Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
Proposal No.
*
:
SIA/JK/MIN/56864/2018
Project Name
*
:
(River Bed Material) Basantar River Upstream NH1A Bridge, Samba at Block No. 3/5, Village- Daboh Tehsil & District- Sambha, J&K (Area- 9.98 ha
Project Sector
*
:
Non-Coal Mining
Date of submission
*
:
12 Nov 2020
Submitted by Proponent
Query for Shortcoming(if any) by SEIAA
Resubmission of Proposal by Proponent
Accepted by SEIAA and forwarded to SEAC
Query for Shortcoming(if any) by SEAC
Resubmission of Proposal by Proponent
Accepted by SEAC
Forwarded to SEIAA for EC
EC Letter Uploaded On/EC Granted
22/09/2020
22/09/2020
22/09/2020
29/09/2020
15/10/2020
12/11/2020
21/11/2020
04/12/2020
02/02/2021