EC Report
1. Project Details
   Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? : No
1. Project Details
   i. Proposal No. : IA/TN/NCP/72042/2018    ii. MoEFCC File No. : 21-67/2010-IA-III    iii.Short narrative of the project: India-based Neutrino Observatory    iv. Project Sector : INFRA-1    v. Company/Proponent : INDIA BASED NEUTRINO OBSERVATORY
  vi.Details of State of the project
Details of State of the project
S.no. State Name District Name Tehsil Name
1.Tamil NaduTheniUthamapalayam
 
   vii.Date of TOR Granted N/A viii.TOR letter issued by Ministry: N/A ix.Date of Submission for EC: 05 Jan 2018 x.Project Type: New
2. Uploaded Documents of EIA/EMP,Risk Assessment,Public Hearing etc.
i.EIA/EMP: Annexure-EIA/EMP ii.Risk Assessment: Annexure-Risk Assessment iii.Public Hearing: Annexure-Public Hearing    iv. Date of Public Hearing: 01 Jan 1900   v. Uploaded Additional Report/Study/Document as desired by Ministry/EAC: Annexure-Additional Report/Study/Document   vi. Uploaded Cover Letter: Annexure-Cover Letter   vii.Remarks: EC clearance was applied for from SEIAA, TN under Category B/8a. SEIAA directed us to apply to MOEF. Hence we are uploading Form 1 and Form 1a.
Additional Attachments, if any
S.no. Attached File Date of Submission
1. Form1A04 Jan 2018
3. Additional Detail Sought
Additional Detail Sought
Sno. ADS Letter Remarks Date of ADS
1.NAKindly see the Minutes of 27th meeting of EAC Infra-II 05 Feb 2018
2. ADS LetterSubmission Compliance report of India-Based Neutrino Observatory at Bodi West Hills, Pottipuram Village, Theni District, Tamilnadu for Environmental Clearance 20 Feb 2018
3.NAKindly upload conceptual plan, Disaster Management Plan and Risk Assessment Plan as submitted after EAC Infra-2 observations in its 28th meeting held on 05.03.2018. 16 Mar 2018
4. ADS LetterPlease find attached conceptual plan, Disaster Management Plan and Risk Assessment Plan with reference to EAC Infra-2 in its 28th meeting held on 05.03.2018. 16 Mar 2018
4. Accredited Consultant Details
   i. Accreditation status : No    ii. Reason for not hiring the Consultant : The relevant documents were already prepared by a team including iNO scientists and engineers for EC in 2010.
5. Undertaking
I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost.
   i. Name of Applicant : Vivek    ii. Designation : ProjectDirectorINO    iii. Name of Company(Applicant Name should not be given here) : INDIA BASED NEUTRINO OBSERVATORY    iv. Address : INO Cell, Tata Institute of Fundamental Research, 1 Homi Bhabha Road, Colaba, Mumbai 400005 v. Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency: Annexure-Uploaded copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency
Print