| APPENDIX I | | (See Paragraph-6) | | FORM 1 | | | | Note : If space provided against any parameter is inadequate, Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form1. Please note that all such Annexures must be part of single pdf document. | | (I) Basic Information | | | Is your project Comes under Notified Industrial Area | No |
| | Whether proposal involved violation of EIA notification | No | tr > | Weather Consent to Establishment Obtained | N/A | | Upload copy of CTE | N/A |
| | 1. | |
| Name of the Project/s | “Development of 4/6 lane (green field) access control expressway from Varanasi to Kolkata Package-IV from Km 184.400 (near Shahpur village, Bihar/Jharkhand Border) to Km 375.600 (near Kamalpur village, Jharkhand/WB Border) in the state Jharkhand under Bharatmala Pariyojana Phase-II (lot-9 package-3). Proposed Length – 191.200Km | Brief summary of project | Annexure-Brief summary of project | | Proposal Number | IA/JH/NCP/253250/2022 | | Project Cost | 7466 cr | |
| | 2. | |
| S. No. in the schedule | 7(f) Highways
| Project Sector | INFRA-1 | |
| | 3. | Proposed capacity/area/length/tonnage to be handled/command area/lease area/number or wells to be drilled | Proposed length: 191.200 km ha. | | | 4. | | New/Expansion/Modernization | New | | | | 5. | Existing Capacity/Area etc. | 0 ha. | | | 6. | Category of project i.e. 'A' or 'B' | A | | | 7. | | Does it attract the general condition? If yes, please specify | Yes | | d) | Inter-State boundaries and international boundaries | | | | 8. | | Does it attract the specific condition? If yes, please specify | No | | | | 9. | |
| Location of the project | The proposed highway starts at Km 184.400 (near Shahpur village, Bihar/Jharkhand Border) to Km 375.600 (near Kamalpur village, Jharkhand/WB Border) in the state Jharkhand. | | Shape of the project land | Block (Polygon) | | Uploaded GPS file | Annexure-GPS file  | | Uploaded copy of survey of India Toposheet | Annexure-Survey of india toposheet | | Plot/Survey/Khasra No. | Refer form 1 enclosed | | Town / Village | Refer form 1 enclosed | | State of the project | Jharkhand | |
| | Details of State of the project |
|---|
| S.no | State Name | District Name | Tehsil Name |
|---|
| (1.) | Jharkhand | Ramgarh | No Data | | (2.) | Jharkhand | Chatra | Hunterganj | | (3.) | Jharkhand | Chatra | Chatra | | (4.) | Jharkhand | Chatra | Pathalgora | | (5.) | Jharkhand | Chatra | Simaria | | (6.) | Jharkhand | Hazaribag | Hazaribag | | (7.) | Jharkhand | Hazaribag | Barkagaon | | (8.) | Jharkhand | Hazaribag | Churchu | | (9.) | Jharkhand | Bokaro | Gumia | | (10.) | Jharkhand | Bokaro | Peterwar | | (11.) | Jharkhand | Bokaro | Kasmar | | (12.) | Jharkhand | Bokaro | Jaridih | | | 10. | |
| Nearest railway station along with distance in kms | Ranchi Railway Station, 40 km | Nearest airport along with distance in kms | Ranchi airport, 45 km | |
| | 11. | Nearest Town/City/District Headquarters along with distance in kms | Chatra , 5 km | | | 12. | Village Panchayats, Zila Parishad, Muncipal Corporation, Local body (Complete postal address with telephone nos. to be given) | Village Panchayat | | | 13. | Name of the Applicant | Dr Biswajit | | | 14. | Registered Address | G-5 & 6, Sector-10, Dwarka, New DElhi-110075 | | | 15. | |
| Address for correspondance: | | Name of the Company | DR.B.Mukhopadhyay | | Name of the Applicant | Dr Biswajit | | Designation (Owner/ Partner/ CEO) | General Manager | | Pin code | 110075 | | E-mail | biswajit@nhai.org | | Telephone No. | 11-25074200 | | Fax No. | 11-25093543 | | Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
| | 16. | | Details of Alternative Sites examined, if any. Location of these sites should be shown on a toposheet | Yes | | Uploaded details | Annexure-Uploaded details | |
| | 17. | Whether part of Interlinked projects? | Yes | | | 18. | Whether separate application of Interlinked project has been submitted? | N/A | | | 19. | | If Yes, MoEF file number | N/A | | Date of submission | N/A | | | | | | 21. | | Whether the proposal involves Approval/ Clearance under: if yes, details of the same and their status to be given | | (i) Whether the proposal involves approval/clearance under the Forest (Conservation) Act,1980? | Yes | | Status | Application for Forest Clearance yet to be submitted | | (ii) Whether the proposal involves approval/clearance under the wildlife (Protection) Act,1972? | No | | (iii) Whether the proposal involves approval/clearance under the C.R.Z notification, 2011? | No | | | | | 23. | | Whether any Forest Land Involved? | Yes | | Area of Forest land Involved (hectares) | 510 ha. | |
| | 24. | | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No | | (a) Name of the Court | N/A | | (b) Name of the Sub court | N/A | | (c) Case No. | N/A | | (d) Orders/directions of the court, if any and relevance with the proposed project | N/A | |
| | 1 | Construction, operation or decommissioning of the Project involving actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) | | S.No | Information/Checklist confirmation | Yes/No | Details there of (with approximate quantities/rates, wherever possible) with source of information data | | 1.1 | Permanent or temporary change in land use, land cover or topography including increase in intensity of land use (with respect to local land use plan) | Yes | Total length of the project is 191.2 Km and proposed RoW is 90 m in non forest Area and 60 m in Forest area. Total land requirement will be approx. 1460.8 ha. out of which approx. 510 Ha is forest land and 950.8 Ha is Non forest land include agriculture and non agriculture land. | | 1.2 | Clearance of existing land, vegetation and buildings? | Yes | The alignment will require cutting of approximately 40000 of trees.
* the tree counting is in process therefore the total no. of trees which needs to be cut will be provided at the time of submission of Final EIA/EMP report and Most of the trees falling along the alignment are the part of agro forestry. | | 1.3 | Creation of new land uses? | Yes | New highway will be constructed | | 1.4 | Pre-construction investigations e.g. bore houses, soil testing? | Yes | Preliminary alignment survey has been completed and pre-construction survey & geo technical testing would be taken up. | | 1.5 | Construction works? | Yes | The project consists of the following key components:
i. Construction of highway having length 191.200 Km
ii. Major Bridges – 4
iii. Minor Bridges-35
iv. LVUP- 75
v. SVUP -85
vi. ROB-6
vii. Interchage-3
viii. Fly-2 | | 1.6 | Demolition works? | Yes | Some building structure will be demolished. As per proposed alignment approx. 340 semi pucca and pucca structures will be affected. | | 1.7 | Temporary sites used for construction works or housing of construction workers? | Yes | Temporary sites will be used for construction yards, labour camps, and construction camps. | | 1.8 | Above ground buildings, structures or earthworks including linear structures, cut and fill or excavations and fill or excavations | Yes | The above ground structure includes animal passages, viaducts, bridges, flyovers, Truck lay bays and Bus –Bays and wayside amenities and Toll Plazas. | | 1.9 | Underground works including mining or tunnelling? | Yes | Not Applicable | | 1.10 | Reclamation works? | No | Not Applicable | | 1.11 | Dredging? | No | Not Applicable | | 1.12 | Offshore structures? | No | Not Applicable | | 1.13 | Production and manufacturing processes? | No | Not Applicable | | 1.14 | Facilities for storage of goods or materials? | Yes | Materials for construction such as bitumen cement, paints, steel etc. will be stored in the construction shed/storage tanks. | | 1.15 | Facilities for treatment or disposal of solid waste or liquid effluents? | Yes | The liquid effluent generates from labour /construction camps will be treated in septic /sedimentation tank before diverting it to soak pit. The solid waste will be disposed as per Solid Waste Management rules, 2016. | | 1.16 | Facilities for long term housing of operational workers? | No | Not Applicable; The labors would be accommodated in temporary camps. | | 1.17 | New road, rail or sea traffic during construction or operation? | No | New Haul road may be required for access to the sites. | | 1.18 | New road, rail, air water borne or other transport infrastructure including new or altered routes and stations, ports, airports etc? | Yes | New Haul road may be required for access to the sites. | | 1.19 | Closure or diversion of existing transport routes or infrastructure leading to changes in traffic movements? | No | This is a Greenfield alignment. No change in traffic movements. | | 1.20 | New or diverted transmission lines or pipelines? | Yes | Will be diverted as per utility shifting plan. | | 1.21 | Impoundment, damming, culverting, realignment or other changes to the hydrology of watercourses or aquifers? | Yes | It would be temporary and adequate structure for Cross drainage works shall be constructed in order to maintain the natural hydrology of the area. | | 1.22 | Stream crossings? | Yes | Rivers – 10 Nos.
Nalahs/ Canals– 3 Nos.
Ponds- 6 Nos.
Total –19 Nos. | | 1.23 | Abstraction or transfers of water from ground or surface waters? | Yes | Water will be extracted from suitable surface sources (river/canals) or ground water after obtaining necessary permissions from the competent authority. | | 1.24 | Changes in water bodies or the land surface affecting drainage or run-off? | Yes | That would be impacted temporarily during construction phase. | | 1.25 | Transport of personnel or materials for construction, operation or decommissioning? | Yes | The Construction materials will be transported during construction from different sources, construction labour will be transported from labour camp. | | 1.26 | Long-term dismantling or decommissioning or restoration works? | No | Not applicable. | | 1.27 | Ongoing activity during decommissioning which could have an impact on the environment? | No | No ongoing activity will be affected during decommissioning | | 1.28 | Influx of people to an area in either temporarily or permanently? | Yes | During the construction of the road project around 10,95,000 man days will be requiring during construction phase and approx. 1000 persons would be employed temporarily for a period of 2 years. In addition to above approx. 100 persons will be employed on permanent basis due to operation of toll plazas. | | 1.29 | Introduction of alien species? | No | Only indigenous species shall be planted | | 1.30 | Loss of native species or genetic diversity? | No | Not applicable | | 1.31 | Any other actions? | No | Not as such | | | 2 | Use of Natural resources for construction or operation of the Project (such as land, water, materials or energy, especially any resources which are non-renewable or in short supply): | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 2.1 | Land especially undeveloped or agricultural land (ha) | Yes | Approx. 1460.8 ha. out of which approx. 510 Ha is forest land and 950.8 Ha is Non forest land include agriculture and non agriculture land | | 2.2 | Water (expected source & competing users) unit: KLD | Yes | 6750 KLD Water will be extracted from suitable surface sources (river/canals) or ground water after obtaining necessary permissions from the competent authority. | | 2.3 | Minerals (MT) | Yes | Minor minerals use in construction:-
Coarse Sand (cum)-2300
Coarse Agg. (cum)- 1305875
Fine Agg. (cum)- 2611750 | | 2.4 | Construction material – stone, aggregates, sand / soil (expected source – MT) | Yes | Cement (MT)- 238130
Coarse Sand (cum)-2300
Coarse Agg. (cum)- 1305875
Fine Agg. (cum)- 2611750
Steel (ton)- 7680
Bitumen (ton)- 4737000
Bitumen Emulsion (ton)- 2458100
Borrow Earth/Fly Ash (cum)- 12290600
Steel and Cement would be sourced from Authorized Vendor. Soil, Sand and Aggregate will be procured from operational licensed borrow areas and quarries located around nearby areas. Fly Ash from nearest Thermal Power Stations. | | 2.5 | Forests and timber (source – MT) | Yes | NA | | 2.6 | Energy including electricity and fuels (source, competing users) Unit: fuel (MT),energy (MW) | Yes | Temporary electricity connection will be taken from State Electricity Board for construction camp and Diesel generator will provide electricity required for construction equipment and power backup. Labour camps will be provided with LPG as fuel sourced from authorized Supplier. | | 2.7 | Any other natural resources (use appropriate standard units) | No | Not applicable; No other natural source would be required. | | | 3 | Use, storage, transport, handling or production of substances or materials, which could be harmful to human health or the environment or raise concerns about actual or perceived risks to human health | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 3.1 | Use of substances or materials, which are hazardous (as per MSIHC rules) to human health or the environment (flora, fauna, and water supplies | Yes | A construction camp housing around 1000 labors may increase the risk of occurrence of disease or affect disease vectors. Adequate precautions would be taken to prevent stagnation of sewage and grey water from labour camp. Routine inspection and spray of disinfectants shall be made to prevent outbreak of water borne diseases. | | 3.2 | Changes in occurrence of disease or affect disease vectors (e.g. insect or water borne diseases) | No | Adequate precautions shall be taken to prevent stagnation of sewage and grey water from labour camp. Routine inspection and spray of disinfectants shall be made to prevent outbreak of water borne disease. | | 3.3 | Affect the welfare of people e.g. by changing living conditions? | Yes | The proposed project will result in appreciable welfare of the people with respect to health care, educational, employment and agricultural developments as a result of fast connectivity to these facilities. Overall there will be improvement in quality of life of people. | | 3.4 | Vulnerable groups of people who could be affected by the project e.g. hospital patients, children, the elderly etc. | No | There is no School, Hospitals and other sensitive spots which houses vulnerable people are identified along the proposed alignment. No adverse impact is envisaged to vulnerable groups of people due to the project.
There will be positive impact due to faster connectivity to hospitals & schools. | | 3.5 | Any other causes | No | Not applicable | | | 4 | Production of solid wastes during construction or operation or decommissioning (MT/month) | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 4.1 | Spoil, overburden or mine wastes | No | Not applicable | | 4.2 | Municipal waste (domestic and or commercial wastes) | Yes | Construction Phase
Domestic waste of approx. 500 kg/day shall be generated from temporary construction camps @ 500 grams per head per day. The solid waste will be disposed as per Solid Waste Management rules, 2016.
Operation Phase
Solid waste will be generated during operation phase from way side amenities and will be handled as per established rules. | | 4.3 | Hazardous wastes (as per Hazardous Waste Management Rules) | Yes | Used / Waste oil and lubricants will be utilized in oiling shuttering and remaining balance will be sold to authorized recyclers. The hazardous waste (management, handling & trans boundary movement) rules, 2008 and its amendments till date will be followed. | | 4.4 | Other industrial process wastes | No | No other industrial process wastes will be generated during construction and operational stages. | | 4.5 | Surplus product | No | No surplus product will be produced. | | 4.6 | Sewage sludge or other sludge from effluent treatment | Yes | The solid waste will be disposed as per Solid Waste Management rules, 2016. | | 4.7 | Construction or demolition wastes | Yes | The resulting used bitumen waste / oil spill from various machineries may contaminate soil. Required precautions including routine checks and maintenance of machinery and equipment will be taken to avoid or minimize contamination of soils. C & D rules, 2016 will be followed. | | 4.8 | Redundant machinery or equipment | No | Not applicable. | | 4.9 | Contaminated soils or other materials | No | Not applicable. | | 4.10 | Agricultural wastes | No | Not applicable. | | 4.11 | Other solid wastes | No | Not applicable. | | | 5 | Release of pollutants or any hazardous, toxic or noxious substances to air(Kg/hr) | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 5.1 | Emissions from combustion of fossil fuels from stationary or mobile sources | Yes | Emissions from Diesel Generator (DG) sets, hot mix plants and construction machineries. Emission norms of CPCB& SPCB for DG set and HM plant will be followed as per MoEF&CC notification no. 595 dated December, 2013 for DG sets. | | 5.2 | Emissions from production processes | No | No production process is contemplated in the project. | | 5.3 | Emissions from materials handling including storage or transport | Yes | The use of transport vehicle for carriage of material shall lead to emission. However, there will be no emission during material handling except for the dust pollutants during handling of cement bags, which will be controlled. Ambient air quality monitoring will be done and NAAQS, 2009 will be followed. | | 5.4 | Emissions from construction activities including plant and equipment | Yes | Fugitive emissions such as gases &fumes are emitted from construction equipment and transportation vehicles, batching & mixing plants of Bitumen is generated. Hot mix plant shall be located at least 500 m down windward direction and away from nearest human habitations. Also the machineries and equipment shall be fitted with suitable dust catching devices, precipitators and filters | | 5.5 | Dust or odours from handling of materials including construction materials, sewage and waste | Yes | Dust will be generated from earth mixing sites, asphalt mixing site and crushers, transportation of raw materials. Water will be sprayed regularly to prevent dust generation from these areas. | | 5.6 | Emissions from incineration of waste | No | No waste would be allowed to be
burnt in this project | | 5.7 | Emissions from burning of waste in open air (e.g. slash materials, construction debris) | No | No burning of waste is proposed. | | 5.8 | Emissions from any other sources | Yes | Emissions of Particulate Matter, CO, SO2 and NOx from vehicles used for transportation of construction materials. However all the vehicles would be complied as per prevailing emission norms and fuel used would be as per MOPNG norms. The PUC certificate for all the vehicles would be mandatory. | | | 6 | Generation of Noise and Vibration, and Emissions of Light and Heat: | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 6.1 | From operation of equipment e.g. engines, ventilation plant, crushers | Yes | Noise will be generated from operation of construction equipment. Use of protective equipment, scheduling of activities, maintenance and isolation of equipment will be practiced. | | 6.2 | From industrial or similar processes | No | No industrial process is involved in the project. | | 6.3 | From construction or demolition | Yes | Noise and vibration will be generated due to construction activity. Compliance to ambient air quality standards with respect to noise, 2000, MoEF&CC would be ensured in the project. | | 6.4 | From blasting or piling | No | There shall be no piling or blasting activity. | | 6.5 | From construction or operational traffic | Yes | During construction, noise will be generated from trucks for transportation of material. | | 6.6 | From lighting or cooling systems | No | Not applicable. | | 6.7 | From any other sources | No | Not applicable. | | | 7 | Risks of contamination of land or water from releases of pollutants into the ground or into sewers, surface waters, groundwater, coastal waters or the sea: | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 7.1 | From handling, storage, use or spillage of hazardous materials | Yes | Short term accidental spills may happen during handling and storage of such material during construction. To avoid contamination of soil and ground/surface water from fuel and lubricants, the vehicles and equipment shall be properly maintained and repaired. The hazardous waste (management, handling & trans boundary movement) rules, 2008 and its amendments till date will be followed. | | 7.2 | From discharge of sewage or other effluents to water or the land (expected mode and place of discharge) | Yes | The direct discharge of sewage in to water or on land would not be allowed in the project. Septic tank, soak pit would be proposed for canteen/kitchen waste in construction camp and toilet waste liquids would be discharged to septic/soak pit. Other liquid waste treated at sites by using storage and sedimentation tank. The effluent of the sedimentation tank would be discharged within permissible limits of respective parameters. | | 7.3 | By deposition of pollutants emitted to air into the land or into water | Yes | There may be minimal deposition of pollutants. However following measures shall be adopted to minimize the contamination to land, water and air.
• Water spraying will be done during loading and unloading of raw materials and the earth work, all construction machinery shall be operated using controlled devices. All construction vehicles shall be operated with in permissible emission norms.
• The liquid effluent generates from labour /construction camps will be treated in septic /sedimentation t | | 7.4 | From any other sources | No | Not applicable | | 7.5 | Is there a risk of long term build up of pollutants in the environment from these sources? | No | Not applicable | | | 8 | Risk of accidents during construction or operation of the Project, which could affect human health or the environment | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 8.1 | From explosions, spillages, fires etc from storage, handling, use or production of hazardous substances | Yes | There is a possibility of risks from handling of petrochemical and other chemical substances. Fire safety equipment and first aid kit will be provided at such locations. To avoid accident due to handling of explosives, proper precautionary and safety measures as suggested in relevant Act and codes shall be adopted. Handling of explosives/chemicals would be governed as per the PESO guidelines. Fire Prevention and Life Safety Measures Act, Rules and Regulation. | | 8.2 | From any other causes | No | Not applicable | | 8.3 | Could the project be affected by natural disasters causing environmental damage (e.g. floods, earthquakes, landslides, cloudburst etc)? | No | The design of the road and structures would be designed in compliance to all the relevant codes and guidelines to take care for these natural disasters. | | | 9 | Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality | | S.No | Information/Checklist confirmation | Yes/No | Details thereof (with approximate quantities/rates, wherever possible) with source of information data | | 9.1 | Lead to development of supporting utilities, ancillary development or development stimulated   by the project which could have impact on the environment e.g.:
- Supporting infrastructure (roads, power supply,waste or waste water treatment, etc.)
- housing development
- extractive industries
- supply industries
- Other
| Yes | The proposed project is the development of Highway. | | 9.2 | Lead to after-use of the site, which could have an impact on the environment | Yes | The road project under Bharatmala Scheme envisages development of the area through which the road passes hence ancillary development of housing, industries is possible in due course of time. | | 9.3 | Set a precedent for later developments | Yes | Beyond the RoW of the highway, no role of NHAI/MoRTH, the ribbon development along the road and other development in surrounding areas generally starts during operational phase under the statute of local law. | | 9.4 | Have cumulative effects due to proximity to other existing or planned projects with similar effects | No | Not applicable | | | (III) | Environmental Sensitivity | | S.No | Areas | Name/Identity | Aerial distance (within 15km.) Proposed project location boundary | | 1 | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | No | NA | | 2 | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | No | Following Rivers are crossing along the project alignment:
Amihar Nadi
Lilajan Nadi
Hira Nadi
Jatha Nala
Budh Nadi
Lora Nadi
Bokaro Nala
Dudhi Nadi
Damodar Nadi
Kadma Nadi
Ljri Nadi
Gobai Nadi
Approx. 85 Km the proposed project passes through notified/Protected Forest. | | 3 | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | No | NA | | 4 | Inland, coastal, marine or underground waters | Yes | Rivers – 10 Nos.
Nalahs/ Canals– 3 Nos.
Ponds- 6 Nos.
Total –19 Nos. | | 5 | State, National boundaries | No | Jharkhand/Bihar Border adjacent to the starting point
Jharkhand/West Bengal border adjacent to the end point | | 6 | Routes or facilities used by the public for access to recreation or other tourist, pilgrim areas | No | NA | | 7 | Defence installations | No | NA | | 8 | Densely populated or built-up area | Yes | Hunterganj approx. 15 Km NE
Chatra approx. 5 Km SW
Belumath approx. 25 Km SW
Hazaribagh approx. 15 Km NE
Ranchi approx. 45 Km SW
Gola approx. 7 Km SW
Ramgarh approx. 20 Km SW
Bokaro approx. 25 Km NE
Dhanbad approx. 70 Km NE | | 9 | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship, community facilities) | Yes | Along the proposed alignment primary health centre and primary school are established in every village. | | 10 | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | No | Not applicable | | 11 | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | No | Not applicable | | 12 | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) similar effects | Yes | The area falls under seismic zone III which is categorized as moderate seismic zone. | | | (IV) | Proposed Terms of Reference for EIA studies | | Essential Detail Sought : NIL | | | Additional Detail Sought: |
|---|
| Sno. | ADS Letter | Remarks | Date of ADS |
|---|
| 1. | ADS Reply Letter | The required letter has been submitted | 01 Apr 2022 | | 2. | NA |
3.16.1 The EAC, taking into account the submission made by the project proponent, had a detailed deliberation in its 289th EAC meeting during 17th – 18th February 2022 and deferred the proposal for the want of following documents/information:
i. The proposal will be considered based on the recommendations and reviews by the concerned PCCF. The proposal will be considered after the report from concerned PCCF
ii. The project location falls in the elephant corridor. The alignment has to be cross checked with the concerned PCCF.
| 04 Mar 2022 | | | (V) | Undertaking | | I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. | | V.(i) | | Name of Applicant | Dr Biswajit | | Designation | General Manager | | Name of Company (Applicant Name should not be given here) | DR.B.Mukhopadhyay | | Address | G-5 & 6, Sector-10, Dwarka, New DElhi-110075 |
|
|