Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) INTEGRATED MUNICIPAL SOLID WASTE PROCESSING FACILITY FOR SRINAGAR, Khasra No – 169, 170, 171, 187, 188, 189, 190, At Village –Girgaon, Tehsil- Srinagar, District- Pauri Garhwal (Uttarakhand),
(b)Name of the Company / Organisation NAGAR PALIKA PARISHAD, SRINAGAR
(c)Registered Address Nagar Palika Parishad Srinagar, Near Bus Stand, Uttarakhand,,Pauri Garhwal,Uttarakhand-246174
(d)Legal Status of the Company Central Government
2.
Address for the correspondence:
(a)Name of the Applicant Ram Jaiswal
(b)Designation (Owner/ Partner/ CEO) Executive Engineer
(c)Address Nagar Palika Parishad Srinagar, Near Bus Stand, Uttarakhand,Pauri Garhwal,Uttarakhand-246174
(d)Pin code 246174
(e)E-mail srinagarnpp89@gmail.com
(f)Telephone No. 1346-252484
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity7(i) Common Municipal Solid Waste Management Facility (CMSWMF)
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/UK/MIS/61450/2019
(e)Master Proposal Number(Single Window) SW/201193/2021
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra No – 169, 170, 171, 187, 188, 189, 190,
(b)Pincode 246148
(c)Bounded Latitudes (North)
From
Degree 30.206796
Minutes
Second
From
Degree 30.206796
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 78.739509
Minutes
Second
From
Degree 78.741428
Minutes
Second
(e)Survey of India Topo Sheet No. 53J/12 & 53J/16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 635
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 1.30
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttarakhand
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)UttarakhandPauri GarhwalSrinagarGirgaon
6.
Details of Terms of Reference (ToR):
(a)Whether TOR is mandatory for submitting application Yes
(b)MoEF&CC / SEIAA File Number SIA/UK/MIS/47701/2019
(c)Date of Apply of TOR 02 Dec 2019
(d)Date of Issue of TOR / Standard ToR 17 Jan 2020
(e)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :18 Dec 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :18 Jan 2021
Distance of Public Hearing Venue from the Proposed Project :0
Project Site, Girgaon - Village, Tehsil – Srinagar District- Pauri Garhwal – Uttarakhand.
State :Uttarakhand
District :Pauri Garhwal
Tehsil :Srinagar
Village :Girgaon
84Effluent & Leachate Treatment, conservation of animals, birds and local flora, fauna will be done.OthersAddl. District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Composting FacilityMechanical Composting
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Compost1.058OthersTonnes Per DayRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 7.52
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.15
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.15
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.027
(e) Funds Allocated for Environment Management Capital(%) 1.99
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 22.1
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 22.1
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Municipal Solid Waste8066.5Tons per AnnumHousehold, Commercial & InstitutionalRoad9 OthersNot ApplicableCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 16 Dec 2019 To 15 Mar 2020
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)NOxMicro Gram per Meter Cube21.838.2819.6280
(2.)PM10Micro Gram per Meter Cube67.4948.0467.18100
(3.)SO2Micro Gram per Meter Cube10.198.519.9780
(4.)PM2.5Micro Gram per Meter Cube39.8725.1139.3360
    14.2.     No. of Ground Water Monitoring Locations : 7
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)Total Hardnessmg/l216164200600
(2.)TSSNA0000
(3.)TDSmg/l3462685002000
(4.)Chloridesmg/l42222501000
(5.)pHNA7.626.918.58.5
(6.)Fluoridemg/l0.80.511.5
(7.)Heavy MetalsIronmg/l0.200.130.30.3
    14.3.     No. of Surface Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.767.61A
(2.)DOmg/l7.57.2A
(3.)BODmg/l1.91.7A
(4.)CODmg/l8.687.71A
    14.4.     No. of Ambient Noise Monitoring Locations : 7
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Day)A-weighted decibels(dB(A))54.547.775
(2.)Leq(Night)A-weighted decibels(dB(A))39.235.370
    14.5.     No. of Soil Sample Monitored Locations : 7
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Kilogram per hectare260.5238.38
(2.)K(Potassium)Kilogram per hectare123.1111.1
(3.)pH7.96.8
(4.)P(Phosphorus)Kilogram per hectare24.0418.18
(5.)Electric ConductivityOthersµS/cm531.1368.6
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 54.7 To 55.04
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 55.50 To 56.75
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Surface50.060Copy of Permission LetterPipelineOthersPump with PipelineNil03 Mar 20215
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic1.62STPOthersSTP1.60
(2.)Washing0.35.0Leachate Treatment plantReuse within the Plant & Recycling0.3
(3.)Process1.55Leachate Treatment plantReuse within the Plant & Recycling1.5
16.1.
(a)Total Waste Water Generation 3.4
(b)Total Discharged Water 0
(c)Total Reused Water 3.4
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Municipal Solid WasteMunicipal Solid Waste8066.5Tons0RoadOthersComposting and SLF
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM2.5Microgram per Meter Cube00000
(2.)NOxMicrogram per Meter Cube00000
(3.)SO2Microgram per Meter Cube00000
(4.)PM10Microgram per Meter Cube00000
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)0000PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 250
(b)Source State Electricity Board
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 250KvA
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 1.07
(d)Revenue Land 0
(e)Other Land 0
    Total Land 1.07
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : Government Ownership Land 1.07
    Total 1.07
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Built Up Area0.1989
(2.)Green belt0.36
(3.)LandFill0.312
(4.)OthersRoad Area & Platform Area0.1996
Total 1.0705
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)WLSNot Applicable0Nil
(2.)ESZsNot Applicable0Nil
(3.)Critically Polluted AreaNot Applicable0Nil
(4.)CorridorsNot Applicable0Nil
(5.)Wildlife CorridorsNot Applicable0Nil
(6.)ESAsNot Applicable0Nil
(7.)NPANot Applicable0Nil
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNot Applicable0Nil
(2.)Archaeological SitesNot Applicable0Nil
(3.)ForestSigad Reserved Fores9.50Sigad RF is 9.50Km from Project site
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 1.07
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Not Apllicable
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Perennial Nadi
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 0.060
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 25
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 25
(d)Temporary Employment- During Operation 15
(e)No. of working days 365
(f)Total Manpower 125
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.3659
(b)Percentage of Total Project Area 34.20
(c)No. of Plants to be Planted 700
(d)Funds Allocated for Plantation 300000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)SocialBetter living Conditions, Improved Health Conditions, Enhancement of Aesthetic Value of Area, Direct & Indirect Employment Opportunities
(2.)EnvironmentalPrevention of Air, Water & Soil Contamination, Development of Green Belt
(3.)FinancialImproved Economic Status, Revenue from Waste
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 0
(b)Total No. of Flats to be Build 0
(c)No. of Buildings 0
(d)Total plot area (sqm) 0
(e)Total built up area (sqm) 0
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 1
    Capacity 136
(b)No. of Recharge Pits 5
    Capacity 27
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 8
5.
Energy Saving Measures:
(a)Source/Mode Recover of energy through biological & thermal pro
(b)Percentage 0
(c)Quantity 0
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area Separate drainage systems are proposed for storm w
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1821/SA 103
(ii)Name of the EIA Consultant WOLKEM INDIA LIMITED (CONSULTANCY DIVISION)
(iii)Address Wolkem India Limited, E-101-102, Mewar Industrial Area, Madri, Udaipur, Rajasthan, INDIA Pin Code: 313003
(iv)Mobile No. 9772833835
(v)Landline No. 0294249460
(vi)Email Id om.shukla@wolkem.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 07 May 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantRam Jaiswal
DesignationExecutive Engineer
Name of Company (Applicant Name should not be given here)NAGAR PALIKA PARISHAD, SRINAGAR
AddressNagar Palika Parishad Srinagar, Near Bus Stand, Uttarakhand