Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) M/s Kanodia Cem Private Limited
(b)Name of the Company / Organisation MS KANODIA CEMENT LIMITED
(c)Registered Address 1164 k, 1165 k, 1168, 1170, 1140 kha, 1162 ga, 1167 mi village nagardeeh,,Amethi,Uttar Pradesh-227406
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Gautam Kanodia
(b)Designation (Owner/ Partner/ CEO) Director
(c)Address 1164 k, 1165 k, 1168, 1170, 1140 kha, 1162 ga, 1167 mi village nagardeeh,Gautam Buddha Nagar,Uttar Pradesh-201301
(d)Pin code 201301
(e)E-mail gautamkanodia1907@gmail.com
(f)Telephone No. 5368-4002545
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity3(b) Cement plants
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/UP/IND/56593/2019
(e)Master Proposal Number(Single Window) SW/173017/2020
(f)EAC concerned (for category A Projects only) Industrial Projects - 1
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Khasra No. 1164 k, 1165 k, 1168, 1170, 1140 Kha, 1
(b)Pincode 227405
(c)Bounded Latitudes (North)
From
Degree 26.119521
Minutes
Second
From
Degree 26.120809
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 81.964412
Minutes
Second
From
Degree 81.965354
Minutes
Second
(e)Survey of India Topo Sheet No. 63F16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 102
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 99
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttar Pradesh
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)Uttar PradeshAmethiNo DataNagardeeh
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 5078
(b)Date of Apply of TOR 20 Oct 2019
(c)Date of Issue of TOR / Standard ToR 16 Jan 2020
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :11 Jan 2020
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :11 Feb 2020
Distance of Public Hearing Venue from the Proposed Project :4.5
Phanchayat Ghar Khathar
State :Jammu and Kashmir
District :Jammu
Tehsil :Akhnoor
Village :Khathar
200Stressed on the need of planting Minimum 2000 trees per year Demanded repair of 3 to 4 link roads in addition to the approach road to site Wanted assurance that preference shall be given to thDistrict Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Cement Plant2.0 MTPA Cement Plant
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)8.06 hactare2000Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 183.69
(b) Funds Allocated for Environment Management (Capital) (in crores) 12
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 3.5
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 8
(e) Funds Allocated for Environment Management Capital(%) 6.53
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 2000
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 2000
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)fly ash500Tons per AnnumJP Bara, NTPC Meja, Unchahar, RenukutRoad,Rail50 MoUCopy of Linkage
(2.)Gypsum500Tons per AnnumBikanerRoad,Rail500 MoUCopy of Linkage
(3.)Clinker1000Tons per Annummadhya Pradesh, Chattishgarh and RajasthanRoad,Rail50 MoUCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Dec 2019 To 29 Feb 2020
(b)Season Winter
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube19811498100
(2.)SO2Micro Gram per Meter Cube13.66.8380
(3.)NOxMicro Gram per Meter Cube35.022.8180
(4.)PM2.5Micro Gram per Meter Cube98441360
    14.2.     No. of Ground Water Monitoring Locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)TDSmg/l5041825002000
(2.)Fluoridemg/l1.20.911.5
(3.)Heavy MetalsCamg/l58.033.675200
(4.)pHNA7.717.056.58.5
(5.)Total Hardnessmg/l408256200600
(6.)TSSmg/l00000000
(7.)Chloridesmg/l53.919.92501000
    14.3.     No. of Surface Water Monitoring Locations : 1
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l200C
(2.)pHNA7.7700C
(3.)DOmg/l5.10B
(4.)BODmg/l3.20C
    14.4.     No. of Ambient Noise Monitoring Locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))46.642.870
(2.)Leq(Day)A-weighted decibels(dB(A))61.156.075
    14.5.     No. of Soil Sample Monitored Locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)K(Potassium)Othersmg/gm4523
(2.)P(Phosphorus)Othersmg/gm28.618.6
(3.)pHOthersmg/gm10.18.17
(4.)N(Nitrogen)Othersmg/gm280232
(5.)Electric ConductivityMillisiemens per Centimetre395365
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 2.97 To 14.58
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 0.98 To 12.12
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater5.50Copy of Permission LetterPipelineTube Well008 Sep 20205.5
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic3.34STPReuse within the Plant & Recycling,Green Belt Renewal Plant3.3
16.1.
(a)Total Waste Water Generation 3.3
(b)Total Discharged Water 0
(c)Total Reused Water 3.3
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)MSWMunicipal Solid Waste2Tons0RoadOthersNA
(2.)HWHazardous Waste (as per Hazardous and Other Waste Management rules 2016)1Tons0RoadTreatment, Storage and Disposal Facility(TSDF)
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube160.323.4178.410
(2.)PM2.5Microgram per Meter Cube114.651.1838.670
(3.)SO2Microgram per Meter Cube18.551.1813.580
(4.)NOxMicrogram per Meter Cube59.450.6212.750
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)BoilerDiesel304PM10,SO2,NOx0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 42.5
(b)Source Power corporation
(c)Uploaded Copy of Agreement Not Applicable
(d)Standby Arrangement (Details of DG Sets) one DG Set
(e)Stack Height (in m) 30
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 8.09
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 0
    Total Land 8.09
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : 0 0
    Total 0
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)OthersCement Plant8.09
Total 8.09
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)CorridorsNo0NA
(2.)Critically Polluted AreaNo00
(3.)WLSNo0NA
(4.)ESAsNo0NA
(5.)ESZsNo0NA
(6.)Wildlife CorridorsNo0NA
(7.)NPANo0NA
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestNone in 10 Km0NA
(2.)Archaeological SitesNone in 10 Km0NA
(3.)Defence InstallationsNone in 10 Km0NA
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 0
(b)Land yet to be acquired(Ha) 8.09
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? No
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? No
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 25
(b)Permanent Employment-During Operation 65
(c)Temporary Employment- During Construction 45
(d)Temporary Employment- During Operation 25
(e)No. of working days 365
(f)Total Manpower 160
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 2.67
(b)Percentage of Total Project Area 33.00
(c)No. of Plants to be Planted 1500
(d)Funds Allocated for Plantation 500000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)FinancialRevenue Generation to Govt
(2.)EnvironmentalEnvironment friendly technology to be adopted
(3.)SocialEmployment Generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details : NOT APPLICABLE
   35.   Sector Specific Details For Industrial Projects - 1
S. No.Item Details
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. 116
(ii)Name of the EIA Consultant PARAMARSH Servicing Environment and Development
(iii)Address M.S.-1/10, Sector A, Sitapur Road Yojna(Near St. Anthony School, Ram Ram Bank Chauraha) Aliganj, Lucknow-226024, UP
(iv)Mobile No. 9044905077
(v)Landline No. 4307467
(vi)Email Id paramarsh.env@gmail.com
(vii)Category of Accreditation B
(viii)Sector of Accreditation Industrial Projects - 1
(ix)Validity of Accreditation 01 May 2021
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(i)Uploaded Additional File NA
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGautam Kanodia
DesignationDirector
Name of Company (Applicant Name should not be given here)MS KANODIA CEMENT LIMITED
Address1164 k, 1165 k, 1168, 1170, 1140 kha, 1162 ga, 1167 mi village nagardeeh