Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Expansion of Steel Plant by Vaswani Industries Limited
(b)Name of the Company / Organisation VASWANI INDUSTRIES LIMITED
(c)Registered Address Village Sondra, Bahesar Road, Near Phase 2 Siltara Industrial Area, Tehsil and District Raipur,,Raipur,Chhattisgarh-493111
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Yashwant Vaswani
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address Village Sondra, Bahesar Road, Near Phase 2 Siltara Industrial Area, Tehsil and District Raipur,Raipur,Chhattisgarh-493111
(d)Pin code 493111
(e)E-mail yashwant@vaswaniindustries.com
(f)Telephone No. 771-4226000
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity3(a) Metallurgical industries (ferrous & non ferrous)
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/CG/IND/37370/2019
(e)Master Proposal Number(Single Window) SW/107369/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 1
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 409/1, 416/4, 411/1, 411/2, 418/2, 418/4, 463/1, 4
(b)Pincode 493111
(c)Bounded Latitudes (North)
From
Degree 21.220577
Minutes
Second
From
Degree 21.221540
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 81.382925
Minutes
Second
From
Degree 81.384158
Minutes
Second
(e)Survey of India Topo Sheet No. 64 G 11
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 271.3
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 2.50
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)ChhattisgarhRaipurRaipurSondra
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 122
(b)Date of Apply of EC 23 Apr 2019
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Not required
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Nagpur
(iii)Letter No. 122
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Sponge Iron Manufacturing90000090000Tons per Annum(TPA)Road
(2.)WHRB based Power Plant909Mega Watt(MW)OthersTransmission Lines
(3.)FBC based Power Plant2.502.5Mega Watt(MW)OthersTransmission Lines
(4.)Induction furnace unit360002352059520Tons per Annum(TPA)RoadTransmission Lines
(5.)New Hot Charged Rolling Mill05778657786Tons per Annum(TPA)RoadTransmission Lines
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Sponge Iron Kilns3 x 100 Tons/ day03 x 100 Tons/ day
(2.)Induction Furnaces36000 Tons/ year23520 Tons/ year59520 Tons/ year
(3.)Hot Charged Rolling Mill0 tons/ year57786 Tons/ Year57786 Tons/ Year
(4.)WHRB based Power Plant9 MW09 MW
(5.)FBC based Power Plant2.5 MW02.5 MW
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 08 Mar 2018
(iv)Valid Upto 31 Mar 2021
(v)File No. 6959
(vi)Application No. 684012
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 16
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.50
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.50
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.15
(e) Funds Allocated for Environment Management Capital(%) 0.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 34580
(b)Existing quantity of raw material/fuel 34580
(c)Total quantity of raw material/fuel 69160
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)sponge Iron53000Tons per AnnumOwn GenerationRoad0 CaptiveCopy of Linkage
(2.)Iron Scrap15500Tons per AnnumLocal marketRoad3 MoUCopy of Linkage
(3.)Ferro alloys660Tons per AnnumLocal marketRoad5 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2019 To 31 May 2019
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube47.941.847.860
(2.)SO2Micro Gram per Meter Cube20.4015.6020.380
(3.)PM10Micro Gram per Meter Cube88.3067.582.0100
(4.)NOxMicro Gram per Meter Cube31.5026.3031.4080
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.87.28.58.5
(2.)Total Hardnessmg/l255205300600
(3.)TSSmg/l0.50.30.000.00
(4.)Fluoridemg/l0.590.501.01.50
(5.)Heavy MetalsMercurymg/l0.00050.00050.0010.001
(6.)TDSmg/l7056155002000
(7.)Chloridesmg/l1551222501000
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.57.2C
(2.)BODmg/l2.62.4C
(3.)DOmg/l43.5C
(4.)CODmg/l13.510.4C
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))674275
(2.)Leq(Night)A-weighted decibels(dB(A))463770
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare3410
(2.)K(Potassium)Kilogram per hectare235136
(3.)Electric ConductivityMillisiemens per Centimetre8851
(4.)N(Nitrogen)Kilogram per hectare244136
(5.)pH8.06.5
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 10.5 To 5.0
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.1 To 5.5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersCG Ispat Bhumi Limited7400.0Copy of Permission LetterPipelineIntake Well0531 May 20191000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Sanatory8200Septic Tanks followed by Soak pitsReuse within the Plant & Recycling8
16.1.
(a)Total Waste Water Generation 8
(b)Total Discharged Water 0
(c)Total Reused Water 8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Mill ScalesIndustrial Waste434Tons5RoadOthersSold to Ferro Alloys and Pellet plant
(2.)Furnace SlagIndustrial Waste7440Tons5RoadOthersSold to Slag Crushing Units
(3.)End CuttingIndustrial Waste1300Tons0RoadOthersReused as Raw material in Induction furnaces
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube88.98003.292.1100
(2.)SO2Microgram per Meter Cube29.58004.834.380
(3.)NOxMicrogram per Meter Cube39.780016.35680
(4.)PM2.5Microgram per Meter Cube44.58000.54560
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Induction FurnaceNil300.8PM100.50
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5900
(b)Source CSPDCL Grids
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 750
(e)Stack Height (in m) 3.5
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 12.53
(c)Government Land 0.0
(d)Revenue Land 0.0
(e)Other Land 0.0
    Total Land 12.53
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0.00
(b)Waste/Barren Land 0.00
(c)Grazing/ Community Land 0.00
(d)Surface Water Bodies 0.00
(e)Settlements 0.00
(f)Industrial 12.53
(g)Forest 0.00
(h)Mangroves 0.00
(i)Marine Area 0.00
(j)Others : Not appllicable 0.00
    Total 12.53
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant3.50
(2.)Green belt4.18
(3.)OthersRoads Utilities and Storage4.85
Total 12.53
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil80Not Applicable
(2.)WLSNil80Not Applicable
(3.)NPANil80Not Applicable
(4.)ESZsNil80Not Applicable
(5.)CorridorsNil80Not Applicable
(6.)ESAsNil80Not Applicable
(7.)Wildlife CorridorsNil80Not Applicable
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNil30Nil within the area
(2.)ForestNil30Nil within the area
(3.)Archaeological SitesNil30Nil within the area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 12.53
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area River Kharun
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 125
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 600
(e)No. of working days 310
(f)Total Manpower 1030
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt4.1804
(2.)Percentage of Total Project Area33033
(3.)No. of Plants750007500
(4.)Funds Allocated150000100000250000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalReduction in emissions by implementing stringent norms
(2.)SocialJob Creations
(3.)FinancialIntegration of Project will make unit financial viable
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant Not Required
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantYashwant Vaswani
DesignationDirector
Name of Company (Applicant Name should not be given here)VASWANI INDUSTRIES LIMITED
AddressVillage Sondra, Bahesar Road, Near Phase 2 Siltara Industrial Area, Tehsil and District Raipur
Print