1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Expansion of Grain based Distillery (30 KLPD to 110 KLPD) & Cogeneration Power Plant (0.5 MW to 3.5 MW) at SP-67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar (R | (b)Name of the Company / Organisation | HSB AGRO INDUSTRIES PVT. LTD. | (c)Registered Address | Baikuntha Nagar,Behrampur,,Ganjam,Orissa-760001 | (d)Legal Status of the Company | Others | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Manish Kumar Singh | (b)Designation (Owner/ Partner/ CEO) | GM | (c)Address | HSB Agro Industries Pvt. Ltd., SP 67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar, Rajasthan,,Sri Madhopur,Sikar,Rajasthan-332404 | (d)Pin code | 332404 | (e)E-mail | manishs.ads@rediffmail.com | (f)Telephone No. | 1575-517818 | (g)Fax No. | 517831 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 5(g) Distilleries
| (b)Minor Project/Activity | NIL | (c)Category | B1 | (d)Proposal Number | SIA/RJ/IND2/42628/2003 | (e)Master Proposal Number(Single Window) | SW/117557/2019 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (g)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | SP-67 and Khasra no. 6/2 11, 12, 13 | (b)Pincode | 332404 | (c)Bounded Latitudes (North) | | From | | Degree | 27.3355555 | Minutes | | Second | | From | | Degree | 27.3383333 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 75.5752777 | Minutes | | Second | | From | | Degree | 75.57833333 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 45 M/7, 45 M/11, 45M/12 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 468 | (h)Uploaded (kml) File | Copy of Kml File | (i)Distance of Nearest HFL from the project boundary within the study area | 0.4 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Rajasthan | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Rajasthan | Sikar | Sri Madhopur | Shri Khatushyamji Industrial Complex, Reengus | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | MoEFCC File No. J-11011/5/2014-IA II (I) | (b)Date of Apply of EC | 06 Oct 2018 | (c)Date of Issue of EC | 31 Dec 1899 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 24 Jun 2019 | Distance of Public Hearing Venue from the Proposed Project : | 4 |
| Municipality, Reengus | State : | Rajasthan | District : | Sikar | Tehsil : | Sri Madhopur | Village : | Reengus |
| 131 | employment, Air & Water Pollution, CSR Activities etc | Others | | |
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Lucknow | (iii)Letter No. | IV/ENV/R/Ind-30/287/2004/36 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | N/A | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | IMFL/CL Bottles | 7000 | 11000 | 18000 | Others | Cases per day | Road,Others | Cables | (2.) | By Product -DDGS | 0 | 52 | 52 | Others | TPD | Road | Cables | (3.) | By Product CO2 | 22 | 60 | 82 | Others | TPD | Road | Cables | (4.) | By Product Fusel Oil | 0.06 | 0.14 | 0.2 | Kilo Litre per Day(KLD) | | Road | Cables | (5.) | ENA / RS/ Ethanol / AA | 30 | 80 | 110 | Kilo Litre per Day(KLD) | | Road | | (6.) | Power | 0.5 | 3.0 | 3.5 | Mega Watt(MW) | | Others | Cables | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | Co-Generation Power Plant | 0.5 | 3.0 | 3.5 | MW | (2.) | Blending & Bottling Plant | 7000 | 11000 | 18000 | cases/day | (3.) | Grain Based Distillery | 30 | 80 | 110 | KLPD | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 31 Jul 2018 | (iv)Valid Upto | 31 Mar 2023 | (v)File No. | F(Plan)/Sikar(Sri Madhopur)/2(1)/2016-2017/2955-29 | (vi)Application No. | 2018-2019/PDF/3842 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 35 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 7 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.35 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 1.5 | (e) Funds Allocated for Environment Management Capital(%) | 20.00 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 56350 | (b)Existing quantity of raw material/fuel | 24300 | (c)Total quantity of raw material/fuel | 80650 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Coal | 42000 | Tons per Annum | | Through Suppliers | Road | | 1000 | Open Market | | Copy of Linkage | (2.) | Grain - Broken Rice, Sorghum, Bajra, Maize etc. | 84700 | Tons per Annum | | Through Suppliers | Road | | 1000 | MoU | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Oct 2018 To 31 Dec 2018 | (b)Season | Post-Monsoon | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 89.4 | 58.7 | 86.25 | 100 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 56.5 | 30.4 | 54.16 | 60 | (3.) | SO2 | | Micro Gram per Meter Cube | 13.1 | 5.8 | 12.92 | 80 | (4.) | NOx | | Micro Gram per Meter Cube | 27.2 | 9.2 | 26.48 | 80 | |
14.2. No. of Ground Water Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | Fluoride | | | mg/l | | 0.76 | 0.26 | 1 | 1.5 | (2.) | pH | | | NA | | 8.12 | 7.2 | 6.5 | 8.5 | (3.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (4.) | Total Hardness | | | mg/l | | 177.7 | 132.8 | 200 | 600 | (5.) | Chlorides | | | mg/l | | 258.7 | 42.2 | 250 | 1000 | (6.) | TDS | | | mg/l | | 884.8 | 451.2 | 500 | 2000 | |
14.3. No. of Surface Water Monitoring Locations : 0 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | DO | | mg/l | | 0 | 0 | A | (2.) | BOD | | mg/l | | 0 | 0 | A | (3.) | COD | | mg/l | | 0 | 0 | A | (4.) | pH | | NA | | 0 | 0 | A | |
14.4. No. of Ambient Noise Monitoring Locations : 7 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 63.8 | 43.2 | Industrial 70 & Residential 45 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 66.4 | 53.7 | Industrial 75, Commercial 65 & Residential 55 | |
14.5. No. of Soil Sample Monitored Locations : 6 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | pH | | | 8.2 | 7.52 | (2.) | Electric Conductivity | Millisiemens per Centimetre | | 0.36 | 0.1 | (3.) | K(Potassium) | Kilogram per hectare | | 306.4 | 228.06 | (4.) | P(Phosphorus) | Kilogram per hectare | | 77.15 | 64.3 | (5.) | N(Nitrogen) | Kilogram per hectare | | 176.55 | 126.84 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 27.72 To 58.95 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 27.80 To 58.20 | (c)Whether Ground Water Intersection will be there ? | NA | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | GroundWater | | 528 | 0 | Copy of Permission Letter | Pipeline | | Tube Well | | 21-4(6)/WR/CGWA/05-608 | 06 Jul 2005 | 528 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial | 224 | 500 | Anaerobic, aerobic, filters and RO Plant | Reuse within the Plant & Recycling | | 224 | | |
|
16.1. | (a)Total Waste Water Generation | 224 | (b)Total Discharged Water | 0 | (c)Total Reused Water | 224 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Ash | Fly Ash | | 14700 | Tons | 50 | Road | | Others | Supplied to Brick & Cement manufacturers | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 74.8 | 1 | 0.81 | 75.61 | 100 | (2.) | NOx | | Microgram per Meter Cube | 24.8 | 1 | 1.96 | 26.76 | 80 | (3.) | PM2.5 | | Microgram per Meter Cube | 44.6 | 1 | 0.33 | 44.93 | 60 | (4.) | SO2 | | Microgram per Meter Cube | 10.3 | 1 | 1.42 | 11.72 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Boiler 30 TPH | Coal | 45 | 2.5 | PM10 | | 30 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 4375 | (b)Source | Proposed 3.5 MW co-gen power plant & Grid | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 500 KVA & 1000 KVA | (e)Stack Height (in m) | 9 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 0 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 5.81 | Total Land | 5.81 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 17960.93 | (b)Waste/Barren Land | 674.13 | (c)Grazing/ Community Land | 5723.88 | (d)Surface Water Bodies | 1331.23 | (e)Settlements | 5232.55 | (f)Industrial | 155.74 | (g)Forest | 80.53 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : Open land | 1277.85 | Total | 32436.84 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Green belt | | 1.94 | | (2.) | Others | Admin office & Others | 1.62 | | (3.) | Main Plant | | 2.25 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | Not Applicable | 0 | No CPA within 10 km radius | (2.) | WLS | Not Applicable | 0 | No WLS within 10 km radius | (3.) | NPA | Not Applicable | 0 | No NPA within 10 km radius | (4.) | ESAs | Not Applicable | 0 | No ESA within 10 km radius | (5.) | ESZs | Not Applicable | 0 | No ESZ within 10 km radius | (6.) | Corridors | Not Applicable | 0 | No Corridors within 10 km radius | (7.) | Wildlife Corridors | Not Applicable | 0 | No Wildlife Corridors within 10 km radius | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | No RF & PF | 0 | Some open scrub areas lies within 10 km radius of the plant site | (2.) | Archaeological Sites | | Not Applicable | 0 | No Archaeological sites within 10 km radius | (3.) | Defence Installations | | Not Applicable | 0 | No defence installations within 10 km radius | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 5.81 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | Already Acquired | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Mendha River (Seasonal River) | (ii)Direction of Water Bodies in Buffer Area | North West | (iii)Distance of Water Bodies in Buffer Area | 0.4 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 5 | (b)Permanent Employment-During Operation | 125 | (c)Temporary Employment- During Construction | 100 | (d)Temporary Employment- During Operation | 200 | (e)No. of working days | 350 | (f)Total Manpower | 430 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 1.34 | 0.6 | 1 | (2.) | Percentage of Total Project Area | 33 | 0 | 33 | (3.) | No. of Plants | 2010 | 900 | 2910 | (4.) | Funds Allocated | 20 | 5 | 25 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Employment generation and CSR Activities | (2.) | Financial | Revenue generation | (3.) | Environmental | Zero Liquid Discharge Project and Greenbelt development | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1619/RA 0069 | (ii)Name of the EIA Consultant | J M EnviroNet Pvt. Ltd. | (iii)Address | 202-A, ABW Tower, MG Road, IFFCO Chowk, Sector 25, Gurugram (Haryana) – 122001 | (iv)Mobile No. | 9015209362 | (v)Landline No. | 9015209362 | (vi)Email Id | jmenviron@hotmail.com | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 07 Feb 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 22/10/2019 | The application/proposal submitted by PP has been examined and the proposals/ application is found deficient /incomplete in respect to following:-
a) Form 1.
b) In case of Expansion-Point wise compliance report of earlier EC duly certified by RSPCB/SEIAA/MoEF.
c) Location (maps showing general location/specific location /project boundaries and project site layout).
d) Affidavit regarding violation of EIA notification and regarding correctness of submitted data & document by consultant as well as project proponent.
e) Duly filled environment sensitivity portion of Form I clearly showing distance from national/state boundary/protected areas / sanctuaries/National park and if area falls within 10 kms. from boundary of sanctuaries /National park a copy of application submitted to NBWL, New Delhi.
f) Partnership deed/Directors list(if applicable).
g) Water demand and source of water with copy of application submitted to CCWA for withdrawal of ground water. | EDS Letter | (2.) | 01/11/2019 | The correction have been made as per the instruction received | | (3.) | 15/10/2022 | while uploading aforesaid documents you are required to check for any overwriting of existing files. you are advised not to overwrite existing documents.
You have not yet submitted the requested yet. kindly submit. | | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Manish Kumar Singh | Designation | GM | Name of Company (Applicant Name should not be given here) | HSB AGRO INDUSTRIES PVT. LTD. | Address | SP 67, Shri Khatushyamji Industrial Complex, Reengus, Tehsil Sri Madhopur, District Sikar (Raj.) |
|