APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Basant Agro Tech ( India ) Limited,New Acid Slurry ‘’LABSA’’ unit.
(b)Name of the Company / Organisation BASANT AGROTECH INDIA LTD
(c)Registered Address 329, Mhow Nasirabad Road, Nayagaon, Neemuch,,Neemuch,Madhya Pradesh-458468
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Sudarshan Jain
(b)Designation (Owner/ Partner/ CEO) Projectmanager
(c)Address 329, Mhow- Nasirabad Road, Nayagaon, Neemuch,,Jawad,Neemuch,Madhya Pradesh-458468
(d)Pin code 458468
(e)E-mail sudarshan.jain@basantagro.com
(f)Telephone No. 7420-236235
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/MP/IND2/43900/2019
(e)Master Proposal Number(Single Window) SW/119892/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 329
(b)Pincode 458468
(c)Bounded Latitudes (North)
From
Degree 24.302356
Minutes
Second
From
Degree 24.342598
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 74.404833
Minutes
Second
From
Degree 74.454433
Minutes
Second
(e)Survey of India Topo Sheet No. 45L14
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 458
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 11.65
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshNeemuchJawadNayagaon
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 2413/2019
(b)Date of Apply of TOR 19 Sep 2019
(c)Date of Issue of TOR / Standard ToR 24 Sep 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The Proposed Project is involves the production of
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Acid Slurry LABSAAcid Slurry with spent AcidSpent acid by product
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Acid Slurry LABSA (Spent Acid By product)20200Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 18 Sep 2019
(iv)Valid Upto 24 Sep 2019
(v)File No. 2413/2019
(vi)Application No. 2413
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 4.20
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.15
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.10
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.12
(e) Funds Allocated for Environment Management Capital(%) 0.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 15600
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 15600
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)LAB15600Tons per AnnumOpen MarketRoad10.0 Open MarketCopy of Linkage
(2.)Sulfuric acid24000Tons per AnnumOpen MarketRoad10.0 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube0000
(2.)SO2Micro Gram per Meter Cube0000
(3.)PM10Micro Gram per Meter Cube0000
(4.)NOxMicro Gram per Meter Cube0000
    14.2.     No. of Ground Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHmg/l0000
(2.)TDSmg/l0000
(3.)Total Hardnessmg/l0000
(4.)Chloridesmg/l0000
(5.)TSSmg/l0000
(6.)Fluoridemg/l0000
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l00D
(2.)CODmg/l00D
(3.)pHmg/l00D
(4.)DOmg/l00D
    14.4.     No. of Ambient Noise Monitoring Locations : 0
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))000
(2.)Leq(Day)A-weighted decibels(dB(A))000
    14.5.     No. of Soil Sample Monitored Locations : 0
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare00
(2.)Electric ConductivityKilogram per hectare00
(3.)pHKilogram per hectare00
(4.)P(Phosphorus)Kilogram per hectare00
(5.)K(Potassium)Kilogram per hectare00
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 408 To 408
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 428 To 428
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater180.200Copy of Permission LetterPipelineOpen WellNA10 Sep 201918
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Process,Cooling and Domestic00Zero Out putReuse within the Plant & Recycling0
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.020Tons0.30RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube00000
(2.)PM10Microgram per Meter Cube00000
(3.)PM2.5Microgram per Meter Cube00000
(4.)NOxMicrogram per Meter Cube00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 100
(b)Source MPSEB
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 82 KVA
(e)Stack Height (in m) 20
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0.2695
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 0.2695
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Private land 0.2695
    Total 0.2695
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant0.1500
(2.)Green belt0.0800
(3.)Othersstorage and other area0.0395
Total 0.2695
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife CorridorsNA0NA
(2.)Critically Polluted AreaNA0NA
(3.)CorridorsNA0NA
(4.)NPANA0NA
(5.)ESAsNA0NA
(6.)ESZsNA0NA
(7.)WLSNA0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNA0None within 10km radius
(2.)Defence InstallationsNA0None within 10km radius
(3.)ForestJawad11.50None within 10km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 10
(b)Permanent Employment-During Operation 5
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 5
(e)No. of working days 300
(f)Total Manpower 25
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.089
(b)Percentage of Total Project Area 33.02
(c)No. of Plants to be Planted 50
(d)Funds Allocated for Plantation 0.025
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialFrom the foregoing analysis, it is observed that proposal is environmental compatible and will helps to people improving their financial status, performance and repayment capability. This also helps
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant Not required for project
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)01/10/2019Kindly upload the following:-1) declaration regarding construction/production activities commenced on project site.2) DFO letter regarding distance of national park,sanctuary from the project site. 3) A letter from PWD regarding distance of interstate boundary from the project site.4) water supply NOC for the project, from the concern deppt.
(2.)03/10/2019The correction have been made as per the instruction received
(3.)11/10/2019The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance.
(4.)11/10/2019The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance.
(5.)11/10/2019The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance.
(6.)11/10/2019The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance.
(7.)11/10/2019The interstate boundary exist within 05 km from project site as per PWD letter. Kindly justify why you applied MPSEIAA for environmental clearance.
(8.)24/10/2019The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSudarshan Jain
DesignationProjectmanager
Name of Company (Applicant Name should not be given here)BASANT AGROTECH INDIA LTD
Address329, Mhow Nasirabad Road, Nayagaon, Neemuch