Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Windlass Developer Private Limited has proposed to develop “Township project” at Village – Harrawala, Kuanwala & Balawala, District - Dehradun, Uttarakhand
(b)Name of the Company / Organisation WINDLASS DEVELOPERS PRIVATE LIMITED
(c)Registered Address
(d)Legal Status of the Company
2.
Address for the correspondence:
(a)Name of the Applicant Pranav Rastogi
(b)Designation (Owner/ Partner/ CEO) MD
(c)Address Harrawala, Kuawala, & Balawala,Dehradun,Uttarakhand-248001
(d)Pin code 248001
(e)E-mail puneet@northernridge.earth
(f)Telephone No. 135-2717711
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity8(b) Townships and Area Development projects.
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/UK/MIS/39302/2012
(e)Master Proposal Number(Single Window) SW/174646/2020
(f)EAC concerned (for category A Projects only) INFRA-2
(g)Project Type Expansion
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Village – Harrawala, Kuanwala & Balawala, District
(b)Pincode 248161
(c)Bounded Latitudes (North)
From
Degree 3015024
Minutes
Second
From
Degree 30152524
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 7855012
Minutes
Second
From
Degree 7855688
Minutes
Second
(e)Survey of India Topo Sheet No. 7855688
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 636
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 384.6
(j)Seismic Zone 4
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttarakhand
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)UttarakhandDehradunDehradunt” at Village – Harrawala, Kuanwala & Balawala,
6.
Details of Terms of Reference (ToR)/EC:
(a)MoEF&CC / SEIAA File Number 2047(15)/2013
(b)Date of Apply of EC 24 Aug 2012
(c)Date of Issue of EC 31 Dec 1899
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(b)Reason The project is a case of Township project
(c)Supporting Document Copy of Supporting Document
8.
Details of Project Configuration/Product:
Details Not Applicable
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
(a)Details of certified report on compliance of earlier environmental clearance condition
(i)Certified Compliance By Regional
(ii)Details of Regional Office of MoEFCC / Zonal Office of CPCB / SPCB / UTPCC from which certified report on Dehradun
(iii)Letter No. NC-RO/ENV/CON/UK/10/2015/332
(iv)Status of Compliance Compiled
(v)Certified report on compliance of earlier environmental clearance conditions (Including Monitoring Report) Copy of Certified Compliance Report
(vi)Date of site visit N/A
(b)Details of Capacity Expansion
S. No.Product/Activity (Capacity/Area)Quantity FromQuantity ToTotal QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Area193373.30531422.0724795.3OtherssqmRoad
(c)Details of Configuration
S. No.Plant / Equipment / Facility Existing ConfigurationProposed ConfigurationFinal configuration after expansionRemarks
(1.)Housing projectAffordable housing projectTownship ProjectTownship projectTownnship
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 06 Mar 2019
(iv)Valid Upto 31 Mar 2020
(v)File No. 2033
(vi)Application No. 2024/2019/2033
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 67
(b) Funds Allocated for Environment Management (Capital) (in crores) 18.85
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 16.20
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.98
(e) Funds Allocated for Environment Management Capital(%) 28.13
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 40
(b)Existing quantity of raw material/fuel 20
(c)Total quantity of raw material/fuel 60
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Bricks2000000OthersnumbersroadRoad50 Open MarketCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 15 Dec 2019 To 15 Mar 2020
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube85.6471.4585.33100
(2.)PM2.5Micro Gram per Meter Cube41.1837.5640.3260
(3.)SO2Micro Gram per Meter Cube15.5914.7114.4280
(4.)NOxMicro Gram per Meter Cube0.750.710.7180
    14.2.     No. of Ground Water Monitoring Locations : 6
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.817.258.50
(2.)Fluoridemg/l0.150.1211.5
(3.)TSSmg/l50415002000
(4.)Chloridesmg/l50.6946.642501000
(5.)TDSmg/l2662305000
(6.)Total Hardnessmg/l11680200600
(7.)Heavy MetalsAsmg/l0.010.010.010.05
    14.3.     No. of Surface Water Monitoring Locations : 02
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l52.8044.80A
(2.)BODmg/l5.904.40A
(3.)pHmg/l7.447.33A
(4.)DOmg/l7.87.3A
    14.4.     No. of Ambient Noise Monitoring Locations : 06
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))41.439.645
(2.)Leq(Day)A-weighted decibels(dB(A))59.950.755
    14.5.     No. of Soil Sample Monitored Locations : 05
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.517.26
(2.)N(Nitrogen)Milligram per Kilogram7550
(3.)P(Phosphorus)Milligram per Kilogram55.8146.41
(4.)Electric ConductivityOthersµmhos/cm328.2284.9
(5.)K(Potassium)Milligram per Kilogram314.57179.05
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.89 To 4.64
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 3.00 To 3.50
(c)Whether Ground Water Intersection will be there ? NA
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater19282 Not Appliacble PipelineTube Welljjj27 Feb 20191928
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)municipal water/ borewall source19022500Sewage treatment plantReuse within the Plant & Recycling1902
16.1.
(a)Total Waste Water Generation 1902
(b)Total Discharged Water 0
(c)Total Reused Water 1902
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Solid wasteMunicipal Solid Waste14Tons0RoadOthersIn-house organic waste convertor
(2.)E-wasteE Waste6.5Tons0RoadAuthorized Recyclers
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube11.041.204.3115.31100
(2.)PM2.5Microgram per Meter Cube0.201.200.120.3260
(3.)SO2Microgram per Meter Cube3.195600.383.5780
(4.)NOxMicrogram per Meter Cube23.225600.3323.2380
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)DGoil305PM1015.35
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 200000
(b)Source Uttarakhand power corporation limited.
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 18000
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0.0
(b)Private Land 0.0
(c)Government Land 0.0
(d)Revenue Land 0.0
(e)Other Land 13.26
    Total Land 13.26
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0.0
(b)Waste/Barren Land 0.0
(c)Grazing/ Community Land 0.0
(d)Surface Water Bodies 0.0
(e)Settlements 0.0
(f)Industrial 0.0
(g)Forest 0.0
(h)Mangroves 0.0
(i)Marine Area 0.0
(j)Others : non- agricutural land 13.26
    Total 13.26
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Township13.23na
Total 13.23
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)NPANA0.0NA
(2.)ESAsNA0.0NA
(3.)ESZsNA0.0NA
(4.)CorridorsNA0.0NA
(5.)Wildlife CorridorsNA0.0NA
(6.)Critically Polluted AreaNA0.00.
(7.)WLSNA0.0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Defence InstallationsNA0.0NA
(2.)Archaeological SitesNA0.0NA
(3.)ForestKansaro Range – 20 Km (Rajaji National Park)20NOC given by forest department
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0.0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 13.26
(b)Land yet to be acquired(Ha) 0.0
(c)Status of Land acquisition if not acquired 0.0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0.0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0.0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0.0
(f)Status of R&R Yet To Start
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0.0
(b)Permanent Employment-During Operation 0.0
(c)Temporary Employment- During Construction 200
(d)Temporary Employment- During Operation 313
(e)No. of working days 365
(f)Total Manpower 513
32.
Green Belt in Ha:
(a)Uploaded Green Belt plan Copy of Green Belt Plan
S. No.Description ExistingProposedTotal
(1.)Percentage of Total Project Area24472.3943438.5367910
(2.)Percentage of Total Project Area18.5132.8050
(3.)No. of Plants225545770
(4.)Funds Allocated206080
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalGreen belt devlopment
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For INFRA-2
S. No.Item Details
1.
Details of Building Construction:
(a)Maximum Height of the Building (Meters) 30
(b)Total No. of Flats to be Build 3168
(c)No. of Buildings 05
(d)Total plot area (sqm) 132360
(e)Total built up area (sqm) 531422
2.
Foreshore Facilities and/or Marine Disposal:
(a)Whether Project Involves Foreshore Activities and/or marine Disposal? No
3.
Rain Water Harvesting:
(a)No. of Storage 88
    Capacity 140.62
(b)No. of Recharge Pits 88
    Capacity 140.62
4.
Parking:
(a)Details of 4 Wheeler/ 2 Wheeler Parking 4968
5.
Energy Saving Measures:
(a)Source/Mode solar energy
(b)Percentage 70
(c)Quantity 70
6.
Other details:
(a)Details of impact on Water Bodies and Drainage patters of catchment area none
(b)Details of Traffic Density Impact Assessment and Modelling Study Copy of Details of Traffic Density Impact Assessment and Modelling Study
(c)In case Underground Tunnel Project below the Forest Land - Subsidence Impact Study report Copy of Underground Tunnel Project below the Forest Land - Subsidence Impact Study report
     7.       Type of Industries to be established with Industrial Estate as per their category A/B
S. No.Type of IndustryNo. of UnitsCategory A/B
NIL
8.
Length of the alignment N/A
9.
Details Bridges/ROB/Interchanges,Flyovers,Vehicle Underpass and Pedestrian Underpass
Details Not Applicable
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 116
(ii)Name of the EIA Consultant PARAMARSH
(iii)Address M.S.-1/10, Sector A, Sitapur Road Yojna(Near St. Anthony School, Ram Ram Bank Chauraha)Aliganj, Lucknow-226024, UP
(iv)Mobile No. 9044905077
(v)Landline No. 4307467
(vi)Email Id paramarsh.env@gmail.com
(vii)Category of Accreditation A
(viii)Sector of Accreditation INFRA-2
(ix)Validity of Accreditation 01 May 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
(1.)26/11/20201.Submit final EIA report completely. 2.check other relevent documents also.
(2.)26/11/2020The correction have been made as per the instruction received
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantPranav Rastogi
DesignationMD
Name of Company (Applicant Name should not be given here)WINDLASS DEVELOPERS PRIVATE LIMITED
AddressHarrawala, Kuawala, & Balawala
Print