1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s Basant Agro Tech ( India ) Limited,New Acid Slurry ‘’LABSA’’ unit. | (b)Name of the Company / Organisation | BASANT AGROTECH INDIA LTD | (c)Registered Address | 329, Mhow Nasirabad Road, Nayagaon, Neemuch,,Neemuch,Madhya Pradesh-458468 | (d)Legal Status of the Company | Private | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Sudarshan Jain | (b)Designation (Owner/ Partner/ CEO) | Projectmanager | (c)Address | 329, Mhow- Nasirabad Road, Nayagaon, Neemuch,,Jawad,Neemuch,Madhya Pradesh-458468 | (d)Pin code | 458468 | (e)E-mail | sudarshan.jain@basantagro.com | (f)Telephone No. | 7420-236235 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| (b)Minor Project/Activity | NIL | (c)Category | B2 | (d)Proposal Number | SIA/MP/IND2/43900/2019 | (e)Master Proposal Number(Single Window) | SW/119892/2019 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (g)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | 329 | (b)Pincode | 458468 | (c)Bounded Latitudes (North) | | From | | Degree | 24.302356 | Minutes | | Second | | From | | Degree | 24.342598 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 74.404833 | Minutes | | Second | | From | | Degree | 74.454433 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 45L14 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 458 | (h)Uploaded (kml) File | Copy of Kml File ![](../images/download.png) | (i)Distance of Nearest HFL from the project boundary within the study area | 11.65 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Madhya Pradesh | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Madhya Pradesh | Neemuch | Jawad | Nayagaon | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | 2413/2019 | (b)Date of Apply of TOR | 19 Sep 2019 | (c)Date of Issue of TOR / Standard ToR | 24 Sep 2019 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | The Proposed Project is involves the production of | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Acid Slurry LABSA | Acid Slurry with spent Acid | Spent acid by product | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Acid Slurry LABSA (Spent Acid By product) | 20200 | Tons per Annum | | Road | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 18 Sep 2019 | (iv)Valid Upto | 24 Sep 2019 | (v)File No. | 2413/2019 | (vi)Application No. | 2413 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 4.20 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 0.15 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.10 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 0.12 | (e) Funds Allocated for Environment Management Capital(%) | 0.00 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 15600 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 15600 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | LAB | 15600 | Tons per Annum | | Open Market | Road | | 10.0 | Open Market | | Copy of Linkage | (2.) | Sulfuric acid | 24000 | Tons per Annum | | Open Market | Road | | 10.0 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2019 To 31 May 2019 | (b)Season | Pre-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM2.5 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (2.) | SO2 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (3.) | PM10 | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | (4.) | NOx | | Micro Gram per Meter Cube | 0 | 0 | 0 | 0 | |
14.2. No. of Ground Water Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | mg/l | | 0 | 0 | 0 | 0 | (2.) | TDS | | | mg/l | | 0 | 0 | 0 | 0 | (3.) | Total Hardness | | | mg/l | | 0 | 0 | 0 | 0 | (4.) | Chlorides | | | mg/l | | 0 | 0 | 0 | 0 | (5.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (6.) | Fluoride | | | mg/l | | 0 | 0 | 0 | 0 | |
14.3. No. of Surface Water Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | BOD | | mg/l | | 0 | 0 | D | (2.) | COD | | mg/l | | 0 | 0 | D | (3.) | pH | | mg/l | | 0 | 0 | D | (4.) | DO | | mg/l | | 0 | 0 | D | |
14.4. No. of Ambient Noise Monitoring Locations : 0 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 0 | 0 | 0 | |
14.5. No. of Soil Sample Monitored Locations : 0 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 0 | 0 | (2.) | Electric Conductivity | Kilogram per hectare | | 0 | 0 | (3.) | pH | Kilogram per hectare | | 0 | 0 | (4.) | P(Phosphorus) | Kilogram per hectare | | 0 | 0 | (5.) | K(Potassium) | Kilogram per hectare | | 0 | 0 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 408 To 408 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 428 To 428 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 18 | 0.200 | Copy of Permission Letter | Pipeline | | Open Well | | NA | 10 Sep 2019 | 18 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Process,Cooling and Domestic | 0 | 0 | Zero Out put | Reuse within the Plant & Recycling | | 0 | | |
|
16.1. | (a)Total Waste Water Generation | 0 | (b)Total Discharged Water | 0 | (c)Total Reused Water | 0 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.020 | Tons | 0.30 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | SO2 | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 0 | (2.) | PM10 | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 0 | (3.) | PM2.5 | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 0 | (4.) | NOx | | Microgram per Meter Cube | 0 | 0 | 0 | 0 | 0 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | 0 | 0 | 0 | 0 | PM10 | | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 100 | (b)Source | MPSEB | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | 82 KVA | (e)Stack Height (in m) | 20 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 0.2695 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 0 | Total Land | 0.2695 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 0 | (b)Waste/Barren Land | 0 | (c)Grazing/ Community Land | 0 | (d)Surface Water Bodies | 0 | (e)Settlements | 0 | (f)Industrial | 0 | (g)Forest | 0 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : Private land | 0.2695 | Total | 0.2695 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Main Plant | | 0.1500 | | (2.) | Green belt | | 0.0800 | | (3.) | Others | storage and other area | 0.0395 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Wildlife Corridors | NA | 0 | NA | (2.) | Critically Polluted Area | NA | 0 | NA | (3.) | Corridors | NA | 0 | NA | (4.) | NPA | NA | 0 | NA | (5.) | ESAs | NA | 0 | NA | (6.) | ESZs | NA | 0 | NA | (7.) | WLS | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Archaeological Sites | | NA | 0 | None within 10km radius | (2.) | Defence Installations | | NA | 0 | None within 10km radius | (3.) | Forest | | Jawad | 11.50 | None within 10km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 0 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 10 | (b)Permanent Employment-During Operation | 5 | (c)Temporary Employment- During Construction | 5 | (d)Temporary Employment- During Operation | 5 | (e)No. of working days | 300 | (f)Total Manpower | 25 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt (in hectare) | 0.089 | (b)Percentage of Total Project Area | 33.02 | (c)No. of Plants to be Planted | 50 | (d)Funds Allocated for Plantation | 0.025 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Financial | From the foregoing analysis, it is observed that proposal is environmental compatible and will helps to people improving their financial status, performance and repayment capability. This also helps | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | No | (i)Reason for not Hiring the Consultant | Not required for project | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 01/10/2019 | Kindly upload the following:-1) declaration regarding construction/production activities commenced on project site.2) DFO letter regarding distance of national park,sanctuary from the project site. 3) A letter from PWD regarding distance of interstate boundary from the project site.4) water supply NOC for the project, from the concern deppt. | | (2.) | 03/10/2019 | The correction have been made as per the instruction received | | (3.) | 11/10/2019 | The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance. | | (4.) | 11/10/2019 | The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance. | | (5.) | 11/10/2019 | The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance. | | (6.) | 11/10/2019 | The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance. | | (7.) | 11/10/2019 | The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance. | | (8.) | 24/10/2019 | The correction have been made as per the instruction received | | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Sudarshan Jain | Designation | Projectmanager | Name of Company (Applicant Name should not be given here) | BASANT AGROTECH INDIA LTD | Address | 329, Mhow Nasirabad Road, Nayagaon, Neemuch |
|