1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Augmentation of facilities at Crude Oil Terminal at Mundra
(b)Name of the Company / Organisation HPCL MITTAL PIPELINE LIMITED
(c)Registered Address Old Port Road, Mundra, Kutch,,kutch,Gujarat-370421
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Prodip kumar Biswas
(b)Designation (Owner/ Partner/ CEO) Asst. General Manager
(c)Address Old Port Road, Mundra, Kutch,,Mundra,kutch,Gujarat-370421
(d)Pin code 370421
(e)E-mail hmplmoef@gmail.com
(f)Telephone No. 120-4634702
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity6(b)Isolated storage & handling of hazardous chemicals (As per threshold planning
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/GJ/IND2/31366/2018
(e)Master Proposal Number(Single Window) SW/93993/2019
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Sy No. 141P, Existing Mundra Crude Oil Terminal
(b)Pincode 370421
(c)Bounded Latitudes (North)
From
Degree 224733.38
Minutes
Second
From
Degree 224734.50
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 6941.32.57
Minutes
Second
From
Degree 694216.18
Minutes
Second
(e)Survey of India Topo Sheet No. 42
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 9
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.625
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number SEIAA/GUJ/ToR/6(b)/1078/2018
(b)Date of Apply of EC 18 Jun 2018
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :20 Dec 2018
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :22 Jan 2019
Distance of Public Hearing Venue from the Proposed Project :9.5
Kudrati Upchar Kendra, Mundra-Gundala road Mundra, Gujarat
State :Gujarat
District :kutch
Tehsil :Mundra
Village :Mundra
40issue raised during public hearing are given in chapter-7 of Final EIA ReportDistrict Magistrate
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Bhopal
(iii)Letter No. 6-1/2009 (Parya)/109 dated 17.03.2017
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)1800008456851800001025685OthersKLPipe Conveyor
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)-----
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 29 Feb 2016
(iv)Valid Upto 24 Mar 2021
(v)File No. AWH-76797
(vi)Application No. 101701 dated 30.12.2015
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 156.60
(b) Funds Allocated for Environment Management (Capital) (in crores) 9.9
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 1.174
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.83
(e) Funds Allocated for Environment Management Capital(%) 5.77
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Crude Oil180000OthersKLpipelinePipe Conveyor10 OthersMundra-Bhatinda PipelineCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Nov 2016 To 31 Jan 2017
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube915088100
(2.)PM2.5Micro Gram per Meter Cube54245160
(3.)SO2Micro Gram per Meter Cube1351280
(4.)NOxMicro Gram per Meter Cube27112380
(5.)OthersCOMili Gram per Meter Cube0.690.130.62
    14.2.     No. of Ground Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l18792183.2200
(2.)Chloridesmg/l211172209.8250
(3.)Heavy MetalsPbmg/l000.010.01
(4.)TSSmg/l2115100100
(5.)pHmg/l7.97.17.88.5
(6.)TDSmg/l381290380.3500
(7.)Fluoridemg/l0000
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHmg/l8.47.3B
(2.)BODmg/l1810B
(3.)DOmg/l6.14.1A
(4.)CODmg/l6044B
    14.4.     No. of Ambient Noise Monitoring Locations : 2
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))53.150.175
(2.)Leq(Night)A-weighted decibels(dB(A))41.139.170
    14.5.     No. of Soil Sample Monitored Locations : 2
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare8.26.4
(2.)N(Nitrogen)Kilogram per hectare11541
(3.)Electric ConductivityOtherspmhos/cm388134
(4.)pH7.97.4
(5.)K(Potassium)Kilogram per hectare10580
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.20 To 53.64
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.65 To 98.80
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersAdani Ports and Special Economic Zone Ltd.9013Copy of Permission LettermodeOthersTankerOthersAdani Ports and Special Economic Zone Ltd.17.2.201217 Feb 201290
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic812ETPOtherssoak pit71
16.1.
(a)Total Waste Water Generation 8
(b)Total Discharged Water 1
(c)Total Reused Water 7
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)sewageMunicipal Solid Waste2400Kilolitre0RoadOtherssoak pit
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube13100.7212013.721280
(2.)NOxMicrogram per Meter Cube271000.243427.243480
(3.)PM2.5NA54100060
(4.)PM10particulate matterMicrogram per Meter Cube90100.132790.1327100
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG setDiesel12.050.5PM1090.1327
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 9300
(b)Source nearest grid
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 1 no of DG set of 500 KVA
(e)Stack Height (in m) 12.05
20.
Land Ownership Pattern:
(a)Forest Land 0.0
(b)Private Land 0.0
(c)Government Land 0.0
(d)Revenue Land 0.0
(e)Other Land 94.95
    Total Land 94.95
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 4.66
(b)Waste/Barren Land 15.25
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 6.96
(e)Settlements 2.35
(f)Industrial 5.65
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : open area and vegetation area 65.25
    Total 100.12
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt10.17
(2.)OthersETP and other processing undit28.54
(3.)Main Plant55.61
Total 94.32
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Wildlife Corridorsnone0.0None in present in 5 km study area
(2.)ESAsnone0None in present in 5 km study area
(3.)NPAnone0None in present in 5 km study area
(4.)Corridorsnone0None in present in 5 km study area
(5.)ESZsnone0None in present in 5 km study area
(6.)Critically Polluted Areanone0None in present in 5 km study area
(7.)WLSnone0None in present in 5 km study area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological Sitesgylf of kutch0None in present in 5 km study area
(2.)Forestnone0None in present in 5 km study area
(3.)Defence Installationsnone0None in 5 Km study area
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired not required
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Surrai River
(ii)Direction of Water Bodies in Buffer Area South West
(iii)Distance of Water Bodies in Buffer Area 3
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 0
(c)Temporary Employment- During Construction 300
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 300
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Total Area of Green Belt10.712674526755
(2.)No. of Plants267452674553490
(3.)Percentage of Total Project Area11.271021
(4.)Funds Allocated26.112046
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialemployment will be generated
(2.)Financialsupply of crude oil will increase economic growth
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 2
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1619/RA0063
(ii)Name of the EIA Consultant Mantec Consultants Pvt. Ltd
(iii)Address D36, sector 6 Noida
(iv)Mobile No. 9911994264
(v)Landline No. 0120421580
(vi)Email Id envmantec@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 2
(ix)Validity of Accreditation 29 Sep 2019
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantProdip kumar Biswas
DesignationAsst. General Manager
Name of Company (Applicant Name should not be given here)HPCL MITTAL PIPELINE LIMITED
AddressOld Port Road, Mundra, Kutch
Print