Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Commercial complex "Wave One" at Plot no. L-2A (L-2A/1 & L-2A/2), sector-18, Noida, Uttar Pradesh
(b)Name of the Company / Organisation WAVE CITY CENTRE PVT LTD
(c)Registered Address Plot No. 02A, Block L, Sector-18, Gautam Buddh Nagar, Noida, Uttar Pradesh,,Gautam Buddha Nagar,Uttar Pradesh-201301
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Harmandeep Singh Kandhari
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Plot No. 02A, Block L, Sector-18, Gautam Buddh Nagar, Noida, Uttar Pradesh,Gautam Buddha Nagar,Uttar Pradesh-201301
(d)Pin code 201301
(e)E-mail waveone2019@gmail.com
(f)Telephone No. 11-47325555
(g)Fax No. 47325525
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(a) Building and Construction projects
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/UP/MIS/32034/2019
(e)Master Proposal Number(Single Window) SW/97484/2019
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Modernization
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot no. L-2A(L-2A/1 & L-2A/2)
(b)Pincode 201301
(c)Bounded Latitudes (North)
From
Degree 283409.07
Minutes
Second
From
Degree 283414.85
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 771922.27
Minutes
Second
From
Degree 771922.67
Minutes
Second
(e)Survey of India Topo Sheet No. 4316
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 204
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 2699/Parya/SEAC/773/2011/AD(H)
(b)Date of Apply of EC 21 Feb 2019
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per EIA Notification 2006, All the Building or
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. 0
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1.68598020.259620Hectares(ha)OthersNot Applicable
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Commercial complex0202596202596Environement clearance extension
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 22 Feb 2019
(iv)Valid Upto 22 Feb 2019
(v)File No. not issued
(vi)Application No. Not issued
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 00
(b) Funds Allocated for Environment Management (Capital) (in crores) 0
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0
(e) Funds Allocated for Environment Management Capital(%) NaN
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Diesel2000Otherslitre/hourNARoad0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 03 Dec 2010 To 28 Feb 2011
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube94.677.493.6100
(2.)SO2Micro Gram per Meter Cube12.88.212.180
(3.)PM2.5Micro Gram per Meter Cube48.935.247.660
(4.)NOxMicro Gram per Meter Cube29.418.628.380
    14.2.     No. of Ground Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.357.356.58.5
(2.)TDSmg/l6356355002000
(3.)Heavy MetalsManganesemg/l252530100
(4.)Total Hardnessmg/l264264300600
(5.)TSSNA0000
(6.)Fluoridemg/l0.40.411.5
(7.)Chloridesmg/l1861862501000
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA00A
(2.)BODNA00A
(3.)CODNA00A
(4.)DONA00A
    14.4.     No. of Ambient Noise Monitoring Locations : 1
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))63.163.165
(2.)Leq(Night)A-weighted decibels(dB(A))49.549.555
    14.5.     No. of Soil Sample Monitored Locations : 1
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.627.62
(2.)Electric ConductivityMillisiemens per Centimetre203203
(3.)P(Phosphorus)00
(4.)K(Potassium)Milligram per Kilogram320.67320.67
(5.)N(Nitrogen)00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.84 To 58.89
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMunicipal water supply6380Copy of Permission LetterPipelineOtherspipeline022 Feb 2019638
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic, flushing384460STP of 460 KLDReuse within the Plant & Recycling384
16.1.
(a)Total Waste Water Generation 384
(b)Total Discharged Water 0
(c)Total Reused Water 384
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal solid wasteMunicipal Solid Waste3.091Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube10.013.6223<1.65
(2.)NOxMicrogram per Meter Cube22.311857,1.60
(3.)PM10Microgram per Meter Cube84.311.923000.2
(4.)PM2.5Microgram per Meter Cube41.2138.5122<18
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG set (2000KVA)HSD1750.1PM10BDL
(2.)DG set (2000KVA)HSD1750.1SO2BDL
(3.)DG set (2000KVA)HSD1750.1OthersCOBDL
(4.)DG set (2000KVA)HSD1750.1NOx5.6
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 8844
(b)Source UPPCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 5 DG set of capacity of 2000 KVA
(e)Stack Height (in m) 175
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 1.68598
    Total Land 1.68598
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Total Plot Area 1.68598
    Total 1.68598
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Built Up Area20.2596
Total 20.2596
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0NA
(2.)ESAsNA0NA
(3.)ESZsNA0NA
(4.)Wildlife CorridorsNA0NA
(5.)NPANA0NA
(6.)WLSNA0NA
(7.)CorridorsNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0NA
(2.)OthersMetro StationSector 180.2Towards East direction
(3.)ForestKhodnakhurd Reserve Forest17.86South East Direction
(4.)Defence InstallationsNA0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.68598
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Yamuna River
(ii)Direction of Water Bodies in Buffer Area West
(iii)Distance of Water Bodies in Buffer Area 1.1
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 250
(b)Permanent Employment-During Operation 250
(c)Temporary Employment- During Construction 250
(d)Temporary Employment- During Operation 250
(e)No. of working days 365
(f)Total Manpower 1000
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Funds Allocated05050
(2.)Total Area of Green Belt07365.287365
(3.)Percentage of Total Project Area058.0858
(4.)No. of Plants08080
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialDevelopment of the region
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 169
(b)Total No. of Flats to be Build 1
(c)No. of Buildings 1
(d)Total plot area (sqm) 16859.8
(e)Total built up area (sqm) 202596
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 6
    Capacity 28.26
(b)No. of Recharge Pits 6
    Capacity 28.26
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 2485 ECS
5.
Energy Saving Measures:
(a)Source/Mode Solar
(b)Percentage 1
(c)Quantity 60
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Not Applicable
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/ENV/ACO/17/0457
(ii)Name of the EIA Consultant Ascenso Enviro Pvt. Ltd
(iii)Address D-79,IInd Floor Sector-6,Noida-201301
(iv)Mobile No. 9958149985
(v)Landline No. 1204333226
(vi)Email Id projects@amcgroup.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 03 Oct 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter NA
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)13/03/2019Please Submit the Land Papers along with Layout/Building Plan.
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantHarmandeep Singh Kandhari
DesignationDirector
Name of Company (Applicant Name should not be given here)WAVE CITY CENTRE PVT LTD
AddressPlot No. 02A, Block L, Sector-18, Gautam Buddh Nagar, Noida, Uttar Pradesh