Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Mixed Use Development under SEZ as per IT/ ITES Sector and Integrated Township Project (ITP) policy
(b)Name of the Company / Organisation PERSIPINA DEVELOPERS PRIVATE LIMITED
(c)Registered Address Alpha Building, 11th Floor, Main Street, Hiranandani Gardens, Powai,,Mumbai City,Maharashtra-400076
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant N Prashanth
(b)Designation (Owner/ Partner/ CEO) Vice President (Contracts and Procurement)
(c)Address 514, Dalamal Towers, Free Press Journal Marg, Nariman Point, Mumbai 400 021,,Fort Tondiarpet,Mumbai City,Maharashtra-400021
(d)Pin code 400021
(e)E-mail persipina_parivesh@hrealty.com
(f)Telephone No. 22-25758241
(g)Fax No. 25766455
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/MH/MIS/62216/2020
(e)Master Proposal Number(Single Window) SW/205912/2021
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Village Barvai, Bhokarpada at Taluka Panvel and vi
(b)Pincode 410222
(c)Bounded Latitudes (North)
From
Degree 18545619
Minutes
Second
From
Degree 18554867
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 73103399
Minutes
Second
From
Degree 73105682
Minutes
Second
(e)Survey of India Topo Sheet No. 47F/01, 47F/05 & 47E/04
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 37.06
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0.006
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Maharashtra
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)MaharashtraRaigadPanvelVillage Barvai and Bhokarpada at Taluka Panvel and village Panshil and Talegaon at Taluka Khalapur
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number SIA/MH/NCP/51654/2020
(c)Date of Apply of TOR 28 Feb 2020
(d)Date of Issue of TOR / Standard ToR 28 May 2020
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason Township and area development project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Total Construction BUA6219577.38 Sq. mt.--
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Total Construction BUA6219577.38OthersSq. mt.OthersConstruction material
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 12 Jun 2020
(iv)Valid Upto 31 Dec 2021
(v)File No. Format1.0/CAC-CELL/UAN No. 0000085029/CO-200600058
(vi)Application No. MPCB-CONSENT-0000085029
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 6375
(b) Funds Allocated for Environment Management (Capital) (in crores) 331.59
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 27.43
(e) Funds Allocated for Environment Management Capital(%) 5.20
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 30069324
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 30069324
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Building & construction raw materials (sand, Cement & steel)30069324OthersTons, Kg, bags etc.Nearby vendorsRoad500 OthersNot ApplicableCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2020 To 31 Dec 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube755875100
(2.)NOxMicro Gram per Meter Cube20152080
(3.)SO2Micro Gram per Meter Cube15131580
(4.)PM2.5Micro Gram per Meter Cube33253360
(5.)OthersCOMili Gram per Meter Cube1.40.91.404
    14.2.     No. of Ground Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.57.46.58.5
(2.)TSSmg/l6.03.000
(3.)Fluoridemg/l0.610.311.01.5
(4.)Heavy MetalsZincmg/l00515
(5.)Total Hardnessmg/l284128200600
(6.)Chloridesmg/l68452501000
(7.)TDSmg/l4282345002000
    14.3.     No. of Surface Water Monitoring Locations : 9
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l12412D
(2.)DOmg/l6.34.8A
(3.)BODmg/l17.70D
(4.)pHNA7.96.7A
    14.4.     No. of Ambient Noise Monitoring Locations : 6
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))54.248.255
(2.)Leq(Night)A-weighted decibels(dB(A))43.738.845
    14.5.     No. of Soil Sample Monitored Locations : 2
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare117102
(2.)K(Potassium)Milligram per Kilogram4847
(3.)Electric ConductivityMillisiemens per Centimetre0.5250.422
(4.)pH7.87.2
(5.)P(Phosphorus)Kilogram per hectare5649
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.0 To 3.1
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.0 To 3.1
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)OthersMaharashtra Jeevan Pradhikaran (MJP)207920Copy of Permission LetterPipelineOthersNANo. MJPP/TB/1271/200629 Aug 200633000
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Treated Sewage for recycling2904131010MBBRGreen Belt Renewal Plant,OthersReused for flushing and gardening1206216979
16.1.
(a)Total Waste Water Generation 29041
(b)Total Discharged Water 16979
(c)Total Reused Water 12062
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)BiodegradableMunicipal Solid Waste15232Tons0OthersTreatment in organic waste convertorOthersWill be used as manure on site
(2.)Non- biodegradableMunicipal Solid Waste22848Tons0RoadOthersTo Agency named M/s. Sai Aarti Enterprises
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube3005.03560
(2.)PM10Microgram per Meter Cube6506.071100
(3.)NOxMicrogram per Meter Cube1908.02780
(4.)SO2Microgram per Meter Cube150102580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DG Set on siteDiesel60.5OthersSPM, SO20
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 400500
(b)Source Maharashtra State Electricity Distribution Compan
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) Phase 1: 81 nos. of DG sets of total capacity 9609
(e)Stack Height (in m) 6
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 174.76
    Total Land 174.76
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Township 174.76
    Total 174.76
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersTownship174.76Integrated Township Project & SEZ
Total 174.76
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNA0--
(2.)ESZsMatheran0.5Project site is not affected by the ESZ as the boundary of the site under reference is 500 mts. away from the nearest boundary of ESZ of Matheran. Hence NOC is not applicable.
(3.)ESAsNA0--
(4.)WLSKarnala Bird Sanctuary5.00NOC from Wild Life Board is Not Applicable as per final Notification reg. ESZ of Karnala Wildlife Sanctuary published by MOEF & CC u/no. S. O. 230(E) dated 22/01/2016 as our project site is not affect
(5.)NPANA0--
(6.)Critically Polluted AreaNA0--
(7.)Wildlife CorridorsNA0--
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Others(Partly mixed jungle & partly open scrub land)Reserved Forest near Ambivali0Abutting (South-West Side of Plot)
(2.)Defence InstallationsNot applicable0--
(3.)Archaeological SitesNot applicable0--
(4.)Forest--0--
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 1461
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 174.76
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not applicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Yes - Natural drain (Barvai Nalla) within the project site, Pond within the project site
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? Yes
(i)Uploaded copy of permission Copy of permission
(ii)Letter No. 2/503/Year 2021
(iii)Date of issue 10 Mar 2021
(iv)Recommendation --
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Mohopada Lake
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 1.00
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 30125
(c)Temporary Employment- During Construction 5000
(d)Temporary Employment- During Operation 40000
(e)No. of working days 28
(f)Total Manpower 75125
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 9.55
(b)Percentage of Total Project Area 5.46
(c)No. of Plants to be Planted 15598
(d)Funds Allocated for Plantation 110536000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialThis Integrated Township Project comprises of Residential buildings, EWS (Economical Weaker Section), Social Housing LIG (Lower Income Group) Scheme, along with amenities like School, Commercial, IT/
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 164.45
(b)Total No. of Flats to be Build 45600
(c)No. of Buildings 199
(d)Total plot area (sqm) 1747600
(e)Total built up area (sqm) 6219577.38
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 183
    Capacity 228855
(b)No. of Recharge Pits 14
    Capacity 840
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 4 W: 58270 Nos. & 2W: 84394 Nos.
5.
Energy Saving Measures:
(a)Source/Mode Maharashtra State Electricity Distribution Compan
(b)Percentage 21.73
(c)Quantity 445000
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Details given in chapter 3 of EIA report.
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/2023/RA0194
(ii)Name of the EIA Consultant ULTRA TECH
(iii)Address Unit No. 224, 225, 206 Jai Commercial Complex, Eastern Express Highway, Opp. Cadbury Factory, Khopat,Thane(w).400601
(iv)Mobile No. 8692900073
(v)Landline No. 0222534277
(vi)Email Id dipti@ultratech.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 09 Mar 2023
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)11/04/2021PP to submit details of scrutiny fees paid as per important notice published on 10th November,2020 by SEIAA on ec.ecmpcb.in website.
(2.)20/05/2021The correction have been made as per the instruction received
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
(1.)29/09/2021Pls go through the minutes uploaded.
(2.)13/10/2021As per the suggestion of Hon. Committee, we have submitted application for amendment in the received ToR on Parivesh (MoEF & CC) portal on dt. 01.10.2021 and received Proposal No. SIA/MH/MIS/232330/2021. Hence we request your good office to withdraw our application for EC submitted dt. 25.03.2021 (Proposal No. SIA/MH/MIS/62216/2020) on Parivesh portalADS Letter
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantN Prashanth
DesignationVice President (Contracts and Procurement)
Name of Company (Applicant Name should not be given here)PERSIPINA DEVELOPERS PRIVATE LIMITED
AddressAlpha Building, 11th Floor, Main Street, Hiranandani Gardens, Powai
Print