Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Kuakhai River Sand Quarry, Kalyanpur B Sand Bed Mines on River Kuakhai over an area of 20.214 Ha/ 49.948 Acres (Cluster area: 34.475 Ha) at village Kalyanpur, under Bhubaneswar Tahasil of Khordha district, Odisha
(b)Name of the Company / Organisation SARAT BEHERA
(c)Registered Address AT- KHOLAMUNDA, TAHSIL- PALLAHARA, DIST.- ANUGUL,,Anugul,Orissa-759118
(d)Legal Status of the Company Individual
2.
Address for the correspondence:
(a)Name of the Applicant Sarat Behera
(b)Designation (Owner/ Partner/ CEO) lessee
(c)Address AT- KHOLAMUNDA, TAHSIL- PALLAHARA, DIST.- ANUGUL,,,Anugul,Orissa-759118
(d)Pin code 759118
(e)E-mail beherasarat784@gmail.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/OR/MIN/59663/2021
(e)Master Proposal Number(Single Window) SW/290567/2022
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khata No.-221, Plot No. 1061
(b)Pincode 751002
(c)Bounded Latitudes (North)
From
Degree 20
Minutes 22
Second 31.56
From
Degree 20
Minutes 22
Second 54.64
(d)Bounded Longitudes (East)
From
Degree 85
Minutes 52
Second 20.52
From
Degree 85
Minutes 52
Second 45.78
(e)Survey of India Topo Sheet No. F45T15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 22
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Orissa
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)OrissaKhordhaBhubaneswarKalyanpur
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 59663/61-MINB1/01-2021
(b)Date of Apply of TOR 16 Jan 2021
(c)Date of Issue of TOR / Standard ToR 07 Jun 2021
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :13 Nov 2021
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :15 Dec 2021
Distance of Public Hearing Venue from the Proposed Project :3
Block Conference Hall, Bhubaneswar situated under Bhubaneswar Tahasil in Khurda District, Odisha
State :Orissa
District :Khordha
Tehsil :Bhubaneswar
Village :Bhubaneswar
48A) Environmental Issues I. 2. Restoration of Nearest forest area. Apprehension of damage to River Bank due to mining activities. 2.Apprehension of villagers regarding disturbance of childrenOthersAdditional District Magistrate, Khordha
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Safety gears Helmets, safety shoes,Goggles & Hand gloves---As required
(2.)Excavator0.9 Cum4 Nos
(3.)Haiwa /Trucks/Tractors13 Cum/6Cum/3Cum10/20/30
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Sand85500OthersCubic Meter Per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.10
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.035
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.084
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.035
(e) Funds Allocated for Environment Management Capital(%) 35.00
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)No raw material will be required0OthersCubic Meter Per AnnumCaptiveRoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2020 To 28 Feb 2021
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube61.440.052.2100
(2.)PM2.5Micro Gram per Meter Cube34.418.824.560
(3.)NOxMicro Gram per Meter Cube21.310.216.380
(4.)SO2Micro Gram per Meter Cube11.15.28.880
    14.2.     No. of Ground Water Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.36.88.58.5
(2.)TSSmg/l0000
(3.)Total Hardnessmg/l188132200600
(4.)Chloridesmg/l38.315.32501000
(5.)Fluoridemg/l0.90.1411.5
(6.)OthersAlkalinitymg/l192149200600
(7.)TDSmg/l4102025002000
(8.)Heavy MetalsMercurymg/l< 0.0005< 0.00050.0010.001
    14.3.     No. of Surface Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.27.5C
(2.)DOmg/l7.36.8C
(3.)BODmg/l21.2C
(4.)OthersTotal ColiformsOthersMPN/100ml24080C
(5.)CODmg/l106C
    14.4.     No. of Ambient Noise Monitoring Locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))48.340.255
(2.)Leq(Night)A-weighted decibels(dB(A))35.430.245
    14.5.     No. of Soil Sample Monitored Locations : 4
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare125.587.9
(2.)P(Phosphorus)Kilogram per hectare51.716
(3.)Electric ConductivityMillisiemens per Centimetre0.4350.102
(4.)K(Potassium)Kilogram per hectare107.543
(5.)pH6.906.30
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 6 To 8
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 4 To 6
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersTanker31.5Copy of Permission LetterPipelineOthersPurchasedNil27 Aug 20223
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)000NaOthersnil00
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)0OthersNil0Tons0RoadOthersNil
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube8.90.508.980
(2.)PM2.5Microgram per Meter Cube24.70.5024.760
(3.)PM10Microgram per Meter Cube59.710.52.2962100
(4.)NOxMicrogram per Meter Cube16.40.5016.480
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM10,SO2,NOx ,PM2.50
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source Nil
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) Nil
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 20.214
(d)Revenue Land 0
(e)Other Land 0
    Total Land 20.214
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 13228.75
(b)Waste/Barren Land 6108.32
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 3189.75
(e)Settlements 3569.62
(f)Industrial 322.91
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Tree Cover 4977.82
    Total 31397.17
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Quarry Area17.827
(2.)Safety Zone2.387
Total 20.214
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0No critically polluted area within 10Km.
(2.)CorridorsNil0No corridors within 10Km.
(3.)WLSNil0No WLS within 10Km.
(4.)ESZsNil0No ESZs within 10Km.
(5.)Wildlife CorridorsNil0No wildlife corridors within 10Km.
(6.)NPANil0No NPA within 10Km.
(7.)ESAsNil0No ESAs within 10Km.
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil0No forest within 10 Km.
(2.)Archaeological SitesNil0No archaeological site within 10 Km.
(3.)Defence InstallationsNil0No defence installation within 10 Km.
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 20.214
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Kuakhai River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Puri Main Canal
(ii)Direction of Water Bodies in Buffer Area East
(iii)Distance of Water Bodies in Buffer Area 0.9
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 86
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 258
(e)No. of working days 200
(f)Total Manpower 344
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0
(b)Percentage of Total Project Area 0.00
(c)No. of Plants to be Planted 250
(d)Funds Allocated for Plantation 75000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialAssistance to primary school in Kalyanpur Village
(2.)EnvironmentalPlantation of fruit trees in village waste land and schools
(3.)SocialHealth check-up camps
(4.)SocialRain water harvesting structure at school building
(5.)SocialEmployment opportunity to the local people
(6.)FinancialEmployment opportunity to the local people
(7.)SocialProvision of repair and maintenance of tube well and provision for drinking water facility
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)SandMinor
2.
Mine Capacity in ROM (Run of Mine) 85500
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. GXVII (g)-320/19 4835/DG
(b)Date of Approval 06 Jul 2020
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Government of Odisha, Directoorate of Geology
(e)Approved Mining Lease Area 20.214
(f)Approved Capacity 85500
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 2.09
(b)Mineable Reserves (Million Ton) 1.85
(c)Extractable Reserves(Million Ton) 1.11
(d)Percent(%) of Extraction 53.11
(e)Grade of Coal /Ore /Mineral 1
(f)Stripping Ratio 1 : 0
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) Na
(h)Average Gradient(Degree) 35
(i)Mining Method Opencast
(j)Life of Mine (Years) 5
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 20.214
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 16 Sep 2020
(iii)Validity of LOI 5
(iv)Reference No. of LOI 5988
(c)Whether Lease Deed Executed ? No
(i)Reason thereof This is a new mines not yet executed by the lessee
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof Not in operation
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 17.827
(b)Depth (in meter) 1
(c)Volume (in Million Cubic meter) 17.827
12.
Details of Quarry:
(a)Final Void of 17.827 (hectare) at a Depth of 1 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 20214
13.
Details of Transportation:
(a)In Pit/Underground to Surface 300m
(b)Surface to Siding/Loading 500m
(c)Transportation / Conveyor Details Trucks/tractors
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND000
(2.)SETTLEMENTS000
(3.)OTHERS(Specify)River Bed20.214020.214
(4.)FOREST LAND000
(5.)WASTE LAND000
(6.)GRAZING LAND000
(7.)SURFACE WATER BODIES000
TOTAL20.214020.214
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)GREEN BELT0000
(2.)VIRGIN AREA0000
(3.)EXCAVATION/QUARRY017.827017.827
(4.)EXTERNAL OB DUMPS0000
(5.)INTERNAL OB DUMPS0000
(6.)TOP SOIL STORAGE0000
(7.)ROADS0000
(8.)BUILT UP AREA (COLONY/OFFICE)0000
(9.)OtherQuarry Safety zone area02.38702.387
TOTAL020.2140020.214
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 0
(d)Safety Zone(in hectare) 0
(e)Final Void of 17.827 (hectare) at a Depth of 1 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 0
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)2022008550000
(2.)2024008550000
(3.)2025008550000
(4.)2026008550000
(5.)2023008550000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/2023/SA 0149
(ii)Name of the EIA Consultant Kalyani Laboratories Pvt. Ltd.
(iii)Address Plot No.: 78/944, Pahala, The Millenium City, Bhubaneswar, 752101
(iv)Mobile No. 9937327084
(v)Landline No. 0674297405
(vi)Email Id kalyanilab@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 02 Mar 2023
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantSarat Behera
Designationlessee
Name of Company (Applicant Name should not be given here)SARAT BEHERA
AddressAT- KHOLAMUNDA, TAHSIL- PALLAHARA, DIST.- ANUGUL
Print