| Form-1 | | APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE | | | | 1. Basic Informations | | Project Name | Establishment of Active Pharma Ingredients (Bulk drug and intermediates) manufacturing unit by M/s. YS Drugs | Company/Organisation Name | YS DRUGS | | Registered Address | 2-2-1105/34/1, Flat No 303 Reliance Avens Arena, Tilak Nagar, Amberpet, Hyderabad Telangana 500013 | Legal Status of the Company | Private |
| | 2. | | Address for the correspondence: | | (a)Name of the Applicant | Chandra Shekar Reddy | | (b)Designation (Owner/ Partner/ CEO) | Partner | | (c)Address | 2-2-1105/34/1, Flat No 303,Nalgonda,Telangana-508116 | | (d)Pin code | 508116 | | (e)E-mail | ysdrugs2019@gmail.com | | (f)Telephone No. | 8499-850053 | | (g)Fax No. | | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | NIL | |
| | 3. | | Category of the Project/Activity as per Schedule of EIA Notification,2006: | | (a)Major Project/Activity | 5(f)-API
| | (b)Minor Project/Activity | NIL | | (c)Category | B2 | | (d)Proposal Number | SIA/TG/IND2/225704/2021 | | (e)Master Proposal Number(Single Window) | SW/199252/2021 | | (f)EAC concerned (for category A Projects only) | Industrial Projects - 2 | | (g)Project Type(New/Expansion/Modernization) | Fresh EC |
|
| | 4. | | (a)Number of States in which Project will be Executed | 1 | | (b)Main State of the project | Telangana | |
| | Details of State(s) of the project |
|---|
| S. No. | State Name | District Name | Tehsil Name | Village Name |
|---|
| (1.) | Telangana | Yadadri Bhuvanagiri | Bommalaramaram | Pyararam | | | 5. | | Details of Public Consultation: | | (a)Whether the Project Exempted from Public Hearing? | Yes | | (c)Reason | -1 | | (d)Supporting Document | NILL | |
| | Location of the project | Sy No. 344 (Part), 345 (Part), 347 (Part), Pyararam village Bommalaramaram Mandal Yadadri Bhuvanagiri District Telangana | | | Town / Village (Name of more than one town may be entered by separating with) | Pyararam village | Plot/Survey/Khasra No. (Name of more than one town may be entered by separating with) | Sy No. 344 (Part), 345 (Part), 347 (Part), | | State | Telangana | District | Yadadri Bhuvanagiri | | Tehshil | Bommalaramaram | Pincode | 508116 | | Nearest railway station | Bibinagar | Distance from the project site | 18.3 | | Nearest airport | Rajiv Gandhi International Airport | Distance from the project site | 51.7 | | Nearest Town/City/District Headquarters | Bommalaramaram | Distance from the project site | 6.47 | | Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) | Muneerabad | Upload GPS file | Copy of Kml File  Uploaded GPS file | | Shape of the project land | Block (Polygon) | Site alternative under consideration(If any) | Uploaded Site alternative under consideration | | Brief summary of project | Uploaded Brief summary of project | | | | Does your project location falls under out of any following areas | None of above Areas | | | | Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) | 5893.75 | Existing Built Up Area(In Meter /Sqr) | 0 | | Does it attract any of the general conditions given below? | No | | | | Does it attract the specific condition given below? | No | | | | Interlinked Projects | No | | | | Whether separate application of interlinked projects has been submitted? | | Date of Submission | | | Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | | | Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | | | Whether the proposal involves approval/clearance under the C.R.Z notification,2011? | No | | | | Whether there is any Government Order/Policy relevent/relating to the site? | No | | | | Forest land involved(hectares) | 0 | | | | Is there any litigation pending against the project? | No | | |
| 1. | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | The proposal is a green field project. The land use presently is barren. The land is plain and does not involve much of leveling/ excavation. The land use shall change to industrial and may change the topography by way of extensive greening and industrial construction. | | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | The land is barren and no major vegetation need to be cleared and no buildings etc., in the site area. | | 1.3 | Creation of new land uses? | Yes | Barren land/Single crop rain fed agricultural land shall be converted to industrial use. | | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Soil test done and soil load bearing capacity established. | | 1.5 | Construction works? | Yes | Construction activity involves creation of new additional utilities like Boiler, DG set, Chilling Plant etc and ZLD system. | | 1.6 | Demolition works? | No | Not Applicable. The proposal is a green field project | | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | Construction labor from local villages shall be employed. | | 1.8 | Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations | Yes | Manufacturing blocks, land scaping for greenery and roads. Effluent treatment plant, Solvent storage facility shall be constructed. No major cut and fill or excavation is anticipated. | | 1.9 | Underground works including mining or tunneling? | No | No underground works like mining and tunneling. | | 1.10 | Reclamation works? | No | No reclamations works are anticipated. | | 1.11 | Dredging? | No | No dredging works are anticipated. | | 1.12 | Offshore structures? | No | No offshore structures are anticipated. | | 1.13 | Production and manufacturing processes? | Yes | Enclosed in Annexure – I | | 1.14 | Facilities for storage of goods or materials? | No | Raw materials and solvents shall be stored with in factory premises. Materials in bags and drums will be stored in flame proof ware houses. Bulk quantities of raw materials will be stored in tank farms with retention dykes. | | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | High TDS and low TDS effluents are treated in Zero liquid discharge principle based effluent treatment plant and treated effluent will be re-used for boilers and cooling towers make-up.
Organic waste is sent to cement plants for co-incineration. Solid waste generated from Multiple Effect evaporators sent to secure land. Details of waste treatment facilities presented in Annexure II | | 1.16 | Facilities for long term housing of operational workers? | No | No long-term housing envisaged | | 1.17 | New road, rail or sea traffic during construction or operation? | Yes | Construction materials shall be transported to the site by road. The traffic density of the existing connecting road is negligible. | | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | Only upgradation of existing connecting roads to the project site. | | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | The proposed connectivity shall not attract any closure or diversion of the existing transport routes. | | 1.20 | New or diverted transmission lines or pipelines? | No | New Power transmission for the proposed project | | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | Storm water management plan shall ensure minimum disturbance of drainage within the site, without disturbing the inlet and outlet points of storm water drainage | | 1.22 | Stream crossings? | No | | | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Total water required shall be met from ground water. Total water required shall be 221.1 KLD out of which 156.1 KLD fresh water and the balance shall be recycled water. | | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | There are no natural water bodies or major drainage channels within the site. However, the drainage shall be planned by considering intensity of rain fall of the area. | | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The construction material shall be drawn from local sources within 10 – 15 km. There is no transport of personnel, as the construction workers shall be drawn from local villages. | | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | No Long-term dismantling or decommissioning or restoration works is envisaged. | | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | No ongoing activity is envisaged. | | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During construction phase local people will be hired from local villages on temporary bases. The proposed green field project shall increase employment potential. | | 1.29 | Introduction of alien species? | No | No introduction of alien species is envisaged | | 1.30 | Loss of native species or genetic diversity? | No | | | 1.31 | Any other actions? | No | | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | The land use is barren/rainfed single dry crop agricultural land and there is no double crop agricultural land. The proposed area for land development is 4 acres 28.75 guntas. | | 2.2 | Water (expected source & competing users) unit: KLD | Yes | Total water required shall be met from ground water. Total water required shall be 221.1 KLD out of which 156.1 KLD fresh water and the balance shall be recycled water. (Water Balance Enclosed in Annexure III) | | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Shall be sourced from the local villages. | | 2.5 | Forests and timber (source – MT) | No | | | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | The required energy shall be drawn from TS Transco. Standby DG sets of 2 x 500 kVA capacity is proposed. It is proposed to establish 1 x 3 TPH and 2 x 2 TPH coal fired boilers to meet the steam requirement for process. 1 x 2 TPH coal fired boiler will be kept as standby. It is proposed to establish coal based Thermic fluid heater of capacity 1 x 2 lac K.cal.
Coal consumption is 17.04 TPD. | | 2.7 | Any other natural resources (use appropriate standard units) | No | | |
| 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | Hazardous chemicals shall be used for manufacturing of CMC. MSIHC rules shall be followed during storage, transportation and handling of raw materials. Hazardous chemicals and solvent shall be stored and handled in closed systems. | | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | | | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | There will be a positive impact on the welfare of the people. The estimated employment generation potential of the project is 110 including direct employment generation of 50. Direct and Indirect employment during construction and operation phases of the project. | | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | No sensitive receptors are present in the immediate vicinity of the site. The project shall not have any significant impact on vulnerable groups of people. | |
| 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 4.1 | Spoil, overburden or mine wastes | No | No soil, overburden and mine waste are envisaged. | | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Wastes from canteen, other commercial wastes like paper, empty containers etc. The canteen wastes shall be in the range of 1 kg/day during operation. | | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Hazardous waste generation during construction shall be limited to waste oils, batteries and containers of paints etc. The quantity of hazardous wastes generated during operation contain salts from evaporators, process residue, and solvent residues, ETP sludge and filtration media etc. Detail of solid waste and disposal is enclosed in Annexure – IV | | 4.4 | Other industrial process wastes | Yes | Enclosed at Annexure IV | | 4.5 | Surplus product | No | Not Applicable | | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | Sludge from Effluent treatment plant and evaporation salts shall be sent to TSDF. | | 4.7 | Construction or demolition wastes | Yes | Disposed as per C&D Rules and guidelines | | 4.8 | Redundant machinery or equipment | Yes | Disposed to recyclers | | 4.9 | Contaminated soils or other materials | No | All pipe lines including pipe lines of waste streams shall be above ground level to eliminate possibility of any contamination due to seepage and for ease of maintenance. | | 4.10 | Agricultural wastes | No | No Agricultural wastes are used or generated. | | 4.11 | Other solid wastes | Yes | Hazardous waste and packing material | |
| 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Coal Shall be used as fuel for boiler. Diesel is for DG set. Quantity of fuel and emissions details are enclosed in Annexure V | | 5.2 | Emissions from production processes | Yes | Process emissions contain hydrogen chloride, sulfur dioxide. Details of treatment and disposal is enclosed in Annexure - VI | | 5.3 | Emissions from materials handling including storage or transport | No | Material transfer takes place in closed pipeline systems using pumps with mechanical seals. | | 5.4 | Emissions from construction activities including plant and equipment | Yes | Dust may rise during transport of material and construction activity. The dust emissions shall be mitigated by water spraying on the roads within the premises. | | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust may rise during transport of material and construction activity. The dust emissions shall be mitigated by water spraying on the roads within the premises. | | 5.6 | Emissions from incineration of waste | No | Organic waste streams are sent to cement plants for co-incineration. Incinerators are not proposed. | | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | There will not be any burning of wastes. | | 5.8 | Emissions from any other sources | Yes | Accidental release/spillage of chemicals may result in fugitive emission. | |
| 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Material transport and construction equipment shall be source of noise, while transfer pumps, vacuum systems, DG sets are the sources of noise during operation. | | 6.2 | From industrial or similar processes | Yes | DG sets, controlled by providing Acoustic Enclosures. | | 6.3 | From construction or demolition | Yes | Noise during construction shall be due to construction equipment and emergency DG sets. | | 6.4 | From blasting or piling | No | | | 6.5 | From construction or operational traffic | No | The increased traffic shall not have any significant impact | | 6.6 | From lighting or cooling systems | Yes | May result in marginal increase in the baseline at the boundary of the site due to noise levels from cooling towers. | | 6.7 | From any other sources | No | | |
| 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | All the hazardous materials are stored on elevated platform and stored in closed storage tanks and containers (Liner/MS/GI/HDPE) are stored in a closed shed and contamination of soil is anticipated in case of spillages and accidental releases. | | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | All the waste from domestic operations sent to Effluent Treatment Plant. Treated waste will be disposed to sea through marine outfall facility. | | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | All the emissions from process are controlled by providing control equipment like scrubbers, Dust Collectors and emissions from proposed boiler shall be controlled by providing electro static precipitators | | 7.4 | From any other sources | No | | | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | There is no risk of accumulation of long-term pollutants. Advanced treatment facilities are being used to treat the pollutants. Readings of on line TOC meter and Continuous Ambient Air monitoring stations will be installed to monitor the pollutants regularly. | |
| 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | All Inbuilt Safety precautions will be adopted and there will not be any damage to environment or human health. | | 8.2 | From any other causes | No | | | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | | |
| 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality |
| S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The project shall enhance the socio economic status of the area by increasing the demand for housing, improving the employment. There are no major support industries required for this plant. | | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | | | 9.3 | Set a precedent for later developments | No | | | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | The baseline environmental status of the surrounding areas is within the prescribed limits as observed from the Secondary data. | | | (III) | Environmental Sensitivity | | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | | | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Yes | Nearest Water body-0.55 km-NW,
Sharmirpet Vagu -0.81 km-SW,
Somajpalli RF -1.92 km-NW,
Keshavapur RF -4.6 km-SW,
Parvatapuram RF -7.7 km-S,
Kisaragutta RF -8.1 km-S,
Vasalamarri RF -7.9 km-NE,
Gopalpur RF -8.3 km-N | | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | There is no record of any sensitive species of flora and fauna. | | 4 | Inland, coastal, marine or underground waters | No | | | 5 | State, National boundaries | No | | | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | | | 7 | Defence installations | No | | | 8 | Densely populated or built-up area | Yes | Nearest habitation from the site is Muneerabad village at a distance of 1.0 km in west direction. | | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | No | | | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | | | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | No record of exceedance | | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | | | | Essential Details Sought |
|---|
| S. No. | EDS Sought Date | EDS Sought | Letter |
|---|
| NO Record | | | Additional Details Sought |
|---|
| S. No. | ADS Sought Date | ADS Sought | Letter |
|---|
| NO Record | | | | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. | | | | Name of Applicant | Chandra Shekar Reddy | | Designation | Partner | | Name of Company (Applicant Name should not be given here) | YS DRUGS | | Address | 2-2-1105/34/1, Flat No 303 |
|
|