Form-1
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
1. Basic Informations
Project Name Expansion of API (Bulk drug and intermediates manufacturing) unit by M/s. Sri Krishna Pharmaceuticals Limited - Unit IV Company/Organisation Name SRI KRISHNA PHARMACEUTICALS LIMITED,
Registered Address Sri Krishna Pharmaceuticals Limited, C-4 IDA, Uppal, Hyderabad Telangana 500039 Legal Status of the Company Private
2.
Address for the correspondence:
(a)Name of the Applicant G Chandra Sekhar
(b)Designation (Owner/ Partner/ CEO) DGM-Corporate EHS
(c)Address M/S SRI KRISHNA PHARMACEUTICALS LIMITED, Unit-IV Sy. No. 296/7/10, INDUSTRIAL DEVELOPMENT AREA, BOLLARAM, JINNARAM (M), MEDAK DISTRICT, TELANGANA STATE,,Jinnaram,Medak,Telangana-502325
(d)Pin code 502325
(e)E-mail gcssrikrishna@gmail.com
(f)Telephone No. 40-23748555
(g)Fax No.
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . NIL
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a)Major Project/Activity5(f)-API
(b)Minor Project/ActivityNIL
(c)Category B2
(d)Proposal Number SIA/TG/IND2/152928/2020
(e)Master Proposal Number(Single Window) SW/152927/2020
(f)EAC concerned (for category A Projects only) Industrial Projects - 2
(g)Project Type(New/Expansion/Modernization) Expansion
4.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Telangana
Details of State(s) of the project
S. No. State Name District Name Tehsil Name Village Name
(1.)TelanganaSangareddyJinnaramIDA Bollaram
5.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?Yes
(c)Reason -1
(d)Supporting Document NILL
Project Profile
Location of the project Sy. No. 296/7/10, Industrial Development Area, Bollaram, Jinnaram Mandal, Sangareddy District, Telangana
Town / Village
(Name of more than one town may be entered by separating with)
IDA Bollaram Plot/Survey/Khasra No.
(Name of more than one town may be entered by separating with)
Sy. No. 296/7/10
State Telangana District Sangareddy
Tehshil Jinnaram Pincode 502325
Nearest railway station Patancheru Distance from the project site 6.77
Nearest airport Rajiv Gandhi International Airport Distance from the project site 35.25
Nearest Town/City/District Headquarters Sangareddy Distance from the project site 27
Village Panchayats, Zila Parishad, Municipal Corporation, Local body(Complete postal addresses with telephone nos. to be given) Bollaram Village Upload GPS file Copy of Kml File     
Uploaded GPS file
Shape of the project land Block (Polygon) Site alternative under consideration(If any) Uploaded Site alternative under consideration
Brief summary of project Uploaded Brief summary of project
Does your project location falls under out of any following areas Patancheru-Bollaram (A.P.)
Proposed Built up area (Built up area or covered area on all the floors puttogether including its basement and other service areas which are proposed in the building or construction projects)(In Meter /Sqr) 2450 Existing Built Up Area(In Meter /Sqr) 12140.62
Does it attract any of the general conditions given below? Yes
Does it attract the specific condition given below? No
Interlinked Projects No
Whether separate application of interlinked projects has been submitted? Date of Submission
Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? No
Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? No
Whether the proposal involves approval/clearance under the C.R.Z notification,2011? No
Whether there is any Government Order/Policy relevent/relating to the site? No
Forest land involved(hectares) No forest land involved
Is there any litigation pending against the project? No


Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) No The proposal is for expansion Bulk Drugs Unit Chemicals in the existing unit. No additional land. Total Land area after proposed expansion 4.5 Acres.
1.2 Clearance of existing land, vegetation and buildings? No The proposal is for expansion Bulk Drugs Unit Chemicals in the existing unit. No additional land. Total Land area after proposed expansion 4.5 Acres
1.3 Creation of new land uses? No
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Soil Testing completed
1.5 Construction works? Yes Construction activity involves creation of new additional utilities like Boiler, DG set, Chilling Plant etc and ZLD system.
1.6 Demolition works? No
1.7 Temporary sites used for construction works or housing of construction workers? No Construction labor from local villages shall be employed.
1.8 Above ground buildings, structures or earthworks including linear structures,cut and fill or excavations and fill or excavations Yes Storage facilities shall be constructed. No major cut and fill or excavation is anticipated.
1.9 Underground works including mining or tunneling? No
1.10 Reclamation works? No
1.11 Dredging? No
1.12 Offshore structures? No
1.13 Production and manufacturing processes? Yes Enclosed in Annexure – I
1.14 Facilities for storage of goods or materials? No Raw materials and solvents shall be stored with safety precautions.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes Solid waste shall be disposed to end users/recyclers or sent to incineration. Effluent generated from the plant are treated and reused. Details presented in Annexure II
1.16 Facilities for long term housing of operational workers? No Local people shall be employed.
1.17 New road, rail or sea traffic during construction or operation? No
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No
1.20 New or diverted transmission lines or pipelines? No
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No
1.22 Stream crossings? No
1.23 Abstraction or transfers of water from ground or surface waters? No Total water required shall increase from 104.0 KLD to 734.4 KLD out of which 394.4 KLD shall be met from TSIIC (Industrial supply) and the balance shall be recycled water.
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes The construction material shall be drawn from local sources within 10 – 15 km. There is no transport of personnel, as the construction workers shall be drawn from local villages.
1.26 Long-term dismantling or decommissioning or restoration works? No
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No
1.28 Influx of people to an area in either temporarily or permanently? Yes The proposed project shall increase the employment potential and hence may lead to migration to surrounding villages.
1.29 Introduction of alien species? No
1.30 Loss of native species or genetic diversity? No
1.31 Any other actions? No
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) No Existing Unit
2.2 Water (expected source & competing users) unit: KLD Yes Total water required shall increase from 104.0 KLD to 734.4 KLD out of which 394.4 KLD shall be met from TSIIC (Industrial supply) and the balance shall be recycled water. (Water Balance Enclosed in Annexure III)
2.3 Minerals (MT) No
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Shall be sourced from the local villages.
2.5 Forests and timber (source – MT) No
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes The required energy shall be drawn from TS TRANSCO. The power shall be drawn from DG sets during load shut downs. Existing DG sets of 1 x 625 KVA and proposed 1 x 1500 KVA DG sets shall be provided to cater to energy requirement during load shut downs. The other energy source is coal fired boilers to meet the steam requirement for process and ZLD system. It is proposed to establish with 1 X 5 TPH and 1 x 10 TPH boilers. Existing 1 x 3 TPH coal fired boiler will be replace with proposed 1 x 5 T
2.7 Any other natural resources (use appropriate standard units) No
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies Yes Solvents shall be used as reaction media. MSIHC rules shall be followed during storage, transportation and handling of raw materials and hazardous chemicals.
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Shall increase the employment potential for locals and affect the living conditions for betterment.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No No sensitive receptors are present in the immediate vicinity of the site. The project shall not have any significant impact on vulnerable groups of people.
3.5 Any other causes No
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes No
4.2 Municipal waste (domestic and or commercial wastes) No Wastes from canteen, other commercial wastes like paper, empty containers etc. The canteen wastes and commercial wastes shall be in the range of 5 kg/day
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes The quantity of hazardous waste generated during operation contain salts from evaporators, stripper distillate, process residue, and solvent residues, ETP sludge and filtration media etc. enclosed in Annexure – IV
4.4 Other industrial process wastes Yes Enclosed at Annexure IV
4.5 Surplus product No
4.6 Sewage sludge or other sludge from effluent treatment Yes Sludge from Effluent treatment plant and Salts from MEE & ATFD shall be sent to TSDF.
4.7 Construction or demolition wastes Yes Construction activity involves creation of new additional utilities like boiler, DG set, Chilling Plant etc and enhancement of treatment system.
4.8 Redundant machinery or equipment No
4.9 Contaminated soils or other materials No
4.10 Agricultural wastes No
4.11 Other solid wastes No Enclosed at Annexure IV
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes Coal Shall be used as fuel for boiler. Diesel is for DG set. Quantity of fuel and emissions details are enclosed in Annexure V
5.2 Emissions from production processes Yes Enclosed in Annexure - VI
5.3 Emissions from materials handling including storage or transport No Material transfer takes place in closed pipeline systems.
5.4 Emissions from construction activities including plant and equipment Yes Dust may rise during transport of material and construction activity. The dust emissions shall be mitigated by water spraying on the roads within the premises.
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust may rise during transport of material and construction activity. The dust emissions shall be mitigated by water spraying on the roads within the premises.
5.6 Emissions from incineration of waste No
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) No
5.8 Emissions from any other sources No
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Material transport and construction equipment shall be source of noise, while transfer pumps, vacuum systems, DG sets are the sources of noise during operation.
6.2 From industrial or similar processes Yes DG sets, controlled by providing Acoustic Enclosures.
6.3 From construction or demolition Yes Noise during construction shall be due to construction equipment and emergency DG sets.
6.4 From blasting or piling No
6.5 From construction or operational traffic No The increased traffic shall not have any significant impact.
6.6 From lighting or cooling systems No
6.7 From any other sources No
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No All the hazardous materials will be stored in MS drums, in a covered shed and no contamination of soil is expected
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) No All the wastes from domestic operations are sent to Biological effluent treatment plant followed by RO plant.
7.3 By deposition of pollutants emitted to air into the land or into water No All the emissions from process are controlled by providing control equipment like scrubbers, Dust Collectors and emissions from boilers shall be controlled by providing bag filters.
7.4 From any other sources No
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes All Inbuilt Safety precautions will be adopted and there will not be any damage to environment or human health
8.2 From any other causes No
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes The project shall enhance the socio economic status of the area by increasing the demand for housing, improving the employment. There are no major support industries required for this plant.
9.2 Lead to after-use of the site, which could have an impact on the environment No
9.3 Set a precedent for later developments No
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No The baseline environmental status of the surrounding areas is within the prescribed limits as observed from the Secondary data.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Wailal RF – N – 7 Km Pottaguda RF – NW - 8.6 Km Kazipalli RF – N – 2.7 Km Kodakanchi RF – NW – 8.8 Km Dundigal RF – NE – 8.7 Km Suraram RF – E – 9.5 Km Gajularamaram RF – E – 9.3 Km Borampet RF – E – 9.1 Km
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No
4 Inland, coastal, marine or underground waters No
5 State, National boundaries No
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No
7 Defence installations No
8 Densely populated or built-up area Yes Bollaram – 1.45 Km.
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) No 1.5 Km away from the site
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects No
Document to be attached
1. Upload a copy of PFR Uploaded a copy of PFR.
2. Upload a copy of EMP Uploaded a copy of EMP.
3. Upload Scanned copy of covering letter. Uploaded Scanned copy of covering letter..
4. Upload Additional attached if any(Single PDF) Uploaded Additional attached if any(Single PDF).
5. Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? No
           Essential Details Sought
S. No.EDS Sought DateEDS SoughtLetter
NO Record
           Additional Details Sought
S. No.ADS Sought DateADS SoughtLetter
NO Record
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.
Name of ApplicantG Chandra Sekhar
DesignationDGM-Corporate EHS
Name of Company (Applicant Name should not be given here)SRI KRISHNA PHARMACEUTICALS LIMITED,
AddressSri Krishna Pharmaceuticals Limited, C-4 IDA, Uppal, Hyderabad