Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
Details of Project:
(a)Name of the project(s) Soapstone Mining Project at Village Bheruchaubatta, Tehsil & District- Bageswar, Uttarakhand by Sh. Gopal Ram S/o Sh. Laccham Ram
(b)Name of the Company / Organisation BHERUCHAUBATTA SOAPSTONE MINES
(c)Registered Address village- Bheruchaubatta, district- bageshwar,Bageshwar,Uttarakhand-263642
(d)Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant Gopal Ram
(b)Designation (Owner/ Partner/ CEO) Mr
(c)Address village- Bheruchaubatta, district- bageshwar,Bageshwar,Uttarakhand-263642
(d)Pin code 263642
(e)E-mail ramgopalbheruchaubatta24.d@gmail.com
(f)Telephone No. 9412-152105
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity1(a) Mining of minerals
(b)Minor Project/ActivityNIL
(c)Category B1
(d)Proposal Number SIA/UK/MIN/53214/2019
(e)Master Proposal Number(Single Window) SW/153574/2020
(f)EAC concerned (for category A Projects only) Non-Coal Mining
(g)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. enclosed with mining plan
(b)Pincode 263642
(c)Bounded Latitudes (North)
From
Degree 295148.45
Minutes
Second
From
Degree 295148.45
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 795053.73
Minutes
Second
From
Degree 795053.73
Minutes
Second
(e)Survey of India Topo Sheet No. H44N13F, H44N9F
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 1334.9
(h)Uploaded (kml) File Copy of Kml File     
(i)Distance of Nearest HFL from the project boundary within the study area 0
(j)Seismic Zone 5
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Uttarakhand
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)UttarakhandBageshwarBageshwarBheruchaubatta
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 75/SEAC
(b)Date of Apply of TOR 05 Jan 2019
(c)Date of Issue of TOR / Standard ToR 01 Jun 2019
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :16 Dec 2019
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :23 Jan 2020
Distance of Public Hearing Venue from the Proposed Project :0
Village Bheruchaubatta
State :Uttarakhand
District :Bageshwar
Tehsil :Bageshwar
Village :Bheruchaubatta
110Regarding basic facilities of nearby employersOthersADM
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Soapstone Mining30000TPA
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Soapstone30000Tons per AnnumRoad
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue 14 Jun 2019
(iv)Valid Upto 21 Nov 2019
(v)File No. 00
(vi)Application No. 00
(vii)Copy of Consent to operate valid as on date Copy of Consent to Operate
10.
Project Cost:
(a)Total Cost of the Project at current price level (in crores) 0.35
(b) Funds Allocated for Environment Management (Capital) (in crores) 0.047
(c) Funds Allocated Towards ESC (Entrepreneur Social Responsibility) (in crores) 0.007
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in crores) 0.005
(e) Funds Allocated for Environment Management Capital(%) 13.43
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)Soapstone0Tons per AnnumNARoad0 LinkageCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2019 To 31 Dec 2019
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) Monitoring Locations : 5
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube83.105879.72100
(2.)SO2Micro Gram per Meter Cube11.07.010.6480
(3.)PM2.5Micro Gram per Meter Cube49.302847.7860
(4.)NOxMicro Gram per Meter Cube23.015.018.3380
    14.2.     No. of Ground Water Monitoring Locations : 4
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)pHNA7.67.16.58.5
(2.)TSSmg/l0000
(3.)TDSmg/l2902605002000
(4.)Total Hardnessmg/l189150300600
(5.)Chloridesmg/l32222501000
(6.)Heavy MetalsFemg/l0.300.130.31
(7.)Fluoridemg/l0.50.211.5
    14.3.     No. of Surface Water Monitoring Locations : 2
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)pHNA7.837.34B
(2.)DOmg/l6.05.0B
(3.)BODmg/l3.53.0B
(4.)CODmg/l66B
    14.4.     No. of Ambient Noise Monitoring Locations : 5
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))48.43370
(2.)Leq(Day)A-weighted decibels(dB(A))544775
    14.5.     No. of Soil Sample Monitored Locations : 5
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)N(Nitrogen)Percent0.0520.03
(2.)Electric ConductivityMillisiemens per Centimetre230160
(3.)pH7.87.1
(4.)P(Phosphorus)Milligram per Kilogram1610
(5.)K(Potassium)Milliequivalents per 100 Gram0.200.14
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.72 To 51.5
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 1.0 To 51.42
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required QuantityDistance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)Othersnatural source6.01.0Copy of Permission LetterPipelineOthersTankna04 Jul 20196.0
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Domestic0.80.8soak pitsReuse within the Plant & Recycling0.8
16.1.
(a)Total Waste Water Generation 0.8
(b)Total Discharged Water 0
(c)Total Reused Water 0.8
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Total Mineral RejectOthersmine waste6791.01Tons0RoadOthersbackfilling
(2.)top soilOthersmine waste4074.6Tons0RoadOthersbackfilling
(3.)InterburdenOthersmine waste2716.4Tons0RoadOthersbackfilling
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)SO2Microgram per Meter Cube10.640010.6480
(2.)NOxMicrogram per Meter Cube22.540022.5480
(3.)PM10Microgram per Meter Cube84.2700.55084.82100
(4.)PM2.5Microgram per Meter Cube49.300049.3060
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)nana00PM100
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 0
(b)Source na
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) na
(e)Stack Height (in m) 0
20.
Land Ownership Pattern:
(a)Forest Land 0
(b)Private Land 0
(c)Government Land 0
(d)Revenue Land 0
(e)Other Land 4.156
    Total Land 4.156
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area 0
(b)Waste/Barren Land 0
(c)Grazing/ Community Land 0
(d)Surface Water Bodies 0
(e)Settlements 0
(f)Industrial 0
(g)Forest 0
(h)Mangroves 0
(i)Marine Area 0
(j)Others : crop land 4.156
    Total 4.156
    22.     Land Requirement for Various Activities
S. No.Description of Activity / Facility / Plant / Others OthersLand RequirementRemarks
(1.)Green belt0.357
(2.)Township0.009Office Infrastructure
(3.)Quarry Area2.666
(4.)OB Dump Area0.188Waste Dump
(5.)Main Plant0.011Mineral stack/sub-grade mineral stack
(6.)Ash Pond0
(7.)Tailing Pond0
(8.)LandFill0
(9.)Water Reservoir0
(10.)Desalination Plant0
(11.)Area for Solid Waste Management0
(12.)Built Up Area0
(13.)Safety Zone0.327road
(14.)Othersundisturbed land0.598
Total 4.156
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Species; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted Areana0not found withiin 10km area
(2.)ESAsNA0not found withiin 10km area
(3.)ESZsNA0not found withiin 10km area
(4.)CorridorsNA0not found withiin 10km area
(5.)NPANA0not found withiin 10km area
(6.)Wildlife CorridorsNA0not found withiin 10km area
(7.)WLSJim Corbett National Park84not found withiin 10km area
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)Othersnana00
(2.)Defence Installationsna0not found withiin 10km area
(3.)ForestGirar Reserved forest1.30Reserved forest
(4.)Archaeological Sitesna0not found withiin 10km area
23.3.
(a)Whether Noc / Permission from the competent authority is required? Yes
(i)Uploaded Noc / Permission from the competent authority Copy of Noc / Permission from the competent authority
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Copy of Details of Tree Cutting and Planting of Trees
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 4.156
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired 0
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages 0
(b)No. of Households 0
(c)No. of PDFs (Project Displaced Families) 0
(d)No. of PAFs (Project Affected Families) 0
(e)Funds Allocated for R&R(in Rs) 0
(f)Status of R&R Completed
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? Yes
(i)Details of Schedule-I Species Leopard and Asiatic Black Bear
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Saryu River
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Sarju River
(ii)Direction of Water Bodies in Buffer Area North
(iii)Distance of Water Bodies in Buffer Area 9.5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 33
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 250
(f)Total Manpower 33
32.
Green Belt in Ha:
(a)Total Area of Green Belt (in hectare) 0.357
(b)Percentage of Total Project Area 8.59
(c)No. of Plants to be Planted 375
(d)Funds Allocated for Plantation 200000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalLandscaping
(2.)FinancialRevenue generation
(3.)SocialEmployment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)SoapstoneMinor
(2.)SoapstoneMinor
2.
Mine Capacity in ROM (Run of Mine) 142000
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. 1939/Mukhya Kkhanij/MA-paln-111/BHU.KHANI.E/2017-1
(b)Date of Approval 17 Feb 2018
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 4.156
(f)Approved Capacity 30000
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 0.6462037
(b)Mineable Reserves (Million Ton) 0.3877222
(c)Extractable Reserves(Million Ton) 0.372809
(d)Percent(%) of Extraction 96
(e)Grade of Coal /Ore /Mineral 90
(f)Stripping Ratio 1 : 0.64
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) 45
(i)Mining Method Opencast
(j)Life of Mine (Years) 25
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 4.156
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 22 Dec 2016
(iii)Validity of LOI 5
(iv)Reference No. of LOI 1957/VII-1/26-SOAPSTONE/2016
(c)Whether Lease Deed Executed ? No
(i)Reason thereof pending
(d)Whether Lease Deed Renewed ? No
(i)Reason thereof pending
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 1
(ii)Total Area (in Hectare) 0.188
(iii)Height (in meter) 3
(iv)Quantity (in Million Cubic meter) 54614
(v)No. of year back fill up 5
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 1
(ii)Total Area (in Hectare) 0.188
(iii)Height (in meter) 3
(iv)Quantity (in Million Cubic meter) 29478
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 54614
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 54614
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 0
(b)Depth (in meter) 0
(c)Volume (in Million Cubic meter) 0
12.
Details of Quarry:
(a)Final Void of 0 (hectare) at a Depth of 0 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 0
13.
Details of Transportation:
(a)In Pit/Underground to Surface 0
(b)Surface to Siding/Loading 0
(c)Transportation / Conveyor Details 0
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)GRAZING LAND000
(2.)OTHERS(Specify)crop land4.15604.156
(3.)WASTE LAND000
(4.)SETTLEMENTS000
(5.)AGRICULTURE LAND000
(6.)FOREST LAND000
(7.)SURFACE WATER BODIES000
TOTAL4.15604.156
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY0000
(2.)TOP SOIL STORAGE0000
(3.)EXTERNAL OB DUMPS0000
(4.)INTERNAL OB DUMPS0000
(5.)BUILT UP AREA (COLONY/OFFICE)0000
(6.)GREEN BELT0.357000.357
(7.)VIRGIN AREA000.0530.053
(8.)ROADS0000
(9.)Otherundisturbed land0000
TOTAL0.35700.05300.41
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 0
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 2.666
(d)Safety Zone(in hectare) 0
(e)Final Void of 0 (hectare) at a Depth of 0 meter
    which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 375
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 0.357
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)5300003000030000300000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? No
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1720/SA095
(ii)Name of the EIA Consultant M/s ECO LABORATORIES AND CONSULTANTS PVT. LTD. MO
(iii)Address Eco Bhawan, E-207, Phase VIII B, Sector 74, Industrial Area, Mohali- 160071
(iv)Mobile No. 9814003103
(v)Landline No. 0172461622
(vi)Email Id ems@ecoparyavaran.org
(vii)Category of Accreditation B
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 13 Dec 2020
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a.I)Upload Copy of EIA/EMP(Text) Copy of EIA/EMP(Text)
(a.II)Upload Copy of EIA/EMP(Annexures) Report Copy of EIA/EMP(Annexures)
(a.III)Upload Copy of EIA/EMP(Maps/Plans/Figures only) Copy of EIA/EMP(Maps/Plans/Figures only)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Copy of District Survey Report NA
(h)Uploaded Copy of Replenishment Study Report & Baseline Survey Data NA
(i)Uploaded Additional File Copy of Additional File
(j)Uploaded Proposal Presentation (To be given in EAC/SEIAA/SEAC meeting) NA
(k)Uploaded Updated Form1 NA
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Addtional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantGopal Ram
DesignationMr
Name of Company (Applicant Name should not be given here)BHERUCHAUBATTA SOAPSTONE MINES
Addressvillage- Bheruchaubatta, district- bageshwar
Print