Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s. Ma Bhavani Industries
(b)Name of the Company / Organisation MABHAVANIINDUSTRIES
(c)Registered Address Plot No. 25/5,25/6,25/7, Dhandhuka Ind. Estate,Ahmedabad,Gujarat-382460
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Nimesh Patel
(b)Designation (Owner/ Partner/ CEO) Partner
(c)Address Plot No. 25/5,25/6,25/7, Dhandhuka Ind. Estate,Ahmedabad,Gujarat-382460
(d)Pin code 382460
(e)E-mail mabhavaniindustries@gmail.com
(f)Telephone No. 0-
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/GJ/IND3/71650/2021
(e)Master Proposal Number(Single Window) SW/250688/2022
(f)EAC concerned (for category A Projects only) Industrial Projects - 3
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No.25/5, 25/6 & 25/7
(b)Pincode 382460
(c)Bounded Latitudes (North)
From
Degree 22
Minutes 22
Second 22.62
From
Degree 71
Minutes 57
Second 8.57
(d)Bounded Longitudes (East)
From
Degree 22
Minutes 22
Second 20.77
From
Degree 71
Minutes 57
Second 11.23
(e)Survey of India Topo Sheet No. a3/a2
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 48
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Gujarat
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)GujaratAhmedabadDhandhukaDhandhuka
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SIA/GJ/106506/2021
(b)Date of Apply of TOR 12 Jun 2021
(c)Date of Issue of TOR / Standard ToR 14 Jun 2021
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason As project fall in GIDC
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)FILTER PRESS48''X48"QTY1
(2.)Vessel20KLQty 2
(3.)AIR COMPRESSOR1 HPQTY 1
(4.)HAG20L KCAL/hrQTY 1
(5.)HAG8 LKCAL/hrQTY 1
(6.)SPRAY DRYER2500 LPH1
(7.)SPRAY DRYER500 LPHQTY 1
(8.)BAG MILL4TQTY1
(9.)BAG MILL2TQTY1
(10.)PULVERIZER10 HPQTY 1
(11.)BLENDER10 TQTY1
(12.)Vessel60KLQty 2
(13.)Vessel5KLQty 2
(14.)Vessel10KLQty 2
(15.)BAG MILL1TQTY 1
(16.)Vessel40KLQty 2
(17.)BOILER3 TPHQTY 2
(18.)BAG MILL4TQTY1
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Crude Acid Black- 21074OthersMT/MRoad
(2.)Crude Direct Black- 2274OthersMT/MRoad
(3.)Crude Solvent Red- 2474OthersMT/MRoad
(4.)Crude Acid Black- 10 BX74OthersMT/MRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 3
(b) Funds Allocated for Environment Management (Capital) (in crores) 1.60
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.03
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 1.14
(e) Funds Allocated for Environment Management Capital(%) 53.33
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 18177
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 18177
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Aniline150Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(2.)Beta naphthol300Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(3.)Caustic soda sodium nitrate54Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(4.)DASA220Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(5.)FC Acid198Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(6.)Gamma Acid282Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(7.)Garnet GB Base550Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(8.)H Acid800Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(9.)HCL2117Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(10.)Ice4000Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(11.)MPD60Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(12.)m- Phenelne Diamine144Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(13.)NaOH150Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(14.)Octanol4Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(15.)PNA354OthersKG/MTLocal marketRoad5 Open MarketCopy of Linkage
(16.)Caustic soda190Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(17.)Soda ash796Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(18.)Sodium Nitrate680Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(19.)stream170Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(20.)Sulfamic acid58Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
(21.)Water6900Otherskg/mtlocal marketRoad5 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2020 To 28 Feb 2021
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM2.5Micro Gram per Meter Cube24.116.923.860
(2.)NOxMicro Gram per Meter Cube12.47.912.380
(3.)SO2Micro Gram per Meter Cube7.84.97.780
(4.)PM10Micro Gram per Meter Cube73.554.672.8100
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Chloridesmg/l4062122501000
(2.)Total Hardnessmg/l368276200600
(3.)pHNA7.747.246.58.5
(4.)Fluoridemg/l0.420.2711.5
(5.)TSSmg/l0000
(6.)TDSmg/l9628345002000
    14.3.     No. of Surface Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.827.16A
(2.)DOmg/l2.51.8A
(3.)BODmg/l83A
(4.)CODmg/l2814A
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))64.250.175
(2.)Leq(Night)A-weighted decibels(dB(A))58.240.770
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)P(Phosphorus)Milligram per Kilogram2610
(2.)pH7.927.74
(3.)N(Nitrogen)Milligram per Kilogram140115
(4.)Electric ConductivityOthersMicrosiemens per cm154118
(5.)K(Potassium)Milligram per Kilogram6440
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.28 To 22.58
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.06 To 16.52
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersGIDC water5010Copy of Permission LetterPipelineTube WellGIDC/RM/ABD/TFR/DDK/98420 Feb 201635
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Industrial2010ETP-RO- InhouseMEEOthersReuse for cooling128
(2.)Domestic31STPReuse within the Plant & Recycling3
16.1.
(a)Total Waste Water Generation 23
(b)Total Discharged Water 8
(c)Total Reused Water 15
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)ETP SludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)95Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube73.5100.69920.6992100
(2.)PM2.5Microgram per Meter Cube24.1100.2790.27960
(3.)SO2Microgram per Meter Cube7.8100.13740.137480
(4.)NOxMicrogram per Meter Cube12.4100.2990.29980
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Steam Boiler 3 TPHImported Coal/Briquettes of agro waste311.5PM10,SO2,NOx
(2.)Steam Boiler 3TPHImported coal/Briquettes of agro waste311.5PM10,SO2,NOx
(3.)Hot Air Generator 20L Kal/hrImported Coal/Briquettes of agro waste 15MT/day311PM10,SO2,NOx
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 150
(b)Source UGVCL
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 125 KVA
(e)Stack Height (in m) 11
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0.32775
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 0.32775
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 27039.79
(b)Waste/Barren Land 2265.02
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 543.24
(e)Settlements 0
(f)Industrial 96.57
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Settlement and Open scrub LAnd 1518.49
    Total 31463.110000000004
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Main Plant31683
(2.)Green belt1092
Total 32775
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNone within 10km0None within 10km
(2.)ESZsNone within 10km0None within 10km
(3.)CorridorsNone within 10km0None within 10km
(4.)Wildlife CorridorsNone within 10km0None within 10km
(5.)Critically Polluted AreaNone within 10km0None within 10km
(6.)NPANone within 10km0None within 10km
(7.)ESAsNone within 10km0None within 10km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Archaeological SitesNone within 10km0None within 10km
(2.)Defence InstallationsNone within 10km0None within 10km
(3.)ForestNone within 10km0None within 10km
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 00
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 13266
(b)Land yet to be acquired(Ha) 00
(c)Status of Land acquisition if not acquired Already Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 22
(b)No. of Households 27797
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 5
(b)Permanent Employment-During Operation 10
(c)Temporary Employment- During Construction 5
(d)Temporary Employment- During Operation 10
(e)No. of working days 365
(f)Total Manpower 30
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.109
(b)Percentage of Total Project Area 33.26
(c)No. of Plants to be Planted 162
(d)Funds Allocated for Plantation 0
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalOut of 3277.5 m2 of total area , 1092 m2 area is for green belt area
(2.)SocialTotal man power during construction and operational phase are 30
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/2124/RA 0219
(ii)Name of the EIA Consultant GREEN CIRCLE INC
(iii)Address GREEN CIRCLE INC., Green Empire (Anupushpam), Beside Canara Bank, Nr. Yash Complexs above axis bank, Gotri Main Road , Vadodara, Gujarat, India
(iv)Mobile No. 8734973898
(v)Landline No. 0265237126
(vi)Email Id eia5@greencircleinc.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 26 Jan 2024
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)24/02/20221. Pl. submit authenticated document regarding non applicability of public hearing to proposed project. 2. Pl. submit GIDC plot allotment letter with mentioning purpose of plot for chemical manufacturing unit. 3. Pl. submit SEAC b1 prescribed format. 4.Submit a certificate of no plagiarism by running a plagiarism test in a suitable software and submit the requisite report along with EIA/EMP report as per the MoEF&CC’s OM F. No. 22-17/2020-IA.III dated 07.07.2020.
(2.)09/03/2022The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)20/06/2022asper minutes
(2.)15/09/2022WITHDRAWAL OF EIA REPORT & TOR for obtaining Environment Clearance for our expansion project Ma bhavaniADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantNimesh Patel
DesignationPartner
Name of Company (Applicant Name should not be given here)MABHAVANIINDUSTRIES
AddressPlot No. 25/5,25/6,25/7, Dhandhuka Ind. Estate
Print