Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Grain based Distillery (30 KLPD to 110 KLPD) & Cogeneration Power Plant (0.5 MW to 3.5 MW) at SP-67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar (R
(b)Name of the Company / Organisation HSB AGRO INDUSTRIES PVT. LTD.
(c)Registered Address Baikuntha Nagar,Behrampur,,Ganjam,Orissa-760001
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Manish Kumar Singh
(b)Designation (Owner/ Partner/ CEO) GM
(c)Address HSB Agro Industries Pvt. Ltd., SP 67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar, Rajasthan,,Sri Madhopur,Sikar,Rajasthan-332404
(d)Pin code 332404
(e)E-mail manishs.ads@rediffmail.com
(f)Telephone No. 1575-517818
(g)Fax No. 517831
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(g) Distilleries
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/RJ/IND2/42628/2003
(e)Master Proposal Number(Single Window) SW/117557/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. SP-67 and Khasra no. 6/2 11, 12, 13
(b)Pincode 332404
(c)Bounded Latitudes (North)
From
Degree 27.3355555
Minutes
Second
From
Degree 27.3383333
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 75.5752777
Minutes
Second
From
Degree 75.57833333
Minutes
Second
(e)Survey of India Topo Sheet No. 45 M/7, 45 M/11, 45M/12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 468
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.4
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Rajasthan
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)RajasthanSikarSri MadhopurShri Khatushyamji Industrial Complex, Reengus
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number MoEFCC File No. J-11011/5/2014-IA II (I)
(b)Date of Apply of EC 06 Oct 2018
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :18 May 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :24 Jun 2019
Distance of Public Hearing Venue from the Proposed Project :4
Municipality, Reengus
State :Rajasthan
District :Sikar
Tehsil :Sri Madhopur
Village :Reengus
131employment, Air & Water Pollution, CSR Activities etcOthers
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Lucknow
(iii)Letter No. IV/ENV/R/Ind-30/287/2004/36
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)IMFL/CL Bottles70001100018000OthersCases per dayRoad,OthersCables
(2.)By Product -DDGS05252OthersTPDRoadCables
(3.)By Product CO2226082OthersTPDRoadCables
(4.)By Product Fusel Oil0.060.140.2Kilo Litre per Day(KLD)RoadCables
(5.)ENA / RS/ Ethanol / AA3080110Kilo Litre per Day(KLD)Road
(6.)Power0.53.03.5Mega Watt(MW)OthersCables
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Co-Generation Power Plant0.53.03.5MW
(2.)Blending & Bottling Plant70001100018000cases/day
(3.)Grain Based Distillery3080110KLPD
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 31 Jul 2018
(iv)Valid Upto 31 Mar 2023
(v)File No. F(Plan)/Sikar(Sri Madhopur)/2(1)/2016-2017/2955-29
(vi)Application No. 2018-2019/PDF/3842
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 35
(b) Funds Allocated for Environment Management (Capital) (in crores) 7
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.35
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 1.5
(e) Funds Allocated for Environment Management Capital(%) 20.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 56350
(b)Existing quantity of raw material/fuel 24300
(c)Total quantity of raw material/fuel 80650
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Coal42000Tons per AnnumThrough SuppliersRoad1000 Open MarketCopy of Linkage
(2.)Grain - Broken Rice, Sorghum, Bajra, Maize etc.84700Tons per AnnumThrough SuppliersRoad1000 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube89.458.786.25100
(2.)PM2.5Micro Gram per Meter Cube56.530.454.1660
(3.)SO2Micro Gram per Meter Cube13.15.812.9280
(4.)NOxMicro Gram per Meter Cube27.29.226.4880
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Fluoridemg/l0.760.2611.5
(2.)pHNA8.127.26.58.5
(3.)TSSmg/l0000
(4.)Total Hardnessmg/l177.7132.8200600
(5.)Chloridesmg/l258.742.22501000
(6.)TDSmg/l884.8451.25002000
    14.3.     No. of Surface Water Monitoring Locations : 0
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l00A
(2.)BODmg/l00A
(3.)CODmg/l00A
(4.)pHNA00A
    14.4.     No. of Ambient Noise Monitoring Locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))63.843.2Industrial 70 & Residential 45
(2.)Leq(Day)A-weighted decibels(dB(A))66.453.7Industrial 75, Commercial 65 & Residential 55
    14.5.     No. of Soil Sample Monitored Locations : 6
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH8.27.52
(2.)Electric ConductivityMillisiemens per Centimetre0.360.1
(3.)K(Potassium)Kilogram per hectare306.4228.06
(4.)P(Phosphorus)Kilogram per hectare77.1564.3
(5.)N(Nitrogen)Kilogram per hectare176.55126.84
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 27.72 To 58.95
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 27.80 To 58.20
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater5280Copy of Permission LetterPipelineTube Well21-4(6)/WR/CGWA/05-60806 Jul 2005528
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial224500Anaerobic, aerobic, filters and RO PlantReuse within the Plant & Recycling224
16.1.
(a)Total Waste Water Generation 224
(b)Total Discharged Water 0
(c)Total Reused Water 224
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)AshFly Ash14700Tons50RoadOthersSupplied to Brick & Cement manufacturers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube74.810.8175.61100
(2.)NOxMicrogram per Meter Cube24.811.9626.7680
(3.)PM2.5Microgram per Meter Cube44.610.3344.9360
(4.)SO2Microgram per Meter Cube10.311.4211.7280
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Boiler 30 TPHCoal452.5PM1030
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 4375
(b)Source Proposed 3.5 MW co-gen power plant & Grid
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 500 KVA & 1000 KVA
(e)Stack Height (in m) 9
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 5.81
    Total Land 5.81
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 17960.93
(b)Waste/Barren Land 674.13
(c)Grazing/ Community Land 5723.88
(d)Surface Water Bodies 1331.23
(e)Settlements 5232.55
(f)Industrial 155.74
(g)Forest 80.53
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Open land 1277.85
    Total 32436.84
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt1.94
(2.)OthersAdmin office & Others1.62
(3.)Main Plant2.25
Total 5.81
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNot Applicable0No CPA within 10 km radius
(2.)WLSNot Applicable0No WLS within 10 km radius
(3.)NPANot Applicable0No NPA within 10 km radius
(4.)ESAsNot Applicable0No ESA within 10 km radius
(5.)ESZsNot Applicable0No ESZ within 10 km radius
(6.)CorridorsNot Applicable0No Corridors within 10 km radius
(7.)Wildlife CorridorsNot Applicable0No Wildlife Corridors within 10 km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNo RF & PF0Some open scrub areas lies within 10 km radius of the plant site
(2.)Archaeological SitesNot Applicable0No Archaeological sites within 10 km radius
(3.)Defence InstallationsNot Applicable0No defence installations within 10 km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 5.81
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Already Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Mendha River (Seasonal River)
(ii)Direction of Water Bodies in Buffer Area North West
(iii)Distance of Water Bodies in Buffer Area 0.4
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 125
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 200
(e)No. of working days 350
(f)Total Manpower 430
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt1.340.61
(2.)Percentage of Total Project Area33033
(3.)No. of Plants20109002910
(4.)Funds Allocated20525
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialEmployment generation and CSR Activities
(2.)FinancialRevenue generation
(3.)EnvironmentalZero Liquid Discharge Project and Greenbelt development
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0069
(ii)Name of the EIA Consultant J M EnviroNet Pvt. Ltd.
(iii)Address 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001
(iv)Mobile No. 9015209362
(v)Landline No. 9015209362
(vi)Email Id jmenviron@hotmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 07 Feb 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)22/10/2019The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:- a) Form 1. b) In case of Expansion-Point wise compliance report of earlier EC duly certified by RSPCB/SEIAA/MoEF. c) Location (maps showing general location/specific location /project boundaries and project site layout). d) Affidavit regarding violation of EIA notification and regarding correctness of submitted data & document by consultant as well as project proponent. e) Duly filled environment sensitivity portion of Form I clearly showing distance from national/state boundary/protected areas / sanctuaries/National park and if area falls within 10 kms. from boundary of sanctuaries /National park a copy of application submitted to NBWL, New Delhi. f) Partnership deed/Directors list(if applicable). g) Water demand and source of water with copy of application submitted to CCWA for withdrawal of ground water.EDS Letter
(2.)01/11/2019The correction have been made as per the instruction received
(3.)15/10/2022while uploading aforesaid documents you are required to check for any overwriting of existing files. you are advised not to overwrite existing documents. You have not yet submitted the requested yet. kindly submit.
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantManish Kumar Singh
DesignationGM
Name of Company (Applicant Name should not be given here)HSB AGRO INDUSTRIES PVT. LTD.
AddressSP 67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar (Raj.)
Print