Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? Yes
Type of Violation Started the work onsite without prior EC under EIA notification,2006.
Details of Violation Giridih OCP is pre 1993-94 mine.The mine has obtained ToR vide lette ro. F-No.23-268/2018-IA.III(V) dated 27.04.2021.The proejct has come into violation due to production in excess peak production of 1993-94 level i.e.0.23 MTPA
Upload document of Damage Assessment Report
Upload document of Remediation Plan and Natural & Community augmentation plan
Upload TOR Letter(if issued earlier)
Upload EC Letter(if issued earlier)
Details of Project:
(a)Name of the project(s) Giridih OCP
(b)Name of the Company / Organisation CENTRAL COALFIELDS LIMITED
(c)Registered Address DARBHANGA HOUSE CCL HQ, KUTCHERY ROAD, RANCHI, JHARKHNAD,,Ranchi,Jharkhand-834001
(d)Legal Status of the Company Central PSU
2.
Address for the correspondence:
(a)Name of the Applicant Sanjay Kumar Singh
(b)Designation (Owner/ Partner/ CEO) Project Officer
(c)Address DARBHANGA HOUSE CCL HQ, KUTCHERY ROAD, RANCHI, JHARKHNAD,Giridih,Jharkhand-815311
(d)Pin code 815311
(e)E-mail pokabribad@gmail.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/JH/CMIN/77491/2018
(e)Master Proposal Number(Single Window) SW/275526/2022
(f)EAC concerned (for category A Projects only) Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot no. 193, 194, Khata no. 114, 145-147,160,9,11
(b)Pincode 815311
(c)Bounded Latitudes (North)
From
Degree 24
Minutes 10
Second 3.62
From
Degree 24
Minutes 10
Second 42.73
(d)Bounded Longitudes (East)
From
Degree 86
Minutes 14
Second 51.63
From
Degree 86
Minutes 15
Second 41.80
(e)Survey of India Topo Sheet No. 72L/8
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 277
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.06
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Jharkhand
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 23-268/2018-IA.III(V)
(b)Date of Apply of TOR 13 Apr 2018
(c)Date of Issue of TOR / Standard ToR 27 Apr 2021
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :21 Jan 2022
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :26 Feb 2022
Distance of Public Hearing Venue from the Proposed Project :0
Offiecr's Club,Beniadih,CCL,Giriidih Project
State :Jharkhand
District :Giridih
Tehsil :Giridih
Village :Giridih
78Issues related to environment,health,education,road,electricityOthersMr.Alok Kumar,Director,DRDA,Giridih
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Project Area122.70
(2.)Balance life4 years
(3.)Mineable reserve2.30 Mte
(4.)Capacity0.70 MTPA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Capacity700000Tons per AnnumRoad,Rail
(2.)Area122.70HectaresRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 23.67
(b) Funds Allocated for Environment Management (Capital) (in crores) 11.12
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 1
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 1.10
(e) Funds Allocated for Environment Management Capital(%) 46.98
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 157
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 157
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Explosives157Tons per AnnumIDL and IOCLRoad6 Fuel Supply AgreementCopy of Linkage
(2.)HSD0.59Kilo Litre per DayIOCLRoad5 Fuel Supply AgreementCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2020 To 31 Dec 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube27.37.726.680
(2.)PM10Micro Gram per Meter Cube83.751.883.4100
(3.)PM2.5Micro Gram per Meter Cube46.326.84560
(4.)SO2Micro Gram per Meter Cube20.4518.1080
    14.2.     No. of Ground Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA6.686.636.678.85
(2.)TDSmg/l476.3392.90474.60500
(3.)Chloridesmg/l13076128.92250
(4.)Fluoridemg/l0.620.510.6171.5
(5.)OthersCalciummg/l80.2068.9079.9775
(6.)Total Hardnessmg/l288280287.84200
(7.)Heavy MetalsIronmg/l0.120.080.1190.30
(8.)TSSNA0000
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l7.97.4C
(2.)pHNA6.866.7C
(3.)BODmg/l21.90C
(4.)CODmg/l54.90C
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))44.3030.1070
(2.)Leq(Day)A-weighted decibels(dB(A))54.936.975
    14.5.     No. of Soil Sample Monitored Locations : 3
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare492.80268.80
(2.)Electric ConductivityMillisiemens per Centimetre0.510.35
(3.)P(Phosphorus)Kilogram per hectare13.506.90
(4.)K(Potassium)Kilogram per hectare280.20160.70
(5.)pH5.875.41
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 15.40 To 7.32
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 12.10 To 2.49
(c)Whether Ground Water Intersection will be there ? Yes
(d)Upload Copy of Central Ground Water Authority Letter Copy of Central Ground Water Authority Letter
(e)Letter No. CGWA/NOC/MIN/ORIG/2021/13953
(f)Date of Issue 03 Dec 2021
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMine discharge2370Copy of Permission LetterPipelineOthersMine pumpCGWA/NOC/MIN/ORIG/2021/1395303 Dec 2021246
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial1192ETP with oil and grease trap with settling pondReuse within the Plant & Recycling11
(2.)Domestic535350Sewage treatment plant with secondary bioloical treatment technology like activated sludge processOthersSoak pit5350
16.1.
(a)Total Waste Water Generation 546
(b)Total Discharged Water 0
(c)Total Reused Water 546
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)OverburdenIndustrial Waste58000000Tons0OthersRear loading dumperOthersExternal dumping and backfilling
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube18.101.031.1019.2080
(2.)NOxMicrogram per Meter Cube29.601.0310.2536.8580
(3.)PM2.5Microgram per Meter Cube451.031.8046.8060
(4.)PM10Microgram per Meter Cube83.401.034.7088.10100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000Others0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 3000
(b)Source DVC Substation Beniadih
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 122.70
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 122.70
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Private land 122.70
    Total 122.7
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Quarry Area56.35
(2.)OB Dump Area18.68
(3.)OthersInfrastructure4.80
(4.)Safety Zone42.87vacant land is also included
Total 122.7
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNA0no such area is located in the core zone of the project
(2.)WLSNA0no such area is located in the core zone of the project
(3.)ESAsNA0no such area is located in the core zone of the project
(4.)Wildlife CorridorsNA0no such area is located in the core zone of the project
(5.)NPANA0no such area is located in the core zone of the project
(6.)ESZsNA0no such area is located in the core zone of the project
(7.)CorridorsNA0no such area is located in the core zone of the project
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNA0no such area is located in the core zone of the project
(2.)Defence InstallationsNA0no such area is located in the core zone of the project
(3.)Archaeological SitesNA0no such area is located in the core zone of the project
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 122.70
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Pea-fowl,Python and monitor lizard in the buffer zone
(b)Whether conservation plan for Schedule-I Species has been prepared ? Yes
(i)Uploaded copy of conservation plan Copy of conservation plan
(ii)Fund Provision made Capital cost Rs.60 lakh and revenue cost of Rs.28
(iii)Period of Implementation during the life of mine
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Khako river
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Barakar River flowing from west to east at a distance of around 6.0 km to the south of the Giridih mine.
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 6
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 226
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 226
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 99.77
(b)Percentage of Total Project Area 81.31
(c)No. of Plants to be Planted 249425
(d)Funds Allocated for Plantation 4000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialContribution to exchequer
(2.)EnvironmentalEnhancement of green cover of the mine
(3.)Socialthe project will provide direct and indirect employment opportunities.
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)CoalMajor
2.
Mine Capacity in ROM (Run of Mine) 0.7
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. CS/BM/515/2022/609
(b)Date of Approval 14 May 2022
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department CCL Board
(e)Approved Mining Lease Area 122.70
(f)Approved Capacity 0.7
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 2.56
(b)Mineable Reserves (Million Ton) 2.30
(c)Extractable Reserves(Million Ton) 2.30
(d)Percent(%) of Extraction 100
(e)Grade of Coal /Ore /Mineral 10
(f)Stripping Ratio 5.80 : 2.30
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 8
(i)Mining Method Opencast
(j)Life of Mine (Years) 4
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable Yes
(b)No. of seams 1
(c)Thickness of seams to be worked on 11.5
(d)Maximum Thickness of Seams (metres) 12.5
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 122.70
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Land acquired under CB act
(c)Whether Lease Deed Executed ? No
(i)Reason thereof Land acquired under CB act
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Land acquired under CB act
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
(v)No. of year back fill up
(b) Details of Internal Dumps:
(i)No. of Internal Dumps
(ii)Total Area (in Hectare)
(iii)Height (in meter)
(iv)Quantity (in Million Cubic meter)
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare)
(b)Depth (in meter)
(c)Volume (in Million Cubic meter)
12.
Details of Quarry:
(a)Final Void of 20.93 (hectare) at a Depth of 40 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 56.35
13.
Details of Transportation:
(a)In Pit/Underground to Surface Dumpers
(b)Surface to Siding/Loading Tipping trucks
(c)Transportation / Conveyor Details By road
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)WASTE LAND000
(2.)SURFACE WATER BODIES000
(3.)SETTLEMENTS000
(4.)OTHERS(Specify)tenancy land122.700122.7
(5.)AGRICULTURE LAND000
(6.)FOREST LAND000
(7.)GRAZING LAND000
TOTAL122.70122.7
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)INTERNAL OB DUMPS0000
(2.)ROADS0022
(3.)VIRGIN AREA0000
(4.)EXTERNAL OB DUMPS18.680018.68
(5.)GREEN BELT18.200018.2
(6.)TOP SOIL STORAGE0000
(7.)BUILT UP AREA (COLONY/OFFICE)27.470027.47
(8.)EXCAVATION/QUARRY35.4220.93056.35
TOTAL99.7720.9320122.7
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 18.68
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 35.42
(d)Safety Zone(in hectare) 18.20
(e)Final Void of 20.93 (hectare) at a Depth of 40 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 27.47
(h)Total afforestation plant (in hectare) 99.77
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)20030.320.230.230.230.09
(2.)19980.230.230.230.380.15
(3.)20100.23.23.230.48.25
(4.)20080.23.23.23.410.18
(5.)20060.230.23.23.35.12
(6.)20090.23.23.23.40.17
(7.)20050.230.230.230.37.14
(8.)20130.230.230.230.500.27
(9.)20070.23.23.23.350.12
(10.)20160.230.230.230.300.07
(11.)20110.230.230.230.490.26
(12.)20150.230.230.230.45.22
(13.)20040.23.23.23.33.1
(14.)20170.230.230.230.450.22
(15.)20120.230.230.230.530.30
(16.)20140.230.230.230.420.19
(17.)19990.230.230.230.260.03
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/EIA/ACO/22/2339
(ii)Name of the EIA Consultant Central Mine Planning And Design Institute Limited
(iii)Address Gondwana Place, Kanke Road, Ranchi, Jharkhand
(iv)Mobile No. 8987789101
(v)Landline No. 0651279222
(vi)Email Id gmenv.cmpdi@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Coal Mining
(ix)Validity of Accreditation 22 Aug 2024
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)02/06/2022You are requested to upload/submit the following documents for further action:: I. Form-I mentioning all applied khata & plot number. II. DFO Territorial & DFO Wildlife Certificate mentioning all applied khata & plot number (as per the format given in 67th Meeting of SEIAA). III. CO Certificate mentioning all applied khata & plot number (as per the format given in 58th Meeting of SEIAA).
(2.)28/12/2022The correction have been made as per the instruction received
(3.)29/12/2022You are requested to submit the hard copy of proposal in two set (every page of both copies must be attested by Project Proponent) along with Scrutiny fee to this office for further action.
(4.)04/01/2023The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)28/01/2023Clarification sought from PAs.ADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSanjay Kumar Singh
DesignationProject Officer
Name of Company (Applicant Name should not be given here)CENTRAL COALFIELDS LIMITED
AddressDARBHANGA HOUSE CCL HQ, KUTCHERY ROAD, RANCHI, JHARKHNAD
Print