Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) T. Abdul Rahiman Quarry
(b)Name of the Company / Organisation T ABDUL RAHIMAN QUARRY
(c)Registered Address Thirikkot House, Pazhoor P.O, Mavoor Via, Kozhikode District, Kerala,,Kozhikode,Kerala-673661
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant TAbdul Rahiman
(b)Designation (Owner/ Partner/ CEO) Owner
(c)Address Thirikkot House, Pazhoor P.O, Mavoor Via, Kozhikode District, Kerala,,Kozhikode,Kozhikode,Kerala-673661
(d)Pin code 673661
(e)E-mail abdulrahi809@gmail.com
(f)Telephone No. 471-2599069
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/Activity1(a) Mining of minerals
(c)Category B2
(d)Proposal Number SIA/KL/MIN/45319/2019
(e)Master Proposal Number(Single Window) SW/122783/2019
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 172
(b)Pincode 673661
(c)Bounded Latitudes (North)
From
Degree 76.02638889
Minutes
Second
From
Degree 76.02805556
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 11.28194444
Minutes
Second
From
Degree 11.28284722
Minutes
Second
(e)Survey of India Topo Sheet No. 172
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 145
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 1
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Kerala
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)KeralaKozhikodeKozhikodeKodiyathur
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SW/122783/2019
(b)Date of Apply of TOR 11 Jul 2019
(c)Date of Issue of TOR / Standard ToR 15 Aug 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? No
(c)Reason The project is less than 5 ha
(d)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)NANANot Proposed
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Granite Building Stone33650Tons per AnnumRoad
(2.)Capacity33650Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.50
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.03
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.05
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.08
(e) Funds Allocated for Environment Management Capital(%) 6.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building Stone33650Tons per Annum0Road0 LinkageCopy of Linkage
(2.)NA0Tons per Annum0Road0 CaptiveCopy of Linkage
(3.)No raw material required0Tons per Annum0Road0 LinkageCopy of Linkage
(4.)Fuel for running of machinery0Tons per Annum0Road0 CaptiveCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 May 2019 To 16 Jun 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube32.630.22060
(2.)NOxMicro Gram per Meter Cube20202080
(3.)PM2.5Micro Gram per Meter Cube32.630.22060
(4.)SO2Micro Gram per Meter Cube23.523.52060
    14.2.     No. of Ground Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)Total Hardnessmg/l19.619.619.6200
(3.)Chloridesmg/l12.312.312.3250
(4.)Heavy MetalsIronmg/l0.480.480.480.3
(5.)TDSmg/l969696500
(6.)Fluoridemg/l0000
(7.)pHmg/l9.86.9888.5
    14.3.     No. of Surface Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l6.746.74B
(2.)DOmg/l5.95.9B
(3.)CODmg/l2.42.4B
(4.)BODmg/l3.63.6B
    14.4.     No. of Ambient Noise Monitoring Locations : 2
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))46.341.250
(2.)Leq(Night)A-weighted decibels(dB(A))34.233.240
    14.5.     No. of Soil Sample Monitored Locations : 2
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)00
(2.)K(Potassium)00
(3.)N(Nitrogen)Percent00
(4.)pH5.840.01
(5.)Electric Conductivity00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 70 To 88
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 70 To 88
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface30.3 Not Appliacble PipelineOpen Well00025 May 20193
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Na00NaGreen Belt Renewal Plant0
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)SoilOthersQuarry waste6934Tons0.3RoadCo-Processing
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube56.2100056.20
(2.)NOxMicrogram per Meter Cube5.28005.20
(3.)SO2Microgram per Meter Cube6.68006.60
(4.)PM2.5Microgram per Meter Cube30.260030.20
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 100
(b)Source KSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) If required provided
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 1.0514
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.0514
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : 1.0514 0
    Total 0
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersQuarry Operation1.0514no
Total 1.0514
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNa0None within 15km radius
(2.)Wildlife CorridorsNa0None within 15km radius
(3.)NPANa0None within 15km radius
(4.)ESZsNa0None within 15km radius
(5.)CorridorsNa0None within 15km radius
(6.)ESAsNa0None within 15km radius
(7.)Critically Polluted AreaNa0None within 15km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNa0None within 15Km radius
(2.)Archaeological SitesNa0None within 15Km radius
(3.)Defence InstallationsNa0None within 15Km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.0514
(b)Land yet to be acquired(Ha) 0.2920
(c)Status of Land acquisition if not acquired private patta land
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 3
(c)Temporary Employment- During Construction 2
(d)Temporary Employment- During Operation 2
(e)No. of working days 250
(f)Total Manpower 12
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.2920
(b)Percentage of Total Project Area 27.77
(c)No. of Plants to be Planted 120
(d)Funds Allocated for Plantation 50000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmentalcreate employment opportunities to local people
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)MinorMinor
2.
Mine Capacity in ROM (Run of Mine) 33650
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. DOZ/M-972/10
(b)Date of Approval 25 Feb 2019
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department State
(e)Approved Mining Lease Area 1.0514
(f)Approved Capacity 33650
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 731875
(b)Mineable Reserves (Million Ton) 336500
(c)Extractable Reserves(Million Ton) 395375
(d)Percent(%) of Extraction 54
(e)Grade of Coal /Ore /Mineral 1
(f)Stripping Ratio 1 : 0.0053
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 10
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 1.0514
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 03 Nov 2018
(iii)Validity of LOI 10
(iv)Reference No. of LOI 5867/M3/2018
(c)Whether Lease Deed Executed ? No
(i)Reason thereof New Application
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof New Application
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 1
(ii)Total Area (in Hectare) 0.05
(iii)Height (in meter) 6
(iv)Quantity (in Million Cubic meter) 6934
(v)No. of year back fill up 2
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 0.05
(iii)Height (in meter) 6
(iv)Quantity (in Million Cubic meter) 6934
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 9872
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 9872
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 9872
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0.8772
(b)Depth (in meter) 6
(c)Volume (in Million Cubic meter) 0.258
12.
Details of Quarry:
(a)Final Void of 0.258 (hectare) at a Depth of 6 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0.8772
13.
Details of Transportation:
(a)In Pit/Underground to Surface by tipper
(b)Surface to Siding/Loading Excavator
(c)Transportation / Conveyor Details transportation by tipper
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND000
(2.)SURFACE WATER BODIES000
(3.)SETTLEMENTS000
(4.)WASTE LAND000
(5.)GRAZING LAND000
(6.)FOREST LAND000
TOTAL000
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0000
(2.)VIRGIN AREA0000
(3.)GREEN BELT0000
(4.)TOP SOIL STORAGE0000
(5.)EXTERNAL OB DUMPS0000
(6.)INTERNAL OB DUMPS0000
(7.)ROADS0000
(8.)BUILT UP AREA (COLONY/OFFICE)0000
TOTAL00000
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0.8772
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 1.0514
(d)Safety Zone(in hectare) 0.2920
(e)Final Void of 0.8772 (hectare) at a Depth of 6 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 120
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 250
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. DMG/KERALA/RQP/4/2016
(ii)Name of the EIA Consultant V.K Roy
(iii)Address Saral, T.C 27/487(2), Swaraj Line, RC Junction, Kunnukuzhy, Thiruvananthapuram,
(iv)Mobile No. 9387805668
(v)Landline No. 0471259906
(vi)Email Id vkroysaral@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 08 Sep 2026
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)12/11/2019the Processing Fee should be remitted to treasury directly in the Head of Account ‘1425-00-501-99-Processing Charge on Environment Clearance by the State Environment Impact Assessment Authority’ and upload the Chelan via PARIVESH.
(2.)22/11/2019The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)02/03/2020: The Committee directed the proponent to submit the following documents/details: 1. Rework the project cost 2. Details of tree cutting /planting 3. Details of Green belt plan 4. Form-1 M 5. Rework CER.Year wise break up to be provided. 6. Recent cluster certificate 7. Land use & Land Form Map within 500 m radius certified by Village Officer. 8. Hazard Zonation Map
(2.)23/05/2020Submitting the additional document refered in 109th minutes.ADS Letter
(3.)19/06/2020The proponent is directed to submit Form 1(M) and recent cluster certificate.
(4.)19/08/2020Submitting Form 1M and Recent Cluster CertificateADS Letter
(5.)18/03/2021Please submit the documents as per the minutes of 119th SEAC meetingADS Letter
(6.)27/09/2022Submitting Additional Documents referred in 116th SEAC Minutes and 119th SEAC MinutesADS Letter
(7.)27/09/2022Submitting Additional Documents referred in 116th SEAC Minutes and 119th SEAC MinutesADS Letter
(8.)27/09/2022Submitting Additional Documents referred in 116th SEAC Minutes and 119th SEAC MinutesADS Letter
(9.)28/10/2022Please see the attached file for details of the additional documents sought as per the decision of 133th SEAC meeting.ADS Letter
(10.)08/03/2024Submitting the additional documents in the 133rd SEAC MeetingADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantTAbdul Rahiman
DesignationOwner
Name of Company (Applicant Name should not be given here)T ABDUL RAHIMAN QUARRY
AddressThirikkot House, Pazhoor P.O, Mavoor Via, Kozhikode District, Kerala
Print