Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) STORAGE CAPACITY EXPANSION OF LPG BOTTLING PLANT FROM 450 MT TO 1800 MT
(b)Name of the Company / Organisation HPCL JABALPUR LPG BP
(c)Registered Address Plot 1&2 phase II Industrial Growth center at Maneri, Mandla Jabalpur.,,Mandla,Madhya Pradesh-481886
(d)Legal Status of the Company Central PSU
2.
Address for the correspondence:
(a)Name of the Applicant Lokender Garbyal
(b)Designation (Owner/ Partner/ CEO) PlantManager
(c)Address Plot 1&2 phase II Industrial Growth center at Maneri, Mandla Jabalpur.,Mandla,Madhya Pradesh-481886
(d)Pin code 481886
(e)E-mail lokendergarbyal@hpcl.in
(f)Telephone No. 7643-233200
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/MP/IND2/33355/2018
(e)Master Proposal Number(Single Window) SW/99761/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 1 & 2, Phase II
(b)Pincode 481886
(c)Bounded Latitudes (North)
From
Degree 20.101092
Minutes
Second
From
Degree 20.103739
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 80.200719
Minutes
Second
From
Degree 80.201053
Minutes
Second
(e)Survey of India Topo Sheet No. F44I1(64 B/1), F44I5(64 B/5)
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 680
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Madhya Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Madhya PradeshMandlaNiwasMANERI INDUSTRIAL AREA
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 66/PS-MS/MPPCB/SEAC/TOR(306)/2018
(b)Date of Apply of TOR 20 Nov 2017
(c)Date of Issue of TOR / Standard ToR 21 Feb 2018
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason It is in Notified Industrial Area
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)VesselNos. of Tanks (Proposed): 3x600 MTTotal Capacity (MT): 1800
(2.)VesselNos. of Tanks (Existing): 3x150 MTTotal Capacity (MT): 450
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1800 (Proposed)1800OthersMTRoad
(2.)450 (Existing)450OthersMTRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 30 Jun 2016
(iv)Valid Upto 30 Jun 2019
(v)File No. NA
(vi)Application No. 209057
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 21
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.035
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.021
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.06
(e) Funds Allocated for Environment Management Capital(%) 0.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 1800
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 1800
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bulk LPG90000OthersMTGAILRoad550 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 03 Oct 2017 To 22 Dec 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube84.042.161.5100(24 hr)
(2.)PM2.5Micro Gram per Meter Cube37.015.625.360(24 hr)
(3.)SO2Micro Gram per Meter Cube13.95.612.480(24 hr)
(4.)OthersCOMicro Gram per Meter Cube0.6330.0730.242(8 hr)
(5.)NOxMicro Gram per Meter Cube26.58.717.480(24 hr)
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l7182025001000
(2.)Total Hardnessmg/l397.4430.2200600
(3.)Fluoridemg/l0.930.6311.5
(4.)Chloridesmg/l42.2521.852501000
(5.)pHNA8.277.258.58.5
(6.)Heavy MetalsLeadmg/l0.00100.010.01
(7.)TSSmg/l121000
    14.3.     No. of Surface Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)DOmg/l6.36.0A
(2.)CODmg/l31.6614.75D
(3.)BODmg/l14.579.71D
(4.)pHNA8.027.52A
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))71.547.175
(2.)Leq(Night)A-weighted decibels(dB(A))62.136.570
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.526.48
(2.)N(Nitrogen)Kilogram per hectare156.4090.43
(3.)K(Potassium)Kilogram per hectare15.951.87
(4.)Electric ConductivityOthersmicro second per centimeter584.6270.3
(5.)P(Phosphorus)Kilogram per hectare1.1920.14
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.90 To 10.70
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0 To 5
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface5040 Not Appliacble PipelineOthersMPAKVN1421526907 Oct 201850
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic80Septic tank and soak pitReuse within the Plant & Recycling8
16.1.
(a)Total Waste Water Generation 8
(b)Total Discharged Water 0
(c)Total Reused Water 8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)NAOthersNA0Tons0RoadOthersNA
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube8410.2483.24100
(2.)PM2.5Microgram per Meter Cube3710060
(3.)SO2Microgram per Meter Cube13.910.00913.89180
(4.)NOxMicrogram per Meter Cube26.51521.580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG SetDiesel50.15PM10,SO2,NOx0.005, 0.0002, 0.1
(2.)DG SetDiesel70.15PM10,SO2,NOx0.016, 0.0006, 0.3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA))
(b)Source
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets)
(e)Stack Height (in m)
20.
Land Ownership Pattern:
(a)Forest Land
(b)Private Land
(c)Government Land
(d)Revenue Land
(e)Other Land
    Total Land
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area
(b)Waste/Barren Land
(c)Grazing/ Community Land
(d)Surface Water Bodies
(e)Settlements
(f)Industrial
(g)Forest
(h)Mangroves
(i)Marine Area
(j)Others :
    Total
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt2.05
Total 2.05
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0There is no NPA area
(2.)ESAsNA0There is no ESAs area
(3.)CorridorsNA0There is no corridors
(4.)Wildlife CorridorsNA0There is no wildlife corridors
(5.)WLSNA0There is no WSL area
(6.)ESZsNA0There is no ESZs area
(7.)Critically Polluted AreaNA0There is no Critically Polluted area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)OthersNANA0Not Applicable
(2.)Defence InstallationsNA0Not Applicable
(3.)ForestParariya RF7.8Direction - SE
(4.)Archaeological SitesNA0Not Applicable
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 38
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired acquired land is sufficient inside the plant area.
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Gaur Nadi, Jhamil Nadi, Bidri N
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 3.22
31.
Manpower Requirement:
(a)Permanent Employment-During Construction
(b)Permanent Employment-During Operation
(c)Temporary Employment- During Construction
(d)Temporary Employment- During Operation
(e)No. of working days
(f)Total Manpower
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare)
(b)Percentage of Total Project Area
(c)No. of Plants to be Planted
(d)Funds Allocated for Plantation
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialReduce the use of fire wood & fossil fuels.
(2.)FinancialEconomy strengthens democratic set-up.
(3.)EnvironmentalMaintain Continuity of LPG gas cylinder supply
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ?
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ?
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document?
(i)Accreditation No.
(ii)Name of the EIA Consultant
(iii)Address
(iv)Mobile No.
(v)Landline No.
(vi)Email Id
(vii)Category of Accreditation
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantLokender Garbyal
DesignationPlantManager
Name of Company (Applicant Name should not be given here)HPCL JABALPUR LPG BP
AddressPlot 1&2 phase II Industrial Growth center at Maneri, Mandla Jabalpur.