TimeLine Details
Form for seeking prior approval of Central Government under section 2 of the Forest(Conservation) Act,1980 for Diversion of fresh forest area
Proposal received date at each stage of flow.
Proposal No.
*
:
SIA/GJ/IND2/37351/2018
Project Name
*
:
Proposed New SSP Manufacturing Unit (SSP -200 MTPD and GSSP-200 MTPD)
Project Sector
*
:
Industrial Projects - 2
Date of submission
*
:
29 Aug 2019
Submitted by Proponent
Query for Shortcoming(if any) by SEIAA
Resubmission of Proposal by Proponent
Accepted by SEIAA and forwarded to SEAC
Query for Shortcoming(if any) by SEAC
Resubmission of Proposal by Proponent
Accepted by SEAC
Forwarded to SEIAA for EC
EC Letter Uploaded On/EC Granted
29/08/2019
27/08/2019
29/08/2019
03/09/2019
N/A
N/A
12/09/2019
03/04/2021
N/A