1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | M/s. Shree Coloperse Pvt. Ltd. | (b)Name of the Company / Organisation | SHREE COLOSPERSE PVT. LTD. | (c)Registered Address | Plot No-6412, GIDC Estate, Ankleshwar, Dist: Bharuch-393002,,Bharuch,Gujarat-393002 | (d)Legal Status of the Company | Private | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Manshukh Vekaria | (b)Designation (Owner/ Partner/ CEO) | MD | (c)Address | Plot No-6412, GIDC Estate, Ankleshwar, Dist: Bharuch-393002,Bharuch,Gujarat-393002 | (d)Pin code | 393002 | (e)E-mail | shreecolosperse@gmail.com | (f)Telephone No. | 2646-0000000 | (g)Fax No. | | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a)Major Project/Activity | 5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
| (b)Minor Project/Activity | NIL | (c)Category | B1 | (d)Proposal Number | SIA/GJ/IND2/36234/2018 | (e)Master Proposal Number(Single Window) | SW/105405/2019 | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | (g)Project Type | Expansion |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Plot no. 6412, GIDC Estate, Ankleshwar, Dist- Bhar | (b)Pincode | 393002 | (c)Bounded Latitudes (North) | | From | | Degree | 21.371048 | Minutes | | Second | | From | | Degree | 21.37827 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 73.23375 | Minutes | | Second | | From | | Degree | 73.23519 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | F43M14 | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 20 | (h)Uploaded (kml) File | Copy of Kml File ![](../images/download.png) | (i)Distance of Nearest HFL from the project boundary within the study area | 4.20 | (j)Seismic Zone | 3 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Gujarat | |
|
|
Details of State(s) of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
(1.) | Gujarat | Bharuch | Anklesvar | Ankleshwar | |
|
6. | Details of Terms of Reference (ToR)/EC: | (a)MoEF&CC / SEIAA File Number | SEIAA/GJ/IND2/5(f)/ 15./2018. | (b)Date of Apply of EC | 13 Jun 2018 | (c)Date of Issue of EC | 31 Dec 1899 | (d)Previous EC Letter | Copy of Previous EC letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | Yes | (b)Reason | Public hearing is exempted as per para 7(i) III st | (c)Supporting Document | Copy of Supporting Document | |
|
8. | Details of Project Configuration/Product: | Details Not Applicable | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | (a)Details of certified report on compliance of earlier environmental clearance condition | (i)Certified Compliance By | Regional | (ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on | Bhopal | (iii)Letter No. | 000000 | (iv)Status of Compliance | Compiled | (v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) | Copy of Certified Compliance Report | (vi)Date of site visit | N/A | (b)Details of Capacity Expansion | |
|
S. No. | Product/Activity (Capacity/Area) | Quantity From | Quantity To | Total Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Disperse navy blue 3G(And/or)) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (2.) | Disperse rubine 3B (and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (3.) | Disperse rubin GFL (and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (4.) | Diperse violet B(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (5.) | Disperse scarlet RR(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (6.) | Disperse rubine S2GL(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (7.) | Disperse yellow 119(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (8.) | Disperse yellow 241(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (9.) | Disperse yellow 211(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (10.) | Disperse violet 93(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (11.) | Disperse violet 93(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (12.) | Disperse yellow 5RX(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (13.) | Disperse yellow M7G(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (14.) | Disperse red 17(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (15.) | Disperse yellow 3(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (16.) | Disperse red 1(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (17.) | Disperse blue FFR(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (18.) | Disperse blue BN(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (19.) | Disperse red 13 | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (20.) | Disperse blue 60(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (21.) | Pigment yellow 17(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (22.) | Pigment yellow 83(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (23.) | Pigment orange 13(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (24.) | Pigment rubin tonner (and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (25.) | Pigment lake red CT(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (26.) | Disperse orange 288(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (27.) | Disperse blue 291(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (28.) | M-8(n-cyano ethyl methyl aniline) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (29.) | Disperse rubine 5B(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (30.) | Disperse blue SE2R1(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (31.) | Disperse blue 291(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (32.) | Disperse yellow FFL(and/or) | 12 | 108 | 120 | Tons per Annum(TPA) | | Road | | (33.) | Disperse red 11(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (34.) | Disperse violet 26(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (35.) | Pigment yellow 12(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (36.) | Disperse yellow brown REL(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (37.) | Disperse orange 25(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (38.) | Disperse brown 3REL(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (39.) | Disperse golden yellow 2GD(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (40.) | Disperse yellow 241(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (41.) | Dispersing agent SS | 12 | 588 | 600 | Tons per Annum(TPA) | | Road | | (42.) | Pigment orange 34(and/or) | 0 | 120 | 120 | Tons per Annum(TPA) | | Road | | (43.) | Disperse golden yellow GG(and/or)) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (44.) | Disperse yellow AL (And/or) | 12 | 108 | 120 | Tons per Annum(TPA) | | Road | | (45.) | Disperse yellow 7 GL(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (46.) | Disperse scarlet 3R(and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | (47.) | Disperse red 9 (and/or) | 81 | 879 | 960 | Tons per Annum(TPA) | | Road | | |
| (c)Details of Configuration | |
|
S. No. | Plant / Equipment / Facility | Existing Configuration | Proposed Configuration | Final configuration after expansion | Remarks |
---|
(1.) | MSRLTL | 15000 Liter | 0 | 15000 Liter | 1 nos. | (2.) | MSRLTL | 25000 Liter | 0 | 25000 Liter | 1 nos. | (3.) | MSRLTL | 5000 Liter | 0 | 5000 Liter | 1 nos. | (4.) | Filter press | 36 Inch | 0 | 36 Inch | 3 Nos. | (5.) | Spray Dryer | 100 Liter | 0 | 100 Liter | 1 nos. | (6.) | GLR Reactors | 0 | 3 KL | 3 KL | 1 Nos. | (7.) | FB Dryers/Tray Dryer | 0 | 200 Tray | 200 Tray | 3 Nos. | (8.) | Transfer pump | 0 | 3 HP | 3 HP | 3 Nos. | (9.) | Spray Dryer | 0 | 500 Liter | 500 Liter | 1 Nos. | (10.) | MSRLTL | 9000 Liter | 0 | 9000 Liter | 1 nos. | (11.) | Sand Mills | 125 Liter | 0 | 125 Liter | 3 Nos. | (12.) | ETP | 10 KLD | 30 KLD | 40 KLD | | (13.) | SS Reactors | 0 | 10 KL | 10 KL | 1 Nos. | (14.) | Centrifuges | 0 | 36 Inch | 36 Inch | 1 Nos. | (15.) | Sand Mills | 0 | 125 Liter | 125 Liter | 3 Nos. | (16.) | Tray Dryer | 200 tray | 0 | 200 tray | 3 Nos. | |
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | 29 Jan 2018 | (iv)Valid Upto | 24 Oct 2022 | (v)File No. | GPCB/ANK/CCA-337/ID-15650/443119 | (vi)Application No. | 443119 | (vii)Copy of Consent to operate valid as on date | Copy of Consent to Operate | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in crores) | 2.5 | (b) Funds Allocated for Environment Management (Capital) (in crores) | 0.6 | (c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) | 0.025 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) | 1.9472 | (e) Funds Allocated for Environment Management Capital(%) | 0.00 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 6068.16 | (b)Existing quantity of raw material/fuel | 175.62 | (c)Total quantity of raw material/fuel | 6243.78 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | 6 bromo 2:4 dinitro aniline | 288 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (2.) | Sulphuric Acid | 441.6 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (3.) | Sodium Nitrate | 96 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (4.) | G Salt | 144 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (5.) | Dada mol NKS (Naphthaline Base) | 489.6 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (6.) | N ethyl 4 methyl 3 cyano 6 bhydroxy 2 pyridone | 112.16 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (7.) | 2:4 dinitro chloro benzene | 165.6 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (8.) | Para amino phenol | 84.48 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (9.) | Para nitro aniline | 168.96 | Tons per Annum | | Local | Road | | 100 | Open Market | | Copy of Linkage | (10.) | HCL | 393.6 | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (11.) | Sodium Acetate | 441.6 | Tons per Annum | | Open market | Road | | 10 | Open Market | | Copy of Linkage | (12.) | M3 A ( 3 n n diethyl amino acetanilide) | 451.2. | Tons per Annum | | Local | Road | | 10 | Open Market | | Copy of Linkage | (13.) | Raw Material | 6243.78 | Tons per Annum | | Open market | Road | | 15 | Open Market | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 01 Mar 2018 To 31 May 2018 | (b)Season | Summer | |
|
14.1. No. of ambient Air Quality (AAQ) Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | PM10 | | Micro Gram per Meter Cube | 90 | 59 | 90 | 100 | (2.) | SO2 | | Micro Gram per Meter Cube | 48 | 9 | 48 | 80 | (3.) | NOx | | Micro Gram per Meter Cube | 48 | 12 | 48 | 80 | (4.) | Others | CO | Micro Gram per Meter Cube | 0.8 | 0.3 | 0.8 | 2 | (5.) | PM2.5 | | Micro Gram per Meter Cube | 48 | 22 | 48 | 60 | |
14.2. No. of Ground Water Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 8.2 | 7.1 | 8.5 | 6.5 | (2.) | Total Hardness | | | mg/l | | 520 | 120 | 300 | 600 | (3.) | Fluoride | | | mg/l | | 0.49 | 0.05 | 1 | 1.5 | (4.) | Heavy Metals | | Calcium | mg/l | | 315 | 84 | 75 | 200 | (5.) | TDS | | | mg/l | | 2130 | 285 | 500 | 2000 | (6.) | Others | Nitrate | | mg/l | | 14 | 0.5 | 45 | 100 | (7.) | TSS | | | mg/l | | 0 | 0 | 0 | 0 | (8.) | Chlorides | | | mg/l | | 890 | 110 | 250 | 1000 | |
14.3. No. of Surface Water Monitoring Locations : 8 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 9 | 6 | C | (2.) | DO | | mg/l | | 4 | 3 | C | (3.) | BOD | | mg/l | | 10 | 10 | C | (4.) | Others | Total hardness (as CaCO3) | mg/l | | 220 | 110 | C | (5.) | COD | | mg/l | | 10 | 10 | C | |
14.4. No. of Ambient Noise Monitoring Locations : 8 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Night) | A-weighted decibels(dB(A)) | 55 | 37 | 70 | (2.) | Leq(Day) | A-weighted decibels(dB(A)) | 65 | 45 | 75 | |
14.5. No. of Soil Sample Monitored Locations : 8 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | Electric Conductivity | Others | µmS/cm | 1.45 | 1.18 | (2.) | P(Phosphorus) | Milligram per Kilogram | | 16.1 | 10.2 | (3.) | N(Nitrogen) | Milligram per Kilogram | | 15.1 | 11.4 | (4.) | K(Potassium) | Milligram per Kilogram | | 0.128 | 0.036 | (5.) | pH | Others | . | 8.5 | 7.4 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 00 To 00 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 00 To 00 | (c)Whether Ground Water Intersection will be there ? | No | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Others | GIDC water supply | 75 | 0.5 | Copy of Permission Letter | Pipeline | | Others | | 6412 | 03 Apr 2019 | 75 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Industrial | 41 | 40 | Primary ETP | Others | Send to ETL & CMEE - BEIL for further treatment | 6 | 35 | |
|
16.1. | (a)Total Waste Water Generation | 41 | (b)Total Discharged Water | 35 | (c)Total Reused Water | 6 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | Used Oil | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 0.106 | Tons | 3 | Road | | Authorized Recyclers | | (2.) | Discarded Containers/bags /liners | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 12.5 | Tons | 3 | Road | | Authorized Recyclers | | (3.) | ETP Sludge | Hazardous Waste (as per Hazardous and Other Waste Management rules 2016) | | 12 | Tons | 3 | Road | | Treatment, Storage and Disposal Facility(TSDF) | | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 90 | 10 | 0.255 | 90.255 | 100 | (2.) | NOx | | Microgram per Meter Cube | 48 | 10 | 0.542 | 48.542 | 80 | (3.) | Others(Specify) | CO | Microgram per Meter Cube | 0.8 | 10 | 0 | 0.8 | 2 | (4.) | PM2.5 | | Microgram per Meter Cube | 48 | 10 | 0.255 | 48.255 | 60 | (5.) | SO2 | | Microgram per Meter Cube | 48 | 10 | 0.829 | 48.829 | 80 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Boiler (1 TPH) | Natural Gas | 13 | 0.4 | SO2,NOx ,Others | PM | | (2.) | Boiler (2 TPH) | Natural Gas | 13 | 0.4 | SO2,NOx ,Others | PM | | (3.) | Hot Air Generator(3 lac Kcal) (2 Nos.) | Natural Gas | 15 | 0.4 | SO2,NOx ,Others | PM | | (4.) | Hot Air Generator (1 lack Kcal) | Natural Gas | 15 | 0.4 | SO2,NOx ,Others | PM | | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 300 | (b)Source | Dakshin Gujarat Vij Company Ltd. (DGVCL) | (c)Uploaded Copy of Agreement | Not Applicable | (d)Standby Arrangement (Details of DG Sets) | 200 KVA | (e)Stack Height (in m) | 10 | |
|
20. | Land Ownership Pattern: | (a)Forest Land | 0 | (b)Private Land | 0 | (c)Government Land | 0 | (d)Revenue Land | 0 | (e)Other Land | 0.1888 | Total Land | 0.1888 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area | 4743.53 | (b)Waste/Barren Land | 5097.08 | (c)Grazing/ Community Land | 0 | (d)Surface Water Bodies | 1418.57 | (e)Settlements | 0 | (f)Industrial | 4562.30 | (g)Forest | 0 | (h)Mangroves | 0 | (i)Marine Area | 0 | (j)Others : Fallow Land, Scrub/degraded vegetation & Sandy lan | 15661.18 | Total | 31482.66 | |
|
22. Land Requirement for Various Activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement | Remarks |
---|
(1.) | Green belt | | 500.44 | | (2.) | Main Plant | | 778.26 | | (3.) | Others | | 609.3 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | -- | 00 | No any Ecological Sensitivity | (2.) | WLS | -- | 00 | Not Applicable | (3.) | Corridors | -- | 00 | Not Applicable | (4.) | Wildlife Corridors | -- | 00 | Not Applicable | (5.) | NPA | -- | 00 | No any NPA & Ecological Sensitivity | (6.) | ESAs | -- | 00 | Not Applicable | (7.) | ESZs | -- | 00 | Not Applicable | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | -- | 00 | Not Applicable | (2.) | Archaeological Sites | | -- | 00 | Not Applicable | (3.) | Defence Installations | | -- | 00 | Not Applicable | (4.) | Others | No | -- | 00 | Not Applicable | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | No | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | Not Applicable | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 00 | (b)Land yet to be acquired(Ha) | 00 | (c)Status of Land acquisition if not acquired | Not applicable | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 0 | (b)No. of Households | 0 | (c)No. of PDFs (Project Displaced Families) | 0 | (d)No. of PAFs (Project Affected Families) | 0 | (e)Funds Allocated for R&R(in Rs) | 0 | (f)Status of R&R | Completed | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | No | (b)Whether there is Diversion Required ? | No | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | No | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 15 | (b)Permanent Employment-During Operation | 16 | (c)Temporary Employment- During Construction | 00 | (d)Temporary Employment- During Operation | 27 | (e)No. of working days | 360 | (f)Total Manpower | 58 | |
|
|
S. No. | Description | Existing | Proposed | Total |
---|
(1.) | Total Area of Green Belt | 500.44 | 0 | 500 | (2.) | Percentage of Total Project Area | 26.51 | 0 | 26 | (3.) | Funds Allocated | 100000 | 200000 | 300000 | (4.) | No. of Plants | 20 | 200 | 220 | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | employment opportunity for local people during construction and operation phase. | (2.) | Social | employment opportunity for local people during construction and operation phase. | (3.) | Social | employment opportunity for local people during construction and operation phase. | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details : NOT APPLICABLE |
35. Sector Specific Details For Industrial Projects - 2 |
|
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | Yes | (b)Details of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution) Act / Water (Prevention & Control of Pollution) Act | Air/Water | (c)Uploaded Copy of Direction Issued Under Environment (Protection) Act / Air (Prevention & Control of Pollution) Act / Water (Prevention & Control of Pollution) Act | Copy of Direction Issued | (d)Compliance status of the directions | Show cause notice has been revocated. | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | 12345 | (ii)Name of the EIA Consultant | Jyoti Om Chemical Research Centre Pvt. Ltd | (iii)Address | K-1, 7705/2-4, GIDC Estate, Ankleshwar-393002 | (iv)Mobile No. | 9824150383 | (v)Landline No. | 0264622029 | (vi)Email Id | info@jyotiom.com | (vii)Category of Accreditation | B | (viii)Sector of Accreditation | Industrial Projects - 2 | (ix)Validity of Accreditation | 01 May 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Details Sought |
---|
S. No. | EDS Sought Date | EDS Sought | Letter |
---|
(1.) | 08/06/2019 | Kindly upload attached format with complete details. Upload online CTE Fees receipt (XGN) letter from GPC | EDS Letter | (2.) | 10/06/2019 | The correction have been made as per the instruction received | | |
Addtional Details Sought |
---|
S. No. | ADS Sought Date | ADS Sought | Letter |
---|
NO Record | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Manshukh Vekaria | Designation | MD | Name of Company (Applicant Name should not be given here) | SHREE COLOSPERSE PVT. LTD. | Address | Plot No-6412, GIDC Estate, Ankleshwar, Dist: Bharuch-393002 |
|