APPENDIX I
(See Paragraph-6)
CATEGORY - B
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
Whether proposal involved violation of EIA notificationNA
Weather Consent to Establishment ObtainedNA
Upload copy of CTE NA
1.Name of the Project Production of 540 ltrs per day of country liquor (max.) production at Dapala village in Kantamal Tahasil in the district of Boudh of Odisha State.
Proposal No SIA/OR/IND2/51535/2020
2.Project Sector Industrial Projects - 2
3.Location of the project Dapala
4.
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
5.Brief summary of projectAnnexure-Brief summary of project
6.State of the projectOrissa
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)OrissaBoudhKantamal
7.Town / VillageDapala
8.Plot/Survey/Khasra No.Village-Dapala Khata No-64,Plot No. 782 Area-0.120 Dec, Kissam –Gharabadi
9.S. No. in the schedule5(g) Distilleries
10. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled 0.540 KLD ha.
11.
New/Expansion/ModernizationNew
12. Category of project B
13. Does it attract the general condition? If yes, please specify No
15. Does it attract the specific condition? No
16.Is there any litigation pending against the project?No
17. Nearest railway station along with distance in kms. Rairakhol, 80 km
18. Nearest airport along with distance in kms Bhubaneswar, 250 km
19. Nearest Town/City/District Headquarters along with distance in kms Boudh , 40 km
20. Distance of the project from nearest Habitation 1.0 , 1.0 km
21.
Details of alternative sites examined shown on a toposheetNo
22.
Whether part of interlinked projects?No
23.
Whether the proposal involves approval/clearance under the Forest (Conservation)Act,1980?No
24.
Whether the proposal involves approval/clearance under the wildlife (Protection)Act,1972?No
25.Whether the proposal involves approval/clearance under the C.R.Z notification,2011?No
26.
Whether there is any Government Order/Policy relevent/relating to the site?No
27.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
28. Project Cost(in Lac.) 0.08
30. Whether the proposed project/activity located in notified Industrial area(Yes/No) No
Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes Total area of 0.120 ac. has already been used for installation of this unit. The unit has the entire required infrastructure present there. No additional land will be required. The existing land is a private land and has been changed to industrial use.
1.2 Clearance of existing land, vegetation and buildings? No It is an existing unit.
1.3 Creation of new land uses? No The existing land has already been changed to industrial purpose.
1.4 Pre-construction investigations e.g. bore houses, soil testing? No Not required as it’s an existing unit.
1.5 Construction works? No Not required as it’s an existing unit.
1.6 Demolition works? No Not required.
1.7 Temporary sites used for construction works or housing of construction workers? No Not required.
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations No Not required.
1.9 Underground works including mining or tunneling? No Not required.
1.10 Reclamation works? No Not required.
1.11 Dredging? No Not required.
1.12 Offshore structures? No Not required.
1.13 Production and manufacturing processes? Yes Fermentation & Distillation process is adopted. Details process is incorporated in PFR.
1.14 Facilities for storage of goods or materials? Yes Adequate storage facilities for raw material and finished product have been provided within the project area.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes About 153 Kg of mahua residue & 127\ Kg of Ash from Bhatti is generated daily and being provided to bricks maker unit.
1.16 Facilities for long term housing of operational workers? No Not applicable
1.17 New road, rail or sea traffic during construction or operation? No Not applicable
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No Not applicable
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No Not applicable
1.20 New or diverted transmission lines or pipelines? No Not applicable
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No Not applicable
1.22 Stream crossings? No Not applicable
1.23 Abstraction or transfers of water from ground or surface waters? Yes Total 3 KLD of water is required per day. Total water is withdrawl from ground water source.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Mahul flower are being sourced from the local market and transported to the site by road through trucks.
1.26 Long-term dismantling or decommissioning or restoration works? No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No
1.28 Influx of people to an area in either temporarily or permanently? Yes There are 8 no. of people engaged in this project and are sourced from nearby village.
1.29 Introduction of alien species? No
1.30 Loss of native species or genetic diversity? No
1.31 Any other actions? No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes Dapala O.S. Shop is on gharabadi land over 0.12 Dec of area
2.2 Water (expected source & competing users) unit: KLD Yes 3 KLD is being sourced from Ground water source.
2.3 Minerals (MT) Yes Raw material required is as follows: Mahul flower – 478 Kg /day Reice Husk – 415 Kg /day Water – 3 KLD
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) No
2.5 Forests and timber (source – MT) No
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) No
2.7 Any other natural resources (use appropriate standard units) No
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No No hazardous substances are being used in the unit.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No Project activities are not likely to cause changes in occurrence of disease or affect disease vectors.
3.3 Affect the welfare of people e.g. by changing living conditions? No Local people are benefited by means of direct and indirect employment.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No
3.5 Any other causes No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) Yes Domestic waste generated from the area will be disposed.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) No
4.4 Other industrial process wastes Yes Mahua Flower Residue 153 Kg /day and 127 Kg/day Husk Ash
4.5 Surplus product Yes Mahua flower residue generated will be used as manure for agriculture and cattle feed.
4.6 Sewage sludge or other sludge from effluent treatment No
4.7 Construction or demolition wastes No
4.8 Redundant machinery or equipment No
4.9 Contaminated soils or other materials No
4.10 Agricultural wastes No
4.11 Other solid wastes No
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes No fossil fuel is used. Only Burning of Husk involved, which consists PM, Sox NOx would be discharge to atmosphere through chimney of suitable height.
5.2 Emissions from production processes Yes Burning of Husk 0.5 kg/hr.
5.3 Emissions from materials handling including storage or transport No
5.4 Emissions from construction activities including plant and equipment No
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust generated as mentioned above. No odour problem envisaged.
5.6 Emissions from incineration of waste No
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No
5.8 Emissions from any other sources No
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers No There is no noise as no machinery is involved.
6.2 From industrial or similar processes No
6.3 From construction or demolition No
6.4 From blasting or piling No
6.5 From construction or operational traffic No
6.6 From lighting or cooling systems No
6.7 From any other sources No
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes There will be no discharge of sewage from the unit as water is required for only cooling purpose, which will be recycled.
7.3 By deposition of pollutants emitted to air into the land or into water Yes Since the bhatti is connected with chimney of adequate size, there will be minimal emission.
7.4 From any other sources No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances No
8.2 From any other causes No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No No such event is known to have occurred in the area.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Supporting facilities are available as it is an existing unit. Owner will contribute towards improvement of rural population in the vicinity.
9.2 Lead to after-use of the site, which could have an impact on the environment No
9.3 Set a precedent for later developments No
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Yes Kankadungri RF – 1.0 Km Narghant RF - 10.0 Km
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Forest as above Mahanadi River -= 20.0 Km
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No
4 Inland, coastal, marine or underground waters No
5 State, National boundaries Yes
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas Yes SH 41 – 10 Km
7 Defence installations No
8 Densely populated or built-up area Yes Kantamal - 15.0 Km
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes Dapala - 1.0 Km
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No
(IV) PROPOSED TERMS OF REFERENCE FOR EIA STUDIES
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
ADDITIONAL MULTIPLE ENTERIES
Sr. no. Remarks Uploaded Additional Attachments
1 Land Document Annexure-Additional Attachments
(V) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge
V.(i)
NameSMT MIRA DEVI
DesignationPropreitor
Company SMT MIRA DEVI
AddressAt - Shaktinagar, PS - Ainthapalli
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)18/06/2020Please complyEDS Letter
(2.)19/06/2020CompliedEDS Letter
           Transferred Details(Category A To B)
S. No.Category A(Proposal No)Category B(Proposal No)Transferred DateReasonLetter
NO Record