Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Proposed Establishment of synthetic organic chemicals manufacturing facility by Vinati Organics Limited, Plot No L-2/1, L-2/2, Additional MIDC Mahad, Dist Raigad, Maharashtra
(b)Name of the Company / Organisation VINATI ORGANICS LTD
(c)Registered Address 1102, G- block Parinee Crescenzo, BKC, Bandra East, Mumbai,,Mumbai City,Maharashtra-400051
(d)Legal Status of the Company Others
2.
Address for the correspondence:
(a)Name of the Applicant Jayesh Ashar
(b)Designation (Owner/ Partner/ CEO) C.O.O
(c)Address 1102, G- block Parinee Crescenzo, BKC, Bandra East, Mumbai,Mumbai City,Maharashtra-400051
(d)Pin code 400051
(e)E-mail prasanna@vinatiorganics.com
(f)Telephone No. 22-61244444
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f) Synthetic organic chemicals industry (dyes & dye intermediates; bulk
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/MH/IND3/71245/2016
(e)Master Proposal Number(Single Window) SW/201635/2021
(f)EAC concerned (for category A Projects only) Industrial Projects - 3
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. L-2/1, L-2/2
(b)Pincode 402309
(c)Bounded Latitudes (North)
From
Degree 18
Minutes 6
Second 54.94
From
Degree 18
Minutes 6
Second 51.54
(d)Bounded Longitudes (East)
From
Degree 73
Minutes 31
Second 21.52
From
Degree 73
Minutes 31
Second 25.25
(e)Survey of India Topo Sheet No. E43H8 & E43H12
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 34
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.5
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraRaigadMahadKalij
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number SIA/MH/IND2/11142/2016
(b)Date of Apply of TOR 22 Apr 2016
(c)Date of Issue of TOR / Standard ToR 16 Jul 2016
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Project is in notified industrial area
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Reactor, plant, cooling tower, storage tanksproposed--
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Para Amino Phenol36000Tons per AnnumRoad
(2.)Hydrogen3200OthersNm3/hrRoad
(3.)Cogen plant14Mega Watt(MW)Otherscaptive
(4.)Ortho amino phenol900Tons per AnnumRoad
(5.)Aniline3500Tons per AnnumRoad
(6.)Nitrobenzene40000Tons per AnnumRoad
(7.)Ammonium Sulphate33000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 554
(b) Funds Allocated for Environment Management (Capital) (in crores) 32.5
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 5.54
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 4.17
(e) Funds Allocated for Environment Management Capital(%) 5.87
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 120552
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 120552
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Benzene35500Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(2.)Methanol17500Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(3.)toluene500Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(4.)Anhydrous Ammonia11300Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(5.)Nitric Acid21000Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(6.)Sulphuric acid33000Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(7.)Mono Ethylene Glycol720Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
(8.)Caustic lye1032Tons per AnnumLocalRoad500 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 09 Mar 2017 To 26 May 2017
(b)Season Summer
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube71.341.771.1100
(2.)PM2.5Micro Gram per Meter Cube2312.922.960
(3.)SO2Micro Gram per Meter Cube13.810.213.680
(4.)OthersCOMili Gram per Meter Cube0.50.10.44
(5.)NOxMicro Gram per Meter Cube17.812.617.680
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TSSmg/l0000
(2.)TDSmg/l90205002000
(3.)OthersSulphatemg/l20.69.7200400
(4.)Chloridesmg/l78.74.82501000
(5.)Total Hardnessmg/l17465200600
(6.)Heavy MetalsCadmiummg/l000.0030.003
(7.)pHNA8.27.256.58.5
(8.)Fluoridemg/l0011.5
    14.3.     No. of Surface Water Monitoring Locations : 10
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA8.427.18E
(2.)DOmg/l5.44.2E
(3.)BODmg/l2212E
(4.)CODmg/l00E
(5.)OthersChloridesmg/l743E
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))62.650.275
(2.)Leq(Night)A-weighted decibels(dB(A))57.640.870
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.566.54
(2.)N(Nitrogen)Kilogram per hectare38.921.8
(3.)Electric ConductivityOthersµmhos/cm376236.3
(4.)K(Potassium)Kilogram per hectare138.6115.5
(5.)P(Phosphorus)Kilogram per hectare27.814.7
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.95 To 7.7
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.1 To 4.05
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMIDC & treated recycle47950Copy of Permission LetterPipelineOtherspipelineEE/A50134/of 201707 Feb 20174069
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Trade effluent7871000ETP, UF, RO, MEE, ATFDOthers715 cmd recycle & 29 cmd discharge75829
(2.)Domestic sewage1215MBBRGreen Belt Renewal Plant12
16.1.
(a)Total Waste Water Generation 799
(b)Total Discharged Water 29
(c)Total Reused Water 770
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Fly AshFly Ash48910Tons200RoadOthersto authorised brick manufacturer
(2.)Rubber,Handgloves,shoes,TarpaulinIndustrial Waste2Tons200RoadOthersSale to Authorised recycler
(3.)Insulating material, claddingIndustrial Waste1Tons200RoadOthersSale to Authorised recycler
(4.)Iron scrap, Glass, Paper, Plastic bottlesIndustrial Waste5Tons200RoadOthersSale to Authorised recycler
(5.)Used/ Spent OilHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Kilolitre200RoadOthersCHWTSDF/ to Authorized party
(6.)Exhaust Air or Gas cleaning residueHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2Tons200RoadOthersCHWTSDF
(7.)Chemical sludge from ETPHazardous Waste (as per Hazardous and Other Waste Management rules 2016)165Tons200RoadOthersCHWTSDF
(8.)MEE saltsHazardous Waste (as per Hazardous and Other Waste Management rules 2016)2535Tons200RoadOthersCHWTSDF
(9.)Discarded Drums, carboysHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1000Kilolitre200RoadOthersAuthorized Recycler (UOM- Nos)
(10.)Process wastes, residues and sludgeHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Tons200RoadOthersCHWTSDF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube65.710.165.8100
(2.)NOxMicrogram per Meter Cube14.810.615.480
(3.)PM2.5Microgram per Meter Cube16.80016.860
(4.)SO2Microgram per Meter Cube12.111.713.880
(5.)Others(Specify)CONA0.19000.194
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)750 KVA DG setHSD 150 Lit/hr50.2PM10150 mg/Nm3
(2.)96 TPH BoilerCoal 419 TPD763PM101.09
(3.)Process vent--50.2PM10--
(4.)Thermic fluid heater 15 lac kcal/hrCoal 13.5 TPD300.55PM100.059
(5.)Thermic fluid heater 15 lac kcal/hrCoal 13.5 TPD300.55PM100.059
(6.)750 KVA DG setHSD 150 Lit/hr50.2PM10150 mg/Nm3
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 5000
(b)Source Captive Cogen plant and MSEDCL
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) 2 nos. of 750 KVA DG set
(e)Stack Height (in m) 5
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 10.0054
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 10.0054
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 7
(b)Waste/Barren Land 5220
(c)Grazing/ Community Land 5679
(d)Surface Water Bodies 426
(e)Settlements 174
(f)Industrial 198
(g)Forest 12852
(h)Mangroves 0
(i)Marine Area 120
(j)Others : Open land 8044
    Total 32720
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt3.4389
(2.)Main Plant6.5665
Total 10.0054
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted AreaNil0Nil
(2.)WLSNil0Nil
(3.)NPANil0Nil
(4.)ESAsNil0Nil
(5.)ESZsNil0Nil
(6.)CorridorsNil0Nil
(7.)Wildlife CorridorsNil0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNil0Nil
(2.)Archaeological SitesKol caves13.7caves
(3.)Defence InstallationsNil0Nil
(4.)OthersSongad fortSongad fort14.5Tourist place
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) Not Applicable
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired plot owned by Vinati
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Kal river
(ii)Direction of Water Bodies in Buffer Area South East
(iii)Distance of Water Bodies in Buffer Area 0.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 150
(c)Temporary Employment- During Construction 100
(d)Temporary Employment- During Operation 0
(e)No. of working days 7
(f)Total Manpower 250
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 3.4389
(b)Percentage of Total Project Area 34.37
(c)No. of Plants to be Planted 6880
(d)Funds Allocated for Plantation 20
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)Socialsocial upliftment, local emplyment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Industrial Projects - 3
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/SA 0129
(ii)Name of the EIA Consultant Aditya Environmental Services Pvt. Ltd.
(iii)Address 107, Hiren Light Industrial estate, Mogul Lane, Mahim- west, Mumbai
(iv)Mobile No. 9821513367
(v)Landline No. 0224212750
(vi)Email Id rajiv@aespl.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Industrial Projects - 3
(ix)Validity of Accreditation 01 May 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantJayesh Ashar
DesignationC.O.O
Name of Company (Applicant Name should not be given here)VINATI ORGANICS LTD
Address1102, G- block Parinee Crescenzo, BKC, Bandra East, Mumbai