Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Polymers India
(b)Name of the Company / Organisation POLYMERS INDIA
(c)Registered Address Plot No. C-1/355 GIDC Odhav, Ahmedabad,,Ahmedabad,Gujarat-382415
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Mukesh Patel
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Plot No. C-1/355 GIDC Odhav Ahmedabad,,Ahmedabad City,Ahmedabad,Gujarat-382415
(d)Pin code 382415
(e)E-mail sagarmilan75@yahoo.in
(f)Telephone No. 79-22870207
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/GJ/IND2/25618/2018
(e)Master Proposal Number(Single Window) SW/104959/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Shed No. C-1/355, GIDC Odhav, Ahmedabad, Gujarat
(b)Pincode 382415
(c)Bounded Latitudes (North)
From
Degree 23.01935
Minutes
Second
From
Degree 23.01936
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 72.65813
Minutes
Second
From
Degree 72.65834
Minutes
Second
(e)Survey of India Topo Sheet No. F43A12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 47
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 00
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratAhmedabadAhmedabad CityOdhav
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number SIA/GJ/42604/2018
(b)Date of Apply of EC 05 May 2018
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Public Hearing is exempted in our case as our unit
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. AWH71517
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Polyester Resin6150156OthersMTPMRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Thermic Fluid Heater1.0 Lac Kcal/hr.001.0 Lac Kcal/hr.
(2.)Blending Vessel001 KL – 1 no.1 KL – 1 no.
(3.)SS Reactor3.0 KL – 1 no.5.0 KL – 1 no.8.0 KL - 2 nos.
(4.)Cooling Tower50 TPH– 1 no.100 TPH– 1 no.50 TPH– 1 no., 100 TPH– 1 no.
(5.)DG Set0065 KVA– 1 no.65 KVA– 1 no.
(6.)Premix Vessel1 KL– 1 no.3 KL– 1 no.4 KL - 2 nos.
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 03 Jul 2015
(iv)Valid Upto 18 May 2020
(v)File No. CCA/ABD/OD-124/ID13085
(vi)Application No. 71517
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.90
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.033
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.035
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.0705
(e) Funds Allocated for Environment Management Capital(%) NaN
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1947.4
(b)Existing quantity of raw material/fuel 75.3
(c)Total quantity of raw material/fuel 2022.7
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)file attached2022.7Tons per AnnumLocal MarketRoad25 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2018 To 31 Dec 2018
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube90.862.284.55100
(2.)SO2Micro Gram per Meter Cube34.614.226.7780
(3.)NOxMicro Gram per Meter Cube40.818.732.380
(4.)PM2.5Micro Gram per Meter Cube43.128.439.7260
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHOtherspH units7.827.288.58.5
(2.)TSSmg/l25200000
(3.)TDSmg/l142910955002000
(4.)Fluoridemg/l0.550.481.01.5
(5.)Chloridesmg/l6615252501000
(6.)Total Hardnessmg/l378271300600
(7.)Heavy MetalsCoppermg/l0.050.050.051.5
    14.3.     No. of Surface Water Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)BODmg/l21A
(2.)DOmg/l7.33.6A
(3.)pHOtherspH unit7.657.29A
(4.)CODmg/l52A
(5.)OthersSodiummg/l295119A
    14.4.     No. of Ambient Noise Monitoring Locations : 9
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))57.251.875
(2.)Leq(Night)A-weighted decibels(dB(A))43.939.870
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pHOtherspH Unit8.057.48
(2.)N(Nitrogen)Milligram per Kilogram2.481.29
(3.)Electric ConductivityMillisiemens per Centimetre3.252.5
(4.)K(Potassium)Milligram per Kilogram236151
(5.)P(Phosphorus)Milligram per Kilogram12630
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 20 To 40
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 10 To 20
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC water supply2.410 Not Appliacble PipelineOthersGIDC water supplyGIDC/DMA/ODV/876023 Mar 20122.4
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic0.751Soak PitOthersDischarge in Soak pit000.75
(2.)Industrial0.280.5ETP and kettle type evaporatorOthersEvaporated in evaporator000.28
16.1.
(a)Total Waste Water Generation 1.03
(b)Total Discharged Water 1.03
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.6Tons25RoadTreatment, Storage and Disposal Facility(TSDF)
(2.)Evaporation residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.9Tons25RoadTreatment, Storage and Disposal Facility(TSDF)
(3.)Discarded Drums/ContainersHazardous Waste (as per Hazardous and Other Waste Management rules 2016)52.8Tons25RoadAuthorized Recyclers
(4.)Liners/BagsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)3.85Tons25RoadAuthorized Recyclers
(5.)Used OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)0.3Kilolitre25RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube75.461.4162.21.323100
(2.)NOxMicrogram per Meter Cube25.551.4118.71.18419.884
(3.)SO2Microgram per Meter Cube20.581.4114.20.61880
(4.)PM2.5Microgram per Meter Cube34.781.4128.41.32360
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)D G SetDiesel70.225OthersSPM, SO2 NOX85 mg/Nm3, 25 ppm, 30 ppm
(2.)Thermic Fluid HeaterNatural gas120.45OthersSPM, SO2 & NOx10 mg/Nm3, 12 ppm, 32 ppm
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 60
(b)Source Torrent Power Limited
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) D G Set of 65 kVA
(e)Stack Height (in m) 7
20.
Land Ownership Pattern:
(a)Forest Land 00
(b)Private Land 0.0696
(c)Government Land 00
(d)Revenue Land 00
(e)Other Land 00
    Total Land 0.0696
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 5721
(b)Waste/Barren Land 2609
(c)Grazing/ Community Land 00
(d)Surface Water Bodies 2452
(e)Settlements 10000
(f)Industrial 10653
(g)Forest 00
(h)Mangroves 00
(i)Marine Area 00
(j)Others : NA 00
    Total 31435
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt0.021
(2.)Main Plant0.0185
(3.)Built Up Area0.0080
(4.)OthersRoad, open margin0.0221
Total 0.0696
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNone within 10 km radius00None within 10 km
(2.)WLSNone within 10 km radius00None within 10 km
(3.)NPANone within 10 km radius00None within 10 km
(4.)ESZsNone within 10 km radius00None within 10 km
(5.)CorridorsNone within 10 km radius00None within 10 km
(6.)ESAsNone within 10 km radius00None within 10 km
(7.)Wildlife CorridorsNone within 10 km radius00None within 10 km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone within 10 km00None within 10 km
(2.)Defence InstallationsNone within 10 km00None within 10 km
(3.)Archaeological SitesNone within 10 km00None within 10 km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0.0696
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired NA
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 00
(b)No. of Households 00
(c)No. of PDFs (Project Displaced Families) 00
(d)No. of PAFs (Project Affected Families) 00
(e)Funds Allocated for R&R(in Rs) 00
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Odhav pond
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 00
(b)Permanent Employment-During Operation 16
(c)Temporary Employment- During Construction 15
(d)Temporary Employment- During Operation 00
(e)No. of working days 26
(f)Total Manpower 31
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt25185210
(2.)Percentage of Total Project Area3.526.529
(3.)No. of Plants74754
(4.)Funds Allocated0.30.70
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialContributing to nation via paying various taxes
(2.)SocialEmployment generation, CSR activities
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA 0084
(ii)Name of the EIA Consultant San Envirotech Pvt. Ltd., Ahmedabad
(iii)Address 424, Medicine Market, Paldi Cross Road, Paldi, Ahmedabad
(iv)Mobile No. 9825007201
(v)Landline No. 0792658307
(vi)Email Id manhendra.sepl@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 23 Dec 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)29/05/2019Documents not visible, Kindly apply again.
(2.)06/06/2019The correction have been made as per the instruction received
(3.)15/06/2019Documents not visible, Kindly rectify the issue with the help of NIC, Delhi.
(4.)26/06/2019The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantMukesh Patel
DesignationPartner
Name of Company (Applicant Name should not be given here)POLYMERS INDIA
AddressPlot No. C-1/355 GIDC Odhav, Ahmedabad