Form-2
APPLICATION FOR PRIOR ENVIRONMENTAL CLEARANCE
S. No.Item Details
1.
Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? Yes
Details of Project:
Type of Appraised Select
Details of Project:
Type of Violation Started the work onsite without prior EC under EIA notification,2006.
Details of Violation Violation to E(P) Act,1986 was identified as the mining was in operation without obtaining EC after the renewal fell due in 2007.
Upload document of Damage Assessment Report
Upload document of Remediation Plan and Natural & Community augmentation plan
Upload TOR Letter(if issued earlier)
Upload EC Letter(if issued earlier)
Details of Project:
(a)Name of the project(s) Proposed 70,200 TPA of Limestone production including subgrade and OB from Putka Limestone Mine (MLA 97.031 Ha) of M/s Jyoti Pramanik located at Village-Putka,Tehsil- Jharbandh,Dist-Bargarh,Odisha.
(b)Name of the Company / Organisation PUTKA LIMESTONE MINES
(c)Registered Address Village- Putka,Tahasil-Jharbandh,Dist-Bargarh,Odisha,,Bargarh,Orissa-768604
(d)Legal Status of the Company Private
(e)Joint Venture No
2.
Address for the correspondence:
(a)Name of the Applicant Jyoti Pramanik
(b)Designation (Owner/ Partner/ CEO) Lessee
(c)Address At-Mission Road,Sambalpur,Odisha,768001,,Jharabandha,Bargarh,Orissa-768001
(d)Pin code 768001
(e)E-mail jyotipramanik2021@gmail.com
(f)STD Code. 674(f)Telephone No. 2974059
(g)Fax No.
(h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . Annexure-Uploaded Copy of documents in support of the competence/authority
3.
Category of the Project/Activity as per Schedule of EIA Notification,2006:
(a.I)Project/Activity1(a) Mining of minerals
Minor Activity
(b)Category A
(c)Proposal Number IA/OR/MIN/195617/2018
(d)Master Proposal Number(Single Window) SW/195612/2021
(e)EAC concerned (for category A Projects only) Non-Coal Mining
(f)Project Type Fresh EC
4.
Location of the Project:
(a)Plot/Survey/Khasra No. Plot No. 24/P, 63/P, 64, 65/P, 66, 67, 68, 69, 70,
(b)Pincode 768042
(c)Bounded Latitudes (North)
From
Degree 21.17
Minutes
Second
From
Degree 21.18
Minutes
Second
(d)Bounded Longitudes (East)
From
Degree 82.960
Minutes
Second
From
Degree 82.966
Minutes
Second
(e)Survey of India Topo Sheet No. 64K/16
(f)Uploaded Topo Sheet File Copy of Topo Sheet File
(g)Maximum Elevation Above Means Sea Level(AMSL) 126
(h)Uploaded (kml) File Copy of Kml File      
(i)Distance of Nearest HFL from the project boundary within the study area 2
(j)Seismic Zone 3
5.
(a)Number of States in which Project will be Executed 1
(b)Main State of the project Orissa
Details of State of the project
S. No. State Name District Name Tehsil Name Village Name
NIL
6.
Details of Terms of Reference (ToR):
(a)MoEF&CC / SEIAA File Number 23-151/2018-IA.III(V)
(b)Date of Apply of TOR 23 Nov 2018
(c)Date of Issue of TOR / Standard ToR 24 Nov 2020
(d)Previous TOR Letter Copy of Previous TOR letter
7.
Details of Public Consultation:
(a)Whether the Project Exempted from Public Hearing?No
(b)Whether details of Public Hearing available? Yes
(c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above Yes
     7.1.       Details of Public Hearing
S. No.Details of Advertisement Details of Public Hearing Venue Location DetailsNo. of People AttendedIssues RaisedDesignation of Presiding OfficerOther Designation of Presiding Officer
(1.)
Date of Advertisement :04 Oct 2016
Copy of advertisement :Copy of Advertisement
Copy of Public Hearing :Copy of Public Hearing
Date :04 Nov 2016
Distance of Public Hearing Venue from the Proposed Project :2
At Putka Village Under Jharbandh block of Bargarh District
State :Orissa
District :Bargarh
Tehsil :Jharabandha
Village :Putka
70Proposed Environmental measures to be taken before start of operation of mines The mining activities have not upheld the economic status of nearby peopleOthersAdditional District Magistrate
8.
Details of Project Configuration/Product:
     8.1.       Project Configuration
S. No.Plant/Equipment/FacilityConfigurationRemarks
(1.)Compressor300cfm1 nos
(2.)Excavator0.9m31 nos
(3.)Jack Hammer Drill32mm2 nos
(4.)Tippers10t2 nos
     8.2.       Product
S. No.Product/Activity (Capacity/Area)QuantityUnitOther UnitMode of Transport / Transmission of ProductOther Mode of Transport / Transmission of Product
(1.)Limestone70200Tons per AnnumRoad,Rail
9.
In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii):
Details Not Applicable
9.1.
Details of Consent to Operate
(i)Whether Consent to operate obtained ? NA
(ii)Copies of all Consent to operate obtained since inception NA
(iii)Date of Issue N/A
(iv)Valid Upto N/A
(v)File No. NA
(vi)Application No. NA
(vii)Copy of Consent to operate valid as on date NA
10.
Project Cost:
(a)Total Cost of the Project at current price level (in Crores) 10
(b) Funds Allocated for Environment Management (Capital) (in Crores) 0.5
(c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) 0.285
(d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) 0.1
11.
Whether project attracts the General Condition specified in the Schedule of EIA Notification ? No
12.
Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? No
13.
Raw Material / Fuel Requirement:
(a)Proposed quantity of raw material/fuel 0
(b)Existing quantity of raw material/fuel N/A
(c)Total quantity of raw material/fuel 0
    13.1.        Raw Material / Fuel Profile
S. No.Raw Material / Fuel QuantityUnitOther UnitSource (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received )Mode of TransportOther Mode of TransportDistance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received)Type of Linkage Other Type of Linkage Uploaded Copy of Linkage
(1.)00OthersNANilOthersnil0 OthersNilCopy of Linkage
14.
Baseline Data :
(a)Period of Base Line Data Collection FROM 01 Oct 2020 To 31 Dec 2020
(b)Season Post-Monsoon
    14.1.     No. of ambient Air Quality (AAQ) monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitMaximum ValueMinimum Value98 Percentile ValuePrescribed Standard
(1.)PM10Micro Gram per Meter Cube79.830.038.8100
(2.)PM2.5Micro Gram per Meter Cube39.116.72660
(3.)SO2Micro Gram per Meter Cube10.35.26.6580
(4.)NOxMicro Gram per Meter Cube28.39.410.4580
    14.2.     No. of Ground Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsHeavy MetalUnitOther UnitMaximum ValueMinimum ValueDesirable LimitMaximum Permissible Limit
(1.)OthersHgmg/l0.000.000.000.00
(2.)Total Hardnessmg/l192120200600
(3.)TDSmg/l4802205002000
(4.)Heavy MetalsPbmg/l0.000.000.000.00
(5.)Fluoridemg/l0.550.251.01.5
(6.)TSSNA0000
(7.)pHNA7.37.16.58.5
(8.)Chloridesmg/l9082501000
    14.3.     No. of Surface Water monitoring locations : 8
S. No.Criteria Pollutants Other Criteria PollutantsUnitOther UnitMaximum ValueMinimum ValueClassification of inland water body
(1.)CODmg/l125.0C
(2.)OthersTotal Hardness as CaCO3mg/l12076C
(3.)pHNA7.97.4C
(4.)DOmg/l6.95.9C
(5.)BODmg/l2.51.0C
    14.4.     No. of Ambient Noise monitoring locations : 8
S. No.Parameter UnitMaximum ValueMinimum ValuePrescribed Standard
(1.)Leq(Night)A-weighted decibels(dB(A))29.717.645
(2.)Leq(Day)A-weighted decibels(dB(A))38.928.455
    14.5.     No. of Soil Sample Monitored locations : 8
S. No.Parameter UnitOther UnitMaximum ValueMinimum Value
(1.)pH7.65.8
(2.)N(Nitrogen)Kilogram per hectare263.6113
(3.)P(Phosphorus)Kilogram per hectare182.678.2
(4.)K(Potassium)Kilogram per hectare268.894.1
(5.)Electric ConductivityOthersMicro Siemens per Centimetre31590
14.6.
Details of Ground Water Table:
(a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) From 3 To 7
(b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) From 12.6 To 6.9
(c)Whether Ground Water Intersection will be there ? No
     15.      Details of Water Requirement (During Operation)
S. No.Source Source Other Required Quantity (Kilolitre per Day (Kld))Distance from SourceCopy of Permission from Competent Authority Mode of TransportOther Mode of TransportMethod of Water WithdrawalOther Method of Water WithdrawalLetter No.Date of IssuePermitted Quantity
(1.)GroundWater252Copy of Permission LetterPipelineOthersBore well5-22/SER/CGWA/2017-18-103621 Sep 201725
15.1.
(a)Whether Desalination is proposed No
    16.       Waste Water Management(During Operation)
S. No.Type/Source Quantity of Waste Water Generated (Kilolitre per Day)Treatment Capacity (Kilolitre per Day) Treatment MethodMode of DisposalOther Mode of DisposalQuantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day)Quantity of Discharged Water (Kilolitre per Day)
(1.)Nil00NilOthersNo waste water will be generated00
16.1.
(a)Total Waste Water Generation (Kilolitre per Day) 0
(b)Total Discharged Water (Kilolitre per Day) 0
(c)Total Reused Water (Kilolitre per Day) 0
    17.       Solid Waste Generation/Management
S. No.Name of Waste Item Other ItemQuantity per AnnumUnitDistance from Site(KM)Mode of TransportOther Mode of TransportMode of DisposalOther Mode of Disposal
(1.)Mining WasteOthersMining Waste19988Tons2RoadOthersBack filling in mining quarry
18.
    18.1.     Air Quality Impact Prediction
S. No.Criteria Pollutants Other Criteria PollutantsUnitBaseline ConcentrationDistance GLCIncremental ConcentrationTotal GLCPrescribed Standard
(1.)PM10Microgram per Meter Cube38.80.231.2640.06100
(2.)PM2.5Microgram per Meter Cube260.2302660
(3.)SO2Microgram per Meter Cube6.650.2306.6580
(4.)NOxMicrogram per Meter Cube10.450.23010.4580
    18.2.     Stack Details
S. No.Source FuelStack Height(m)Stack Diameter(m)PollutantsOther PollutantsEmission (GLS)
(1.)Nil000OthersNA0
19.
Power Requirement:
(a)Quantity (Kilo Volt Amps (kVA)) 125
(b)Source DG Set
(c)Uploaded Copy of Agreement Copy of Agreement
(d)Standby Arrangement (Details of DG Sets) 1
(e)Stack Height (in m) 1.5
20.
Land Ownership Pattern:
(a)Forest Land (ha.) 0
(b)Private Land (ha.) 0
(c)Government Land (ha.) 97.0310
(d)Revenue Land (ha.) 0
(e)Other Land (ha.) 0
    Total Land (ha.) 97.031
21.
Present Land Use Breakup of the Study Area in Ha:
(a)Agriculture Area (ha.) 61.747
(b)Waste/Barren Land (ha.) 34.034
(c)Grazing/ Community Land (ha.) 0
(d)Surface Water Bodies (ha.) 0
(e)Settlements (ha.) 0
(f)Industrial (ha.) 0
(g)Forest (ha.) 0
(h)Mangroves (ha.) 0
(i)Marine Area (ha.) 0
(j)Others (ha.) : Road 1.25
    Total (ha.) 97.0310
    22.     Land requirement for various activities
S. No.Description of Activity / Facility / Plant / Others OthersLand Requirement (ha.)Remarks
(1.)Quarry Area8.349--
(2.)Green belt5--
(3.)OB Dump Area2.010--
(4.)Area for Solid Waste Management0.578--
(5.)OthersOther land uses81.094--
Total (ha.) 97.031
23.
Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones :
    23.1.     Details of Ecological Sensitivity :
S. No.Details of Ecological Sensitivity NameDistance from the Project (Km)Remarks
(1.)Critically Polluted Areanil0No Critically Polluted area within 10 Km
(2.)NPAnil0No NPA within 10 Km
(3.)Corridorsnil0No Corridors within 10 Km
(4.)Wildlife Corridorsnil0No Wildlife Corridors within 10 Km
(5.)WLSnil0No WLS within 10 Km
(6.)ESZsnil0No ESZs within 10 Km
(7.)ESAsnil0No ESAs within 10 Km
    23.2.     Details of Environmental Sensitivity :
S. No.Details of Environmental Sensitivity Other Details of Environmental Sensitivity NameDistance from the Project (Km)Remarks
(1.)ForestPalsapali RF2Reserved Fortest
(2.)OthersForestPutka RF3Reserved Fortest
(3.)Defence Installationsnil0nil
(4.)Archaeological Sitesnil0nil
23.3.
(a)Whether Noc / Permission from the competent authority is required? No
(b)Whether NBWL recommendation is required? No
24.
Forest Land:
Whether any Forest Land involved? No
25.
Tree Cutting:
(a)No. of Trees Cut for the Project (if Forest Land not Involved) 0
(b)Details of Tree Cutting and Planting of Trees Not Applicable
26.
Land Acquisition Status:
(a)Acquired Land(Ha) 97.03
(b)Land yet to be acquired(Ha) 0
(c)Status of Land acquisition if not acquired Already Acquired
27.
Rehabilitation and Resettlement (R&R):
(a)No. of Villages
(b)No. of Households
(c)No. of PDFs (Project Displaced Families)
(d)No. of PAFs (Project Affected Families)
(e)Funds Allocated for R&R(in INR) (in Lacs)
(f)Status of R&R NA
28.
Details of Presence of Schedule-I Species:
(a)Whether there is Presence of Schedule-I Species ? No
(b)Whether conservation plan for Schedule-I Species has been prepared ? No
(c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? No
29.
Details of Presence of Water Bodies in Core Area:
(a)Whether there is Presence of Water Bodies in Core Area ? Yes
(i)Details of Water Bodies in Core Area Murmuri nala flowing in SW boundary of lease area
(b)Whether there is Diversion Required ? No
(c)Whether permission has been obtained from competent authority ? No
30.
Details of Presence of Water Bodies in Buffer Area:
(a)Whether there is Presence of Water Bodies in Buffer Area ? Yes
(i)Details of Water Bodies in Buffer Area Ong River
(ii)Direction of Water Bodies in Buffer Area South
(iii)Distance of Water Bodies in Buffer Area 5
31.
Manpower Requirement:
(a)Permanent Employment-During Construction 0
(b)Permanent Employment-During Operation 60
(c)Temporary Employment- During Construction 0
(d)Temporary Employment- During Operation 0
(e)No. of working days 300
(f)Total Manpower 60
32.
Green Belt in Ha:
(a)Total Area of Green Belt 5
(b)Percentage of Total Project Area 5.15
(c)No. of Plants to be Planted 2500
(d)Funds Allocated for Plantation 675000
(e)Uploaded Green Belt plan Copy of Green Belt Plan
    33.         Project Benefits
S. No.Type of Project Benefits Details of Project Benefits
(1.)EnvironmentalNatural resource management,Damage assessment and greenbelt development
(2.)SocialCommunity augmentation and peripheral development
(3.)FinancialEmployment generation
   34.   CRZ Specific Details : Not Applicable
   35.   Sector Specific Details For Non-Coal Mining
S. No.Item Details
     1.       No. of Mineral(s) to be Mined : 1
S. No.Mineral(s) to be Mined Major or Minor Mineral
(1.)Lime StoneMajor
2.
Mine Capacity in ROM (Run of Mine) 70200
3.
Uploaded 500 meters Cluster Certificate from State Mines and Geology in case of minor minerals Copy of 500 meters Cluster Certificate from State Mines and Geology
4.
Mining Plan:
(a)Approval Letter No. MPN/OTFM/06-ORI/BHU/2016-17
(b)Date of Approval 02 Sep 2016
(c)Approved Letter Copy of Approved Letter
(d)Approved By State Mining and Geology Department IBM
(e)Approved Mining Lease Area 97.031
(f)Approved Capacity 70200
5.
Technical Details:
(a)Total Geological Reserves (Million Ton) 1.495
(b)Mineable Reserves (Million Ton) 1.44
(c)Extractable Reserves(Million Ton) 1.44
(d)Percent(%) of Extraction 95
(e)Grade of Coal /Ore /Mineral 35% CaO
(f)Stripping Ratio 1 : 0.15
(g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) NA
(h)Average Gradient(Degree) NA
(i)Mining Method Opencast
(j)Life of Mine (Years) 13
6.
Details of Beneficiations:
(a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area No
(b)Whether it is proposed to install crusher within the mining lease area No
7.
Details of Seams:
(a)Whether details of seam applicable No
8.
Details of Mining Lease:
(a)Mining Lease Area (in Hectare) 97.031
(b)Whether obtained Letter of Intent (LOI) from the state government ? Yes
(i)Copy of Letter of Intent Copy of Letter of Intent
(ii)Date of issue of LOI 25 Sep 1974
(iii)Validity of LOI 50
(iv)Reference No. of LOI NIL
(c)Whether Lease Deed Executed ? Yes
(i)Copy of Executed Lease deed valid as on Date Copy of Executed Lease deed
(ii)Provide area in Hectare as per executed lease deed (initial) document 97.031
(iii)Validity of the lease deed From : 25 Sep 1994 To : 24 Sep 2024
(iv)Date of Execution of Mining Lese 13 Sep 1994
(v)Reference Number 105/2016
(d)Whether Lease Deed Renewed ? Yes
     8.1.    Earlier Renewals:
S. No.Lease Details Date of Renewal Period Copy of Earlier Lease Letter No.Area Remarks
(1.)Renewal 25 Sep 1994 From : 25 Sep 1974 To : 24 Sep 2024 Copy of Earlier LeaseNIL 97.031 nil
9.
OB (Over Burden) Management:
(a) Details of External Dumps:
(i)No. of OB Dumps 6
(ii)Total Area (in Hectare) 2.010
(iii)Height (in meter) 4
(iv)Quantity (in Million Cubic meter) 0.0944
(v)No. of year back fill up 5
(b) Details of Internal Dumps:
(i)No. of Internal Dumps 0
(ii)Total Area (in Hectare) 0
(iii)Height (in meter) 0
(iv)Quantity (in Million Cubic meter) 0
10.
Details of Topsoil Management:
(a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) 0.19
(b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) 0.19
(c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) 0
11.
Details of Final Mine Void:
(a)Area (in Hectare) 8.349
(b)Depth (in meter) 16
(c)Volume (in Million Cubic meter) 1.335
12.
Details of Quarry:
(a)Final Void of 8.349 (hectare) at a Depth of 6 meter which is Proposed to be Converted into a Water Body.
(b)Total Quarry Area (ha) 97.031
13.
Details of Transportation:
(a)In Pit/Underground to Surface 1Km
(b)Surface to Siding/Loading 5 Km
(c)Transportation / Conveyor Details 16 Trucks
     14.      Details of Land Usage (Pre-Mining)
S. No.LAND USE Other LAND USEWITHIN ML AREA (Hectare)OUTSIDE ML AREA (Hectare)TOTAL (Hectare)
(1.)AGRICULTURE LAND61.747061.747
(2.)OTHERS(Specify)Road0.93500.935
(3.)WASTE LAND34.034034.034
(4.)GRAZING LAND000
(5.)FOREST LAND000
(6.)SURFACE WATER BODIES000
(7.)SETTLEMENTS0.31500.315
TOTAL97.031097.031
     15.      Details of Land Usage (Post-Mining)
S. No.LAND USE Other LAND USEPlantation (ha)Water Body (ha)Public Use (ha)Undisturbed (ha)Total
(1.)EXCAVATION/QUARRY8.349008.349
(2.)BUILT UP AREA (COLONY/OFFICE)000.050.05
(3.)GREEN BELT5005
(4.)VIRGIN AREA0076.21476.214
(5.)EXTERNAL OB DUMPS0000
(6.)TOP SOIL STORAGE0.578000.578
(7.)ROADS000.820.82
(8.)INTERNAL OB DUMPS2.01002.01
(9.)OtherMineral Storage,Mineral beneficiation4.01004.01
TOTAL19.947077.084097.031
16.
Details of Reclamation:
Total Afforestation Plan shall be Implemented Covering of Mining.
This will Include:
(a)External OB Dump(in hectare) 2.01
(b)Internal Dump(in hectare) 0
(c)Quarry(in hectare) 8.349
(d)Safety Zone(in hectare) 5
(e)Final Void of 8.349 (hectare) at a Depth of 6 meter which is Proposed to be Converted into a Water Body.
(f)Density of Tree Plantation per ha (in no.) 2500
(g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) 0
(h)Total afforestation plant (in hectare) 19.947
17.
Status of progressive Mining Closure Plan:
Details Not Applicable
     18.      Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception:
S. No.Financial Year Sanctioned Capacity as per EC (MTPA)Sanctioned Capacity as per CTOSanctioned Capacity as per approved mining planActual Production Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA)
(1.)198900046.50
(2.)1994000500
(3.)19950004100
(4.)1996000680
(5.)199800000
(6.)19930001500
(7.)198600044010
(8.)2006006493533163316
(9.)1987000075750
(10.)200100000
(11.)200300000
(12.)2008006921700
(13.)198800012000
(14.)1990000479.60
(15.)199100016.00
(16.)19920001500
(17.)199700000
(18.)19990005.50
(19.)200000000
(20.)200200000
(21.)200400000
(22.)2005006037200
(23.)20070067041503503
(24.)2009007020000
S. No.Item Details
36.
Details of Court Cases:
(a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? Yes
(b)Name of the Court High Courts
(c)Name of the Sub Court Orissa
(d)Case No. II(c)CC02/2015
(e)Orders/Directions of the court ,if any and its relevance with the proposed project Summon issued
(f)Case Details Under violation to E(P) Act,1986
(g)Uploaded Court Order Copy of Court Order
37.
Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act:
(a)Whether any Direction issued under EPA Act/Air Act/Water Act ? No
38.
Details of EIA Consultant:
(a)Have you hired Consultant for preparing document? Yes
(i)Accreditation No. NABET/EIA/1922/RA0154
(ii)Name of the EIA Consultant Kalyani Laboratories Private Limited
(iii)Address Plot No: 78/944, Millenium City, Pahala, BBSR, 752101
(iv)Mobile No. 9437306091
(v)Landline No. 0674297405
(vi)Email Id kalyanilab@yahoo.co.in
(vii)Category of Accreditation A
(viii)Sector of Accreditation Non-Coal Mining
(ix)Validity of Accreditation 24 Apr 2022
(x)Uploaded Certificate of Accreditation certified by QCI/NABET Copy of Certificate of Accreditation
39.
Documents to be Attached:
(a)Uploaded Copy of EIA/EMP Report Copy of EIA/EMP
Copy of EIA/EMP(Annexures)
Copy of EIA/EMP(Plans/Figures)
(b)Uploaded Copy of Risk Assessment Report Copy of Risk Assessment
(c)Uploaded Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan Copy of Feasibility Report/ Detailed Project Report(DPR) /Detailed Engineering Report /Detailed Conceptual Plan /Approved Mining Plan
(d)Uploaded Copy of Final Layout Plan Copy of Final Layout Plan
(e)Uploaded Cover Letter Copy of Cover Letter
(f)Uploaded Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
(g)Uploaded Additional File Copy of Additional File
(h)Uploaded Proposal Presentation (To be given in EAC meeting) NA
      Essential Detail Sought : NIL
            Additional Detail Sought:
Sno. ADS Letter Remarks Date of ADS
1. ADS Reply LetterCompliance to ADS submitted 11 Jan 2023
2. ADS Raise LetterNA 16 Sep 2021
3. ADS Reply LetterCompliance to ADS 14 Aug 2021
4. ADS Raise LetterNA 07 Jul 2021
5. ADS Reply LetterCompliance to ADS submitted 12 Mar 2021
6.NAAs per minutes of 43rd meeting of EAC, deferred the project for want of following information: 1) Revised damage assessment cost as suggested during the meeting shall be assessed. Remediation, Natural and Community resource Augmentation plan is related to the EMP activities and confined to project site, therefore activities under all the three plan shall be revised for outside he project area. 2) Remediation, Natural and Community resource augmentation plan shall be prepared for three with monitorible capital investments 3) Rework on the table for monitoring stations w.r.t to predominant wind direction and accordingly incremental load shall be assessed using modelling tools. 4) Safety measures for water bodies in the vicinity of the mine lease area with details of safety zone for near habitation, agriculture and water bodies. 5) Rework on the dumpling plan with details of garland drain and toe wall etc. 6) Details of peripheral plantation shall be submitted. 7) Monitorible Physical targets w.r.t the issues raised during Public Hearing shall be identified and incorporated under EMP. 8) Issues raised during the Public Hearing shall be tabulated alogwith the compliance submitted in response. 9) Details for reclamation of external dumps. 10) Details of transportation of mineral. 10 Mar 2021
7.NAEAC deliberated on the information submitted by the Project Proponent (Form 2, EIA EMP report, PH issues, Annexures etc) in the 43rd meeting held on 8-9 February, 2021, deferred the project for want of following information 1) Revised damage assessment cost as suggested during the meeting shall be assessed. Remediation, Natural and Community resource Augmentation plan is related to the EMP activities and confined to project site, therefore activities under all the three plan shall be revised for outside he project area. 2) Remediation, Natural and Community resource augmentation plan shall be prepared for three with monitorible capital investments 3) Rework on the table for monitoring stations w.r.t to predominant wind direction and accordingly incremental load shall be assessed using modelling tools. 4) Safety measures for water bodies in the vicinity of the mine lease area with details of safety zone for near habitation, agriculture and water bodies. 5) Rework on the dumpling plan with details of garland drain and toe wall etc. 6) Details of peripheral plantation shall be submitted. 7) Monitorible Physical targets w.r.t the issues raised during Public Hearing shall be identified and incorporated under EMP. 8) Issues raised during the Public Hearing shall be tabulated alogwith the compliance submitted in response. 9) Details for reclamation of external dumps. 10) Details of transportation of mineral. 10 Mar 2021
8.NAEAC deliberated on the information submitted by the Project Proponent (Form 2, EIA EMP report, PH issues, Annexures etc) in the 43rd meeting held on 8-9 February, 2021, deferred the project for want of following information: 1) Revised damage assessment cost as suggested during the meeting shall be assessed. Remediation, Natural and Community resource Augmentation plan is related to the EMP activities and confined to project site, therefore activities under all the three plan shall be revised for outside he project area. 2) Remediation, Natural and Community resource augmentation plan shall be prepared for three with monitorible capital investments 3) Rework on the table for monitoring stations w.r.t to predominant wind direction and accordingly incremental load shall be assessed using modelling tools. 4) Safety measures for water bodies in the vicinity of the mine lease area with details of safety zone for near habitation, agriculture and water bodies. 5) Rework on the dumpling plan with details of garland drain and toe wall etc. 6) Details of peripheral plantation shall be submitted. 7) Monitorible Physical targets w.r.t the issues raised during Public Hearing shall be identified and incorporated under EMP. 8) Issues raised during the Public Hearing shall be tabulated alogwith the compliance submitted in response. 9) Details for reclamation of external dumps. 10) Details of transportation of mineral. 10 Mar 2021
9.NAEAC deliberated on the information submitted by the Project Proponent (Form 2, EIA/EMP report, PH issues, Annexures etc) in the 43rd meeting held on 8-9 February, 2021, deferred the project for want of following information: 1) Revised damage assessment cost as suggested during the meeting shall be assessed. Remediation, Natural and Community resource Augmentation plan is related to the EMP activities and confined to project site, therefore activities under all the three plan shall be revised for outside he project area. 2) Remediation, Natural and Community resource augmentation plan shall be prepared for three with monitorible capital investments 3) Rework on the table for monitoring stations w.r.t to predominant wind direction and accordingly incremental load shall be assessed using modelling tools. 4) Safety measures for water bodies in the vicinity of the mine lease area with details of safety zone for near habitation, agriculture and water bodies. 5) Rework on the dumpling plan with details of garland drain and toe wall etc. 6) Details of peripheral plantation shall be submitted. 7) Monitorible Physical targets w.r.t the issues raised during Public Hearing shall be identified and incorporated under EMP. 8) Issues raised during the Public Hearing shall be tabulated alogwith the compliance submitted in response. 9) Details for reclamation of external dumps. 10) Details of transportation of mineral. 10 Mar 2021
10.NAEAC deliberated on the information submitted by the Project Proponent (Form 2, EIA/EMP report, PH issues, Annexures etc) in the 43rd meeting held on 8-9 February, 2021, deferred the project for want of following information: 1) Revised damage assessment cost as suggested during the meeting shall be assessed. Remediation, Natural and Community resource Augmentation plan is related to the EMP activities and confined to project site, therefore activities under all the three plan shall be revised for outside he project area. 2) Remediation, Natural and Community resource augmentation plan shall be prepared for three with monitorible capital investments 3) Rework on the table for monitoring stations w.r.t to predominant wind direction and accordingly incremental load shall be assessed using modelling tools. 4) Safety measures for water bodies in the vicinity of the mine lease area with details of safety zone for near habitation, agriculture and water bodies. 5) Rework on the dumpling plan with details of garland drain and toe wall etc. 6) Details of peripheral plantation shall be submitted. 7) Monitorible Physical targets w.r.t the issues raised during Public Hearing shall be identified and incorporated under EMP. 8) Issues raised during the Public Hearing shall be tabulated alogwith the compliance submitted in response. 9) Details for reclamation of external dumps. 10) Details of transportation of mineral. 10 Mar 2021
Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up.