| APPENDIX I | | (See Paragraph-6) | | FORM 1 | | | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | Yes |
| | Whether proposal involved violation of EIA notification | No | tr > | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| | 1. | |
| Name of the Project/s | Proposed Development of Talegaon Industrial Area – Phase-IV as an Electronics and Engineering City Expansion on about 2404 Ha of land adjacent to existing Talegaon Industrial Area (Ph-I), Pune, Maharashra | Brief summary of project | Annexure-Brief summary of project | | Proposal Number | IA/MH/NCP/258294/2022 | | Project Cost | 12628 cr | |
| | 2. | |
| S. No. in the schedule | 7(c) Industrial estates/ parks/ complexes/ areas, export processing Zones
| Project Sector | INFRA-1 | |
| | 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Electronics and Engineering city ha. | | | 4. | | New/Expansion/Modernization | New | | | | 5. | Existing Capacity/Area etc. | 0 ha. | | | 6. | Category of project i.e. 'A' or 'B' | A | | | 7. | | Does it attract the general condition? If yes, please specify | Yes | | a) | Protected areas notified under the wildlife (Protection) Act, 1972 | | | | 8. | | Does it attract the specific condition? If yes, please specify | No | | | | 9. | |
| Location of the project | Talegaon Industrial Area– Phase-IV, Village Ambale, Nigade, Kalhat&Pawalewadi, Tal. Maval, Dist. Pune | | Shape of the project land | Block (Polygon) | | Uploaded GPS file | Annexure-GPS file  | | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | | Plot/Survey/Khasra No. | 0 | | Town / Village | Village Ambale, Nigade, Kalhat, Pawalewadi | | State of the project | Maharashtra | |
| | Details of State of the project |
|---|
| S.no | State Name | District Name | Tehsil Name |
|---|
| (1.) | Maharashtra | Pune | Mulshi | | | 10. | |
| Nearest railway station along with distance in kms | Talegaon railway Station, 10 km | Nearest airport along with distance in kms | Lohgaon Airport, 50 km | |
| | 11. | Nearest Town/City/District Headquarters along with distance in kms | Talegaon , 10 km | | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village Panchayat Ambale, Nigade, Kalhat & Pawalewadi. Talegaon Industrial Area– Phase-IV, Village Ambale, Nigade, Kalhat&Pawalewadi, Tal. Maval, Dist. Pune | | | 13. | Name of the Applicant | Sanjay | | | 14. | Registered Address | Office of the Executive Engineer, Civil Division, MIDC, Telco road, Chinchwad, Pune | | | 15. | |
| Address for correspondance: | | Name of the Company | MIDC, CIVIL DIVISION, PUNE | | Name of the Applicant | Sanjay | | Designation (Owner/ Partner/ CEO) | Executive Engineer | | Pin code | 411019 | | E-mail | eepunedn1@midcindia.org | | Telephone No. | - | | Fax No. | - | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| | 16. | | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | No | |
| | 17. | Whether part of Interlinked projects? | No | | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | | 19. | | If Yes, MoEF file number | N/A | | Date of submission | N/A | | | | | | 21. | | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | No | | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | | 23. | | Whether any Forest Land Involved? | No | | Area of Forest land Involved (hectares) | N/A | |
| | 24. | | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | | (a) Name of the Court | N/A | | (b) Name of the Sub court | N/A | | (c) Case No. | N/A | | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| | 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | It is Proposed is to Develop Talegaon Industrial Area – Phase-IV as an Electronics and Engineering City on about 2404 Ha of land adjacent to existing Talegaon Industrial Area (Ph-I) by M/s. Maharashtra Industrial Development Corporation (MIDC) at Villages Ambale, Nigade, Kalhat & Pawalewadi, Tal. Maval, Dist. Pune
The salient features is as under
Area Notified (in Ha.) 2404.468
Proposed Amenity Space (in Ha.) @5% (As per DCR of MIDC) 120.22
Proposed Open Space (in Ha.) @5% (As per DCR of MID | | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | The project development will involve clearing of existing land and trees/vegetation for construction of infrastructure facilities with R&R policy of state of Maharashtra | | 1.3 | Creation of new land uses? | Yes | The proposed project is to Develop Talegaon Industrial Area – Phase-IV as an Electronics and Engineering City Expansion. | | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | MIDC will carry out soil investigation and hydro-geological studies | | 1.5 | Construction works? | Yes | It is Proposed is to Develop Talegaon Industrial Area – Phase-IV as an Electronics and Engineering City on about 2404 Ha of land adjacent to existing Talegaon Industrial Area (Ph-I) by MIDC at Villages Ambale, Nigade, Kalhat & Pawalewadi, Tal. Maval, Dist. Pune
The salient features is as under
Area Notified (in Ha.) 2404.468
Proposed Amenity Space @5% (As per DCR of MIDC)-120.22ha
Proposed Open Space @10%- 240.45ha
Proposed area under roads, services, power corridor @25%-601.117ha | | 1.6 | Demolition works? | No | NA. This is new construction | | 1.7 | Temporary sites used for construction works or housing of construction workers? | No | NA No Housing or labour camp envisaged. Laborers will be hired from nearby villages | | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | Development of Electronics and Engineering industries. As per detailed planning, the quantities shall be worked out by MIDC | | 1.9 | Underground works including mining or tunnelling? | No | NA | | 1.10 | Reclamation works? | No | NA | | 1.12 | Offshore structures? | No | NA | | 1.13 | Production and manufacturing processes? | Yes | The project envisages production and manufacturing from the industries to be setup later viz. Electronics and Engineering industries. | | 1.14 | Facilities for storage of goods or materials? | Yes | During construction period various types of construction material will be stored at designated places with proper environmental care such as mitigation of fugitive emissions etc. by arranging water sprinklers etc. and also environmental monitoring during construction phase | | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | During construction work, the solid waste will be generated in the form of excavated soil, which shall be disposed off at authorized designated sites. After establishment of area, the concern effluent treatment plant & facility for disposal of solid waste shall be provided at later stage | | 1.16 | Facilities for long term housing of operational workers? | No | NA | | 1.17 | New road, rail or sea traffic during construction or operation? | No | NA. Only internal roads will be developed as infrastructure facilities | | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | No | NA | | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | NA | | 1.20 | New or diverted transmission lines or pipelines? | No | NA | | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | No | NA | | 1.22 | Stream crossings? | No | NA. Nalla crossing at certain locations. | | 1.23 | Abstraction or transfers of water from ground or surface waters? | No | NA. No ground water extraction is envisaged | | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | No | NA | | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | There will be transport of construction materials and personnel for the development of proposed Talegaon Industrial Area (Ph-IV) during construction phase as well as operation phase. | | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | NA | | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | NA | | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During construction phase, temporary influx of construction workers of about 150 in number is envisaged. During operation phase, the estimated new employment generation will be in the range of 1,50,000 to 2,00,000 numbers. The figure of employment generation is approximate and projected depending on type of industry which will be establishing. | | 1.29 | Introduction of alien species? | No | NA | | 1.30 | Loss of native species or genetic diversity? | No | NA | | 1.31 | Any other actions? | No | NA | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 2.1 | Land especially undeveloped or agricultural land (ha) | No | NA | | 2.2 | Water (expected source & competing users) unit: KLD | Yes | For MIDC’s project, 15cum/ha/day water demand shall be considered for designing of water supply scheme.
At present the nearest water supply is Andra Dam @5km from project area. | | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | MIDC has planned to develop Talegaon Industrial Area PH-IV as Talegaon Electronic and Engineering City with International Standards. The material to be used for construction would be cement, sand, metal, steel, bitumen, GSB, WMM & other likely construction materials to be used for development of infrastructure works.
All materials will be procured from the authorized quarries | | 2.5 | Forests and timber (source – MT) | No | NA | | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | For total Area = 360MVA
For balance area excluding ESZ = 115MVA | | 2.7 | Any other natural resources (use appropriate standard units) | No | NA | | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | No | No hazardous substances/ material expected to be formed/ used during the construction of the project | | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Appropriate measures will be taken to avoid their presence. e.g. preventing water logging to avoid spread of mosquitoes.
Appropriate measures will be taken for the safety of labors during ongoing COVID-19 Pandemic situation, with regular testing. | | 3.3 | Affect the welfare of people e.g. by changing living conditions? | No | All appropriate mitigation measures will be adopted for this | | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | NA | | 3.5 | Any other causes | No | Na | | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 4.1 | Spoil, overburden or mine wastes | Yes | During construction work, the solid waste will be generated in the form of excavated soil, which shall be disposed off at authorized designated sites | | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | All solid types of solid wastes shall be segregated and disposed through authorized vendors as per prevailing norms | | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | No | No hazardous waste to be used/ generated during construction phase.
During operation: Hazardous waste generated by individual industries shall be handled as per the Hazardous waste Management Rules by MoEF&CC | | 4.4 | Other industrial process wastes | No | All the industrial process wastes during operation phase will be individual industry responsibility to manage | | 4.5 | Surplus product | No | NA | | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | During construction phase, sludge generated from the sewage will be treated as per prevailing norms. | | 4.7 | Construction or demolition wastes | Yes | During construction work, the solid waste will be generated in the form of excavated soil, which shall be disposed off at authorized designated sites | | 4.8 | Redundant machinery or equipment | No | NA | | 4.9 | Contaminated soils or other materials | No | NA | | 4.10 | Agricultural wastes | No | NA | | 4.11 | Other solid wastes | No | NA | | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | The emissions are expected from the vehicles carrying construction material and construction activities.
Well maintained vehicles having EURO/Bharat engines will be used for construction work.
Dust generated during movement of the vehicles (if any) will be mitigated by water sprinkling. PUC certificate of all vehicles shall be maintained.
The construction machinery shall be properly maintained | | 5.2 | Emissions from production processes | Yes | Individual industry may have emissions from Production Processes. It will be necessary for them to provide appropriate Air pollution control measures. | | 5.3 | Emissions from materials handling including storage or transport | Yes | Material handling during construction would generate suspended particles which will be taken care of by on-site sprinkling system
Necessary care will be taken so that during construction as well as operational phases pollutants do not exceed CPCB Standards | | 5.4 | Emissions from construction activities including plant and equipment | Yes | During construction phase emissions may increase due to transportation of raw materials and construction activity. The transportation vehicles will be covered properly and it will be mandatory to use engines fitted with EURO/Bharat mark.
Fugitive emissions during loading and unloading will be taken care by installing water sprinklers in and around the area | | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Temporary increase in dust levels are envisaged during construction phase. It will be totally mitigated using water sprinkling system in and around activity area.
No odour issues are envisaged during construction phase. | | 5.6 | Emissions from incineration of waste | No | NA. | | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | NA. No open burning will be permissible. | | 5.8 | Emissions from any other sources | No | NA | | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | The expected noise level will be ranged from 50-55 dB(a).
Negligible noise is expected during the construction phase.
Wherever required the workers will be provided with personal protective equipment such as by providing mufflers and earplugs to the persons
working at the project site.
Care shall be taken to maintain the standards set by CPCB for noise level.
The machineries used will be properly maintained to avoid noise pollution.
All equipment for construction shall be fitted with silen | | 6.2 | From industrial or similar processes | Yes | It is expected negligible noise emissions from operation of upcoming industries. Care shall be taken to maintain the standards set by CPCB for noise level | | 6.3 | From construction or demolition | Yes | There is no demolition work envisaged.
During construction phase, sources of noise pollution will be due to operation of machinery as well as transportation vehicles.
Noise generated from the equipments will be nominal and to control the same the following measures will be adopted:
• Properly maintained equipments with mufflers will be used.
• Use of equipment generating noise of not greater than 90 db (A) will be used.
• High noise generating construction activities would be carried out | | 6.4 | From blasting or piling | No | NA | | 6.5 | From construction or operational traffic | Yes | Noise is expected from loading and unloading operations of construction materials, equipments etc. However, those are not significant. Wherever required the workers will be provided with personal protective equipment such as by providing mufflers and earplugs to the persons working at the project site.
Care shall be taken to maintain the standards set by CPCB for noise level.
The machinery used will be properly maintained to avoid noise pollution | | 6.6 | From lighting or cooling systems | No | Temporary lighting arrangement shall be provided at site.
Permanent street lighting will provided as infrastructure for the entire industrial area | | 6.7 | From any other sources | No | NA | | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | During construction work, there will not be handling of any hazardous material. During operation: Hazardous waste generated by individual industries shall be handled as per the Hazardous waste Management Rules by MoEF&CC | | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | During construction phase, treated sewage will be utilized for gardening as well as sprinkling purposes.
During operation treated effluent will be connected to CETP | | 7.3 | By deposition of pollutants emitted to air into the land or into water | No | With due adequate mitigation technologies for air, water emissions we do not envisage any deposition of pollutants over time | | 7.4 | From any other sources | No | NA | | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | NA | | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | No | During construction phase, no such hazard is envisaged.
During operation phase, individual industry shall carry out Process hazard study and risk assessment and all possible emergency scenarios will be identified. Accordingly, emergency action plan and emergency response plan shall be kept in place | | 8.2 | From any other causes | No | NA | | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | There is no record of occurrence of severe earth quakes, cloud bursts etc. in this area | | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | New employment opportunities shall be generated due to development of industrial estate
• Supporting infrastructure (roads, power supply, waste or waste water treatment, etc) - Yes- It is proposed to develop Talegaon Electronic & Engineering City. All infrastructure facilities viz. Roads, Water supply arrangement, drainage, sewerage system, Street lights, etc. shall be provided.
• Housing development- Yes- In Project Affected Persons (PAP) plots only and Or if residential area is provided | | 9.2 | Lead to after-use of the site, which could have an impact on the environment | No | NA | | 9.3 | Set a precedent for later developments | No | NA | | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | NA | | | (III) | Environmental Sensitivity | | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | Yes | Two villages are coming under Eco-sensitive zones;
1. Village Nigade Tal. Malval, Dist. Pune having area
1124.328 ha
2. Village Kalhat, Tal. Maval, Dist. Pune having area
495.057 ha | | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | NA | | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | NA | | 4 | Inland, coastal, marine or underground waters | No | NA | | 5 | State, National boundaries | Yes | NA | | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | NA | | 7 | Defence installations | No | NA | | 8 | Densely populated or built-up area | No | The proposed project is situated at about 10 K.m. from Talegaon Town. At present barren land is being acquired | | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | No | NA | | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | NA | | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | NA | | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | No | NA | | | (IV) | Proposed Terms of Reference for EIA studies | | | | Additional Attachments, if any |
|---|
| Attached File |
|---|
| | | | Essential Detail Sought: |
|---|
| Sno. | EDS Letter | Remarks | Date of EDS |
|---|
| 1. | Eds Reply Letter | Pre-Feasibility Report uploaded | 25 Apr 2023 | | 2. | NA | Kindly upload PFR | 02 Mar 2022 | | | Additional Detail Sought: |
|---|
| Sno. | ADS Letter | Remarks | Date of ADS |
|---|
| 1. | NA | Please submit formal letter to include the proposal in the agenda, as PP was not present in the last meeting of EAC | 01 Nov 2023 | | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | | V.(i) | | Name of Applicant | Sanjay | | Designation | Executive Engineer | | Name of Company (Applicant Name should not be given here) | MIDC, CIVIL DIVISION, PUNE | | Address | Office of the Executive Engineer, Civil Division, MIDC, Telco road, Chinchwad, Pune |
|
|