Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) TREND INDIA
(b)Name of the Company / Organisation TREND INDIA
(c)Registered Address Plot no. K1-21 & K1-22, GIDC Estate, Kalol, Dist. Gandhinagar,,Gandhinagar,Gujarat-382721
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Alpesh Patel
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Plot no. K1-21 & K1-22, GIDC Estate, Kalol, Dist. Gandhinagar,,Kalol,Gandhinagar,Gujarat-382721
(d)Pin code 382721
(e)E-mail trendec@rediffmail.com
(f)Telephone No. 2464-000000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/GJ/IND2/51390/2019
(e)Master Proposal Number(Single Window) SW/144596/2020
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.K1-21 & K1-22
(b)Pincode 382721
(c)Bounded Latitudes (North)
From
Degree 23°13'18.36"
Minutes
Second
From
Degree 23°13'18.76"
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72°30'47.40"
Minutes
Second
From
Degree 72°30'47.87"
Minutes
Second
(e)Survey of India Topo Sheet No. 000
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 45
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 45
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratGandhinagarKalolKalol GIDC
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number SIA/GJ/IND2/35858/2019
(b)Date of Apply of EC 29 Jul 2019
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The proposed expansion is in notified Industrial E
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. 000
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)PARA NITRO TOLUENE ORTHO SULFONIC ACID (PANTOSA)100300400OthersMT/MOnthRoad,Rail,OthersShipment
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sulphonation Vessel1 Nos3 Nos4 Nos15 KL Each
(2.)Storage Tank for Sulphuric Acid11220 KL Each
(3.)Oleum Tank12320 KL Each
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 26 Jun 2015
(iv)Valid Upto 15 May 2020
(v)File No. 71100
(vi)Application No. 93955
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 2.00
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.0625
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.02
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.029
(e) Funds Allocated for Environment Management Capital(%) 3.13
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 450
(b)Existing quantity of raw material/fuel 150
(c)Total quantity of raw material/fuel 600
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Oleum350Tons per AnnumOpen MarketRoad25 Open MarketCopy of Linkage
(2.)Para Nitro Toluene150Tons per AnnumOpen MarketRoad25 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube55.7230.7454.7660
(2.)SO2Micro Gram per Meter Cube16.317.6513.7580
(3.)PM10Micro Gram per Meter Cube87.2364.7886.48100
(4.)NOxMicro Gram per Meter Cube22.8411.2515.2080
    14.2.     No. of Ground Water Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l286210600600
(2.)Chloridesmg/l28321010001000
(3.)Fluoridemg/l0.580.251.51.5
(4.)TSSmg/l0.50.311
(5.)TDSmg/l123084320002000
(6.)pHNA8.107.208.508.50
    14.3.     No. of Surface Water Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l4.54.1D
(2.)CODmg/l3517D
(3.)BODmg/l94D
(4.)pHNA8.237.19D
    14.4.     No. of Ambient Noise Monitoring Locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))73.347.185
(2.)Leq(Night)A-weighted decibels(dB(A))66.835.175
    14.5.     No. of Soil Sample Monitored Locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.687.11
(2.)N(Nitrogen)Milligram per Kilogram7163
(3.)K(Potassium)Milligram per Kilogram0.300.21
(4.)Electric ConductivityMillisiemens per Centimetre3521
(5.)P(Phosphorus)Milligram per Kilogram2517
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 15 To 17
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 13 To 15
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC35.81Copy of Permission LetterPipelineIntake Well000006 May 201450
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial Operation5.510PTOthersReuse5.500
16.1.
(a)Total Waste Water Generation 5.5
(b)Total Discharged Water 0
(c)Total Reused Water 5.5
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)SBSHazardous Waste (as per Hazardous and Other Waste Management rules 2016)300Tons50RoadOthersActual Users
(2.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)12.00Tons50RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2.40Kilolitre25RoadAuthorized Recyclers
(4.)Discarded ContainerHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1.6Tons25RoadAuthorized Recyclers
(5.)Dilute Sulphuric AcidHazardous Waste (as per Hazardous and Other Waste Management rules 2016)7200Kilolitre50RoadOthersActual Users
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube55.721.250.0155.7360
(2.)SO2Microgram per Meter Cube16.310.750.0116.3280
(3.)NOxMicrogram per Meter Cube22.840.750.0122.8580
(4.)PM10Microgram per Meter Cube87.231.250.0187.24100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam BoilerBriquettes of Bio Fuel160.1PM10,SO2,NOx150,100,50
(2.)Oleum Tank 02 NosProcess Stack120.05SO250
(3.)Sulphonation VesselProcess Stack120.01SO250
(4.)Sulphonation Vessel 03 NosProcess Stack120.01SO250
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 2200
(b)Source UGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) NA
(e)Stack Height (in m) 00
20.
Land Ownership Pattern:
(a)Forest Land 00
(b)Private Land 0.0829
(c)Government Land 00
(d)Revenue Land 00
(e)Other Land 00
    Total Land 0.0829
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 00
(b)Waste/Barren Land 00
(c)Grazing/ Community Land 00
(d)Surface Water Bodies 00
(e)Settlements 00
(f)Industrial 00
(g)Forest 0000
(h)Mangroves 00
(i)Marine Area 00
(j)Others : NA 00
    Total 0
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant0.082900
Total 0.0829
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA100Not is Study Area
(2.)ESAsNA100Not is Study Area
(3.)ESZsNA100Not is Study Area
(4.)CorridorsNA100Not is Study Area
(5.)Wildlife CorridorsNA100Not is Study Area
(6.)Critically Polluted AreaVatva35Not is Study Area
(7.)WLSNA100Not is Study Area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsGandhinagar35Not is Study Area
(2.)ForestGandhinagar35Not is Study Area
(3.)Archaeological SitesMotera55Not is Study Area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.0829
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired 00
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in Rs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 300
(f)Total Manpower 20
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt5050100
(2.)Percentage of Total Project Area0.0010.0010
(3.)No. of Plants252550
(4.)Funds Allocated250002500050000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalThe expansion proposed with adequate EMS
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 20606
(ii)Name of the EIA Consultant Satva Environ Consultancy
(iii)Address 14,15, Gopal Patel Estate, CTM, Ahmedabad
(iv)Mobile No. 9426347013
(v)Landline No. 0792585321
(vi)Email Id satvaenviron@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 27 Aug 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)04/03/2020Upload Certified Compliance Report as per MoEF&CC Circular dated 30/05/2012 & 07/09/2017.
(2.)28/05/2020The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantAlpesh Patel
DesignationPartner
Name of Company (Applicant Name should not be given here)TREND INDIA
AddressPlot no. K1-21 & K1-22, GIDC Estate, Kalol, Dist. Gandhinagar