Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) DEVELOPMENT OF GROUP HOUSING PROJECT “INTEGRATED TOWNSHIP, MORADABAD” AT VILLAGE MANGUPURA AND MEHALAKPUR MAFI, NEAR NH-24, BYPASS MORE, MORADABAD, UTTAR PRADESH.
(b)Name of the Company / Organisation CHADHA INFRATECH LIMITED
(c)Registered Address D-851, Ilnd Floor, New Friends Colony, New Delhi-110065,,New Delhi,Delhi-110065
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Pankaj Kumar Saxena
(b)Designation (Owner/ Partner/ CEO) GeneralManager
(c)Address D-851, Ilnd Floor, New Friends Colony, New Delhi-110065,,Parliament Street,New Delhi,Delhi-110065
(d)Pin code 110065
(e)E-mail infrachadha@gmail.com
(f)Telephone No. 120-4111527
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/UP/MIS/50786/2019
(e)Master Proposal Number(Single Window) SW/141386/2020
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Mangupura- Gata no. 731, 732, 729, 737, 739, 568,
(b)Pincode 244102
(c)Bounded Latitudes (North)
From
Degree 28.8123
Minutes
Second
From
Degree 28.8233
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.6883
Minutes
Second
From
Degree 78.6991
Minutes
Second
(e)Survey of India Topo Sheet No. 53L/9
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 205
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 1.3
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshMoradabadMoradabadMangupura and Mehalakpur Mafi
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number 4904
(c)Date of Apply of TOR 27 Jun 2019
(d)Date of Issue of TOR / Standard ToR 24 Sep 2019
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As per MoEF Notification, 2006, Township and Area
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Township and Area Development62.59 haIt is a township and Area Development project
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)62.59 of plot area1HectaresRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 369
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.702
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 5.54
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.15
(e) Funds Allocated for Environment Management Capital(%) 0.19
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0.05
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0.05
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)deisel0.05Kilo Litre per DayLocalRoad8 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 11
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube21.211.421.280
(2.)NOxMicro Gram per Meter Cube25.815.225.7580
(3.)PM10Micro Gram per Meter Cube86.353.385.61100
(4.)PM2.5Micro Gram per Meter Cube40.221.340.1160
(5.)OthersCOMicro Gram per Meter Cube6303206302000
    14.2.     No. of Ground Water Monitoring Locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l85.768.22501000
(2.)Fluoridemg/l0.710.571.01.5
(3.)pHNA7.467.26.58.5
(4.)TDSOthersmicroS/cm6506055002000
(5.)Total Hardnessmg/l353.5352.8300600
(6.)OthersIronmg/l0.320.270.30.3
(7.)TSSmg/l0000
    14.3.     No. of Surface Water Monitoring Locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.83.3A
(2.)BODmg/l7.43.9D
(3.)CODmg/l29.414.7E
(4.)pHNA7.67.3A
    14.4.     No. of Ambient Noise Monitoring Locations : 11
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))58.142.565
(2.)Leq(Night)A-weighted decibels(dB(A))48.635.955
    14.5.     No. of Soil Sample Monitored Locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare291.2189.4
(2.)K(Potassium)Kilogram per hectare198.2124.6
(3.)Electric ConductivityOthersmicromhos/cm387304
(4.)P(Phosphorus)Kilogram per hectare34.924.7
(5.)pH7.577.19
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 7
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 7
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater28360Copy of Permission LetterPipelineOthersBore wellN/A03 Jan 20202836
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic sewage37775000MBBR STPOthersReused within the project site37770
16.1.
(a)Total Waste Water Generation 3777
(b)Total Discharged Water 0
(c)Total Reused Water 3777
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)MSWMunicipal Solid Waste7409.5Tons0RoadOthersWaste Management by an NGO
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)Others(Specify)COMicrogram per Meter Cube63010000.64630.642000
(2.)NOxMicrogram per Meter Cube25.810001.7427.5480
(3.)PM2.5Microgram per Meter Cube40.20040.260
(4.)SO2Microgram per Meter Cube21.20021.280
(5.)PM10Microgram per Meter Cube85.610.0785.67100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDiesel300.09PM100.010
(2.)DG SetDiesel300.09SO20.0005
(3.)DG SetDiesel300.09NOx0.26
(4.)DG SetDiesel300.09HBR0
(5.)DG SetDiesel300.09CL20
(6.)DG SetDiesel300.09CS20
(7.)DG SetDiesel300.09PM2.50
(8.)DG SetDiesel300.11PM100.012
(9.)DG SetDiesel300.11NOx0.31
(10.)DG SetDiesel300.09SOCL20
(11.)DG SetDiesel300.11HCL0
(12.)DG SetDiesel300.11CL20
(13.)DG SetDiesel300.09HCL0
(14.)DG SetDiesel300.11BR20
(15.)DG SetDiesel300.11CS20
(16.)DG SetDiesel300.11SO30
(17.)DG SetDiesel300.11SOCL20
(18.)DG SetDiesel300.11NO20
(19.)DG SetDiesel300.11NO30
(20.)DG SetDiesel300.09BR20
(21.)DG SetDiesel300.09NO30
(22.)DG SetDiesel300.11NH30
(23.)DG SetDiesel300.11OthersCO0.11
(24.)DG SetDiesel300.09NO20
(25.)DG SetDiesel300.09SO30
(26.)DG SetDiesel300.11SO20.0006
(27.)DG SetDiesel300.09OthersCO0.10
(28.)DG SetDiesel300.09NH30
(29.)DG SetDiesel300.09H2S0
(30.)DG SetDiesel300.11HBR0
(31.)DG SetDiesel300.11H2S0
(32.)DG SetDiesel300.11PM2.50
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 20000
(b)Source Uttar Pradesh Power Corporation Limited
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 6000 kVA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 62.59
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 62.59
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 52
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0.31
(e)Settlements 0.44
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Plantation, open scrub and brick kiln 9.84
    Total 62.59
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersPlot Area only62.59It is an Area Development Project
Total 62.59
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaMoradabad5Project site is present at the outskirt of Moradabad City
(2.)NPANo0NA
(3.)ESAsNo0NA
(4.)ESZsNo0NA
(5.)CorridorsNo0NA
(6.)Wildlife CorridorsNo0NA
(7.)WLSNo0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersNadiGangan Nadi1.3In North Direction
(2.)ForestNo0NA
(3.)Archaeological SitesNo0NA
(4.)Defence InstallationsNo0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 200
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 62.59
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area The water body shall be retained and preserved by proving a 30 m green buffer
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Gangan Nadi
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 1.3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 80
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 120
(d)Temporary Employment- During Operation 0
(e)No. of working days 330
(f)Total Manpower 205
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 8.71
(b)Percentage of Total Project Area 13.92
(c)No. of Plants to be Planted 1090
(d)Funds Allocated for Plantation 2000000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialLocal People shall be given employment and tangible businesses shall develop
(2.)EnvironmentalThe project as part of its CER, shall lead to improvement of surrounding area through distribution of saplings and solar lanterns to the villagers.
(3.)FinancialThe project has earmarked an amount of Rs. 5.54 crores for CER
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 24
(b)Total No. of Flats to be Build 2592
(c)No. of Buildings 0
(d)Total plot area (sqm) 625909.02
(e)Total built up area (sqm) 931931.3
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 0
    Capacity 0
(b)No. of Recharge Pits 31
    Capacity 2978.2
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 8682 ECS
5.
Energy Saving Measures:
(a)Source/Mode Solar lighting
(b)Percentage 30
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area There are no streams passing through the project s
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. QCI/NABET/EIA/ACO/19/1186
(ii)Name of the EIA Consultant Greencindia Consulting Private Limited
(iii)Address 608-611, Level-V, Shopprix Mall, Vaishali, Sector-5, Ghaziabad-201010
(iv)Mobile No. 9899131527
(v)Landline No. 0120411152
(vi)Email Id information@greencindia.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 29 Mar 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)13/02/2020In view of above, Hon'ble NGT order passed in O.A. No. 1038/2018 dated 14/11/2019 an affidavit with google map from project proponent/consultant should be submitted and clearly mentioned that the project area is not in whole or in part, in or within five kilometres from the boundary of critically polluted areas or severely polluted area.
(2.)16/03/2020The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)30/09/2022Please submit the information/clarification as directed by SEIAA. The minutes of the said meeting is available on the website www.environmentclearance.nic.in and seiaaup.in
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPankaj Kumar Saxena
DesignationGeneralManager
Name of Company (Applicant Name should not be given here)CHADHA INFRATECH LIMITED
AddressD-851, Ilnd Floor, New Friends Colony, New Delhi-110065
Print