Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? Yes
Type of Violation Other
Details of Violation After EC Letter validity expired mining activity was going on site.
Upload document of Damage Assessment Report Annexure-Damage Assessment Report
Upload document of Remediation Plan and Natural & Community augmentation plan Annexure-Remediation Plan and Natural & Community augmentation plan
Upload TOR Letter(if issued earlier) Annexure-Uploaded TOR Letter
Upload EC Letter(if issued earlier) Annexure-Uploaded EC Letter
Details of Project:
(a)Name of the project(s) Devpur Ordinary Stone Quarry Project
(b)Name of the Company / Organisation GAGAN NAHATA
(c)Registered Address Nahata Chowk Post & Tahsil Nagri District Dhamtari Chhattisgarh,,Dhamtari,Chhattisgarh-493778
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Gagan Nahata
(b)Designation (Owner/ Partner/ CEO) applicant
(c)Address Nahata Chowk Post & Tahsil Nagri District Dhamtari Chhattisgarh,,Nagri,Dhamtari,Chhattisgarh-493778
(d)Pin code 493778
(e)E-mail gaganjpnahata@yahoo.co.in
(f)Telephone No. 7700-251324
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/CG/MIN/82960/2021
(e)Master Proposal Number(Single Window) SW/290392/2022
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. 447 Part
(b)Pincode 493778
(c)Bounded Latitudes (North)
From
Degree 20
Minutes 19
Second 11.71
From
Degree 20
Minutes 19
Second 11.90
(d)Bounded Longitudes (East)
From
Degree 81
Minutes 55
Second 48.64
From
Degree 81
Minutes 55
Second 56.80
(e)Survey of India Topo Sheet No. 64H/15
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 600
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 2
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Chhattisgarh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)ChhattisgarhDhamtariNagriDevpur
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number SIA/CG/MIN/192989/2021
(b)Date of Apply of EC 20 Jan 2021
(c)Date of Issue of EC 31 Dec 1899
(d)Previous EC Letter Copy of Previous EC letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? No
(c)Reason Public Hearing is not required as per TOR issued by SEIAA Chhattisgarh dated: 17.05.2022, & a Vide Letter No.: 213/Mine/Dhamtari/1528.
(d)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By SPCB
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on
(iii)Letter No. IRO-RPR/ENV/MIN/112/2021/395
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)4.000400000400000Tons per Annum(TPA)Road
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Shovel/Excavators-For excavation and loading of ordinary stoneFor excavation and loading of ordinary stone11 nos. with 1.0 cum bucket capacity
(2.)Jack Hammer-For drilling ordinary stone bedFor drilling ordinary stone bed20 nos. with 32 mm Capacity
(3.)Water Tanker-For sprinkling of on quarry roadFor sprinkling of on quarry road10 nos. with 1,000 liters Capacity
(4.)Water Pump-For dewatering the working pit during the rainFor dewatering the working pit during the rain4 nos. with 5HP Capacity
(5.)Compressor-For running jack hammerFor running jack hammer5 nos. with 625 cfm Capacity
(6.)Dumpers/Tippers-For transportation of ROM of ordinary stoneFor transportation of ROM of ordinary stone96 nos. with 15T Capacity
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception Copy of Consent to Operate
(iii)Date of Issue 22 Aug 2022
(iv)Valid Upto 28 Aug 2022
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.60
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.17007
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.0225
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.05165
(e) Funds Allocated for Environment Management Capital(%) 28.35
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel 0
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)NA0Tons per AnnumNARoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Mar 2022 To 31 May 2022
(b)Season Pre-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)SO2Micro Gram per Meter Cube16.188.4516.0580
(2.)NOxMicro Gram per Meter Cube30.6420.1230.2880
(3.)PM2.5Micro Gram per Meter Cube56.6135.6156.2160
(4.)PM10Micro Gram per Meter Cube86.2263.4586.01100
    14.2.     No. of Ground Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.687.286.58.5
(2.)TDSmg/l4773785002000
(3.)Total Hardnessmg/l274158200600
(4.)Chloridesmg/l5745.02501000
(5.)Heavy MetalsTotal Iron (as Fe)mg/l0.1860.0871.01.0
(6.)TSSNA0000
(7.)Fluoridemg/l0.470.351.01.5
    14.3.     No. of Surface Water Monitoring Locations : 3
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.367.24C
(2.)DOmg/l7.16.6C
(3.)BODmg/l10.73.0C
(4.)CODmg/l31.411.5C
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))46.440.440-70
(2.)Leq(Day)A-weighted decibels(dB(A))59.555.850-75
    14.5.     No. of Soil Sample Monitored Locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Kilogram per hectare88.452.7
(2.)Electric ConductivityOthersmicroohms/cm775645
(3.)pH7.627.11
(4.)N(Nitrogen)Milligram per Kilogram347289
(5.)K(Potassium)Kilogram per hectare308258
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 40 To 45
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 30 To 35
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater1.000Copy of Permission LetterPipelineOthersBorewell21-4/4701/CT/IND/202130 Jun 20211.00
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)000NAGreen Belt Renewal Plant0
16.1.
(a)Total Waste Water Generation 0
(b)Total Discharged Water 0
(c)Total Reused Water 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Seawage WasteMunicipal Solid Waste0Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube86.220.31.1287.34100
(2.)SO2Microgram per Meter Cube16.180.33.3119.4980
(3.)PM2.5Microgram per Meter Cube56.610.30.5657.1760
(4.)NOxMicrogram per Meter Cube30.640.319.8550.4980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 04
(b)Source Solar Power
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 0
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 4.00
(d)Revenue Land 0
(e)Other Land 0
    Total Land 4.00
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 4.00
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Other 0
    Total 4
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Quarry Area4.00Govt Land
Total 4
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0None within 10km radius
(2.)Wildlife CorridorsNA0None within 10km radius
(3.)Critically Polluted AreaNA0None within 10km radius
(4.)WLSNA0None within 10km radius
(5.)ESAsNA0None within 10km radius
(6.)ESZsNA0None within 10km radius
(7.)CorridorsNA0None within 10km radius
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestRatwa RF4.6in SW direction
(2.)Archaeological SitesNA0None within 10km radius
(3.)OthersWild Life SanctuariesSitanadi Wildlife Sanctuary3.85in N Direction
(4.)Defence InstallationsNA0None within 10km radius
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.00
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 37
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 280
(f)Total Manpower 37
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Percentage of Total Project Area022.2522
(2.)Total Area of Green Belt00.890
(3.)No. of Plants040004000
(4.)Funds Allocated0600000600000
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Environmentalincrease the vegetation
(2.)Environmentalincrease the vegetation
(3.)Environmentalincrease the vegetation
(4.)Environmentalincrease the vegetation
(5.)Environmentalincrease the vegetation
(6.)Environmentalincrease the vegetation
(7.)Environmentalincrease the vegetation
(8.)Environmentalincrease the vegetation
(9.)Environmentalincrease the vegetation
(10.)Environmentalincrease the vegetation
(11.)Environmentalincrease the vegetation
(12.)Environmentalincrease the vegetation
(13.)Environmentalincrease the vegetation
(14.)Environmentalincrease the vegetation
(15.)Environmentalincrease the vegetation
(16.)Environmentalincrease the vegetation
(17.)Environmentalincrease the vegetation
(18.)Environmentalincrease the vegetation
(19.)Environmentalincrease the vegetation
(20.)Environmentalincrease the vegetation
(21.)Environmentalincrease the vegetation
(22.)Environmentalincrease the vegetation
(23.)Environmentalincrease the vegetation
(24.)Environmentalincrease the vegetation
(25.)Environmentalincrease the vegetation
(26.)Environmentalincrease the vegetation
(27.)Environmentalincrease the vegetation
(28.)Environmentalincrease the vegetation
(29.)Environmentalincrease the vegetation
(30.)Environmentalincrease the vegetation
(31.)Environmentalincrease the vegetation
(32.)Environmentalincrease the vegetation
(33.)Environmentalincrease the vegetation
(34.)Environmentalincrease the vegetation
(35.)Environmentalincrease the veg
(36.)Environmentalincrease the vegetation
(37.)Environmentalincrease the vegetation
(38.)Environmentalincrease the vegetation
(39.)Environmentalincrease the vegetation
(40.)Environmentalincrease the vegetation
(41.)Environmentalincrease the veg
(42.)Environmentalincrease the vegetation
(43.)Environmentalincrease the vegetation
(44.)Environmentalincrease the vegetation
(45.)Environmentalincrease the vegetation
(46.)Environmentalincrease the vegetation
(47.)Environmentalincrease the vegetation
(48.)Environmentalincrease the vegetation
(49.)Environmentalincrease the vegetation
(50.)Environmentalincrease the vegetation
(51.)Environmentalincrease the vegetation
(52.)Environmentalincrease the vegetation
(53.)Environmentalincrease the vegetation
(54.)Environmentalincrease the vegetation
(55.)Environmentalincrease the vegetation
(56.)Environmentalincrease the vegetation
(57.)Environmentalincrease the vegetation
(58.)Environmentalincrease the vegetation
(59.)Environmentalincrease the vegetation
(60.)Environmentalincrease the vegetation
(61.)Environmentalincrease the vegetation
(62.)EnvironmentalTrees to be planted.
(63.)EnvironmentalTrees to be planted.
(64.)EnvironmentalTrees to be planted.
(65.)Environmentalincrease the vegetation
(66.)Environmentalincrease the vegetation
(67.)Environmentalincrease the vegetation
(68.)Environmentalincrease the vegetation
(69.)Environmentalincrease the vegetation
(70.)Environmentalincrease the vegetation
(71.)Environmentalincrease the vegetation
(72.)Environmentalincrease the vegetation
(73.)Environmentalincrease the vegetation
(74.)Environmentalincrease the vegetation
(75.)Environmentalincrease the vegetation
(76.)Environmentalincrease the vegetation
(77.)Environmentalincrease the vegetation
(78.)Environmentalincrease the vegetation
(79.)Environmentalincrease the vegetation
(80.)Environmentalincrease the vegetation
(81.)Environmentalincrease the vegetation
(82.)Environmentalincrease the vegetation
(83.)Environmentalincrease the vegetation
(84.)Environmentalincrease the vegetation
(85.)Environmentalincrease the vegetation
(86.)Environmentalincrease the vegetation
(87.)Environmentalincrease the vegetation
(88.)Environmentalincrease the vegetation
(89.)Environmentalincrease the vegetation
(90.)Environmentalincrease the vegetation
(91.)Environmentalincrease the vegetation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)1Minor
2.
Mine Capacity in ROM (Run of Mine) 400000
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 947(A)/Khanij/Utkh.yo.anu./U.P./2020-21
(b)Date of Approval 05 Jan 2021
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department Regional Office, Uttar Bastar Kanker (C.G)
(e)Approved Mining Lease Area 4.00
(f)Approved Capacity 400000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 4.2796175
(b)Mineable Reserves (Million Ton) 1.618461
(c)Extractable Reserves(Million Ton) 1.618461
(d)Percent(%) of Extraction 95
(e)Grade of Coal /Ore /Mineral 0
(f)Stripping Ratio 1 : 0.05
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) 0
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 4
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 4.00
(b)Whether obtained Letter of Intent (LOI) from the state government ? No
(i)Reason thereof Grant Lease Deed
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 4.00
(iii)Validity of the lease deed From : 02 May 2013 To : 01 May 2043
(iv)Date of Execution of Mining Lese 02 May 2013
(v)Reference Number NIL
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof The Lease for granted for 10 years from 02.05.2013
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
(v)No. of year back fill up 0
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 2.96
(b)Depth (in meter) 51
(c)Volume (in Million Cubic meter) 0.400000
12.
Details of Quarry:
(a)Final Void of 2.96 (hectare) at a Depth of 51 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 4.00
13.
Details of Transportation:
(a)In Pit/Underground to Surface Through transport
(b)Surface to Siding/Loading Trucks/Tippers
(c)Transportation / Conveyor Details By Road
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)FOREST LAND000
(2.)WASTE LAND4.0004
(3.)GRAZING LAND000
(4.)SURFACE WATER BODIES000
(5.)SETTLEMENTS000
(6.)AGRICULTURE LAND000
TOTAL404
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY02.9602.96
(2.)VIRGIN AREA0000
(3.)EXTERNAL OB DUMPS0000
(4.)INTERNAL OB DUMPS0000
(5.)ROADS0000
(6.)TOP SOIL STORAGE0000
(7.)BUILT UP AREA (COLONY/OFFICE)0000
(8.)GREEN BELT0000
TOTAL02.96002.96
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 4.00
(d)Safety Zone(in hectare) 0.00075
(e)Final Void of 2.96 (hectare) at a Depth of 51 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 557
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 0.89
17.
Status of progressive Mining Closure Plan:
Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan Copy of Implementation of Various Activities as per Approved Progressive Mine Closure Plan
Any Deviation from the Approved Progressive Mine Closure Plan 0
Total Area Excavated (in hectare) 0
Total Area Backfilled after Excavation (in hectare) 0
Total Area Reclaimed (in hectare) 0
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)000000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court Districts Courts
(c)Name of the Sub Court Raipur
(d)Case No. NA
(e)Orders/Directions of the court ,if any and its relevance with the proposed project NA
(f)Case Details NA
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? No
(i)Reason for not Hiring the Consultant NA
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGagan Nahata
Designationapplicant
Name of Company (Applicant Name should not be given here)GAGAN NAHATA
AddressNahata Chowk Post & Tahsil Nagri District Dhamtari Chhattisgarh