the Thermic Fluid Heaters
and Gas Turbine. For the proposed expansion, the company proposes to install 1
no. of additional Thermic Fluid Heater (10 Million KCal/Hr) – to act as standby
arrangement and a gas fire power engine of 2 MW. It also intends to re-activate
the FO based genset (as a stand-by unit) of 3.1 MVA (i.e. 2.48 MW), which was
dismantled during installation of the existing gas turbine. Natural Gas will be
used in the additional proposed Thermic Fluid Heater of 10 MK.cal/Hr, Gas
Engine of 2 MW. Apart from Natural Gas, FO will be used as fuel in the stand-by
gen set of 3.1 MVA.
The current
power requirement of 5.5 MW presently is sourced through Captive Co-generation
Heat & Power Plant (Gas Turbine with WHR system) of 4.5 MW and 1 MW from
the sanctioned capacity of 2.4 MVA (2.35 MW) from Daksin Gujarat Vij Co. Ltd.
(DGVCL). To meet the additional power requirement of 2.8 MW, power will be
sourced from installation of an additional 2 MW gas based power engine and
additional sanction of 1.6 MVA from DGVCL. As a back-up arrangement, it has
also been proposed to install an FO based generator set.
The existing
fresh water requirement is 918m3/day and the requirement after
proposed expansion will be 1,023 m3/day. The existing and proposed
source of water is GIDC Water Supply Dept. In existing plant, total domestic
wastewater generated is 46 m3/day and disposed off through septic
tank/ soak pit system and from industrial activities 544 m3/day
treated in ETP and the treated effluent will be discharged through GIDC
underground drainage from where ultimately it is conveyed into the deep Arabian
Sea. The total domestic wastewater generated after proposed expansion project of
50 m3/day will be sent to septic tank/ soak pit system. Wastewater
generated from the industrial activities of 675 m3/day will be
treated in ETP and the treated effluent @ 190 KLD will be diverted to RO
system. RO permeate @131 KLD will be recycled to the cooling tower makeup water
and RO rejects will be discharged with ETP treated water through GIDC
underground drainage from where ultimately it will be conveyed into the deep
Arabian Sea.
In the
existing operation, the hazardous waste is generated from process, ETP,
machinery and raw material consumption. ETP waste is sent to TSDF Site-VWEMCL
through SWEMCL for final disposal. Process waste (Lump waste) is sold to actual
users. Used oil from machinery is sold to registered recyclers/re-processors.
Empty containers and bags/ liners are sold to authorized scrap vendor/return
back to supplier. The same practice will be followed for additional quantity of
hazardous waste generated after the proposed expansion project.
Public
hearing is not required as the unit is located in notified industrial area.
After
detailed deliberations, the Committee has recommended the proposal for
environmental clearance subject to stipulation of following specific conditions
along with other environmental conditions:
i.
The gaseous emissions from the Thermic Fluid heater, gas based
power engine FO based genlet and gas turbine shall be dispersed through stack
of height as per the prescribed standards and emissions shall conform to the
prescribed standards.
ii.
The process emissions shall be stripped in the organic stripper and
fed to thermic fluid heater.
iv.
Gaseous emission levels including secondary fugitive emissions
from all the sources shall be controlled within the latest permissible limits
issued by the Ministry vide G.S.R. 414(E) dated 30th May, 2008 and
regularly monitored. Guidelines / Code of Practice issued by the CPCB should be
followed.
v.
The
total water requirement shall not exceed 1,023 m3/day and Permission
shall be obtained to draw the water from the ground water from the State
Ground Water Board /Central Ground Water Authority as may
be applicable to this case.
vi.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir should be enhanced to meet the maximum water
requirement. Only balance water requirement shall be met from other sources.
vii.
Risk & Disaster Management Plan along with the mitigation
measures shall be prepared and a copy submitted to the Ministry’s Regional
Office at Bhopal, SPCB and CPCB
within 3 months of issue of environment clearance letter.
viii.
As proposed, green belt shall be developed in 33 % of the plant
area. Selection of plant species shall be as per the CPCB guidelines in
consultation with the DFO.
ix.
At least 5 % of the total cost of the project shall be earmarked
towards the Enterprise
Social Commitment based on locals need and item-wise
details along with time bound action plan should be prepared and submitted to
the Ministry’s Regional Office at Bhopal.
Implementation of such program should be ensured accordingly in a time bound
manner.
35.3.5
Proposed Asbestos
Cement Sheet Plant (1,50,000 TPA) at Village Nuagaon, Tehsil Sohela, District
Bargarh in Odisha by M/s Viswakarma Roofing’s (India) Pvt. Limited - regarding Environmental Clearance
The
project authorities and their consultant, M/s Visiontek Consultancy Services Pvt. Ltd,
Bhubaneshwar, gave
a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken as per Terms of Reference
(TORs) awarded during the 18th Meeting of the Expert Appraisal Committee
(Industry-1) held during 24th – 25th January 2011 for preparation of EIA/
M/s. Viswakarma
Roofings (India) Pvt Ltd have
proposed for setting up of a green field plant for installation of 6 VAT Ludwig
Hatzchek process machines to manufacture Fully corrugated asbestos fibre cement
sheets with manufacturing capacity of 1,49,000 TPA sheets and 1,000 TPA
accessories at village Nuagaon, Tehsil Sohela, District Bargarh in the State of
Odisha. Total
project area acquired is 18.0 acres. No R & R is involved. No wild life
sanctuary/national park is located within 10 km radius of the unit. The River
in the vicinity is
Ranj River at 4 Km. Nuagaon Village, the nearest habitation is at a distance of
1.2 km and Bargarh is at a distance of 15 km. Total
cost of the project is Rs. 30 crores. Rs. 1.65 crores has been earmarked
towards total capital for environmental pollution control measures. Rs. 33 lacs
per annum have been earmarked as recurring cost/annum for environmental
pollution control measures.
Only
Chrysotile Asbestos Fiber will be used in the plant. HATZCHEK Process shall be
adopted for the manufacture. Asbestos shall be transported in HDPE Bags, shrunk
wrapped on pallets and automatic bag opener will be installed for opening of
Asbestos bags. Vacuum cleaner or wet method will be used to keep the handling
area free from Asbestos dust. Pulse jet types of bag filters will be installed
to avoid fugitive emissions. The stack with bag filters shall be of 30 m. All collected dust will be recycled back in
the process. Power requirement shall be 900 KW which will be supplied by SEB.
Two DG Sets of 750 KVA and 250 KVA shall be installed. Water requirement for
the project will be 150 m3/day which will be sourced from ground
water, clearance for which has been obtained from
Ambient air
quality monitoring in the study area and impact predictions on air quality has
been done. The results of the modeling study indicate that the maximum increase
of GLC for the proposed project is 0.18544 µg/m3 with respect to the
PM2.5 0.016540 µg/m3,
PM10 0.50890 µg/m3,
SO2 0.03157 µg/m3
NOx. The GLC predicted at all receptor locations after the proposed expansion
are well within the PM10, PM2.5, SO2 and NOx
limits prescribed in NAAQS.
Public hearing was conducted by OSPCB on 29.9.2011. The main issues raised in the
public hearing meeting were regarding pollution control measures, local
employment etc. which have been addressed and included in the EIA/EMP.
After detailed deliberations, the Committee has recommended the proposal
for environmental clearance subject to stipulation of following specific
conditions along with other environmental conditions:
i.
The project proponent shall adhere to the prescribed BIS standards
and laws regarding use and handling of asbestos, safety of employees etc. Raw
materials like asbestos fibre and cement shall be transported in closed
containers. Asbestos fibre shall be brought in pelletized form in impermeable
bags and under compressed condition.
ii.
Only Chrysotile white asbestos fibre shall be used. Blue asbestos
shall not be utilized as raw material in the manufacturing process.
iii.
There shall be no manual handling/opening of asbestos fiber bags.
The company shall install fully automatic asbestos fiber debagging system
before commissioning the unit.
iv.
Fugitive emissions shall be controlled by bringing cement in
closed tankers, fly ash in covered trucks and asbestos in impervious bags
opening inside a closed mixer. Dust collectors shall be provided to Fibre mill,
Bag opening device (BOD), Cement and Fly ash silos to control emissions. Bag filters followed by wet washer
shall be provided at automatic bag opening machine, bag shredder, fibre mill
and to cement silo to collect the dust and recycle it into the process.
Fugitive emissions generated from hopper of Jaw crusher and Pulverizer shall be
channelized through hood with proper suction arrangement, bag filter and stack.
v.
The Company shall comply with total dust emission limit of 2 mg/Nm3 as notified under the Environment
(Protection) Act, 1986. Adequate measures shall be adopted to control the
process emission and ensure that the stack emission of asbestos fibre shall not
exceed the emission limit of 0.2 fiber/cc. Asbestos fibre in work zone
environment shall be maintained within 0.1 fibre/cc.
vi.
Bags containing asbestos fibre shall be stored in enclosed area to
avoid fugitive emissions of asbestos fibre from damaged bags, if any.
vii.
Proper house keeping shall be maintained within the plant
premises. Process machinery, exhaust and ventilation systems shall be laid in
accordance with Factories Act. Better house keeping practices shall be adopted
for improvement of the environment within the work environment also. These
include:
(a) All monitoring transfer points
shall be connected to dust extraction system.
(b) Leakages or dust from machines and
ducts shall be plugged.
(c) Floor
shall be cleaned by vacuum cleaner only.
(d) Enclosed
belt conveyer shall be used instead of manual transportation of asbestos
within the premises.
viii.
Quarterly monitoring of pollutant (PM10, asbestos fibre
count) in the work zone area and stack(s) shall be undertaken by the Project
proponents. In addition, the asbestos fibre count in the work zone area shall
be monitored by an Independent monitoring agency like NIOH / ITRC / NCB or any
other approved agency and reports submitted to the Ministry’s Regional Office
at Bhubaneswar, SPCB and CPCB.
ix.
Total
water requirement from ground water shall not exceed 150 m3/day and
prior permission for the drawl of ground water from bore wells shall be
obtained from the State Ground Water Department. All the recommendations of the
State Ground Water Department, Govt. of Odisha shall be implemented in time
bound manner.
x.
As reflected in the Environmental Management Plan, all the treated
effluent shall be recycled and reused in the manufacturing process. No process
water shall be discharged outside the premises and ‘zero’ discharge shall be
maintained. All the domestic wastewater shall be treated in septic tank
followed by soak pit and used for green belt development.
xi.
The Company shall ensure that the entire solid waste generated
including process rejects, cement, fly ash, dust from bag filters and empty
asbestos bag shall be recycled back in the manufacturing process. Process
sludge shall be 100% recycled and reused in the process. Hazardous waste shall be ground in
dust proof pulverizer with integrated bag filter and recycled back to the
process. Asbestos fibres which can not be further recycled due to contamination
of iron dust shall be stored in HDPE lined secured landfill. The disposal
facilities for asbestos waste shall be in accordance with the Bureau of Indian
Standard Code.
xii.
The cut and damaged fibre bags shall immediately be repaired.
Empty fibre bags will be shredded into fine particles in a bag shredder and
recycled into the process. Piling of AC sheets shall be done in wet condition
only.
xiii.
The Company shall obtain a certificate from the supplier of
Chrysotile fibre that it does not contain any toxic or trace metals. A copy of
certificate shall be submitted to the Ministry of Environment and Forests.
xiv.
Regular medical examination of the workers and health monitoring
of all the employees shall be carried out and if cases of asbestosis are
detected, necessary compensation shall be arranged under the existing laws. A
competent occupational health physician shall be appointed to carry out medical
surveillance. Occupational health of all the workers shall be monitored for
lung function test, chest x-ray, sputum for acid-fast-bacilli (AFC) and
asbestos body (AB), urine for sugar and albumen, bloat tests for TLC, DLC, ESR,
Hb and records maintained for at least 40 years from the beginning of the
employment or 15 years after the retirement or cessation of employment
whichever is later. Occupational Health Surveillance shall be carried out as
per the directives of the Hon’ble Supreme Court including the recent Kalyaneswari case.
xv.
To educate the workers, all the work places where asbestos dust
may cause a hazard shall be clearly indicated as a dust exposure area through
the use of display signs which
identifies the hazard and the associated health effects.
xvi.
The company shall also undertake rain water harvesting measures
and plan of action shall be submitted to the Ministry of Environment and
Forests within three months.
xvii.
All
the commitments made to the public during the Public Hearing / Public
Consultation meeting held on 29th September, 2011 shall be satisfactorily implemented and a separate budget for
implementing the same should be allocated and information submitted to the
Ministry’s Regional Office at Bhubaneswar.
xviii.
Green
belt shall be developed in at least 33 % of plant area as per the CPCB
guidelines in consultation with the DFO.
xix.
At
least 5 % of the total cost of the project should be earmarked towards the
Enterprise Social Commitment based on Public Hearing issues and item-wise
details along with time bound action plan should be prepared and submitted to
the Ministry’s Regional Office at Bhubaneswar. Implementation of such program
should be ensured accordingly in a time bound manner.
35.3.6
Proposed 0.3 MTPA Integrated Steel Plant at
Village Malda, Dhanurjayapur, Tehsil Barbil, District Keonjhar, Orissa by M/s
Arya Integrated Steel Private Limited - regarding Environmental Clearance
The project authorities along with their
environmental consultant, M/s. S. S. Environics (India) Pvt. Ltd., Bhubaneswar
gave a detailed presentation on the salient features of their proposal along
with proposed
environmental protection measures to be undertaken as per Terms of References (TORs) issued
during the 21st meeting of
Expert Appraisal Committee (Industry-1) held during 25th – 26th
March, 2011 for preparation of EIA/EMP. All the Integrated Steel Plants are
listed at S. No. 3(a) under Primary Metallurgy Industry of the Schedule of EIA
Notification 2006 under Category’ A’ and appraised by
the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Arya Integrated Steel Private Limited have proposed for 0.3 MTPA
Integrated Steel Plant at Village Malda, Dhanurjayapur, Tehsil Barbil, District
Keonjhar, Orissa The proposed project is a green-field
project over an area of 157 acres and an area of 51.8 acres has
been earmarked for green belt development. Additionally, 30
acres of area has been earmarked adjacent to the project site along the East
Coast Railway Line for setting up own railway siding. No national park, wildlife sanctuary, biosphere reserve etc. exist
within 10 Km radius of the project site. Total project cost is Rs. 546.38 Crores and capital cost of Rs. 27.0 Crores is
earmarked for Environmental Protection Measures.
The following facilities would be
installed:
Ø 1X1.8 MTPA Throughput Iron Ore
Beneficiation Plant
Ø 2X1.2 MTPA Iron Ore Pellet Plant
Ø 9 No. of Producer Gas Plant of capacity
4,500 Nm3/hr each (total 40,500 NM3/hr)
Ø 0.3 MTPA Integrated Steel Plant (HGPIN
Plant -0.3 MTPA; SMS-0.3 MTPA; Rolling Mill-0.2 MTPA)
Raw
materials required will be low grade Iron Ore (18,00,000 TPA) & Iron Ore
Fines (13,50,000 TPA) from local mines, Anthracite Coal (1,70,000 TPA) to be
imported from Russia/South Africa,
Bituminous Coal (1,35,000 TPA) to be sourced from coalfields in Orissa
through open market, Scrap (25,000 TPA) from local vendors, Bentonite (1,68,000
TPA) from Local vendors, Silico Manganese (3,000 TPA) from local ferro alloy
plants, limestone (20,000 TPA) and Dolomite (15,000 TPA) from nearby mines in
Sundargarh District. Power requirement for the proposed plant will be 47 MVA and will be
sourced from NESCO.
Baseline data was collected during
summer season (March to May 2011). Ambient air quality was monitored at eleven
(11) locations with respect to PM10, PM2.5, SO2,
NOX, CO. The AAQ analysis indicates that the concentration of PM10
varies in the range of 37-92 µg/m3, PM2.5 in the
range of 24-53 µg/m3, SO2 in the range of 4.0-18.30 µg/m3, NOX in
the range of 9.0-18.90 µg/m3,
CO in the range of 0.125-0.19 mg/m3.
All these values are within the NAAQS. Prediction of Ground Level
Concentrations (GLCs) due to proposed expansion has been made by Industrial
Source Complex, Short Term (ISCST3) model as per CPCB guidelines, which
indicated an incremental of 5.13209 µg/m3, 4.76973 µg/m3,
10.51421
µg/m3 and 12.53812
µg/m3 for PM10, PM2.5,
SO2 and NOx respectively. Predicted GLCs of pollutants
after implementation of the proposed project are within NAAQS.
Dry fog System will be installed at dust generating points in
Beneficiation Plant, Bag filters will be installed at Coal Pulverizing Unit,
Proportionate building, Dryer for pellet plant, ESP will be installed at Grate
kiln of Pellet plant, Bag Filters will be installed in HGPIN Plant, Bag House
will be installed in Induction Furnace and ESP will be installed in PGP to
control the particulate emissions.
Water requirement of 1,774 m3/day
will be sourced from the River Baitarani. Water samples were
collected from nineteen locations, surface water ten locations and ground water
nine locations. The values indicate that the water quality of the study area
conforms the IS 2296 under Class-C and IS-10500 for surface and ground water
respectively. Zero discharge concept will be adopted in the proposed steel
plant. The generated wastewater from the process will be recycled and reused in
the plant process. Wastewater from STP and water treatment plant will be used
in greenbelt development after proper treatment.
Tailings from the beneficiation plant will be disposed in the
designated tailing area, in cake mode with future proposition of quarry filling
/ further value addition. No solid waste will be generated from the pellet
plant. Generated dust from the pellet plant will be reused in the process
again. Ash generated from the HGPIN Plant will be consumed in the pellet plant.
Slag generated from the SMS will be used in internal Road Making & Low land
filling after metal recovery. Rolling Mill scales / scraps will be reused in
induction furnace. Ash from PGP will be used in Pellet Plant. STP Sludge will
be used as manure in greenbelt development. Proper mitigation measures will be
taken to control the generating noise at the source. The noise level will be
restricted within very short distance from the source and will be kept less
than 85 dB(A) at a distance of 1 m from the equipment/machinery and less than
75 dB(A) at the boundary of the plant.
Public hearing was conducted by OSPCB on 28.3.2012. The main issues raised in the
public hearing meeting were regarding local employment and CSR activities which
have been addressed and included in the EIA/EMP.
After detailed deliberations, the Committee has recommended the proposal
for environmental clearance subject to submission
of revised
plant lay out so as not to disturb the nalah flowing through the project site
by leaving 10 m width of area adjacent to the nalah, which shall be developed
into green belt and stipulation of following specific conditions along with other
environmental conditions:
i.
Measures
shall be taken to control PM levels
in the ambient air. On-line ambient air quality monitoring and continuous stack
monitoring facilities for all major stacks shall be provided and sufficient air
pollution control devices viz. Electrostatic precipitator (ESP), gas cleaning
plant, venturi scrubber, bag
filters etc. shall be provided to keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
ii.
Fume
extraction system shall be provided to induction furnaces to control the
emissions within the prescribed standards.
iii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iv.
Gaseous emission levels including secondary fugitive emissions from all the sources shall be
controlled within the latest permissible limits issued by the Ministry and
regularly monitored. Guidelines/Code of Practice issued by the CPCB shall be
followed.
v.
Total
water requirement from River Baitarani shall
not exceed 1,774 m3/d. Efforts shall further be made to use maximum
water from the rain water harvesting sources.
All the effluent should be treated and used for ash handling, dust
suppression and green belt development. No
effluent shall be discharged and ‘zero’ discharge shall be adopted. Sanitary
sewage should be treated in septic tank followed by soak pit.
vi.
Efforts
shall be made to make use of rain water harvested. If needed, capacity of the
reservoir should be enhanced to meet the maximum water requirement. Only
balance water requirement shall be met from other sources.
vii.
Regular monitoring of influent and effluent
surface, sub-surface and ground water (including chromite) should be ensured
and treated wastewater should meet the norms prescribed by the State Pollution
Control Board or described under the E(P) Act whichever are more stringent.
Leachate study for the effluent generated and analysis shall also be regularly
carried out and report submitted to the Ministry’s Regional Office at Bhubaneswar, SPCB and CPCB.
viii.
The water consumption shall not
exceed as per the standard prescribed for the steel plants.
ix.
Scrap shall be used in steel melting
shop (SMS) and SMS slag and kiln accretions shall
be properly utilized. All the other solid waste including broken
refractory mass shall be properly disposed off in
environment-friendly manner.
x.
Vehicular pollution due to
transportation of raw material and finished products shall be
controlled. Proper arrangements shall also be made to control dust
emissions during loading and unloading of the raw material and finished
product.
xi.
All internal roads shall be black
topped. The roads shall be regularly cleaned with mechanical sweepers. A 3-tier
avenue plantation using native species shall be developed along the roads
xii.
Proper handling, storage,
utilization and disposal of all the solid waste shall be ensured and regular
report regarding toxic metal content in the waste material and its composition,
end use of solid/hazardous waste should be submitted to the Ministry’s Regional
Office at Bhubaneswar,
SPCB and CPCB.
xiii.
A time bound action plan shall be
submitted to reduce solid waste, its proper utilization and disposal.
xiv.
Risk and Disaster Management Plan
along with the mitigation measures shall be prepared and a copy submitted to
the Ministry’s Regional Office at Bhubaneswar,
SPCB and CPCB within 3 months of issue of environment clearance
letter.
xv.
As proposed, green
belt shall be developed in 33 % of plant area as per the CPCB guidelines in
consultation with the DFO.
xvi.
All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the
Steel Plants should be implemented.
xvii.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 28th March, 2012 should
be satisfactorily implemented and a
separate budget for implementing the same should be allocated and information
submitted to the Ministry’s Regional Office at Bhubaneswar.
xviii.
At least 5 % of the total cost of
the project should be earmarked towards the Enterprise Social Commitment (ESC) based on Public
Hearing issues and item-wise details along with time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at Bhubaneswar.
Implementation of such program should be ensured accordingly in a time bound
manner.
xix.
Rehabilitation and Resettlement Plan for
the project affected population including tribals, if any shall be implemented
as per the policy of the State Govt. in consultation with the State Govt. of
Orissa. Compensation paid in any case should not be less than the norms
prescribed under the National Resettlement and
Rehabilitation Policy, 2007.
xx.
The company shall provide housing
for construction labour within the site with all necessary infrastructure and
facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking
water, medical health care, crèche etc. The housing may be in the form of
temporary structures to be removed after the completion of the project.
35.3.7
Proposed expansion of Cement grinding
capacity from 2.2 MTPA to 3.0 MTPA at Village Ghurdang, Tehsil Raghuraj Nagar,
District Satna, Madhya Pradesh by M/s Birla Corporation Limited - regarding Environmental Clearance
The project authorities along with their
environmental consultant, M/s. J.M.
EnviroNet Pvt. Ltd., Gurgaon gave a detailed presentation on the salient features of their proposal
along with proposed
environmental protection measures to be undertaken as per Terms of References (TORs) issued
during the 30th
Meeting of the Expert Appraisal Committee (Industry-1) held during 28th
& 29th November, 2011 for preparation of
EIA/EMP. Although the proposed expansion project activity falls under Category B
of the Schedule of
EIA Notification, 2006, since it is an expansion of a Category A project, the proposal is appraised by
the Expert Appraisal Committee (Industry-1) of MoEF.
M/s.
Birla Corporation Limited (BCL) has an existing Integrated Cement Plant having
Clinker production capacity of 3.4 MTPA, Cement production capacity 2.2 MTPA,
Captive Power Plant (27 MW) & WHRB (19.5 MW) at Village Ghurdang along with Sagmania Limestone Mine
(ML area: 939.78 ha) with limestone production capacity of 4.9 MTPA and Birhuli
Limestone Mine (ML area: 56.2 ha) with limestone production capacity of 0.6
MTPA at Tehsil - Raghuraj Nagar, District – Satna (Madhya Pradesh). BCL
has now proposed for
Expansion of Cement Plant (Cement Grinding Capacity from 2.2 MTPA to 3.0 MTPA)
within its existing plant premises at Village Ghurdang, Tehsil - Raghuraj
Nagar, District – Satna (Madhya Pradesh). Total Plant
area is 499.87 acres. Since, the proposed expansion will be within the existing
plant premises, no additional land will be required for the proposed expansion
project. Out of the total plant area, green
belt has already been developed on 152 acres area (30.41% of the total plant
area) and additional 20 acres area (4%)
will also be developed as green belt area. No
Eco-sensitive area such as National Park, Wildlife Sanctuary, Biosphere
Reserve, Tiger Reserve etc. falls within 10 km radius study area. Two Reserved
Forests and one Protected Forest fall within 10 km radius study area. Total
cost of the project is Rs. 135 Crores. Capital cost for Environmental
Protection Measures is Rs. 3.58 Crores and Recurring Cost is Rs. 54.0
Lacs/annum.
Details of the
products along with their production capacity are given below:
Details |
Existing Capacity |
Proposed Expansion Capacity |
Total Capacity After Expansion |
Cement |
2.2 MTPA |
0.8 MTPA |
3.0 MTPA |
Clinker |
3.4 MTPA |
Nil |
3.4 MTPA |
CPP |
27 MW |
Nil |
27 MW |
WHRS |
19.5 MW |
Nil |
19.5 MW |
Compliance to the conditions stipulated
in the Consent to Operate from the SPCB dated 29.4.2011 was
submitted and found to be satisfactory. The cement plant is based on the dry process technology for cement
manufacturing with pre-heater and pre-calciner technology. Raw materials required for the proposed expansion of Cement Plant are
Clinker, Gypsum & Fly ash, which will be procured from the Captive Plant, Rajasthan State Minerals -Kanasar, Tahiyathamira and
Own TPP, Unchahar, Pali, Birsinghpur, Hindalco, Renusagar, Vindhya Nagar,
respectively. Power required for the proposed expansion project is 7.5 MW.
Existing power requirement for the Cement Plant is 53.5 MW. The source of power
is Captive Power Plant, WHRS & M.P. State Electricity Board.
Ambient Air Quality
Monitoring carried during the winter season reveals that the concentrations of
PM10 and PM2.5 for all the 8 AAQM stations were found
between 45.64
to 80.49 mg/m3
and 23.50 to 38.54 mg/m3
respectively. The concentrations of SO2 and NO2 were
found to be in range of 6.68 to 11.42 mg/m3 and
11.54 to 23.50 mg/m3 respectively.
Prediction of maximum incremental GLCs has been done
for the proposed expansion of cement production capacity only. The maximum GLC
predicted for Particulate Matter is 1.62 µg/m3 at a distance of 700
m from the source in SE direction. All major sources
of air pollution will be provided with Bag Houses/Bag filters & ESP to
maintain the PM emission level below 50 mg/Nm3 to control particulate emissions. All
material transfer points is being / will be provided with bag filters to entrap
the emissions at the source itself. Clinker & fly ash is being / will be
stored in silo and gypsum in covered yard.
Water requirement for proposed expansion project is
576 m3/day. Existing water requirement is 2,255 m3/day. Source of
water will be Captive Mine Reservoirs near the plant site. No ground water will
be withdrawn for the project activity. No industrial waste water will be generated
in the Cement Plant. Domestic waste water generated from Cement Plant will be
treated in STP. The treated water will be utilized for greenbelt development, dust
suppression etc. Rain water harvesting structures will be constructed. No solid
waste is being / will be generated in the cement manufacturing process. Dust
collected from various pollution control equipments is being / will be recycled
back to the process. STP Sludge is being / will be utilized as manure for
greenbelt development.
The proposal was exempted from
public hearing by categorizing in B-2 category due to use of energy efficient
technology, no clinker manufacturing at the proposed site, no sensitive area
within 10 km. radius, ‘zero’ effluent discharge, utilization of all the solid
waste in the process itself including utilization of fly ash etc.
The Committee recommended the proposal for environmental clearance
subject to submission of revised
layout plan to scale using AutoCAD, RSPM characterization as per the latest AAQ
parameters, detailed existing & proposed OHS programme. The requisite
information was furnished:
i.
Particulate emissions shall be controlled
within 50 mg/Nm3 by
installing adequate air pollution control system viz. Bag filters and stacks of adequate
height etc. Data on ambient air, fugitive and stack emissions
shall be submitted to the Ministry’s Regional Office at Bhopal, SPCB and CPCB
regularly.
ii.
The National Ambient Air Quality Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be followed.
iii.
Gaseous emission levels including secondary fugitive emissions from all the sources shall be
controlled within the latest permissible limits issued by the Ministry and
regularly monitored. Guidelines/Code of Practice issued by the CPCB should be
followed.
iv.
The company shall install adequate dust
collection and extraction system to control fugitive dust emissions at various
transfer points, raw mill handling (unloading, conveying, transporting,
stacking), vehicular movement, bagging and packing areas etc. All the raw
material stock piles should be covered. A
closed clinker stockpile system shall be provided. All conveyers should be covered with
GI sheets. Covered sheds for storage of raw materials and fully covered
conveyers for transportation of materials shall be provided besides cement, fly
ash and clinker shall be stored in silos. Pneumatic system shall be used for fly
ash handling.
v.
Asphalting/concreting of roads and water spray all around the
stockyard and loading/unloading areas in the cement plant shall be carried out
to control fugitive emissions. Regular water sprinkling shall be carried out in
critical areas prone to air pollution and having high levels of SPM and RSPM
such as haul road, loading and unloading points, transfer points and other
vulnerable areas. It shall
be ensured that the ambient air quality parameters conform to the norms
prescribed by the Central Pollution Control Board in this regard.
vi.
Measures shall be undertaken to reduce impact of the transport of
the raw materials and end products on the surrounding environment including
agricultural land. All the raw materials including fly ash should be
transported in the closed containers only and should not be overloaded. Vehicular
emissions should be regularly monitored.
vii.
Total ground water requirement for the cement plant shall not
exceed 576 m3/day and necessary permission for the drawl shall be obtained.
All the treated wastewater should be recycled and reused in the process and/or
for dust suppression and green belt development and other plant related
activities etc. No process wastewater shall be discharged outside the factory
premises and ‘zero’ discharge should be adopted.
viii.
Efforts shall be made to make use of rain water harvested. If
needed, capacity of the reservoir shall be enhanced to meet the maximum water
requirement. Only balance water requirement shall be met from other sources.
ix.
All the bag filter dust, raw meal dust, coal dust, clinker dust
and cement dust from pollution control devices should be recycled and reused in
the process used for cement manufacturing.
Spent oil and batteries should be sold to authorized recyclers /
reprocessors only.
x.
Green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
xi.
At least 5 % of the total cost of the project shall be earmarked
towards the Enterprise
Social Commitment based on locals need and item-wise
details along with time bound action plan should be prepared and submitted to
the Ministry’s Regional Office at Bhopal.
Implementation of such program should be ensured accordingly in a time bound
manner.
35.3.8
Expansion of 60,000 TPA Sponge Iron Plant
into 0.5 MTPA Integrated Steel Plant at Village Balanda, Tehsil Kalunga,
District Sundargarh in Odisha by M/s Jay Iron & Steel Limited -
regarding Environmental Clearance
The project
authorities along with their environmental consultant, M/s. S. S. Environics
(India) Pvt. Ltd., Bhubaneswar gave a detailed presentation on the salient
features of their proposal along with proposed environmental protection measures to be undertaken as per
Terms
of References (TORs) issued during 83rd
Meeting of the Expert Appraisal Committee (Industry) held
during 14th -16th July, 2008 for preparation of EIA/EMP.
All the Integrated Steel Plants are listed at S. No. 3(a) under Primary
Metallurgy Industry of the Schedule of EIA Notification 2006 under Category’ A’
and appraised by the Expert Appraisal Committee
(Industry-1) of MoEF.
M/s
Jay Iron & Steel Limited have proposed for expansion of 60,000
TPA Sponge Iron Plant into 0.5 MTPA Integrated Steel Plant at Village Balanda,
Tehsil Kalunga, District Sundargarh in Odisha. The existing plant is spread over an
area of 17.6 acres & proposed expansion requires additional 319 acres of
land. Out of total land of 337 acres, 82.6 acres is under possession, which is
adequate for phase-I and II. Balance land is under active stage of acquisition
with IDCO for establishment of phase-III. Total area of 111 acres
has been earmarked for green belt development. No
national park, wildlife sanctuary, biosphere reserve etc. exist within 10 Km
radius of the project site. Total project cost is Rs. 1,500 crores. Cost towards environmental protection is Rs. 104.05
crores.
The configuration of
the plant after expansion is mentioned hereunder:
Sl. No |
Facilities |
Existing |
Expansion |
Total |
||
Phase I |
Phase II |
Phase III |
||||
1. |
Sponge
Iron Plant |
2 X 100 TPD (60,000 TPA) |
1X100 TPD (30,000 TPA) |
2X350 TPD (2X1,15,000 TPA) |
-- |
3,20,000 TPA |
2. |
Iron
Ore Crusher (TPD) |
1200 |
-- |
1200 |
-- |
2400 |
3. |
CPP v WHRB v FBB |
-- -- |
6 MW 12 MW |
14 MW 36 MW |
-- -- |
20 MW 48 MW |
4. |
Coal
Washery |
-- |
-- |
150 TPH (3X50 TPH module) (0.80 MTPA Throughput) Washed Coal=4,80,000 TPA, Dust & Rejects =3,20,000 TPA |
-- |
150 TPH |
5. |
Ferro Alloys Furnace (Fe-Mn/Si-Mn) |
-- |
5 MVA |
-- |
-- |
8,500 TPA |
6. |
Mini
Blast Furnace (Hot Metal / Pig Iron) |
-- |
-- |
-- |
450 m3 |
450 m3 (0.296 MTPA) (Hot Metal: 0.253 MTPA Pig Iron: 0.043 MTPA) |
7. |
Pig
Casting Machine (PCM) |
-- |
-- |
-- |
200 TPD |
200 TPD |
8. |
Sinter
Plant |
-- |
-- |
-- |
60 m2 (0.52 MTPA) |
60 m2 (0.52 MTPA) |
9. |
Pelletization
Plant |
-- |
-- |
0.66 MTPA |
-- |
0.66 MTPA |
10. |
SMS-I (Steel
Billets) |
-- |
3X12T IF (1X12T Stand By) 2X12T LRF CCM(1X2 strands) |
3X12T IF (1X12T Stand By) 2X12T LRF,AOD/VD CCM(1X2strands) |
-- |
0.136 MTPA |
11. |
SMS-II
(Steel Billets) |
-- |
|
|
2X35T EAF 1X35T LRF,AOD/VD CCM(1X2strands) |
0.382 MTPA |
12. |
Rolling
Mill Rounds,
Bars, Rods & Structurals / Seam less pipe plant |
-- |
-- |
-- |
0.5 MTPA |
0.5 MTPA |
Iron ore required for
the plant will be sourced from mines of Barbil/Koida region. Raw materials for
other units i.e. pellet, washed coal, ferroalloy, sponge iron, pig iron and
sinter will be sourced from captive units within the plant. Dolomite will be sourced
from mines of Sundargarh District. Mn ore will be sourced from Joda, Quartzite
will be sourced from Jashipur and Mayurbhanj district of Odisha. Coke will be
either imported or will be sourced from Tangi/Jagatpur/Kalinganagr-Duburi area.
Initially, coal will be imported till getting sourcing arrangement from Indian
coal fields. The finished product
will be transported by rail/road. Coal linkage
for imported coal from Russia was submitted. Power requirement of the proposed
expansion is 67.3 MW, which will be sourced from CPP.
Baseline data from
December 2008 to February 2009 was presented along with baseline data collected
during December 2011 to February 2012. The recent data shows that the AAQ
monitoring has been carried out at eleven (11) locations for PM10, PM2.5, SO2, NOX,
CO, O3, Ni, Pb, As, NH3, Benzene, Benzo (a) Pyrene. PM10
was found in the range of 23 to 88 µg/m3, PM2.5
in the range of 15 to 56 µg/m3, SO2
in the range of 4.0 to 14.2 µg/m3, NOx in the
range of 9.0 to 17.4 µg/m3, CO in the
range of 0.10 to 0.15 mg/m3, Ozone from 5 to 6.6 µg/m3, NH3 in the range of 20.0
to 29.7 µg/m3, benzene in
the range of 0.1 to 0.29 µg/m3, Benzo (a)
pyrene in the range of 0.1 to 0.17 ng/m3, Ni < 1 ng/m3,
Pb < 0.1 µg/m3 and As <
1 ng/m3. All the parameters monitored are within the NAAQS. Prediction of Ground Level Concentrations (GLCs) due to
proposed expansion has been made by Industrial Source Complex, Short Term
(ISCST3) as per CPCB guidelines, which indicated
an incremental GLC
of 8.28281 µg/m3 for PM10, 4.51480 µg/m3 for PM2.5, 20.22676 µg/m3 for SO2, 11.03629 µg/m3 for NOx and 5.49407 µg/m3 for CO. Predicted GLCs of pollutants after implementation of the proposed
project are within NAAQS.
Air pollution control devices i.e. Bag filter,
ESPs, multicyclone, scrubber, dust catcher, water sprinklers etc. will be
installed at respective plant units to control the air pollution within the
norms. Waste gas from DRI kilns will be
utilized in WHRB to generate power. BF off gas will be partly utilized for BF
stove heating and balance will be utilized for drying in sinter & pellet
plant and preheating of ladle in SMS. Water
requirement for the proposed expansion is 390 m3/hr which will be
sourced from Sankh River/Kalunga nala. Water from cooling tower will be
re-circulated with make-up water. Blow down from different units will be
treated in guard pond and will be reused. Zero discharge will be maintained.
Entire BF slag will be supplied to cement plant.
A part of fly ash will be utilized for fly ash brick making within JISL plant
premises and balance will be supplied to cement plant. Also, 30 acres of land
has been earmarked for ash mound. Total char generated from DRI kilns will be
utilized in captive FBC power plant. Coal washery rejects will be utilized in
captive FBC power plant. Other solid wastes i.e. SMS slag, accretion etc. will
be utilized in road construction. STP sludge will be utilized as manure for
green bet development. Noise levels within plant, near the sources
will be controlled below 85 dB (A) and near the plant boundary it will be
maintained within 75 dB (A).
Public hearing was conducted by OSPCB on 18.8.2011. The main issues raised in the
public hearing meeting were w.r.t. local employment, pollution control
measures, CSR activities etc. which have been addressed and included in
the EIA/EMP.
After detailed
deliberations, the Committee recommended the proposal for environmental
clearance with following specific and general conditions:
i.
Measures
shall be undertaken to mitigate PM levels
in the ambient air and a time bound action plan shall be submitted. On-line
ambient air quality monitoring and continuous stack monitoring facilities for
all the stacks shall be provided and sufficient air pollution control devices
viz. Electrostatic precipitator (ESP), gas cleaning plant, venturi scrubber, bag filters etc. shall be provided to
keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
ii.
As
proposed, Electrostatic precipitator (ESP) shall be provided to sinter plant,
WHRB, CFBC, DRI plants; and dust catcher followed by venturi scrubbers to blast
furnace to control particulate emissions within 50 mg/Nm3. Fume
extraction system shall be provided to induction furnaces to control the
emissions within the prescribed standards.
iii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iv.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed. Standards for the sponge iron plant issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008 should be followed.
v.
Hot
gases from DRI kiln shall be passed through Dust Settling Chamber (DSC) to
remove coarse solids and After Burning Chamber (ABC) to burn CO completely and
used in waste heat recovery boiler (WHRB). The gas then shall be cleaned in ESP
before leaving out into the atmosphere through ID fan and stack.
vi.
Total
water requirement from Sankh
River/Kalunga nala shall not exceed 390 m3/hr. Efforts shall further be made to use maximum
water from the rain water harvesting sources.
Use of air cooled condensers shall be explored and closed circuit
cooling system shall be provided to reduce water consumption and water
requirement shall be modified accordingly. All the effluent should be treated
and used for ash handling, dust suppression and green belt development. No effluent shall be discharged and
‘zero’ discharge shall be adopted. Sanitary sewage should be treated in septic
tank followed by soak pit.
vii.
Efforts
shall be made to make use of rain water harvested. If needed, capacity of the
reservoir should be enhanced to meet the maximum water requirement. Only balance
water requirement shall be met from other sources.
viii.
Regular monitoring of influent and effluent
surface, sub-surface and ground water (including chromite) should be ensured
and treated wastewater should meet the norms prescribed by the State Pollution
Control Board or described under the E(P) Act whichever are more stringent.
Leachate study for the effluent generated and analysis shall also be regularly
carried out and report submitted to the Ministry’s Regional Office at Bhubaneswar, SPCB and CPCB.
ix.
The water consumption shall not
exceed as per the standard prescribed for the steel plants.
x.
All the coal fines, char
from DRI plant and washery rejects shall be
utilized in CFBC boiler of power plant and no char shall be used for briquette
making or disposed off anywhere else. CFBC boiler shall be installed
simultaneously along with the DRI plant to ensure full utilization of char from
the beginning. All
the blast
furnace (BF) slag shall
be provided to the cement manufacturers. Scrap shall be used in steel melting
shop (SMS) and SMS slag and kiln accretions shall
be properly utilized. All the other solid waste including broken
refractory mass shall be properly disposed off in
environment-friendly manner.
xi.
Proper utilization of fly ash shall
be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003.
xii.
Vehicular pollution due to
transportation of raw material and finished products shall be
controlled. Proper arrangements shall also be made to control dust
emissions during loading and unloading of the raw material and finished
product.
xiii.
Transportation of raw coal during the initial
phase shall be by 40-T mechanically covered or tarpaulin covered trucks from
the coalmines to the washery. The raw coal, washed coal and coal wastes (rejects)
shall be stacked properly at earmarked site(s) within sheds/stockyards fitted
with wind breakers/shields. Adequate measures hall be taken to ensure that the
stored minerals do not catch fire.
xiv.
Hoppers of the coal crushing unit at the
crushing shed and washery unit shall be fitted with high efficiency bag
filters/Dust extractors and mist spray water sprinkling system shall be
installed and operated effectively at all times of operation to check fugitive
emissions from crushing operations, transfer points of belt conveyor systems
which shall be closed and from transportation roads.
xv.
All internal roads shall be black
topped. The roads shall be regularly cleaned with mechanical sweepers. A 3-tier
avenue plantation using native species shall be developed along the roads.
Facilities for parking of trucks carrying raw coal from the linked coalmines
shall be created within the Unit.
xvi.
The washery unit shall be a
zero-discharge facility and no wastewater shall be discharged from the washery
into the drains/natural watercourses. Recycled water shall be used for
development and maintenance of green belt and in dust suppression from Plant
operations.
xvii.
Proper handling, storage,
utilization and disposal of all the solid waste shall be ensured and regular
report regarding toxic metal content in the waste material and its composition,
end use of solid/hazardous waste should be submitted to the Ministry’s Regional
Office at Bhubaneswar, SPCB and
CPCB.
xviii.
A time bound action plan shall be
submitted to reduce solid waste, its proper utilization and disposal.
xix.
Risk and Disaster Management Plan
along with the mitigation measures shall be prepared and a copy submitted to
the Ministry’s Regional Office at Bhubaneswar,
SPCB and CPCB within 3 months of issue of environment clearance letter.
xx.
As proposed, green
belt shall be developed in 33 % of plant area as per the CPCB guidelines in
consultation with the DFO.
xxi.
All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the
Steel Plants should be implemented.
xxii.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 18th
August, 2011 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bhubaneswar.
xxiii.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details along with time bound action plan should be prepared and
submitted to the Ministry’s Regional Office at Bhubaneswar.
Implementation of such program should be ensured accordingly in a time bound
manner.
xxiv.
Rehabilitation and Resettlement Plan for
the project affected population including tribals, if any shall be implemented
as per the policy of the State Govt. in consultation with the State Govt. of
Odisha. Compensation paid in any case should not be less than the norms
prescribed under the National Resettlement and
Rehabilitation Policy, 2007.
xxv.
The company shall provide housing
for construction labour within the site with all necessary infrastructure and
facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking
water, medical health care, crèche etc. The housing may be in the form of
temporary structures to be removed after the completion of the project.
Proposals for TORs
35.3.9
Proposed 136 TPD Coke Oven, 300
TPD Coal Washery, 200 TPD Slurry Washery and 110 TPD Briquette Plant at Kandra
Industrial Area (Notified), P.O. Bhitia, District Dhanbad in Jharkhand by M/s OSD Coke Private Limited -
regarding TORs
The project authorities and their consultant, M/s Visiontek
Consultants, Bhubaneswar gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken along
with the draft TORs for preparation of EIA/EMP report. The
proposed project is a Category B project as per the Schedule of EIA Notification 2006 and appraised
by the SEIAA/SEAC. However, due to absence of SEIAA for Jharkhand, the proposal
is appraised by the Expert Appraisal
Committee (Industry-1) of MoEF.
M/s
OSD Coke Pvt. Limited have proposed to establish Hard Coke unit of 136 TPD
(45,000 TPA), Coal Washery of 300 TPD (90,000 TPA) & Slurry Washery of
200TPD (60,000TPA) for raw material preparation and Briquetting Unit of 110TPD
(33,000TPA) for solid waste utilization at Kandra
Industrial Area (Notified), P.O. Bhitia, District Dhanbad in Jharkhand. Total land required for the
proposed plant is 5.5 acres out of which 3.0 acres is already in the possession of the project proponent and rest is
under acquisition process. Green belt will be developed in 33 % area. No
national parks/wild life sanctuary is located within 10 km radius. The project is located at a distance of 5.5
KM from Dhanbad Town. Total cost of the project will
be 14.65 crores. Rs. 80.57 Lakhs and Rs. 16.10 Lakhs are earmarked
towards capital cost and recurring cost per annum for pollution control
measures. No litigation/court case in pending against
the proposal.
The
manufacturing process of hard coke involves of mixing of coal and charging into
coke ovens for carbonization. Hydro
Cyclone and Froth Floatation process will be adopted for coal washery and
slurry washery respectively. The raw materials
required for the proposed plant will be Coking Coal 90,000 TPA for coal
washery, Raw Slurry 60,000 TPA for slurry washery; low ash Coal (49,500 TPA)
and Slurry (15,500 TPA) for hard coke. Raw materials will be procured from
various places and transported by road through covered trucks. Washed coal (150
TPD), and Slurry (47TPD) will be used in-house to manufacture hard coke.
Rejection (inferior coal and slurry– 110 TPD) will be used in Briquette
manufacturing plant. Power (375 KW) will be sourced from JSEB/DVC.
Down-Draught Technology will be
incorporated in the hard coke ovens wherein flue gases will be routed through
down draft for maximum combustion of coal. The clean gas will be
released to the atmosphere by the ID fans through chimney. Dust suppression
water sprinkling system will be provided to control fugitive dust emission.
Closed circuit water system will be installed for the washery to maintain zero
discharge. Total ground water requirement will be 100 m3/day
and will be sourced from
BIADA (Bokaro Industrial Area Development Authority).
The wastewater generated will be treated and recycled in the process. Domestic
effluent will be treated in septic tank followed by soak pit. No effluent
will be discharged outside the premises and Zero discharge will be adopted.
Rejects (Middlings) from coal washery
will be sold or used for high ash coke manufacturing/power plant. The inferior
quality slurry will be partly reused in briquetting plant and rest will be sold
or used for high ash coke manufacturing. Low ash slurry will be sold OSD group
of companies.
Coke
dust from settling pit will be reused in briquetting plant. Waste/used/spent
oil and used batteries will be sold to authorized recyclers / re-processors.
Public
hearing is not required as the unit is located in the notified industrial area.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive summary of the project.
2. Photographs
of the proposed plant area.
3.
Copy of gazette notification for industrial
area
4. A line diagram/flow sheet for the
process and EMP
5. Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land should be included.
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
7.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
8.
Location
of national parks / wildlife sanctuary / reserve forests within
9.
A
list of industries within 10 km radius of the plant area.
10. Details and classification of total
land (identified and acquired) should be included.
11. Project site layout plan showing raw
materials and other storage plans, bore well or water storage, aquifers (within
12. List of raw material required and source
along with mode of transportation should be included. All the trucks for raw
material and finished product transportation must be “Environmentally
Compliant”.
13. Quantification & Characterization
of solid /hazardous waste & its action plan for management should be
included.
14. Mass balance for the raw material and
products should be included.
15. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall is necessary.
16. Ambient air quality at 8 locations
within the study area of
17. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
18. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
19. Ambient air quality as per National
Ambient Air Quality Emission Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be included.
20. Air Quality Impact Predication
Modeling based on ISCST-3 or the latest
models.
21. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided.
22. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
23. Presence of aquifer/aquifers within
24. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included.
25. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
26. ‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
27. A note on the impact of drawl of water
on the nearby River during lean season.
28. Action plan for rainwater harvesting
measures.
29. Surface water quality of nearby River
(
30. If the site is within
31. Pretreatment of raw water, treatment
plant for waste water should be described in detail. Design specifications may
be included.
32. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
33. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources should also be included.
34. Identification and details of land to
be used for all type of slag disposal in the secured land fill as per CPCB
guidelines should be included.
35. End use of solid waste and its
composition should be covered. Toxic
metal content in the waste material and its composition should also be
incorporated particularly of slag.
36. Provision of Toxic Chemical
Leachability Potential (TCLP) test for the slag and its end use should be
included.
37. Action plan for the green belt
development plan in 33 % area should be included.
38. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
39. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
40. Occupational health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
41. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
locals need and item-wise details along with time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
42. Total capital cost and recurring
cost/annum for environmental pollution control measures should also be
included.
43. Any litigation pending against the
project and / or any direction / order passed by any Court of Law against the
project, if so, details thereof.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. Where the documents provided are in a language other than
English, an English translation should be provided. The final EIA report shall be
submitted to the Ministry for obtaining environmental clearance. Public hearing
is not required as the unit is located in the notified industrial area.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP report.
35.3.10
Proposed 1.8 MTPA Iron Ore Beneficiation
Plant (300 TPH), 1.2 MTPA Iron Ore Pelletizing Plant (2x2,000 TPD), 64,500
Nm3/Hr Producer Gas Plant
(2x32,250 m3/hr) and 12 MW Captive Power Plant at Village
Chakdihi & Nua Barkote, Tehsil
Barkote, District Deogarh in Odisha by M/s Ambo Steel & Power Pvt.
Limited - regarding TORs
The
project authorities and their consultant, M/s Visiontek Consultants, Bhubaneswar gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft TORs for preparation of EIA/EMP. All the Pelletization plants are listed at S.No. 3(a) in primary
metallurgical industry under Category-A of the Schedule of EIA notification
2006 and appraised by the Expert Appraisal Committee (Industry-1) in the MoEF.
M/s. Ambo Steel & Power Limited
have proposed 1.8 MTPA (Throughput) Iron Ore
Beneficiation, 1.8 MTPA Pelletization, 2x32,250m3/hr Producer Gas
and 12 MW Captive Power Plant at
Vill- Chakdihi, Tahsil-Barkote, Dist-Deogarh, Odisha.
Total land required for the proposed plant is
141.01 acres and green belt will be developed in 33%
of the total plant area. No national Park/wild life sanctuary is located
within 10 km radius of the project site. Total cost of the project is
Rs. 477.92 Crores. Rs. 26.28 Crores and Rs. 5.75 Crores will be earmarked
towards capital cost and recurring cost for environmental pollution control measures.
Following are the details of the
proposed plants:
SL |
Units |
Configuration |
Capacity |
1 |
|
1x300TPH |
18,00,000 TPA(Throughput) 12,00,000 TPA (Concentrate) |
2 |
Pelletization Plant |
2x2,000TPD (2x0.6 MTPA) |
12,00,000 TPA |
3 |
Producer Gas Plant |
2x32,250 Nm3/Hr |
64,500 Nm3/Hr |
4 |
Captive Power Plant |
1x52TPH FBC Boiler |
12MW |
The
proposed project envisaged to beneficiate low grade iron ore fines to produce
iron ore concentrate through iron ore beneficiation plant. Iron ore concentrate
will be utilized to produce iron ore pellet using producer gas as fuel in the
pellet plant. Coal based Captive power plant will be installed to generate
power for utilization in beneficiation plant. Iron ore fines, high grade iron ore, coal, coke
Breeze, Limestone/Dolomite and Bentonite are the major raw materials used in
the plant process. The unit’s saleable product will be Iron Ore Pellets.
Gaseous emissions will be
controlled by installing air pollution control equipments. Dust suppression
will be done by water sprinkling and dry fog systems to control fugitive
emissions due to transportation and material processing activities. Bag Filters in the crushing plant,
coal mill & additive mill system will be installed, Spot filters at crusher
transfer point & raw coal storage and ESP at the travelling grate kiln each
with an efficiency of about 99.95% have been proposed to minimize air pollution
due to the plant operation. The gas above 4000C
from gassifier main reactor contains tars in vapor form will be directly fed
pellet plant kiln which prevent tar condensation and resulting in “ZERO TAR” pollution.
ESP will be installed at CPP to control emissions.
Total water requirement
for the proposed project is of 154 m3/hr which will be sourced
from River Brahmani. Settling tank will be installed for the treatment of
wastewater and the treated water will be used for dust suppression, plantation
etc. Tailings and slurry will be dewatered and treated water will be reused for
beneficiation. No wastewater will be generated from pellet plant. Domestic
wastewater will be treated in STP and effluent will be reused for greenbelt
development. Zero discharge norms will be maintained in the proposed plant.
Solid waste i.e. tailings
generated from beneficiation unit will be disposed in wet cake form from filter
press in an area of 37.5 acres. It is also
ideally suitable for bricks, tiles & blocks making and would be marketed to
local brick makers. Dust collected through ESP & Bag house etc. will be
recycled in the process. Ash from coal
gasification plant will be disposed in ash mound or will be sold to brick
making industries. Fly ash from CPP will be disposed to cement plants, fly ash
brick & concrete blocks manufacturers and can be used for land filling. Ear
muffs/ear plugs will be provided to workers working in high noise prone areas.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the plant area.
3.
Revised
plant layout and project area after excluding the township from the project
area since the township is at a distance of 2 km from the project site.
4.
A line diagram/flow sheet for the process and
EMP
5.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included. 3-D
view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from the
proposal site. A photograph of the site should also be included.
6.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
7.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
8.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
9.
Project
site layout plan to scale using AutoCAD showing raw materials, fly ash and
other storage plans, bore well or water storage, aquifers (within 1 km.)
dumping, waste disposal, green areas, water bodies, rivers/drainage passing
through the project site should be included.
10.
Details
and classification of total land (identified and acquired) should be included.
A copy of the mutual agreement for land acquisition signed with land oustees.
11.
Break up of small, medium and large farmers from
whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
12.
Rehabilitation
& Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
13.
Permission
from the tribals, if tribal land has also to be acquired along with details of
the compensation plan.
14.
Permission
and approval for the use of forest land, if any, and recommendations of the
State Forest Department. .
15.
A
list of industries containing name and type in 25 km radius should be
incorporated.
16.
Residential
colony should be located in upwind direction.
17.
List
of raw materials, analysis of all the raw materials and source along with mode
of transportation should be included. All the trucks for raw material and
finished product transportation must be “Environmentally Compliant”.
18.
If
the rocks, ores, raw material has trace elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
19.
Action
plan for excavation and muck disposal during construction phase.
20.
Studies
for fly ash, muck, slurry, sludge material disposal and solid waste generated,
if the raw materials used has trace elements and a management plan should also
be included.
21.
Manufacturing
process details for all the plants should be included.
22.
Mass
balance for the raw material and products should be included.
23.
Energy
balance data for all the components of steel plant including proposed power
plant should be incorporated.
24.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
25.
Data
generated in the last three years i.e. air, water, raw material properties and
analysis (major, trace and heavy metals), ground water table, seismic history,
flood hazard history etc.
26. One season site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall and AAQ data (except monsoon) should be
collected. The monitoring stations should take into account the pre-dominant
wind direction, population zone and sensitive receptors including reserved
forests.
27.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
28.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
29.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
30.
Air
quality modeling for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
31.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
32.
Ambient
air quality monitoring modeling along with cumulative impact should be included
for the day (24 hrs) for maximum GLC along with following :
i)
Emissions
(g/second) with and without the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
33.
A
plan for the utilization of waste/fuel gases in the WHRB for generating power
have to be set out.
34.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided. The alternate method of raw
material and end product transportation should also be studied and details
included.
35.
One
season data for gaseous emissions other than monsoon season is necessary.
36.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
37.
Presence
of aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
38.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
39.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
40.
Impact
of water drawl on River Brahmani
41.
Ground
water modeling showing the pathways of the pollutants should be included
42. Column leachate study for all types of
stockpiles or waste disposal sites at 20oC-50oC should be
conducted and included.
43. Commitment for bottom
lining of tailing pond
44. Action plan for rainwater harvesting
measures at plant site should be submitted to harvest rainwater from the roof
tops and storm water drains to recharge the ground water and also to use for
the various activities at the project site to conserve fresh water and reduce
the water requirement from other sources.
Rain water harvesting and groundwater recharge structures may also be
constructed outside the plant premises in consultation with local Gram
Panchayat and Village Heads to augment the ground water level. Incorporation of
water harvesting plan for the project is necessary, if source of water is bore
well.
45.
Permission
for the drawl of water from the State Irrigation Department or concerned
authority and water balance data including quantity of effluent generated,
recycled and reused and discharged is to be provided. Methods adopted/to be
adopted for the water conservation should be included.
46.
A
note on the impact of drawl of water on the nearby River during lean season.
47.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
48.
If
the site is within 10 km radius of any major River, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency.
49.
A
note on treatment of wastewater from different plants, recycle and reuse for
different purposes should be included.
50.
Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents.
51.
If
the water is mixed with solid particulates, proposal for sediment pond before
further transport should be included. The sediment pond capacity should be 100
times the transport capacity.
52.
Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from any
other source should be included.
53.
The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans.
54.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
55.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
56.
Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
57.
A
note on the treatment, storage and disposal of all type of slag should be
included. Identification and details of land to be used for SMS slag disposal
should be included. Details of secured land fill as per CPCB guidelines should
also be included.
58.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
59.
All
stock piles will have to be on top of a stable liner to avoid leaching of
materials to ground water.
60.
Action
plan for the green belt development plan in 33 % area i.e. land with not less
than 1,500 trees per ha. giving details of species, width of plantation,
planning schedule etc. should be included. The green belt should be around the
project boundary and a scheme for greening of the travelling roads should also
be incorporated. All rooftops/terraces should have some green cover.
61.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
62.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
63.
Occupational
health:
a)
Details
of existing Occupational & Safety Hazards. What are the exposure levels of
above mentioned hazards and whether they are within Permissible Exposure level
(PEL). If these are not within PEL, what measures the company has adopted to
keep them within PEL so that health of the workers can be preserved,
b)
Details
of exposure specific health status evaluation of worker. If the workers’ health is being evaluated by
pre designed format, chest x rays, Audiometry, Spirometry, Vision testing (Far
& Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations give the details of the same. Details
regarding last month analyzed data of abovementioned parameters as per age,
sex, duration of exposure and department wise.
c)
Annual
report of heath status of workers with special reference to Occupational Health and Safety.
d)
Plan and fund
allocation to ensure the occupational health & safety of all contract and
sub-contract workers.
64.
Details
regarding infrastructure facilities such as sanitation, fuel, restroom etc. to
be provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
65. Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure needs to be constructed and the agency responsible for the same
with time frame.
66.
Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
67.
Public hearing issues raised and commitments made by
the project proponent on the same should be included separately in EIA/EMP
Report in the form of tabular chart.
68.
At
least 5 % of the total cost of the project should be earmarked towards the
Enterprise Social Commitment based on public hearing issues and item-wise
details along with time bound action plan should be included. Socio-economic
development activities need to be elaborated upon.
69.
Plan
for the implementation of the recommendations made for the steel plants in the
CREP guidelines must be prepared.
70.
A
note on identification and implementation of Carbon Credit project should be
included.
71.
Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It
was decided that ‘TORs’ prescribed by
the Expert Appraisal Committee
(Industry-1) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. Where the documents provided are in a language other than
English, an English translation should be provided. The draft EIA/EMP
report shall be submitted to Odisha State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report
shall be submitted to the Ministry for obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports along with public
hearing proceedings.
35.3.11
Proposed 1.2 MTPA Iron Ore Beneficiation and
0.6 MTPA Pelletization Plant at Sy nos. 191, 192, 193, 210,214, 215, 216, 217,
218 and 219, Village Bannihatti, Taluk Sandur, District Bellary in Karnataka by
M/s V.T. Industrial Corporation Limited - regarding TORs
The project authorities and their consultant, M/s METAMORPHOSISSM,
Bengaluru, Karnataka gave a detailed presentation on the salient features of
the project and proposed environmental protection measures, to be undertaken
along with the draft Terms of Reference for the preparation of EIA/EMP Report. All the Pelletization plants are listed at S.No. 3(a) in primary
metallurgical industry under Category-A of the Schedule of EIA notification
2006 and appraised by the Expert Appraisal Committee (Industry-1) in the MoEF.
M/s. V T Industrial
Corporation Limited have proposed for a beneficiation
plant of capacity 1.2 mtpa & pelletisation plant of capacity 0.6 mtpa to be set up at Bannihatti Village,
Sandur Taluk, Bellary District, Karnataka State. The proposed Plant will be installed within the
already acquired land (127 Acres 10 Guntas) which is developed by Karnataka
Industrial Area Development Board (KIADB) wherein 33% will be demarcated as
green belt. Sandur Reserve Forest is located at 6 km from the project site,
Donimalai Reserve Forest is located at 3 km from the project site, Joga Reserve
Forest is located at 8 km from the project site and
Marutla extn. Reserve forest is located at 8 km from the project site.
The nearest railway station, Bannihatti Railway Line is 2 kms and State Highway
63 is 8 kms from the project site. The nearest water body is Nari Halla which
is 4 kms away. Total cost of the project is Rs. 268.00 Crores.
Iron ore, Coal and Bentonite will be used as the
major raw materials in the plant process. The
total power requirement will be about 15 MW, which will be met from the State Electricity Board GESCOM (State Grid). There will be
emissions during handling of raw materials and products, which will be
controlled by dust suppression system. All the transfer points will be provided
with dry fogging system. The emissions from the production processes will be
passed through bag filters to retain flue dust particles. The cleaned gases will be discharged to the
atmosphere through stacks of adequate heights. Total water requirement for the
proposed project will be 600 m3/day, which will be met from the bore
wells. The unit will be designed for Zero Discharge wherein all discharges will
be treated and reused in the plant.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
5.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
6.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
7.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
8.
Project
site layout plan to scale using AutoCAD showing raw materials, fly ash and
other storage plans, bore well or water storage, aquifers (within 1 km.)
dumping, waste disposal, green areas, water bodies, rivers/drainage passing
through the project site should be included.
9.
Details
and classification of total land (identified and acquired) should be included.
A copy of the mutual agreement for land acquisition signed with land oustees.
10. Break up of
small, medium and large farmers from whom the land is being acquired. If small
farmers are involved, a detailed R&R plan.
11. Rehabilitation & Resettlement (R
& R) should be as per policy of the State Govt. and a detailed action plan
should be included.
12. Permission from the tribals, if tribal
land has also to be acquired along with details of the compensation plan.
13. Permission and approval for the use of
forest land, if any, and recommendations of the State Forest Department. .
14. A list of industries containing name
and type in 25 km radius should be incorporated.
15. Residential colony should be located
in upwind direction.
16. List of raw materials, analysis of all
the raw materials and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
17. If the rocks, ores, raw material has
trace elements their petrography, ore microscopy, XRD, elemental mapping EPMA,
XRF is required to quantify the amount present in it and hence future risk
involved while using it and management plan.
18. Action plan for excavation and muck
disposal during construction phase.
19. Studies for fly ash, muck, slurry,
sludge material disposal and solid waste generated, if the raw materials used
has trace elements and a management plan should also be included.
20. Manufacturing process details for all
the plants should be included.
21. Mass balance for the raw material and
products should be included.
22. Energy balance data for all the
components of steel plant including proposed power plant should be
incorporated.
23. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall should be collected.
24. Data generated in the last three years
i.e. air, water, raw material properties and analysis (major, trace and heavy
metals), ground water table, seismic history, flood hazard history etc.
25.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
26. Ambient air quality at 8 locations
within the study area of 10 km., aerial coverage from project site with one
AAQMS in downwind direction should be carried out.
27. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
28. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
29. Air quality modeling for steel plant
for specific pollutants needs to be done.
APCS for the control of emissions from the kiln and WHRB should also be
included to control emissions within 50 mg/Nm3.
30. Action plan to follow National Ambient
Air Quality Emission Standards issued by the Ministry vide G.S.R. No. 826(E)
dated 16th November, 2009 should be included.
31. Ambient air quality monitoring
modeling along with cumulative impact should be included for the day (24 hrs)
for maximum GLC along with following :
i)
Emissions
(g/second) with and without the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
32. A plan for the utilization of
waste/fuel gases in the WHRB for generating power have to be set out.
33. Impact of the transport of the raw materials
and end products on the surrounding environment should be assessed and
provided. The alternate method of raw material and end product transportation
should also be studied and details included.
34. One season data for gaseous emissions
other than monsoon season is necessary.
35. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
36. Presence of aquifer(s) within 1 km of
the project boundaries and management plan for recharging the aquifer should be
included.
37. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included. Information regarding surface hydrology and water
regime should be included.
38. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
39. Ground water modeling showing the
pathways of the pollutants should be included
40.
Column
leachate study for all types of stockpiles or waste disposal sites at 20oC-50oC
should be conducted and included.
41.
Commitment for bottom lining of tailing pond
42.
Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the
ground water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
Incorporation of water harvesting plan for the project is necessary, if source
of water is bore well.
43. Permission for the drawl of water from
the State Irrigation Department or concerned authority and water balance data
including quantity of effluent generated, recycled and reused and discharged is
to be provided. Methods adopted/to be adopted for the water conservation should
be included.
44. A note on the impact of drawl of water
on the nearby River during lean season.
45. Surface water quality of nearby River
(60 m upstream and downstream) and other surface drains at eight locations must
be ascertained.
46. If the site is within 10 km radius of
any major River, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency.
47. A note on treatment of wastewater from
different plants, recycle and reuse for different purposes should be included.
48. Provision of traps and treatment
plants are to be made, if water is getting mixed with oil, grease and cleaning
agents.
49. If the water is mixed with solid
particulates, proposal for sediment pond before further transport should be
included. The sediment pond capacity should be 100 times the transport
capacity.
50. Wastewater characteristics (heavy
metals, anions and cations, trace metals, PAH) from any other source should be
included.
51. The pathways for pollution via
seepages, evaporation, residual remains are to be studied for surface water
(drainage, rivers, ponds, lakes), sub-surface and ground water with a
monitoring and management plans.
52. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
53. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources, char and fly ash. Copies of MOU regarding utilization of ash should
also be included.
54. Details of evacuation of ash, details
regarding ash pond impermeability and whether it would be lined, if so details
of the lining etc. needs to be addressed.
55. A note on the treatment, storage and
disposal of all type of slag should be included. Identification and details of
land to be used for SMS slag disposal should be included. Details of secured
land fill as per CPCB guidelines should also be included.
56. End use of solid waste and its
composition should be covered. Toxic
metal content in the waste material and its composition should also be
incorporated particularly of slag.
57. All stock piles will have to be on top
of a stable liner to avoid leaching of materials to ground water.
58. Action plan for the green belt
development plan in 33 % area i.e. land with not less than 1,500 trees per ha.
giving details of species, width of plantation, planning schedule etc. should
be included. The green belt should be around the project boundary and a scheme
for greening of the travelling roads should also be incorporated. All
rooftops/terraces should have some green cover.
59. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
60. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
61. Occupational health:
a)
Details
of existing Occupational & Safety Hazards. What are the exposure levels of
above mentioned hazards and whether they are within Permissible Exposure level
(PEL). If these are not within PEL, what measures the company has adopted to
keep them within PEL so that health of the workers can be preserved,
b)
Details
of exposure specific health status evaluation of worker. If the workers’ health is being evaluated by
pre designed format, chest x rays, Audiometry, Spirometry, Vision testing (Far
& Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations give the details of the same. Details
regarding last month analyzed data of abovementioned parameters as per age,
sex, duration of exposure and department wise.
c)
Annual
report of heath status of workers with special reference to Occupational Health and Safety.
d)
Plan and fund allocation
to ensure the occupational health & safety of all contract and sub-contract
workers.
62.
Details
regarding infrastructure facilities such as sanitation, fuel, restroom etc. to
be provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
63.
Impact
of the project on local infrastructure of the area such as road network and
whether any additional infrastructure needs to be constructed and the agency
responsible for the same with time frame.
64. Environment Management Plan (EMP) to
mitigate the adverse impacts due to the project along with item wise cost of
its implementation. Total capital cost and recurring cost/annum for
environmental pollution control measures should be included.
65. Public hearing
issues raised and commitments made by the project proponent on the same should
be included separately in EIA/EMP Report in the form of tabular chart.
66. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
public hearing issues and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
67. Plan for the implementation of the
recommendations made for the steel plants in the CREP guidelines must be
prepared.
68. A note on identification and
implementation of Carbon Credit project should be included.
69. Any litigation pending against the
project and/or any direction/order passed by any Court of Law against the
project, if so, details thereof should also be included.
It
was decided that ‘TORs’ prescribed by
the Expert Appraisal Committee
(Industry-1) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. Where the documents provided are in a language other than
English, an English translation should be provided. The draft EIA/EMP
report shall be submitted to Karnataka State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report
shall be submitted to the Ministry for obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports along with public
hearing proceedings.
35.3.12
Proposed expansion of cement grinding
capacity (1.3 MTPA to 1.7 MTPA) at Village Morak, Tehsil- Ramganj Mandi,
District Kota in Rajasthan by M/s Mangalam Cement Limited - regarding TORs
The project authorities and their consultant,
M/s. J.M. EnviroNet Pvt. Ltd., Gurgaon gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the proposed Terms of References for preparation of
EIA/EMP report. Although the proposed expansion project activity
falls under Category B of
the Schedule of EIA Notification, 2006, since it is an expansion of a Category A project, the proposal is appraised
by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s. Mangalam
Cement Ltd have
proposed expansion of Cement Grinding Capacity by addition of Fly ash (from 1.3 to
1.7 MTPA) At Village: Morak, Tehsil: Ramganj Mandi, District: Kota (Rajasthan). Total Plant area is 36 ha. As, the proposed expansion will
be within the existing plant premises, no additional land acquisition is
required for the proposed expansion project. 33% of the total project area has
already been developed under greenbelt / plantation area. The same will be
maintained & further enhanced for proposed expansion project. No National Park, Wildlife
Sanctuary, Biosphere Reserve exist within 10 km radius of the study area. Two Reserved Forests (3.5 km in NE direction and 3.5 km in NW direction) and
two Protected Forest (2.2 km in WSW direction and 4.8 km in ENE direction) exist
within 10 km radius of the study area. R&R is not
applicable. Total
cost of the project is Rs. 84.5 Lakhs. Capital cost for Environmental
Protection Measures is Rs. 7.50 Lakhs
and Recurring Cost is Rs. 2.5 Lakhs /annum.
Details of the products along with their
production capacity are given below:
Category |
Existing Capacity (Line I) |
Proposed Capacity (Line II) |
Total Capacity after Expansion |
Clinker (MTPA) |
0.99 |
None |
0.99 |
Cement (MTPA) |
1.3 |
0.4 |
1.7 |
Major raw materials required for the proposed expansion project is Fly
ash, which will be sourced from Kota thermal power plant, captive power
plant, Parichha Thermal Power Station Jhansi, Chabra Thermal power Plant,
Chabra and Adani Power Ltd., Jhalawar.
Very less quantity of Gypsum is required, which will be procured from nearby
areas in Rajasthan. Existing Power requirement is 15 MW. Additional Power
required for the proposed expansion project will be 1.01 MW, which will be
sourced from RSEB, Captive Power Plant (I & II) and Wind farms.
To control particulate emissions, all major sources of air pollution are provided with ESPs, Bag filters to
maintain the PM emission level below 50 mg/Nm3. All
material transfer points have been provided with bag filters to entrap the
emissions at the source itself. Clinker is stored in covered gantry. Fly ash is
stored in silo and gypsum in covered shed. Existing water requirement for the
project is 642 m3/ day, sourced from the Mine Sump Water. No
additional water is required for the proposed expansion project. No industrial wastewater is generated in the
Cement Plant. Domestic waste water generated from Cement Plant/Colony is
treated in the STP. The treated water is utilized for Greenbelt
Development/Horticulture activities. Rain water harvesting structures are constructed.
No solid waste is generated in cement manufacturing process. Dust collected
from various pollution control equipments is recycled back to the process. STP
Sludge is utilized as manure for green belt development within the plant
premises.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1. Executive summary of the project.
2. Photographs of the existing and
proposed plant area.
3. Compliance
to the conditions stipulated in the Environmental
Clearance / NOC granted by the SPCB.
4. Recent
monitoring report from SPCB, which shall include data on AAQ, water quality,
solid waste etc. shall be submitted.
5. Has the unit received any notice under
the Section 5 of Environment (Protection) Act, 1986 or relevant Sections of Air
and Water Acts? If so, compliance to the notice(s).
6. A line diagram/flow sheet for the
process and EMP
7.
Proposal
should be submitted to the Ministry for environment clearance only after acquiring
total land. Necessary documents indicating acquisition of land should be
included.
8.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
9.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
10.
Break up of small, medium and large farmers from
whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
11.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
12.
A
list of industries within 10 km radius of the plant area.
13.
Details
and classification of total land (identified and acquired) should be included.
14.
Project
site layout plan to scale using AutoCAD showing raw materials and other storage
plans, bore well or water storage, aquifers (within 1 km.) dumping, waste
disposal, green areas, water bodies, rivers/drainage passing through the
project site should be included.
15.
List
of raw materials required and source along with mode of transportation should
be included. All the trucks for raw material and finished product
transportation must be “Environmentally Compliant”.
16.
Chemical and Trace Element Analysis of coal and fly
ash
17.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
18.
Mass
balance for the raw material and products should be included.
19.
Energy
balance data for all the components of plant should be incorporated.
20.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
21.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
22.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction.
Chemical characterization of RSPM and incorporating of RSPM data.
23.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
24.
Air
quality modeling for specific pollutants needs to be done. APCS for the control of emissions should also
be included to control emissions within 50 mg/Nm3.
25.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
26.
Air
Quality Impact Prediction Modeling based on ISCST-3 or the latest models.
Impact of the transport of the raw materials and end products on the
surrounding environment should be assessed and provided.
27.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
28.
Presence
of aquifer/aquifers within 1 km of the project boundaries and management plan
for recharging the aquifer should be included.
29.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used along
with a Piper and Piper Duro-V diagram.
If surface water is used from river, rainfall, discharge rate, quantity,
drainage and distance from project site should also be included.
30.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
31.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
32.
A
note on the impact of drawl of water on the nearby River during lean season.
33.
Action
plan for rainwater harvesting measures.
34.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
35.
If
the site is within 10 km radius of any major river, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency and a management plan.
36.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
37.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
38.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
39.
Action
plan for the green belt development plan in 33 % area should be included.
40.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
41.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
42.
Occupational
health:
e)
Details
of existing Occupational & Safety Hazards. What are the exposure levels of
above mentioned hazards and whether they are within Permissible Exposure level
(PEL). If these are not within PEL, what measures the company has adopted to
keep them within PEL so that health of the workers can be preserved,
f) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical
examinations give the details of the same. Details regarding last month
analyzed data of abovementioned parameters as per age, sex, duration of
exposure and department wise.
g)
Annual
report of heath status of workers with special reference to Occupational Health and Safety.
h)
Plan and fund
allocation to ensure the occupational health & safety of all contract and
sub-contract workers.
43.
At
least 5 % of the total cost of the project should be earmarked towards the
Enterprise Social Commitment based on locals need and item-wise details along
with time bound action plan should be included. Socio-economic development
activities need to be elaborated upon.
44.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
45.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee (Industry-1) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the
documents provided are in a language other than English, an English translation
should be provided. The final EIA report shall be submitted to the
Ministry for obtaining environmental clearance. The proposal is exempted from public hearing as per Para 7(II) of EIA Notification
2006 due to no additional land and water allocation
requirement, use of energy efficient technology, no clinker manufacturing at
the proposed site, no sensitive area within 10 km. radius, ‘zero’ effluent
discharge, utilization of all the solid waste in the process itself including
utilization of fly ash etc. Environmental
Clearance for the existing plant was accorded on 5.4.2007 and Public Hearing
was held on 23.12.2006.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP report.
35.3.13
Replacement of old 4 stage preheater with
modern 6 stage preheater and energy efficient clinker cooler to reduce specific
heat consumption from 820 KCAL/KG-Clinker to 700 KCAL/KG-Clinker at Village
Andheri Deori, Tehsil Masuda, District Ajmer in Rajasthan by M/s Shree
Cement Limited - regarding Clarification on requirement of EC
The Committee noted that the proposal involves
replacement of 4 stage pre heater with modern 6-stage pre heater and energy
efficient clinker cooler to reduce specific heat consumption from 820 kcal/kg
clinker to 700 Kcal/kg clinker without changing the production capacity of 4000
TPD of clinker and 6000 TPD of cement, land and water requirement.
The Committee recommended that environmental
clearance is not required for the above under the EIA Notification, 2006 and
its amendment.
35.3.14
Proposed expansion of cement grinding
capacity (from 1.7 to 2.3 MTPA) at Village Morak, Tehsil- Ramganj Mandi,
District Kota in Rajasthan by M/s Neer Shree Cement (A unit of M/s Mangalam
Cement Limited) - regarding TORs
The project authorities and their consultant, M/s.
J.M. EnviroNet Pvt. Ltd., Gurgaon gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken along with the proposed Terms of References for preparation of
EIA/EMP report. Although the proposed expansion project activity
falls under Category B of
the Schedule of EIA Notification, 2006, since it is an expansion of a Category A project, the proposal is appraised
by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s Neer
Shree Cement (a unit of M/s. Mangalam Cement Ltd.) have proposed for expansion
of Cement Grinding Capacity (from 1.7 to 2.3 MTPA) at Village: Morak, Tehsil:
Ramganj Mandi, District: Kota (Rajasthan). Total Plant area is 94 ha. Since, the proposed expansion
will be within the existing plant premises, no additional land will be required
for the same. No National Park, Wildlife Sanctuary and Biosphere Reserve fall
within 10 km radius of the study area. Two
Reserved Forests (at 3.5 km in NE direction and 3.5 km in NW direction) and two Protected
Forests (at 2.2 km in WSW direction and 4.8 km in ENE direction) exist within 10 km radius study area. No
R&R is applicable. Total cost of the project is Rs. 2.865 Crores. Capital
cost for Environmental Protection Measures is Rs. 7.50 Crores and Recurring Cost is Rs. 2.5 Crores /annum.
Details
of the products along with their production capacity are given below:
Project Activity |
Existing capacity |
Proposed Expansion |
Total Capacity After Expansion |
Clinker
(MTPA) |
1.32 |
None |
1.32 |
Cement
(MTPA) |
1.7 |
0.6 |
2.3
|
The cement
plant is based on the dry process technology for cement manufacturing with
pre-heating and pre-calciner technology. Major raw materials required for the proposed expansion project is Fly
ash, sourced from Kota thermal
power plant and captive power plant.
Other raw material is Gypsum which
will be procured from nearby areas in Rajasthan. Existing Power
requirement is 17 MW. Additional Power required for the proposed expansion
project will be 0.76 MW, which will be sourced from RSEB, wind farms & own
power source.
To control particulate emissions, all major sources of air pollution are provided with ESPs/ Bag filters to
maintain the PM emission level below 50 mg/Nm3. All
material transfer points have been provided with bag filters to entrap the
emissions at the source itself. Clinker is stored in gantry covered,
fly ash is stored in silo and gypsum in covered shed. Existing water
requirement for the project is 1240 m3/day, sourced from the Mine
sump water. No additional water will be required for proposed expansion. No
industrial wastewater is being generated from the Cement Plant. Domestic wastewater
generated from Cement plant / Colony is being treated in STP and treated water
is being used for green belt development / Horticulture activities. Rain water
harvesting is being practiced at plant and colony area. No solid waste is
generated in cement manufacturing process. Dust collected from various
pollution control equipments is recycled back to the process. STP Sludge is
utilized as manure for green belt development within the plant premises. 33% of
the total project area has already been developed under greenbelt / plantation
area. The same will be maintained & further enhanced for proposed expansion
project.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project.
2.
Photographs
of the existing and proposed plant area.
3.
Compliance to the conditions stipulated in the Environmental
Clearance / NOC granted by the SPCB.
4.
Recent monitoring report from SPCB, which shall
include data on AAQ, water quality, solid waste etc. shall be submitted.
5.
Has
the unit received any notice under the Section 5 of Environment (Protection)
Act, 1986 or relevant Sections of Air and Water Acts? If so, compliance to the
notice(s).
6.
A
line diagram/flow sheet for the process and EMP
7. Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land should be included.
8. A site location map on Indian map of
1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with
at least next 10 Kms of terrains i.e. circle of 10 kms and further 10 kms on
A3/A2 sheets with proper longitude/latitude/heights with min. 100/200 m.
contours should be included. 3-D view i.e. DEM (Digital Elevation Model) for
the area in 10 km radius from the proposal site.
9. Present land use should be prepared
based on satellite imagery. High-resolution satellite image data having 1m-5m
spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the
10Km radius area from proposed site. The same should be used for land used/land-cover
mapping of the area.
10. Break up of
small, medium and large farmers from whom the land is being acquired. If small
farmers are involved, a detailed R&R plan.
11. Location of national parks / wildlife
sanctuary / reserve forests within 10 km. radius should specifically be
mentioned. A map showing land use/land cover, reserved forests, wildlife
sanctuaries, national parks, tiger reserve etc in 10 km of the project site.
12. A list of industries within 10 km
radius of the plant area.
13. Details and classification of total
land (identified and acquired) should be included.
14. Project site layout plan to scale
using AutoCAD showing raw materials and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
15. List of raw materials required and
source along with mode of transportation should be included. All the trucks for
raw material and finished product transportation must be “Environmentally
Compliant”.
16. Chemical and
Trace Element Analysis of coal and fly ash
17. Quantification & Characterization
of solid /hazardous waste & its action plan for management should be
included.
18. Mass balance for the raw material and
products should be included.
19. Energy balance data for all the
components of plant should be incorporated.
20. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall is necessary.
21. Ambient air quality at 8 locations
within the study area of 10 km., aerial coverage from project site with one
AAQMS in downwind direction should be carried out.
22. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
23. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
24. Air quality modeling for specific
pollutants needs to be done. APCS for
the control of emissions should also be included to control emissions within 50
mg/Nm3.
25. Ambient air quality as per National
Ambient Air Quality Emission Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 should be included.
26. Air Quality Impact Prediction Modeling
based on ISCST-3 or the latest models. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided.
27. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
28. Presence of aquifer/aquifers within 1
km of the project boundaries and management plan for recharging the aquifer
should be included.
29. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used along with a Piper and Piper Duro-V diagram. If surface water is used from
river, rainfall, discharge rate, quantity, drainage and distance from project
site should also be included.
30. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
31. ‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
32. A note on the impact of drawl of water
on the nearby River during lean season.
33. Action plan for rainwater harvesting
measures.
34. Surface water quality of nearby River
(60 m upstream and downstream) and other surface drains at eight locations must
be ascertained.
35. If the site is within 10 km radius of
any major river, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency and a management plan.
36. Pretreatment of raw water, treatment
plant for waste water should be described in detail. Design specifications may
be included.
37. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
38. Action plan for solid/hazardous waste
generation, storage, utilization and disposal particularly slag from all the
sources should also be included.
39. Action plan for the green belt
development plan in 33 % area should be included.
40. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
41. Disaster Management Plan including
risk assessment and damage control needs to be addressed and included.
42. Occupational health:
a) Details of existing Occupational &
Safety Hazards. What are the exposure levels of above mentioned hazards and
whether they are within Permissible Exposure level (PEL). If these are not
within PEL, what measures the company has adopted to keep them within PEL so
that health of the workers can be preserved,
b) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical examinations
give the details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c) Annual report of heath status of
workers with special reference to Occupational Health and Safety.
d) Plan and fund allocation to ensure the occupational health & safety
of all contract and sub-contract workers.
43. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
locals need and item-wise details along with time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
44. Total capital cost and recurring
cost/annum for environmental pollution control measures should also be
included.
45. Any litigation pending against the
project and / or any direction / order passed by any Court of Law against the
project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the Expert Appraisal Committee (Industry-1) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. Where the documents
provided are in a language other than English, an English translation should be
provided. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance. The proposal
is exempted from public hearing as per
Para 7(II) of EIA Notification 2006 due to no
additional land and water allocation requirement, use of energy efficient
technology, no clinker manufacturing at the proposed site, no sensitive area
within 10 km. radius, ‘zero’ effluent discharge, utilization of all the solid
waste in the process itself including utilization of fly ash etc. Environmental Clearance for the existing plant was
accorded on 5.4.2007 and Public Hearing was held on 23.12.2006.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP report.
35.3.15
Proposed 0.2 MTPA Integrated Steel Plant
(HGPIN, SMS & Producer Gas Plant) along with 1.2 MTPA Iron Ore Pellet Plant
at Village Pur, Tehsil Bhilwara, District Bhilwara in Rajasthan by M/s
Jindal Saw Limited - regarding TORs
The project authorities
and their consultant, M/s. S.S.Environics
(India) Pvt. Ltd., Bhubaneswar gave a detailed presentation on the salient
features of their proposal and proposed environmental protection
measures to be undertaken along with draft Terms of Reference for
preparation of EIA/EMP report All the Integrated
Steel Plants are listed at S. No. 3(a) under Primary Metallurgy Industry of the
Schedule of EIA Notification 2006 under Category’ A’ and appraised by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s. Jindal Saw Ltd.
has proposed a 0.2 MTPA Integrated Steel Plant (HGPIN, SMS & Producer Gas
Plant) along with 1.2 MTPA Iron Ore Pellet Plant. at Village- Pur, Tehsil-
Bhilwara, District- Bhilwara, State- Rajasthan. Total land requirement for the
project will be 26.33 Ha. An area of 9.40 Ha
is earmarked for Greenbelt development. The
land is Government waste land allocated for Industrial Use. The project site is
having good accessibility i.e; N.H-79 is passing at a distance of 2km from the
project site and Bhilwara railway station is at 9.1 km from the project site. Nearest
Village is Pur at 2 km. Cost of the project is Rs. 416.15
Crores and capital cost of Rs. 20 Crores would be earmarked for Environmental
Protection Measures.
Iron Ore Concentrate,
Anthracite Coal, Bituminous Coal, Limestone etc. will be used as raw material
for Integrated Steel Plant and Iron Ore Concentrate, Coal, Bentonite etc are
the raw material for Pellet Plant. The finished product of the steel plant is
Billet will be sold to open market & pellet will be transported to
Company’s plant at Mundra or will be sold to the open market. Power Requirement
for the proposed project will be 28.5 MW and will be sourced from RVVNL,
Rajasthan.
For control
of Air pollution, Bag Filter will be installed in HGPIN Plant, Induction
Furnace and Proportion Building. ESP will be installed in PGP, Indurating
machine Hood exhaust, Indurating machine wind box exhaust. Fogging Device will
be installed at Raw material ground hopper and bins. Pulse jet dust collector
will be installed at indurating machine feeding end & discharging end. The proposed project
requires 1,428 m3/day of water, which will be sourced from STP
(treated sewage water) of the Company at Kenwara near Bhilwara. No waste water will be generated from the plant,
the plant is designed with zero discharge concept. The effluent after treatment
in ETP will be reused for dust suppression and greenbelt development. SMS Slag
from the integrated steel plant will be used in road making and low land
filling. Fly ash from HGPIN and PGP will be utilized in the pellet plant. There is no solid waste generation from the process of
Pelletization as the dust collected from ESP and bag filter of Induration
Furnace and proportion building will be recycled in the pelletization process.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
5.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
6.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
7.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use/land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
8.
Project
site layout plan to scale using AutoCAD showing raw materials, fly ash and
other storage plans, bore well or water storage, aquifers (within 1 km.)
dumping, waste disposal, green areas, water bodies, rivers/drainage passing
through the project site should be included.
9.
Details
and classification of total land (identified and acquired) should be included.
A copy of the mutual agreement for land acquisition signed with land oustees.
10.
Break up of small, medium and large farmers from
whom the land is being acquired. If small farmers are involved, a detailed
R&R plan.
11.
Rehabilitation
& Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
12.
Permission
from the tribals, if tribal land has also to be acquired along with details of
the compensation plan.
13.
Permission
and approval for the use of forest land, if any, and recommendations of the
State Forest Department. .
14.
A
list of industries containing name and type in 25 km radius should be
incorporated.
15.
Residential
colony should be located in upwind direction.
16.
List
of raw materials, analysis of all the raw materials and source along with mode
of transportation should be included. All the trucks for raw material and
finished product transportation must be “Environmentally Compliant”.
17.
If
the rocks, ores, raw material has trace elements their petrography, ore
microscopy, XRD, elemental mapping EPMA, XRF is required to quantify the amount
present in it and hence future risk involved while using it and management
plan.
18.
Action
plan for excavation and muck disposal during construction phase.
19.
Studies
for fly ash, muck, slurry, sludge material disposal and solid waste generated,
if the raw materials used has trace elements and a management plan should also
be included.
20.
Manufacturing
process details for all the plants should be included.
21.
Mass
balance for the raw material and products should be included.
22.
Energy
balance data for all the components of steel plant including proposed power
plant should be incorporated.
23.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
24.
Data
generated in the last three years i.e. air, water, raw material properties and
analysis (major, trace and heavy metals), ground water table, seismic history,
flood hazard history etc.
25. One season site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall and AAQ data (except monsoon) should be collected. The monitoring
stations should take into account the pre-dominant wind direction, population zone
and sensitive receptors including reserved forests.
26.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
27.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
28.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
29.
Air
quality modeling for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
30.
Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
31.
Ambient
air quality monitoring modeling along with cumulative impact should be included
for the day (24 hrs) for maximum GLC along with following :
i)
Emissions
(g/second) with and without the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged concentration
(MGLC scenario) with downwind distance at every 500 m interval covering the
exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
32.
A
plan for the utilization of waste/fuel gases in the WHRB for generating power
have to be set out.
33.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided. The alternate method of raw
material and end product transportation should also be studied and details
included.
34.
One
season data for gaseous emissions other than monsoon season is necessary.
35.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
36.
Presence
of aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
37.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
38.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
39.
Ground
water modeling showing the pathways of the pollutants should be included
40. Column leachate study for all types of
stockpiles or waste disposal sites at 20oC-50oC should be
conducted and included.
41. Commitment for bottom
lining of tailing pond
42. Action plan for rainwater harvesting
measures at plant site should be submitted to harvest rainwater from the roof
tops and storm water drains to recharge the ground water and also to use for
the various activities at the project site to conserve fresh water and reduce
the water requirement from other sources.
Rain water harvesting and groundwater recharge structures may also be
constructed outside the plant premises in consultation with local Gram
Panchayat and Village Heads to augment the ground water level. Incorporation of
water harvesting plan for the project is necessary, if source of water is bore
well.
43.
Permission
for the drawl of water from the State Irrigation Department or concerned
authority and water balance data including quantity of effluent generated,
recycled and reused and discharged is to be provided. Methods adopted/to be
adopted for the water conservation should be included.
44.
A
note on the impact of drawl of water on the nearby River during lean season.
45.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
46.
If
the site is within 10 km radius of any major River, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency.
47.
A
note on treatment of wastewater from different plants, recycle and reuse for
different purposes should be included.
48.
Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents.
49.
If
the water is mixed with solid particulates, proposal for sediment pond before
further transport should be included. The sediment pond capacity should be 100
times the transport capacity.
50.
Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from any
other source should be included.
51.
The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans.
52.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
53.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
54.
Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
55.
A
note on the treatment, storage and disposal of all type of slag should be
included. Identification and details of land to be used for SMS slag disposal
should be included. Details of secured land fill as per CPCB guidelines should
also be included.
56.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
57.
All
stock piles will have to be on top of a stable liner to avoid leaching of
materials to ground water.
58.
Action
plan for the green belt development plan in 33 % area i.e. land with not less
than 1,500 trees per ha. giving details of species, width of plantation,
planning schedule etc. should be included. The green belt should be around the
project boundary and a scheme for greening of the travelling roads should also
be incorporated. All rooftops/terraces should have some green cover.
59.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
60.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
61.
Occupational
health:
a) Details of existing Occupational &
Safety Hazards. What are the exposure levels of above mentioned hazards and
whether they are within Permissible Exposure level (PEL). If these are not
within PEL, what measures the company has adopted to keep them within PEL so
that health of the workers can be preserved,
b) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical
examinations give the details of the same. Details regarding last month
analyzed data of abovementioned parameters as per age, sex, duration of
exposure and department wise.
c) Annual report of heath status of
workers with special reference to Occupational Health and Safety.
d) Plan and fund allocation to ensure the occupational health & safety
of all contract and sub-contract workers.
62. Details regarding infrastructure
facilities such as sanitation, fuel, restroom etc. to be provided to the labour
force during construction as well as to the casual workers including truck
drivers during operation phase.
63. Impact of the project on local
infrastructure of the area such as road network and whether any additional
infrastructure needs to be constructed and the agency responsible for the same
with time frame.
64.
Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
65.
Public hearing issues raised and commitments made by
the project proponent on the same should be included separately in EIA/EMP
Report in the form of tabular chart.
66.
At
least 5 % of the total cost of the project should be earmarked towards the Enterprise
Social Commitment based on public hearing issues and item-wise details along
with time bound action plan should be included. Socio-economic development
activities need to be elaborated upon.
67.
Plan
for the implementation of the recommendations made for the steel plants in the
CREP guidelines must be prepared.
68.
A
note on identification and implementation of Carbon Credit project should be
included.
69.
Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It
was decided that ‘TORs’ prescribed by
the Expert Appraisal Committee
(Industry-1) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. Where the documents provided are in a language other than
English, an English translation should be provided. The draft EIA/EMP
report shall be submitted to Rajasthan State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report
shall be submitted to the Ministry for obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports along with public hearing
proceedings.
35.3.16
Proposed
Integrated Cement project (Clinker- 2.0 MTPA, Cement - 2.5 MTPA) along with 40
MW coal based Captive Power Plant and WHRB 10 MW at
Villages Tonki, Temberni, Sondual & Golpura Tehsil Manawar, District Dhar in Madhya Pradesh by M/s UltraTech Cement Limited - regarding
TORs
The project authorities and their consultant,
M/s. J.M. EnviroNet Pvt. Ltd., Gurgaon gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the proposed Terms of References for preparation of
EIA/EMP report. The Cement Plants with production capacity
more than 1.0 MTPA are listed at S. No. 3 (b) under Category “A” of the
Schedule of EIA Notification, 2006 and appraised
by the Expert Appraisal Committee (Industry-1) of MoEF.
M/s
UltraTech Cement Ltd have proposed for Integrated Cement Plant with capacities
Clinker of 2.0 MTPA, Cement of 2.5 MTPA & Captive Power Plant (Coal Based)
of 40 MW, and WHRS 10 MW at Villages: Tonki,
Temberni, Sondual & Golpura, Tehsil – Manawar, District - Dhar, State -
Madhya Pradesh. Total project area is 268.804 ha including 156.983 ha Govt. and
111.821 ha Private land. Lawani Reserved Forest exists at approx. 9.6 km in NE
direction from the plant site. R&R is not applicable. Total cost of the
project is Rs. 1,600 Crores. Capital cost for Environmental Protection Measures
is Rs. 70.0 Crores and Recurring Cost is Rs. 2.0 Crores/annum.
Details of the facilities/products along with their production
capacity are given below:
Facility |
Capacity |
Clinker |
2.0 MTPA |
Cement |
2.5 MTPA |
CPP (Coal based) |
40 MW |
WHRB |
10 MW |
D.G. Set |
2x6 MW |
The
cement plant will be based on the dry process technology for cement
manufacturing with pre-heater and pre-calciner technology. Major raw materials required for the Proposed
Greenfield Integrated Project is Limestone, transported from the captive
limestone mine (Sitapuri Block & Mohanpura Block). Other raw materials are Gypsum and
Fly ash which will be procured from Nagaur & Bikaner district of Rajasthan
and Malwa/ Jhabua Captive power plant, respectively. Proposed power requirement
will be about 35 MW, which will be sourced from Captive Power Plant & grid substation at Manawar.
All
major sources of air pollution (Raw Mill & Kiln, Clinker Cooler, Coal Mill,
Cement Mill & Boiler) will be provided with bag house, bag filters &
ESP to maintain stack emissions below 50 mg/Nm3 for cement plant and
<100 mg/ Nm3 for CPP. Bag filters will be provided at all loading
/unloading & transfer points. All the material conveyor belts will be
covered. Coal will be transported in covered trucks. Clinker will be stored in
closed clinker silo and gypsum is stored in covered shed. Fly ash will be
stored in silos.
Total
water requirement for the proposed project will be 3,000 m3/day and
will be sourced from Maan Dam/ Mann River/ Mandawadi River. No industrial waste
water will be generated during cement manufacturing process. Wastewater
generated from CPP & water treatment (RO/DM) plant will be recycled back
for dust suppression after proper neutralization. Sewage treatment will be
provided for the treatment of domestic effluent and treated waste water will be
used for horticulture purpose. Rain water harvesting will be practiced at plant
and colony area. No solid waste will be generated from the cement manufacturing
process. Dust collected from air pollution control equipment will be totally
recycled in process. Sludge from Sewage Treatment Plant (STP) will be used as
manure for green belt development. Personal Protective Equipments like earplugs
and earmuffs will be provided to the workers exposed to high noise level.
Acoustic Sound Proof system will be provided in Captive Power Plant for Turbine
& Generator building.
After
detailed deliberations, the Committee prescribed following TORs for undertaking
detailed EIA/EMP study:
1. Executive
summary of the project
2. Photographs
of the proposed plant area.
3.A line diagram/flow sheet for the
process and EMP
4.
Coal linkage documents
5. The earlier
questionnaire for industry sector should be submitted while submitting EIA/EMP.
6. A site location map on Indian map of
1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an A3/A2 sheet with
at least next 10 Kms of terrains i.e. circle of 10 kms and further 10 kms on
A3/A2 sheets with proper longitude/latitude/heights with min. 100/200 m.
contours should be included. 3-D view i.e. DEM (Digital Elevation Model) for
the area in 10 km radius from the proposal site.
7. Present land use should be prepared
based on satellite imagery. High-resolution satellite image data having 1m-5m
spatial resolution like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the
10Km radius area from proposed site. The same should be used for land
used/land-cover mapping of the area.
8. Location of national parks / wildlife
sanctuary / reserve forests within 10 km. radius should specifically be
mentioned. A map showing land use / land cover, reserved forests, wildlife
sanctuaries, national parks, tiger reserve etc. in 10 km of the project site.
9. Project site layout plan showing raw
materials, fly ash and other storage plans, bore well or water storage,
aquifers (within 1 km.) dumping, waste disposal, green areas, water bodies,
rivers/drainage passing through the project site should be included.
10. Details and classification of total
land (identified and acquired) should be included.
11. Proposal should be submitted to the
Ministry for environment clearance only after acquiring total land. Necessary
documents indicating acquisition of land should be included.
12. Rehabilitation & Resettlement (R
& R) should be as per policy of the State Govt. and a detailed action plan
should be included.
13. Permission and approval for the use of
forest land and recommendations of the State Forest Department regarding impact
of proposed expansion on the surrounding reserve forests, if applicable, should
be included.
14. A list of industries containing name
and type in 10 km radius shall be incorporated.
15. Residential colony should be located
in upwind direction.
16. List of raw material required and
source along with mode of transportation should be included. All the trucks for
raw material and finished product transportation must be “Environmentally
Compliant”.
17. Petrological and Chemical analysis and
other chemical properties of raw materials used (with GPS location of source of
raw material) i.e. ores, minerals, rock, soil, coal, iron, dolomite quartz etc.
using high definition and precision instruments mentioning their detection
range and methodology such Digital Analyzers, AAS with Graphite furnace, ICPMS,
MICRO-WDXRF, EPMA, XRD, Nano studies or at least as per I30-10500 and WHO
norms. These analysis should include trace element and metal studies like Cr
(vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of radioactive elements
(U, Th etc.).
18. Petrography, grain size analysis and
Major element analysis of raw material and soil from project site and raw
material should be done on the same parameters along with analysis for SiO2,
Al2O3, MgO, MnO, K2O, CaO, FeO, Fe2O3,
P2O5, H2O, CO2.
19. If the rocks, ores, raw material has
trace elements their petrography, ore microscopy, XRD, elemental mapping EPMA,
XRF is required to quantify the amount present in it and hence future risk
involved while using it and management plan.
20. Studies for fly ash, muck disposal,
slurry, sludge material and solid waste generated should also be included, if
the raw materials used has trace elements and a management plan.
21. Manufacturing process details for all
the cement plant, captive power plant and mine should be included.
22. Possibility of installation of WHRB
will be explored and details included
23. Mass balance for the raw material and
products should be included.
24. Energy balance data for all the
components including proposed power plant should be incorporated.
25. Site-specific micro-meteorological
data using temperature, relative humidity, hourly wind speed and direction and
rainfall should be collected.
26. Sources of secondary emissions, its
control and monitoring as per the CPCB guidelines should be included. A full
chapter on fugitive emissions and control technologies should be provided.
27. An action plan to control and monitor
secondary fugitive emissions from all the sources as per the latest permissible
limits issued by the Ministry vide G.S.R. 414(E) dated 30th May,
2008.
28. Vehicular pollution control and its
management plan should be submitted.
29. A write up on use of high calorific
hazardous wastes from all the sources in kiln and commitment regarding use of
hazardous waste should be included.
30. Ambient air quality at 8 locations
within the study area of 10 km., aerial coverage from project site with one
AAQMS in downwind direction should be carried out.
31. The suspended particulate matter
present in the ambient air must be analyzed for the presence of poly-aromatic
hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
32. Determination of atmospheric inversion
level at the project site and assessment of ground level concentration of
pollutants from the stack emission based on site-specific meteorological
features.
33. Air quality modeling for all the
plants proposed including mine for specific pollutants needs to be done. APCS
for the control of emissions within 50 mg/Nm3 should be included.
Cumulative impacts of cement plant, Captive Power Plant and mines located at a
distance of 2.0 km on the ambient air
quality shall be assessed.
34. Action plan to follow National Ambient
Air Quality Emission Standards issued by the Ministry vide G.S.R. No. 826(E)
dated 16th November, 2009 should be included.
35. Ambient air quality monitoring
modeling along with cumulative impact should be included for the day (24 hrs)
for maximum GLC along with following :
i) Emissions (g/second) with and without
the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
36. Impact of the transport of the raw
materials and end products on the surrounding environment should be assessed
and provided.
37. One season data for gaseous emissions
other than monsoon season is necessary.
38. Presence of aquifer(s) within 1 km of
the project boundaries and management plan for recharging the aquifer should be
included.
39. Source of surface/ground water level,
site (GPS), cation, anion (Ion Chromatograph), metal trace element (as above)
chemical analysis for water to be used. If surface water is used from river,
rainfall, discharge rate, quantity, drainage and distance from project site
should also be included.
40. Ground water analysis with bore well
data, litho-logs, drawdown and recovery tests to quantify the area and volume
of aquifer and its management.
41. Ground water modeling showing the
pathways of the pollutants should be included
42. Column leachate study for all types of
stockpiles or waste disposal sites, at 20 oC-50 oC should
be conducted and included.
43. Action plan for rainwater harvesting
measures at plant site should be submitted to harvest rainwater from the roof
tops and storm water drains to recharge the ground water and also to use for
the various activities at the project site to conserve fresh water and reduce
the water requirement from other sources.
Rain water harvesting and groundwater recharge structures may also be
constructed outside the plant premises in consultation with local Gram
Panchayat and Village Heads to augment the ground water level. Incorporation of
water harvesting plan for the project is necessary, if source of water is bore
well.
44. Permission for the drawl of water from
the concerned authority and water balance data including quantity of effluent
generated, recycled and reused and discharged is to be provided. Methods
adopted/to be adopted for the water conservation should be included.
45. A note on the impact of drawl of water
on the nearby River during lean season.
46. Surface water quality of nearby River
(60 m upstream and downstream) and other surface drains at eight locations must
be ascertained.
47. If the site is within 10 km radius of
any major river, Flood Hazard Zonation Mapping is required at 1:5000 to
1;10,000 scale indicating the peak and lean river discharge as well as flood
occurrence frequency.
48. A note on treatment of wastewater from
different plants, recycle and reuse for different purposes should be included.
49. Provision of traps and treatment
plants are to be made, if water is getting mixed with oil, grease and cleaning
agents.
50. If the water is mixed with solid
particulates, proposal for sediment pond before further transport should be
included. The sediment pond capacity should be 100 times the transport
capacity.
51. The pathways for pollution via
seepages, evaporation, residual remains are to be studied for surface water
(drainage, rivers, ponds, lakes), sub-surface and ground water with a
monitoring and management plans.
52. Ground water monitoring minimum at 8
locations and near solid waste dump zone, Geological features and
Geo-hydrological status of the study area are essential as also. Ecological status (Terrestrial and Aquatic)
is vital.
53. Action plan for solid/hazardous waste
generation, storage, utilization and disposal. A note on the treatment, storage
and disposal of all type of solid waste should be included. End use of solid
waste viz. fly ash etc. and its composition should be covered.
54. All stock piles will have to be on top
of a stable liner to avoid leaching of materials to ground water.
55. Action plan for the green belt
development plan in 33 % area should be included. The green belt should be
around the project boundary and a scheme for greening of the travelling roads
should also be incorporated. All rooftops/terraces should have some green
cover.
56. A scheme for rainwater harvesting has
to be put in place. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well. Efforts should be made to make use
of rain water harvested. If needed, capacity of the reservoir should be
enhanced to meet the maximum water requirement. Only balance water requirement
should be met from other sources.
57. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
58. Action plan for the green belt
development plan in 33 % area should be included. The green belt should be
around the project boundary and a scheme for greening of the traveling roads
should also be incorporated. All rooftops/terraces should have some green
cover.
59. Detailed description of the flora and
fauna (terrestrial and aquatic) should be given with special reference to rare,
endemic and endangered species.
60. Disaster Management Plan including
risk assessment & damage control needs to be addressed and included.
Landslide hazard map and mitigation plan, Earthquake history and management
plan should be submitted.
61. Occupational health:
a)
Details of existing Occupational & Safety
Hazards. What are the exposure levels of above mentioned hazards and whether
they are within Permissible Exposure level (PEL). If these are not within PEL,
what measures the company has adopted to keep them within PEL so that health of
the workers can be preserved,
b)
Details of exposure specific health status
evaluation of worker. If the workers’
health is being evaluated by pre designed format, chest x rays, Audiometry,
Spirometry, Vision testing (Far & Near vision, colour vision and any other
ocular defect) ECG, during pre placement and periodical examinations give the
details of the same. Details regarding last month analyzed data of
abovementioned parameters as per age, sex, duration of exposure and department
wise.
c)
Annual report of heath status of workers with
special reference to Occupational
Health and Safety.
62. Plan for the implementation of the
recommendations made for the cement plant in the CREP guidelines must be
prepared.
63. At least 5 % of the total cost of the
project should be earmarked towards the Enterprise Social Commitment based on
Public Hearing issues and item-wise details along with time bound action plan
should be prepared and incorporated.
64. A note on identification and
implementation of Carbon Credit project should be included.
65. Total capital cost and recurring
cost/annum for environmental pollution control measures.
66. Public hearing issues raised and
commitments made by the project proponent on the same should be included
separately in EIA/EMP Report in the form of tabular chart with financial budget
for complying with the commitments made.
67. Any litigation pending against the
project and / or any direction / order passed by any Court of Law against the
project, if so, details thereof.
It was decided that ‘TORs’ prescribed
by the Expert Appraisal Committee-1
(Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. Where the
documents provided are in a language other than English, an English translation
should be provided. The draft EIA/EMP report shall be submitted to the Madhya
Pradesh Pollution Control Board for public hearing. The issues emerged and
response to the issues shall be incorporated in the EIA report. The final EIA
report shall be submitted to the Ministry for obtaining environmental
clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP report including public hearing
proceedings.
Any
Other Item
35.3.17
Expansion of Steel
Plant (1,20,000 TPA to 2,50,000 TPA) at Jagdishnagar, District Raigad, Maharashtra by M/s Mahindra Ugine Steel Co.
Limited (MUSCO) – regarding Reconsideration
The above proposal was considered in the 33rd
Meeting of the Expert Appraisal Committee (Industry-1) held during 27th
& 28th February, 2012. The committee noted that
the presentation was not as per the ToRs accorded and a Senior Official of the
Project Proponent, who can make commitments, was also not present. The proposal
was deferred for reconsideration in the next meeting at the request of the
project proponent.
The project authorities and their
consultant, M/s Mahabal Enviro Engineers Pvt. Ltd, Thane gave
a detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken as per Terms of Reference (ToRs)
awarded during the 78th Meeting of the Expert Appraisal Committee
(Industry) held during 20th – 22nd February,
2008 for
preparation of EIA/EMP. The project activity is listed at S. No. 3(a) in Secondary
Metallurgy Industries under Category ‘B’ of the Schedule of EIA Notification
2006 and appraised
by the SEIAA/SEAC. However, due to non existence of SEIAA/SEAC in Maharastra at the time of application, the proposal was
appraised
by the Expert Appraisal Committee (Industry) of MoEF.
M/s Mahindra Ugine Steel Co.
Limited (MUSCO) have proposed for expansion of Steel Plant (1,20,000 TPA to
2,50,000 TPA) at Jagdishnagar, District Raigad,
Maharashtra. The total project area is 71 ha, which is in possession and
expansion will be done within the existing premises. The existing green belt
area is 21.6 ha and 2 ha of area will be developed into green belt. Rs. 22.71 Crores and Rs.
3.7 Crores are earmarked towards the capital and recurring cost per annum towards
pollution control measures.
Following are the
details of existing and proposed products and their production capacities:
Name of Product |
Existing
Production |
Proposed
Production |
Annual
Total Production after expansion |
Alloy Steel, tool
steel |
4,803 |
19,197 |
24,000 |
Carbon construction,
Alloy Construction Steel |
79,469 |
49,531 |
1,29,000 |
Bearing Steel |
45,701 |
-3,701 |
42,000 |
Off shore steel |
20,027 |
24,973 |
45,000 |
Total |
1,50,000 |
90,000 |
2,40,000 |
The primary raw material is scrap,
which is mostly imported and brought in closed containers. The existing and
proposed power requirement for expansion are 4,13,692 kWh/day and 3,63,361
kWh/day respectively. The existing and proposed water requirement for expansion
is 4,740 KLD and 1,510 KLD respectively. Water allocation for drawl of 6,670
KLD from River Patalganga is present.
Primary Fume extraction system for 50
T EBT Furnace of capacity 2,10,000 m3/hr with Combustion chamber,
water cooled duct, gas cooling tower, bag house, ID Fan & chimney is
installed. Fume extraction system for LRF 1 & LRF 2 of capacity 1,10,000 m3/hr
with bag house, ID fan & chimney is installed. Secondary
Fume Extraction system for 50 T EBT Furnace of capacity 6,00,000 m3/hr
with canopy , air cooled duct, bag house, ID fan & chimney is installed. There is no
generation of process wastewater. Slag will be used as raw material for making
tiles. Process dust will be used fro making paving blocks. Coal ash will be
supplied to brick manufacturers.
Public
hearing/Public consultation was conducted by the Maharashtra Pollution
Control Board on 30.7.2011. The issues raised in the public hearing were
regarding pollution control measures, green belt development etc. which have
been addressed in the final EIA/EMP report.
After detailed deliberation, the
Committee recommended the project for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
i.
The company shall install wet
scrubber, bag filters etc. to control the particulate emissions below 50
mg/Nm3.
iii.
Gaseous emission levels including
secondary fugitive emissions from all the sources shall be controlled within
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008 and regularly monitored. Guidelines / Code of
Practice issued by the CPCB should be followed.
v.
The total water requirement for proposed
expansion shall not exceed 1,510 KLD. No effluent shall be discharged and
‘zero’ discharge shall be adopted.
vi.
Risk and Disaster Management Plan along with the mitigation
measures shall be prepared and a copy submitted to the Ministry’s Regional Office at Bhopal, SPCB and CPCB within 3 months
of issue of environment clearance letter.
vii.
As proposed, green belt shall be
developed in 33 % of the plant area. Selection of plant species shall be as per
the CPCB guidelines in consultation with the DFO.
ix.
At least 5 % of the total cost of
the project shall be earmarked towards the Enterprise Social Commitment based
on Public Hearing issues and item-wise details along
with time bound action plan should be prepared and submitted to the Ministry’s
Regional Office at Bhopal. Implementation of
such program should be ensured accordingly in a time bound manner.
35.3.18
Expansion of Captive Power Plant generation
from 70.3 MW to 74.8 MW at Village Dandeli, Tehsil Haliyal, District Uttar
Kannada in Karnataka by M/s West Coast Paper Mills Limited - regarding
reconsideration for amendment in EC
The above proposal was
considered in the 30th Meeting of the Expert Appraisal Committee
(Industry-1) held during 28th & 29th November, 2011. After detailed deliberations, the Committee recommended for revision of CPP capacity from 30 MW to 34.5 MW for reconsideration
after submission of following documents and information:
· EIA / EMP report.
·
Water requirement
in the paper mill and effluent manufacturers.
·
Coal linkage
documents
·
Chemical and Trace
element analysis of coal and raw material.
The above information
was submitted by the PP. The PP and
their consultant, M/s Kadam Environmental
Consultants, Vadodara made a presentation before the EAC. After
detailed deliberation, the Committee recommended the project for amendment in environmental
clearance i.e. revision
of CPP capacity from 30 MW to 34.5 MW subject to submission of Chemical and Trace Element
analysis of coal from the two different coal fields proposed and Arsenic & Chromium
management plan.
35.3.19
Proposed Integrated Steel Plant (1.47 MTPA)
with 298 MW Captive Power Plant at Sukhda, Katod, Kekrabhat in Dabara Tehsil,
District Janjgir-Champa in Chhattisgarh by M/s
SKS Ispat & Power Limited - regarding TORs reconsideration
The
proponent informed that they will not be able to attend the meeting. The
Committee decided to consider the project as and when requested by the
proponent.
35.3.20
Proposed 1.8 MTPA Cement Plant at Village
Rauri, District Solan in Himachal Pradesh by M/s Gujarat Ambuja Cements
Limited - regarding reconsideration for Amendment in environmental clearance
The above proposal was
considered in the 33rd Meeting of the Expert Appraisal Committee
(Industry-1) held during 27th & 28th February, 2012. The
Committee noted that the material was not circulated to EAC before the meeting.
The committee sought the following:
·
A copy of the WAPCOS
Report
·
Impact of ground
water drawl on water table etc.
The above information was submitted by the PP and the PP have also made a presentation before the committee. It was submitted
by the proponent that water consumption will be optimized from 800 cum/day to
500 cum/day. The permission from groundwater extraction was obtained from I
& PH Division Arki, District Solan, vide their letter no. nil dated 13/9/2011
and from Gram Panchayat- Darlaght Tehsil Arki, District Solan vide their letter
no. 167 GDP – 16-9-11-273 dated 13/9/2011. The abstraction of 500 cum/day
groundwater will result in the ground water development stage from 17.63 % to
18.16 % and area will still remain in SAFE category. An amount of 4,80,000 cum
ground water will be recharged annually with proposed 20 number of recharge
structures in plant and colony including roof top RWH. No adverse impact on
ground water regime is expected owing to water augmentation carried out by the
proposed recharge structures.
After detailed deliberations, the committee has recommended for
amendment in
the said environmental clearance for use of 500 cum/day of ground water.
35.3.21
Integrated Steel Plant (3.0 MTPA) along
with 300 MW Captive Power Plant
at Godapiasal, Paschim Medinipur in West Bengal by M/s JSW
Steel Ltd. - regarding transfer of Environment Clearance to Group
Companies
The above proposal was considered in the 34th Meeting of the
Expert Appraisal Committee (Industry-1) held during 29th & 30th
March, 2012. The discussion and deliberations on the subject matter could not be
completed and it was decided that the matter shall be taken up in the next
meeting.
The PP again made a detailed presentation before the
EAC and highlighted on the relative stakes of JSW Bengal Steel Limited and JSW
Energy (Bengal) Limited in various aspects and the anticipated environmental
impacts.
After detailed deliberations, the committee has recommended the transfer of Environmental Clearance accorded to M/s
JSW Steel Limited to M/s JSW Bengal Steel Ltd. for 3 MTPA Steel Plant and JSW Energy (Bengal) Limited for the 300 MW Captive Power Plant subject to the specific and general environmental
conditions.
The meeting
ended with a vote of thanks to the Chair. It was decided that the 36th
EAC (I-1) will be held on 24th -25th May, 2012.
**************
LIST OF PARTICIPANTS IN 35th
EAC (INDUSTRY-1) MEETING (26th
- 27th April, 2012)
Expert
Appraisal Committee (Industry-1) : |
||||
1. |
Dr.
T. S. Vijayaraghavan |
Chairman |
P |
|
2. |
Shri.
Shiban Raina |
Vice-Chairman |
P |
|
3. |
Prof. Manju Mohan |
Member |
P |
|
4. |
Prof.
Jayanta Bhattacharya |
Member |
A |
|
5. |
Prof.
R.C. Gupta |
Member |
A |
|
6. |
Dr.
R.M. Mathur |
Member |
P |
|
7. |
Dr.
S. K. Dave |
Member |
P |
|
8. |
Prof.
C. S. Dubey |
Member |
P |
|
9. |
Prof.
Pradeep Kumar Garg |
Member |
A |
|
10. |
Dr.
K. Sankar |
Member |
P |
|
MOEF
Officials : |
||||
11. |
Dr.
P.L. Ahujarai |
Scientist
‘F’ & Member Secretary |
||
12. |
Shri
Ramesh Motipalli |
Scientist
‘C’ |
||
13. |
Shri
P.R. Sakhare |
Research
Officer |
||
***************