(a) Name of the project : Exploration and Production of coal bed methane gas in Raniganj (South) CBM Block, West Bengal by M/s Great Eastern Energy Corporation Ltd. ; Amendment in EC regarding for replacement of 20 CBM wells w
(e) Joint Venture (Yes/No) : No 2. | Address for the Correspondence |
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006 |
(a). Major Activity. : 1(b) Offshore and onshore oil and gas exploration, development & production
Minor Activity : No
Major Sub Activity. : Onshore oil & Gas Exploration
Minor Sub Activity : No
(b). Category : A
Reason for applicant at central level/state level(in case of B1 and B2 projects): No
(a) Plot No/Survey No/Khasra No : TALKURI, SURAJNAGAR, KALIDASPUR, SALMA, CHOWKHURI
(b) Village : Talkuri
(c) Tehsil : asansol
(d) District : Barddhaman
(e) State : West Bengal
(f) Pin Code : 713305
(g) Bounded Latitudes (North) : Yes
From : Degree:23, Minutes : 33, Second :30
To : Degree:23, Minutes : 41, Second :35
(h) Bounded Longitudes (East) : Yes
From : Degree:86, Minutes : 47, Second :00
To : Degree:87, Minutes : 04, Second :50
(i) Survey of India Topo Sheet No : 73/1/4 5 | Details of Environment Clearance |
(a) Project Name : Exploration and Production of coal bed methane gas in Raniganj (South) CBM Block, West Bengal by M/s Great Eastern Energy Corporation Ltd. ; Amendment in EC regarding for replacement of 20 CBM wells w
(b) MoEF&CC / SEIAA File No : J-11011/352/(2010)-IA II (I)
(c) Date of issue of EC : 24/11/2011 (d) Uploaded EC letter (PDF Only): 6 | Details of Consent to Operate |
(i) Whether Consent to operate obtained (Yes/No) ? : Yes (ii) Uploaded copies of all Consent to operate obtained since inception:
(iii)Date of issue : 30/04/2019
(iv)Valid Upto: 31/01/2024
(v)File No : C0118225
(vi)Application No : No (vii)Uploaded copy of Consent to operate valid as on Date:
Amendment in Configuration/ Amendments in Clearance condition/ Other (specify) : amendment in configuration 8 | Details of Product (as per the approved EC) |
Details of Products |
---|
S.no | Product / Activity (Capacity/ Area). | Quantity | Unit | Mode of Transport/ Transmission of Product |
---|
1 | Production wells for coal bed methane | 200 | numbers | others |
2 | Gas gathering station (GGS) | 5 | numbers | others |
3 | Central Gathering Stations (CGS) | 5 | numbers | others |
9 | Details of Configuration (Multiple Entries Allowed) |
Details of Configurations |
---|
S.no | Plant/ Equipment/ Facility | Existing Configuration | Proposed Configuration | Final configuration after Amendment | Remarks if Any |
---|
1 | facilities | Gas gathering stations (5 numbers) | - | Gas gathering stations (5 numbers | no chnage in exisitng facility |
2 | Facility | Steel pipelines from GGS to CGS | - | Steel pipelines from GGS to CGS | no chnage in exisitng facility |
3 | Wells | Total 200 number CBM wells | Out of Total 200 wells: 180 CBM wells and 20 shale | Out of Total 200 wells: 180 CBM wells and 20 shale | chnages in accordance with the MOPNG notification dated 20th August 2018 |
4 | faciity | Central Gathering Station (5 numbers) | - | Central Gathering Station (5 numbers) | no chnage in existing facility |
5 | Facility | MDPE pipeline for connection well to GGS | - | MDPE pipeline for connection well to GGS | no change in existing facility |
6 | Facility | Steel pipelines from CGS to various gas consumers | - | Steel pipelines from CGS to various gas consumers | no chnage in existing facility |
Reason for Amendment : As per the New MoPNG
Notification dated 20th August,
2018, GEECL is allowed to
explore and exploit
unconventional hydrocarbons
(Shale gas) in the existing
Raniganj (South) CBM block 11 | Any Other Amendment required |
Any Other Amendment Required |
---|
S.no | Reference of Approved EC | Description as per Approved EC | Description as per Proposal. | Remarks |
---|
1 | Paragraph 2.0 | up to 1100 m depth to produced CBM | up to 1100 m for CBM and 3000 m for shale gas | shale layer in area found at 3000m |
2 | Specific Condition A (ii) | up to a depth of 1100 m | up to depth of 1100 m for CBM and 3000 m for shale | shale layer in area found at 3000 m |
12 | Details of EIA Consultant |
Have you hired Consultant for preparing document (Yes/No) ? : Yes
(i) Accereditation No : NABET/EIA/1922/RA 0138
(ii) Name of EIA Consultant : KADAM ENVIRONMENTAL CONSULTANTS
(iii)Address : 871/B/3 GIDC MAKARPURA, VADODARA
(iv)Mobile No: 9714861611
(v)Landline No : 02656131004
(vi)E-mail Id : sangram@kadamenviro.com
(vii)Category of Accreditation : Category A
(viii)Sector of Accreditation : 1(b)
(ix)Validity of Accreditation : 25.05.2022 (x)Uploaded certificate of Accreditation certified by QCI/NABET (Upload PDF Only): 13. | Document to be Attached |
(a) Uploaded addendum to EIA/EMP Report : No Data
(b) Uploaded Copy of revised -Feasibility Report /Detailed Project Report (DPR) / Detailed Engineering Report / Detailed Conceptual Plan / Approved Mining Plan (in case of mining proposals) : No Data
(c) Upload Copy of final Layout Plan : No Data (d)Uploaded Cover Letter duly signed by the project proponent or authorized person: (e)Uploaded a copy of authorization duly signed by the project proponent in support of the person making this application on behalf of the User Agency: (f)Uploaded Additional File, If any:
(g)Uploaded Proposal Presentation : No Data Details of State of the project |
---|
S.no. | EDS Sought Date | EDS Sought | Letter |
---|
NIL |
Additional Detail Sought |
---|
S.no. | Ads Letter | Remarks | Date of Submission |
---|
1. | NIL | Sir/Madam,
This is regarding the proposal No. IA/WB/IND2/115543/2019 dated 24 August, 2019 for amendment in the EC granted by the Ministry vide letter dated 24th November, 2011 in favour of M/s Great Eastern Energy Corporation Limited to the project ‘Expansion of Exploration and Production of Coal Bed Methane gas in Raniganj (South) CBM Block’ located at Burdwan, Bankura and Purulia District (West Bengal).
In this regard, I am directed to request you to submit the technological details of shale gas drilling, for taking the proposal forward. | 20 Feb 2020 |
2. | Additional Information | Technological Details of shale gas drilling is uploaded | 23 Apr 2020 |
(a): I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, The project will be rejected and clearance given, If any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity / construction / expansion has since been taken up. (b)Name : No (c)Designation: No (d)Company: No (e)Address: No