APPENDIX I
(See Paragraph-6)
FORM 1
Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form1. Please note that all such Annexures must be part of single pdf document.
(I) Basic Information
S.No.Item Details
Is your project Comes under Notified Industrial Area NA
Whether proposal involved violation of EIA notificationN/A
Weather Consent to Establishment ObtainedN/A
Upload copy of CTE N/A
1.
Name of the Project/s Environmental Clearance for proposed Integrated Municipal Solid Waste Management Plant (including 23 MW power plant) at Adampur Chhavani, Phanda Block, Huzur Tehsil, Bhopal District by M/s Bhopal Municipal Solid Waste Private Limited.
Brief summary of projectAnnexure-Brief summary of project
Proposal Number IA/MP/THE/69646/2017
Project Cost 29303 lacs
2.
S. No. in the schedule1(d) Thermal Power Plants
Project Sector Thermal Projects
3. Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled Integrated 1000 TPD MSW facility with 23 MW power plant ha.
4.
New/Expansion/ModernizationNew
5. Existing Capacity/Area etc. 0 ha.
6. Category of project i.e. 'A' or 'B' A
7.
Does it attract the general condition? If yes, please specify No
8.
Does it attract the specific condition? If yes, please specify No
9.
Location of the projectBhopal
Shape of the project landBlock (Polygon)
Uploaded GPS fileAnnexure-GPS file      
Uploaded copy of survey of India ToposheetAnnexure-Survey of india toposheet
Plot/Survey/Khasra No.Kolua Khurd, Adampur Chhavani
Town / VillageKolua Khurd, Adampur Chhavani
State of the projectMadhya Pradesh
Details of State of the project
S.no State Name District Name Tehsil Name
(1.)Madhya PradeshBhopalHuzur
10.
Nearest railway station along with distance in kms Bhopal Railway Station, 17.4 km
Nearest airport along with distance in kms Bhopal Airport, 27.9 km
11. Nearest Town/City/District Headquarters along with distance in kms Bhopal City , 16.5 km
12. Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) Bhopal District Head Quarters: 21 KM
13. Name of the Applicant Narayana
14. Registered Address 54, Shyamla hills, Near Bharat Bhawan, Bhopal-462001
15.
Address for correspondance:
Name of the Company BHOPAL MSW PROCESSING PLANT PRIVATE LIMITED
Name of the Applicant Narayana
Designation (Owner/ Partner/ CEO) GM
Pin code 201301
E-mail narayanarao.nelaturi@infra.esselgroup.com
Telephone No. 120-4849592
Fax No. 120-
Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
16.
Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet No
17. Whether part of Interlinked projects? No
18. Whether separate application of Interlinked project has been submitted? N/A
19.
If Yes, MoEF file numberN/A
Date of submissionN/A
20. If No, Reason N/A
21.
Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given
(i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980?No
(ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972?No
(iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011?No
22.
Whether there is any Government Order/Policy relevant/relating to the site?No
23.
Whether any Forest Land Involved?No
Area of Forest land Involved (hectares)N/A
24.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
(a) Name of the CourtN/A
(b) Name of the Sub courtN/A
(c) Case No.N/A
(d) Orders/directions of the court, if any and relevance with the proposed projectN/A
(II) Activity
1 Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.)
S.No Information/Checklist confirmation Yes/No Details there of (with approximate quantities/rates, wherever possible) with source of information data
1.1 Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) Yes Changes in land use, land cover or topography is envisaged. Construction of Landfill & Waste to Energy plant will be developed in the project site. The total plot area is 1,82,059 Sq.m
1.2 Clearance of existing land, vegetation and buildings? Yes Clearance of existing vegetation (bushes & grass) is envisaged.
1.3 Creation of new land uses? Yes Changes in land use, land cover or topography is envisaged. Construction of landfill & Waste to Energy plant will be developed in the project site.
1.4 Pre-construction investigations e.g. bore houses, soil testing? Yes Pre-construction investigations Will be carried after obtaining ToR
1.5 Construction works? Yes The proposed project involves capping/ construction of new secured landfill and Waste to Energy plant etc.
1.6 Demolition works? No Not Applicable
1.7 Temporary sites used for construction works or housing of construction workers? No No temporary sites will be provided for housing of the workers as they are hired from the surrounding local areas/villages.
1.8 Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations Yes Building and structures will be developed for erecting Integrated Solid Waste Management based power plant etc.
1.9 Underground works including mining or tunnelling? No No closure or diversion of existing transport routes are proposed
1.10 Reclamation works? No No reclamation works
1.11 Dredging? No No dredging works
1.12 Offshore structures? No No offshore works
1.13 Production and manufacturing processes? Yes The proposed facility is Integrated Solid Waste Management Facility.
1.14 Facilities for storage of goods or materials? Yes The proposed facility is Integrated Solid Waste Management Facility.
1.15 Facilities for treatment or disposal of solid waste or liquid effluents? Yes 1000 TPD of unsegregated MSW generated from Bhopal, Sehore and Raisen District will pre-segregated, then Landfilled and Incinerated. HDPE will be used as Landfill bottom liner. Leachate generated from the Landfill will be treated in separate ‘Leachate Treatment Plant’. shall be disposed either by sprinkling on landfill cell or by treatment as per CPCB guidelines. The ash generated from Waste to Energy plant will be sent to sanitary landfill.
1.16 Facilities for long term housing of operational workers? No No long term housing is proposed.
1.17 New road, rail or sea traffic during construction or operation? No No Traffic, The site is located well outside the city
1.18 New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? No --
1.19 Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? No --
1.20 New or diverted transmission lines or pipelines? No --
1.21 Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? No --
1.22 Stream crossings? No --
1.23 Abstraction or transfers of water from ground or surface waters? Yes Water will be sourced from Bhopal municipal corporation or it will be sourced from Borewells. 4 nos. of borewells are proposed. Total water requirement id 500 KLD
1.24 Changes in water bodies or the land surface affecting drainage or run-off? No Not envisaged
1.25 Transport of personnel or materials for construction, operation or decommissioning? Yes Construction material will be transported via the existing infrastructure. Workers from nearby villages and town will be engaged.
1.26 Long-term dismantling or decommissioning or restoration works? No No long-term dismantling or decommissioning or restoration works.
1.27 Ongoing activity during decommissioning which could have an impact on the environment? No No Impact due to ongoing activity during decommissioning on environment.
1.28 Influx of people to an area in either temporarily or permanently? Yes Influx of people to the area will be seen: 300 nos. of people will be employed in the construction phase. 115 nos. of people will be employed in the operation phase. All local area people will be employed.
1.29 Introduction of alien species? No No
1.30 Loss of native species or genetic diversity? No No
1.31 Any other actions? No Not envisaged
2 Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply):
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
2.1 Land especially undeveloped or agricultural land (ha) Yes The present land is undeveloped. The project will be constructed on 1,82,059 Sqm/Acres of Land.
2.2 Water (expected source & competing users) unit: KLD Yes 50 KLD (Construction phase) 500 KLD (Operation phase) It will be sourced from 4 nos. of borewell or Bhopal municipal corporation.
2.3 Minerals (MT) No No Minerals will be used
2.4 Construction material – stone, aggregates, sand / soil (expected source – MT) Yes Construction material such as sand, steel, aggregates etc will be used. These materials will be sourced from the nearest market.
2.5 Forests and timber (source – MT) No Not Envisaged
2.6 Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) Yes General electricity required will be hired through 1,500 kVA will be hired through MPPTCL (Madhya Pradesh Power Transmission Company Ltd.) 1 no. of DG Set of 1,250 kVA will be used in case of power failure.
2.7 Any other natural resources (use appropriate standard units) No Not Envisaged
3 Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
3.1 Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies No None
3.2 Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) No No changes in occurrence of disease or affect disease vectors anticipated. Uttermost hygiene care will be taken to avoid any vector borne disease. Regular health check up and PPE will be provided to the workers.
3.3 Affect the welfare of people e.g. by changing living conditions? Yes Socio-economic condition will improve and will have positive impact due to increasing livelihood options for nearby peoples.
3.4 Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. No Not envisaged.
3.5 Any other causes No Not envisaged
4 Production of solid wastes during construction or operation or decommissioning (MT/month)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
4.1 Spoil, overburden or mine wastes Yes All the excavated material generated out of construction of landfill will be used for construction of embankment of the cell, levelling and gardening purposes. Other Construction waste will be disposed as per applicable MSW construction & demolition waste mgmt. rules 2016.
4.2 Municipal waste (domestic and or commercial wastes) Yes Proposed project itself is Integrated solid waste management facility.
4.3 Hazardous wastes (as per Hazardous Waste Management Rules) Yes 750 Litres of spent oil will be generated from the DG Set. It will be sold to authorized hazardous waste recycler.
4.4 Other industrial process wastes No Not applicable
4.5 Surplus product No Not applicable
4.6 Sewage sludge or other sludge from effluent treatment Yes 80 KLD of Leachate will be generated in rainy season. It will be treated in Leachate Treatment plant. Sludge will be utilized for gardening.
4.7 Construction or demolition wastes Yes Construction debris will be disposed as per applicable MSW construction & demolition waste mgmt. rules 2016
4.8 Redundant machinery or equipment Yes No Redundant machinery
4.9 Contaminated soils or other materials No No soil contamination is anticipated with proper lining System for sanitary landfill.
4.10 Agricultural wastes No No agricultural wastes
4.11 Other solid wastes No No other solid waste anticipated.
5 Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr)
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
5.1 Emissions from combustion of fossil fuels from stationary or mobile sources Yes PM, SO2 ,NOX and Dioxins from MSW based power plant. DG set will be dispersed into atmosphere through stack meeting MoEFCC/CPCB standards.
5.2 Emissions from production processes Yes The emissions from MSW based power plant will be controlled by providing necessary air pollution control with NOx reduction by SNCR (Selective Non-Catalytic Reduction systems) Injection of hydrated lime on flue gas, The flue gas will also be passed through activated carbon which will adsorb VoC’s, mercury and dioxins. Other heavy metals in flue gas will be separated by passing through bag filter. Stack height will be provided as per CPCB guidelines
5.3 Emissions from materials handling including storage or transport Yes There will be emissions from the MSW Landfill, appropriate arrangement shall be made by spraying inhibitory agents or masking agent or neutralizers in scenario of intermittent odorous emissions, as per Guidelines on Odour Monitoring & Management in Urban Municipal Solid Waste (MSW) Landfill Site (by CPCB 2017).
5.4 Emissions from construction activities including plant and equipment Yes Dust generated during construction activities will be controlled taking necessary control measures (water sprinkling, transport materials covered with tarpaulin, etc.,)
5.5 Dust or odours from handling of materials including construction materials, sewage and waste Yes Dust is likely to be generated during construction phase, Water sprinkling will be done Tarpaulin cover will be provided over stored raw material to reduce dust emission. Greenbelt development will be taken up along boundary and open areas will be provided
5.6 Emissions from incineration of waste Yes Refer S.no: 5.2: The incinerator will be provided with: SNCR, Semi-Dry Reactor, Bag Filter, Induced draught fan with frequency converter.
5.7 Emissions from burning of waste in open air (e.g. slash materials, construction debris) Yes The MSW will be incinerated. The emission from landfill will be controlled as per CPCB guidelines
5.8 Emissions from any other sources No Not Envisaged
6 Generation of Noise and Vibration, and Emissions of Light and Heat:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
6.1 From operation of equipment e.g. engines, ventilation plant, crushers Yes Noise is generated from Turbines and Generators of MSW based power plant. Expected noise level will be in control 85 dB (A), necessary PPEs (ear muffs, closed chamber) will be provided for the personnel’s working in this area. Most of the equipment structures are static, vibration effect of these will be only local, design of support and foundation will nullify the intensity of vibrations. Green belt will be developed around the plant periphery which will act as noise barrier.
6.2 From industrial or similar processes Yes Noise from the proposed facilities will be confined within the project site.
6.3 From construction or demolition Yes Excavation, drilling and welding during construction is temporary in nature
6.4 From blasting or piling No Not applicable
6.5 From construction or operational traffic Yes Noise levels will be there during daytime due to the vehicular movement and construction and operation activities, but it will be of temporary in nature.
6.6 From lighting or cooling systems Yes Noise levels will be less than 75dB (A) to 95dB (A) are anticipated during daytime due to the vehicular movement and construction and operation activities, but it will be of temporary in nature.
6.7 From any other sources No --
7 Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
7.1 From handling, storage, use or spillage of hazardous materials No This is only a MSW incineration & landfill plant.
7.2 From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) Yes Contamination of land or water is not envisaged as waste water/leachate generated in rainy season will be treated in Leachate treatment Plant.
7.3 By deposition of pollutants emitted to air into the land or into water Yes The major emissions from the proposed facility are PM, SO2, NOx and dioxins. Stack height of 60 m meeting CPCB guidelines will be provided for proper dispersion of emissions. Hence a chance of contamination of land and water by deposition of pollution is not envisaged.
7.4 From any other sources No Not envisaged
7.5 Is there a risk of long term build up of pollutants in the environment from these sources? No All the expected emissions from the proposed plant facility based power plant will be maintained within the prescribed limits as per CPCB / MoEFCC and applicable MSW rules 2016.
8 Risk of accidents during construction or operation of the Project, which could affect human health or the environment
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
8.1 From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances Yes Adequate steps for firefighting will be taken to control fires in case of emergency. During construction & Operation phase all the labours will be provided with suitable personal protective equipment (PPE) as required under the health & safety norms. Proper EHS plan will be implemented which will be periodically updated.
8.2 From any other causes Yes Accidents during equipment handling and machinery operations are expected.
8.3 Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? No The project area falls under seismic zone II as per the Seismic Zoning Map of India (IS 1893-2002). There has been no record on occurrence of floods, landslides, cloud bursts etc in the area.
9 Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality
S.No Information/Checklist confirmation Yes/No Details thereof (with approximate quantities/rates, wherever possible) with source of information data
9.1 Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
  • Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
  • housing development
  • extractive industries
  • supply industries
  • Other
Yes Due to this project positive development is envisaged, as the socioeconomic conditions of the local population will improve.
9.2 Lead to after-use of the site, which could have an impact on the environment Yes The landfill will be scientifically capped after the project completion. Once the landfill is fully utilized, post closure care of landfill shall be conducted for at least 10-15 years. Vegetative cover will be provided over completed cells/site. Monitoring of leachate collection system in accordance with requirement. Monitoring of groundwater in accordance with requirements
9.3 Set a precedent for later developments No It is possible that the closed landfill site may be used for playground, flower garden etc.
9.4 Have cumulative effects due to proximity to other existing or planned projects with similar effects No The project will follow the local laws to keep cumulative effect under control.
(III) Environmental Sensitivity
S.No Areas Name/Identity Aerial distance (within 15km.) Proposed project location boundary
1 Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
No Not Applicable
2 Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Yes Hatayekheda Lake (5.9 km aerial distance), Ghodapachad Dam (1.5 km aerial distance), Water body (1.5 km aerial distance), Lower Lake (14.8 km aerial distance).
3 Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No Not Applicable
4 Inland, coastal, marine or underground waters No Not Applicable
5 State, National boundaries No Not Applicable
6 Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas No Not Applicable
7 Defence installations No Not Applicable
8 Densely populated or built-up area Yes Bhopal City at 16 KM
9 Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) Yes All the facilities like hospitals, schools, places of worship, and community facilities are available within 15 km of the proposed site.
10 Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No not applicable
11 Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Not envisaged
12 Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects Yes The project area falls under seismic zone II as per the Seismic Zoning Map of India (IS 1893-2002). There has been no record on occurrence of floods, landslides, cloud bursts etc.
(IV) Proposed Terms of Reference for EIA studies
1 Uploaded Proposed TOR File Annexure-TOR file
2 Uploaded scanned copy of covering letter Annexure-scanned copy of covering letter
3 Uploaded Pre-Feasibility report(PFR) Annexure-PFR
4 Uploaded additional attachments(only single pdf file) Annexure-Additional attachments
Additional Attachments, if any
Attached File
ADS Letter
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterSubmission of PFR, Letter from BMC commissioner and Topographic map as mentioned in the minutes of 11th EAC (Thermal) meeting. 24 Jan 2018
2.NAFor revisiting the PFR. 02 Nov 2017
(V) Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
V.(i)
Name of ApplicantNarayana
DesignationGM
Name of Company (Applicant Name should not be given here)BHOPAL MSW PROCESSING PLANT PRIVATE LIMITED
Address54, Shyamla hills, Near Bharat Bhawan, Bhopal-462001