1. | Whether it is a violation case and application is being submitted under Notification No. S.O.804(E) dated 14.03.2017 ? | No | Details of Project: | (a)Name of the project(s) | Siarmal Opencast Project | (b)Name of the Company / Organisation | A.K.Singh | (c)Registered Address | Mahanadi Coalfields Limited
Office of the General,Mahanadi Coalfields Limited
Office of the General,Sundargarh,Sikkim-770076 | (d)Legal Status of the Company | Central PSU | (e)Joint Venture | No | |
|
2. | Address for the correspondence: | (a)Name of the Applicant | Satish Chandra Tripathi | (b)Designation (Owner/ Partner/ CEO) | Project Officer, Basundhara-Garjanbahal Area, MCL | (c)Address | Mahanadi Coalfields Limited Office of the General Manager, B-G Area P.O. Basundhara Dist: Sunderg,Mahanadi Coalfields Limited Office of the General Manager, B-G Area P.O. Basundhara Dist: Sunderg,Hemgir,Sundargarh,Sikkim-770076 | (d)Pin code | 770076 | (e)E-mail | gmenvt_mcl@yahoo.co.in | (f)STD Code. | 663(f)Telephone No. | 2542084 | (g)Fax No. | 2542257 | (h)Copy of documents in support of the competence/authority of the person making this application to make application on behalf of the User Agency . | Annexure-Uploaded Copy of documents in support of the competence/authority | |
|
3. | Category of the Project/Activity as per Schedule of EIA Notification,2006: | (a.I)Project/Activity | 1(a) Mining of minerals
| Minor Activity | 7(h) Common Effluent Treatment Plants (CETPs)
| (b)Category | A | (c)Proposal Number | IA/OR/CMIN/24164/2014 | (d)Master Proposal Number(Single Window) | SW/94547/2019 | (e)EAC concerned (for category A Projects only) | Coal Mining | (f)Project Type | Fresh EC |
|
|
4. | Location of the Project: | (a)Plot/Survey/Khasra No. | Siarmal | (b)Pincode | 770076 | (c)Bounded Latitudes (North) | | From | | Degree | 220119 | Minutes | | Second | | From | | Degree | 220359.99 | Minutes | | Second | | (d)Bounded Longitudes (East) | | From | | Degree | 833709 | Minutes | | Second | | From | | Degree | 834249.58 | Minutes | | Second | | (e)Survey of India Topo Sheet No. | 64N/12 (RF 1:50000) | (f)Uploaded Topo Sheet File | Copy of Topo Sheet File | (g)Maximum Elevation Above Means Sea Level(AMSL) | 311 | (h)Uploaded (kml) File | Copy of Kml File  | (i)Distance of Nearest HFL from the project boundary within the study area | 259 | (j)Seismic Zone | 2 | |
|
5. | (a)Number of States in which Project will be Executed | 1 | (b)Main State of the project | Orissa | |
|
|
Details of State of the project |
---|
S. No. | State Name | District Name | Tehsil Name | Village Name |
---|
NIL | |
|
6. | Details of Terms of Reference (ToR): | (a)MoEF&CC / SEIAA File Number | J-1105/230/2014-IA-II(M) | (b)Date of Apply of TOR | 16 Aug 2014 | (c)Date of Issue of TOR / Standard ToR | 20 Feb 2015 | (d)Previous TOR Letter | Copy of Previous TOR letter | |
|
7. | Details of Public Consultation: | (a)Whether the Project Exempted from Public Hearing? | No | (b)Whether details of Public Hearing available? | Yes | (c)Whether Public hearing was presided over by an officer of the rank of Additional District Magistrate or above | Yes | |
|
7.1. Details of Public Hearing |
---|
|
S. No. | Details of Advertisement | Details of Public Hearing | Venue | Location Details | No. of People Attended | Issues Raised | Designation of Presiding Officer | Other Designation of Presiding Officer |
---|
(1.) | | Copy of Public Hearing : | Copy of Public Hearing | Date : | 03 Jan 2019 | Distance of Public Hearing Venue from the Proposed Project : | 4 |
| Kundren Play Ground | State : | Orissa | District : | Sundargarh | Tehsil : | Hemgir | Village : | Siarmal |
| 245 | Regarding employment & Resettlement,Land Compensation. | Others | Additional District Magistrate | |
8. | Details of Project Configuration/Product: | |
|
8.1. Project Configuration |
---|
S. No. | Plant/Equipment/Facility | Configuration | Remarks |
---|
(1.) | Open Cast Coal Mining | 50 MTPA | -- | |
8.2. Product |
---|
S. No. | Product/Activity (Capacity/Area) | Quantity | Unit | Other Unit | Mode of Transport / Transmission of Product | Other Mode of Transport / Transmission of Product |
---|
(1.) | Coal | 50 | Others | Million Tons Per Annum | Rail | | |
|
9. | In case of Expansion / Modernisation / One Time Capacity Expansion (only for Coal Mining) / Expansion under Clause 7(ii) / Modernisation under Clause 7(ii) / Change of Product Mix under Clause 7(ii): | Details Not Applicable | |
|
9.1. | Details of Consent to Operate | (i)Whether Consent to operate obtained ? | NA | (ii)Copies of all Consent to operate obtained since inception | NA | (iii)Date of Issue | N/A | (iv)Valid Upto | N/A | (v)File No. | NA | (vi)Application No. | NA | (vii)Copy of Consent to operate valid as on date | NA | |
|
|
10. | Project Cost: | (a)Total Cost of the Project at current price level (in Crores) | 3756.36 | (b) Funds Allocated for Environment Management (Capital) (in Crores) | 738.26 | (c) Funds Allocated Towards CER (Corporate Environment Responsibility) (in Crores) | 309.56 | (d) Funds Allocated for Environment Management Plan (EMP) (Recurring per Annum) (in Crores) | 0 | |
|
11. | Whether project attracts the General Condition specified in the Schedule of EIA Notification ? | No | | |
12. | Whether project attract the Specific Condition specified in the Schedule of EIA Notification ? | No | | |
13. | Raw Material / Fuel Requirement: | (a)Proposed quantity of raw material/fuel | 121308 | (b)Existing quantity of raw material/fuel | N/A | (c)Total quantity of raw material/fuel | 121308 | |
|
  13.1. Raw Material / Fuel Profile |
---|
S. No. | Raw Material / Fuel | Quantity | Unit | Other Unit | Source (incase of Import. please specify country and Name of the port from which Raw Material / Fuel is received ) | Mode of Transport | Other Mode of Transport | Distance of Source from Project Site (in Kilometres) (In case of import, distance from the port from which the raw material / fuel is received) | Type of Linkage | Other Type of Linkage | Uploaded Copy of Linkage |
---|
(1.) | Diesel | 367.6 | Kilo Litre per Day | | Local | Road | | 0 | Fuel Supply Agreement | | Copy of Linkage | |
|
14. | Baseline Data : | (a)Period of Base Line Data Collection | FROM 04 Nov 2017 To 03 Feb 2018 | (b)Season | Winter | |
|
14.1. No. of ambient Air Quality (AAQ) monitoring locations : 10 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Maximum Value | Minimum Value | 98 Percentile Value | Prescribed Standard |
---|
(1.) | SO2 | | Micro Gram per Meter Cube | 23.60 | 8.50 | 23.30 | 80 | (2.) | PM2.5 | | Micro Gram per Meter Cube | 57.87 | 20.99 | 57.71 | 60 | (3.) | PM10 | | Micro Gram per Meter Cube | 94.80 | 60.65 | 92.73 | 100 | (4.) | NOx | | Micro Gram per Meter Cube | 34.89 | 20.20 | 33.56 | 80 | |
14.2. No. of Ground Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Heavy Metal | Unit | Other Unit | Maximum Value | Minimum Value | Desirable Limit | Maximum Permissible Limit |
---|
(1.) | pH | | | NA | | 7.39 | 7.14 | 6.5 | 8.5 | (2.) | Heavy Metals | | Cadmium | mg/l | | 0 | 0 | 0.003 | 0.003 | (3.) | Total Hardness | | | mg/l | | 340 | 124 | 200 | 600 | (4.) | TSS | | | mg/l | | 0 | 0 | 100 | 100 | (5.) | Chlorides | | | mg/l | | 118 | 28 | 250 | 1000 | (6.) | Others | NA | | NA | | 0 | 0 | 0 | 0 | (7.) | TDS | | | mg/l | | 490 | 152 | 500 | 2000 | (8.) | Fluoride | | | mg/l | | 0.46 | 0.24 | 1 | 1.5 | |
14.3. No. of Surface Water monitoring locations : 4 |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Other Unit | Maximum Value | Minimum Value | Classification of inland water body |
---|
(1.) | pH | | NA | | 7.67 | 7.12 | C | (2.) | BOD | | mg/l | | 0 | 0 | C | (3.) | Others | NA | NA | | 0 | 0 | C | (4.) | COD | | mg/l | | 0 | 0 | C | (5.) | DO | | mg/l | | 5.7 | 5.0 | C | |
14.4. No. of Ambient Noise monitoring locations : 10 |
---|
S. No. | Parameter | Unit | Maximum Value | Minimum Value | Prescribed Standard |
---|
(1.) | Leq(Day) | A-weighted decibels(dB(A)) | 54.7 | 44.8 | 55 | (2.) | Leq(Night) | A-weighted decibels(dB(A)) | 51.5 | 42.0 | 45 | |
14.5. No. of Soil Sample Monitored locations : 4 |
---|
S. No. | Parameter | Unit | Other Unit | Maximum Value | Minimum Value |
---|
(1.) | N(Nitrogen) | Kilogram per hectare | | 333.0 | 187.0 | (2.) | P(Phosphorus) | Kilogram per hectare | | 7.41 | 3.87 | (3.) | Electric Conductivity | Others | microS/cm | 438 | 142 | (4.) | pH | Others | 1:2.5 w:v | 7.68 | 6.21 | (5.) | K(Potassium) | Kilogram per hectare | | 142 | 34 | |
|
14.6. | Details of Ground Water Table: | (a)Range of Water Table Pre-Monsoon Season (Meters Below Ground Level (m bgl)) | From 2.90 To 7.4 | (b)Range of Water Table Post-Monsoon Season (Meters Below Ground Level (m bgl)) | From 1.34 To 2.4 | (c)Whether Ground Water Intersection will be there ? | Yes | (d)Upload Copy of Central Ground Water Authority Letter | Copy of Central Ground Water Authority Letter | (e)Letter No. | 0 | (f)Date of Issue | 06 Feb 2019 | |
|
15. Details of Water Requirement (During Operation) |
---|
S. No. | Source | Source Other | Required Quantity (Kilolitre per Day (Kld)) | Distance from Source | Copy of Permission from Competent Authority | Mode of Transport | Other Mode of Transport | Method of Water Withdrawal | Other Method of Water Withdrawal | Letter No. | Date of Issue | Permitted Quantity |
---|
(1.) | Surface | | 2204 | 0 | Copy of Permission Letter | Pipeline | | Others | Pumping | 35298 | 30 Sep 2009 | 3000 | (2.) | Others | Mine Water | 8500 | 0 | Not Appliacble | Pipeline | | Others | Pumping | 0 | 06 Feb 2019 | 0 | |
|
15.1. | (a)Whether Desalination is proposed | No | |
|
16. Waste Water Management(During Operation) |
---|
S. No. | Type/Source | Quantity of Waste Water Generated (Kilolitre per Day) | Treatment Capacity (Kilolitre per Day) | Treatment Method | Mode of Disposal | Other Mode of Disposal | Quantity of Treated Water Used in Recycling/Reuse (Kilolitre per Day) | Quantity of Discharged Water (Kilolitre per Day) |
---|
(1.) | Workshop | 1750 | 2000 | ETP | Reuse within the Plant & Recycling | | 1750 | | |
|
16.1. | (a)Total Waste Water Generation (Kilolitre per Day) | 1750 | (b)Total Discharged Water (Kilolitre per Day) | 0 | (c)Total Reused Water (Kilolitre per Day) | 1750 | |
|
17. Solid Waste Generation/Management |
---|
S. No. | Name of Waste | Item | Other Item | Quantity per Annum | Unit | Distance from Site(KM) | Mode of Transport | Other Mode of Transport | Mode of Disposal | Other Mode of Disposal |
---|
(1.) | STP/ETP Sludge | Industrial Waste | | 1680 | Tons | 0 | Road | | Others | Landfill/Farmyard Manure | (2.) | Overburden(Lump & Fine) | Industrial Waste | | 98552322 | Tons | 0 | Road | | Others | Dumping & Back-filling | (3.) | Oily Sludge | Industrial Waste | | 1360 | Tons | 0 | Road | | Others | Landfilling | |
|
|
18.1. Air Quality Impact Prediction |
---|
S. No. | Criteria Pollutants | Other Criteria Pollutants | Unit | Baseline Concentration | Distance GLC | Incremental Concentration | Total GLC | Prescribed Standard |
---|
(1.) | PM10 | | Microgram per Meter Cube | 75.30 | 0 | 8.98 | 84.3 | 100 | (2.) | SO2 | | Microgram per Meter Cube | 15.34 | 0 | 0 | 15.4 | 80 | (3.) | NOx | | Microgram per Meter Cube | 23.82 | 0 | 0 | 23.9 | 80 | (4.) | Others(Specify) | NA | NA | 0 | 0 | 0 | 0.01 | 0 | (5.) | PM2.5 | | Microgram per Meter Cube | 36.50 | 0 | 0.94 | 37.5 | 60 | |
|
18.2. Stack Details |
---|
S. No. | Source | Fuel | Stack Height(m) | Stack Diameter(m) | Pollutants | Other Pollutants | Emission (GLS) |
---|
(1.) | Nil | Nil | 0 | 0 | Others | NA | 0 | |
|
19. | Power Requirement: | (a)Quantity (Kilo Volt Amps (kVA)) | 36604.1817 | (b)Source | 220/33kV, Garjanbahal Substation | (c)Uploaded Copy of Agreement | Copy of Agreement | (d)Standby Arrangement (Details of DG Sets) | NA | (e)Stack Height (in m) | 0 | |
|
20. | Land Ownership Pattern: | (a)Forest Land (ha.) | 349.71 | (b)Private Land (ha.) | 0 | (c)Government Land (ha.) | 0 | (d)Revenue Land (ha.) | 0 | (e)Other Land (ha.) | 1940.74 | Total Land (ha.) | 2290.45 | |
|
21. | Present Land Use Breakup of the Study Area in Ha: | (a)Agriculture Area (ha.) | 1382.41 | (b)Waste/Barren Land (ha.) | 126.21 | (c)Grazing/ Community Land (ha.) | 131.79 | (d)Surface Water Bodies (ha.) | 48.23 | (e)Settlements (ha.) | 44.97 | (f)Industrial (ha.) | 0 | (g)Forest (ha.) | 349.71 | (h)Mangroves (ha.) | 0 | (i)Marine Area (ha.) | 0 | (j)Others (ha.) : Greenbelt /Future expn area/Solid Waste Management | 207.13 | Total (ha.) | 2290.4500000000003 | |
|
22. Land requirement for various activities |
---|
S. No. | Description of Activity / Facility / Plant / Others | Others | Land Requirement (ha.) | Remarks |
---|
(1.) | Quarry Area | | 1546.32 | -- | (2.) | OB Dump Area | | 386.08 | | (3.) | Others | Embankment | 28.30 | | (4.) | Safety Zone | | 18.59 | | (5.) | Built Up Area | | 311.16 | | |
|
|
23. | Ecological and Environmental Sensitivity (Within 10 Km):- WLS-Wild Life Sanctuaries; NPA-Notified Protected Area; ESAs-Eco Sensitive Areas; ESZs-Eco Sensitive Zones : | |
|
23.1. Details of Ecological Sensitivity : |
---|
S. No. | Details of Ecological Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Critically Polluted Area | Siarmal OCP | 0 | -- | (2.) | WLS | NA | 0 | NA | (3.) | NPA | NA | 0 | NA | (4.) | Corridors | NA | 0 | NA | (5.) | Wildlife Corridors | NA | 0 | NA | (6.) | ESAs | NA | 0 | NA | (7.) | ESZs | NA | 0 | NA | |
23.2. Details of Environmental Sensitivity : |
---|
S. No. | Details of Environmental Sensitivity | Other Details of Environmental Sensitivity | Name | Distance from the Project (Km) | Remarks |
---|
(1.) | Forest | | Garjanpahar RF | 0 | Adjacent to the Project | (2.) | Defence Installations | | NA | 0 | NA | (3.) | Others | NA | NA | 0 | NA | (4.) | Archaeological Sites | | NA | 0 | NA | |
|
23.3. | (a)Whether Noc / Permission from the competent authority is required? | No | (b)Whether NBWL recommendation is required? | No | |
|
24. | Forest Land: | Whether any Forest Land involved? | Yes | (a)Forests Clearance Status | Application for Forest Clearance yet to be submitted | (b)Legal Status of Forest Land | Reserved | |
|
25. | Tree Cutting: | (a)No. of Trees Cut for the Project (if Forest Land not Involved) | 0 | (b)Details of Tree Cutting and Planting of Trees | Not Applicable | |
|
26. | Land Acquisition Status: | (a)Acquired Land(Ha) | 2290.45 | (b)Land yet to be acquired(Ha) | 0 | (c)Status of Land acquisition if not acquired | 0 | |
|
27. | Rehabilitation and Resettlement (R&R): | (a)No. of Villages | 6 | (b)No. of Households | 2229 | (c)No. of PDFs (Project Displaced Families) | 2229 | (d)No. of PAFs (Project Affected Families) | 2953 | (e)Funds Allocated for R&R(in INR) (in Lacs) | 67804.13 | (f)Status of R&R | In-Progress | |
|
28. | Details of Presence of Schedule-I Species: | (a)Whether there is Presence of Schedule-I Species ? | No | (b)Whether conservation plan for Schedule-I Species has been prepared ? | No | (c)Whether conservation plan for Schedule-I Species has been approved by competent authority ? | No | |
|
29. | Details of Presence of Water Bodies in Core Area: | (a)Whether there is Presence of Water Bodies in Core Area ? | Yes | (i)Details of Water Bodies in Core Area | Chatterjhor Nalla | (b)Whether there is Diversion Required ? | Yes | (i)Details of Diversion Required | Straightening is required | (ii)Details of Study Conducted | Commence from the 25th year of Mining Operation | (c)Whether permission has been obtained from competent authority ? | No | |
|
30. | Details of Presence of Water Bodies in Buffer Area: | (a)Whether there is Presence of Water Bodies in Buffer Area ? | Yes | (i)Details of Water Bodies in Buffer Area | Iccha River | (ii)Direction of Water Bodies in Buffer Area | North East | (iii)Distance of Water Bodies in Buffer Area | 8 | |
|
31. | Manpower Requirement: | (a)Permanent Employment-During Construction | 3773 | (b)Permanent Employment-During Operation | 0 | (c)Temporary Employment- During Construction | 0 | (d)Temporary Employment- During Operation | 0 | (e)No. of working days | 330 | (f)Total Manpower | 3773 | |
|
32. | Green Belt in Ha: | (a)Total Area of Green Belt | 580.99 | (b)Percentage of Total Project Area | 25.37 | (c)No. of Plants to be Planted | 1450675 | (d)Funds Allocated for Plantation | 601555000 | (e)Uploaded Green Belt plan | Copy of Green Belt Plan | |
|
33. Project Benefits |
---|
S. No. | Type of Project Benefits | Details of Project Benefits |
---|
(1.) | Social | Improvement in Physical & Social infrastructure like roads, school building, provision of drinking water, community hall, plantation etc. Increase in employment potential & improvement in electrical power generation in rural areas.Overall economic growth of the country. | (2.) | Financial | Contribution to the Exchequer (both State & Central Govt). | |
|
34. CRZ Specific Details : Not Applicable |
35. Sector Specific Details For Coal Mining |
|
1. No. of Mineral(s) to be Mined : 1 |
---|
S. No. | Mineral(s) to be Mined | Major or Minor Mineral |
---|
(1.) | Coal | Major | |
|
2. | Mine Capacity in ROM (Run of Mine) | 50 | |
|
|
4. | Mining Plan: | (a)Approval Letter No. | MCL/SBP/CS/BD-198/Exct/2018/198 | (b)Date of Approval | 05 Feb 2018 | (c)Approved Letter | Copy of Approved Letter | (d)Approved By State Mining and Geology Department | MCL Board | (e)Approved Mining Lease Area | 2290.45 | (f)Approved Capacity | 50 | |
|
5. | Technical Details: | (a)Total Geological Reserves (Million Ton) | 1895.43 | (b)Mineable Reserves (Million Ton) | 1618.21 | (c)Extractable Reserves(Million Ton) | 1547.82 | (d)Percent(%) of Extraction | 95.65 | (e)Grade of Coal /Ore /Mineral | G 11 | (f)Stripping Ratio | 1.47 : 1 | (g)Category of Gaseousness (Only for Coal Mining, Others may Write NA) | NA | (h)Average Gradient(Degree) | 3-5 | (i)Mining Method | Opencast | (j)Life of Mine (Years) | 38 | |
|
6. | Details of Beneficiations: | (a)Whether it is proposed to install beneficiation plant/Coal washery within the mining lease area | No | (b)Whether it is proposed to install crusher within the mining lease area | No | |
|
7. | Details of Seams: | (a)Whether details of seam applicable | Yes | (b)No. of seams | 16 | (c)Thickness of seams to be worked on | 11.28 | (d)Maximum Thickness of Seams (metres) | 27 | |
|
8. | Details of Mining Lease: | (a)Mining Lease Area (in Hectare) | 2290.45 | (b)Whether obtained Letter of Intent (LOI) from the state government ? | No | (i)Reason thereof | Acquired under CBA (A&D) act 1957 | (c)Whether Lease Deed Executed ? | No | (i)Reason thereof | Acquired under CBA (A&D) act 1957 | (d)Whether Lease Deed Renewed ? | No | (i)Reason thereof | Acquired under CBA (A&D) act 1957 | |
|
9. | OB (Over Burden) Management: | (a) Details of External Dumps: | (i)No. of OB Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | (v)No. of year back fill up | | (b) Details of Internal Dumps: | (i)No. of Internal Dumps | | (ii)Total Area (in Hectare) | | (iii)Height (in meter) | | (iv)Quantity (in Million Cubic meter) | | |
|
10. | Details of Topsoil Management: | (a)Quantity of Topsoil excavated during the entire life of the mine (in Million Cubic metre) | 4.64 | (b)Quantity of Topsoil proposed for utilization for reclamation during the entire life of the mine (in Million Cubic metre) | 4.64 | (c)Quantity of Topsoil proposed for utilization for other activities during the entire life of the mine (in Million Cubic metre) | 0 | |
|
11. | Details of Final Mine Void: | (a)Area (in Hectare) | | (b)Depth (in meter) | | (c)Volume (in Million Cubic meter) | | |
|
12. | Details of Quarry: | (a)Final Void of 549.69 (hectare) at a Depth of 155 meter which is Proposed to be Converted into a Water Body. | (b)Total Quarry Area (ha) | 1546.32 | |
|
13. | Details of Transportation: | (a)In Pit/Underground to Surface | Part by dumper & part by Pit conveyor | (b)Surface to Siding/Loading | Conveyor | (c)Transportation / Conveyor Details | 100% by conveyor | |
|
|
14. Details of Land Usage (Pre-Mining) |
---|
S. No. | LAND USE | Other LAND USE | WITHIN ML AREA (Hectare) | OUTSIDE ML AREA (Hectare) | TOTAL (Hectare) |
---|
(1.) | GRAZING LAND | | 131.789 | 0 | 131.789 | (2.) | SURFACE WATER BODIES | | 48.227 | 0 | 48.227 | (3.) | FOREST LAND | | 349.709 | 0 | 349.709 | (4.) | WASTE LAND | | 126.216 | 0 | 126.216 | (5.) | SETTLEMENTS | | 44.970 | 0 | 44.97 | (6.) | OTHERS(Specify) | Solid Waste Management Area | 207.131 | 0 | 207.131 | (7.) | AGRICULTURE LAND | | 1382.408 | 0 | 1382.408 | |
TOTAL | 2290.45 | 0 | 2290.45 | |
|
15. Details of Land Usage (Post-Mining) |
---|
S. No. | LAND USE | Other LAND USE | Plantation (ha) | Water Body (ha) | Public Use (ha) | Undisturbed (ha) | Total |
---|
(1.) | GREEN BELT | | 93 | 0 | 0 | | 93 | (2.) | EXTERNAL OB DUMPS | | 386.08 | 0 | 0 | | 386.08 | (3.) | EXCAVATION/QUARRY | | 549.69 | 410 | 586.64 | | 1546.33 | (4.) | TOP SOIL STORAGE | | 0 | 0 | 0 | | 0 | (5.) | Other | Embankment | 18 | 0 | 10.3 | | 28.3 | (6.) | BUILT UP AREA (COLONY/OFFICE) | | 8 | 0 | 34.82 | | 42.82 | (7.) | VIRGIN AREA | | 0 | 0 | 193.93 | | 193.93 | (8.) | INTERNAL OB DUMPS | | 0 | 0 | 0 | | 0 | (9.) | ROADS | | 0 | 0 | 0 | | 0 | |
TOTAL | 1054.77 | 410 | 825.69 | 0 | 2290.46 | |
16. | Details of Reclamation: | Total Afforestation Plan shall be Implemented Covering of Mining.This will Include: | (a)External OB Dump(in hectare) | 386.08 | (b)Internal Dump(in hectare) | 996.63 | (c)Quarry(in hectare) | 1546.32 | (d)Safety Zone(in hectare) | 18.59 | (e)Final Void of 549.69 (hectare) at a Depth of 155 meter which is Proposed to be Converted into a Water Body. | (f)Density of Tree Plantation per ha (in no.) | 2500 | (g)Others in ha (such as Excavation Area along ML Boundary, along Roads and Infrastructure, Embankment Area and in Township Located Outside the Lease etc) | 78 | (h)Total afforestation plant (in hectare) | 915.07 | |
|
17. | Status of progressive Mining Closure Plan: | Details Not Applicable | |
|
18. Details of Actual Coal/ ORE Production vis-a-vis Sanctioned Capacity since the Inception: |
---|
S. No. | Financial Year | Sanctioned Capacity as per EC (MTPA) | Sanctioned Capacity as per CTO | Sanctioned Capacity as per approved mining plan | Actual Production | Excess Production Beyond the EC / CTO/ Mining Plan Sanctioned Capacity (MTPA) |
---|
(1.) | 2018 | 0 | 0 | 50 | 0 | 0 | |
|
36. | Details of Court Cases: | (a)Whether there is any Court Cases pending against the project and/or land in which the project is proposed to be set up ? | No | |
|
37. | Details of Direction Issued under Environment (Protection) Act / Air (Prevention & Control of Pollution)) Act / Water (Prevention & Control of Pollution) Act: | (a)Whether any Direction issued under EPA Act/Air Act/Water Act ? | No | |
|
38. | Details of EIA Consultant: | (a)Have you hired Consultant for preparing document? | Yes | (i)Accreditation No. | NABET/EIA/1720/RA 0092 | (ii)Name of the EIA Consultant | Central Mine Planning and Design Institute | (iii)Address | Gondwana Palace, Kanke Road,Ranchi,Jharkhand | (iv)Mobile No. | 8987788797 | (v)Landline No. | 0651223005 | (vi)Email Id | gmenv.cmpdi@coalindia.in | (vii)Category of Accreditation | A | (viii)Sector of Accreditation | Coal Mining | (ix)Validity of Accreditation | 01 Oct 2020 | (x)Uploaded Certificate of Accreditation certified by QCI/NABET | Copy of Certificate of Accreditation | |
|
|
Essential Detail Sought: |
---|
Sno. | EDS Letter | Remarks | Date of EDS |
---|
1. | NA | Project details in respect of OB dump, top soil management mine voids are to be mentioned against items 9(a), 9(b), 10 & 11 of column 35 in Form-2. Proposal for diversion of 349.71 ha of forest land to be submitted for consideration of the present proposal. Also inform about the present status of permission dated 30/9/2002 accorded by State Water Resources Department for drawl of 3 MLD of surface water, and the clearance required for ground water withdrawal. | 28 Mar 2019 | 2. | NA | The correction have been made as per the instruction received | 02 May 2019 | 3. | NA | - Project details in respect of OB dump, top soil management, mine voids, etc, are yet not reflected in Form-2.
- Proposal has been submitted after initial validity of 3 years of ToR dated 20/2/2015, and even after maximum allowable period of 4 years without any approval in this regard.
- The proposal for EC mentions project area as 2580.45 ha, against that of 2475.47 ha as per the said ToR and as such, not compliant with the ToR. | 11 May 2019 | 4. | NA | The correction have been made as per the instruction received | 11 May 2019 | 5. | NA | - In column 14&15 of Form-2, total project area is mentioned as 2287 ha i.e. less than the mine lease area of 2290.45 ha. Whereas, as per the revised ToR dated 9/7/2018, it is 2580.45 ha.
- No information made available regarding diversion of forest land of 349.709 ha. Column 24 of Form-2 shows that the required proposal is yet to be submitted. | 18 May 2019 | 6. | NA | The correction have been made as per the instruction received | 20 May 2019 | 7. | NA | a. Project details in respect of OB dump, top soil management mine voids are not mentioned against items 9(a), 9(b), & 11 of column 35 in Form-2 still.
b. Also inform about the present status of permission dated 30/9/2002 accorded by State Water Resources Department for drawl of 3 MLD of surface water, and the clearance required for ground water withdrawal.
c. Permission / Application for ground water extraction to CGWA
d. Permission / Application of diversion of nallah (Chatterjor nallah)
e. Certificate/validity of consultants used for baseline data (Ecomen laboratories Pvt Ltd) and for flora/fauna (VRDS consultants)
f. Status of Stage-I FC of said forest land involved for non-forestry activity.
g. Fuel Supply Agreement is no enclosed in Form-2 | 11 Jun 2019 | 8. | NA | The correction have been made as per the instruction received | 15 Jul 2019 | |
Additional Detail Sought: |
---|
Sno. | ADS Letter | Remarks | Date of ADS |
---|
1. | ADS Reply Letter | The reply to the ADS dated 08.04.2022 is hereby attached for your kind consideration and grant of Environment Clearance. | 22 Apr 2022 | 2. | ADS Raise Letter | Please see the attachment | 08 Apr 2022 | 3. | ADS Reply Letter | Reply to the ADS dated 14.09.2020 by the EAC(MoEF&CC) is hereby attached for kind consideration. | 11 Feb 2022 | 4. | NA | The EAC after deliberation observed that the various deficiency in filling of Form #2 on PARIVESH Portal and further sought compliance on below mentioned details:
· Incomplete/incorrect details submitted on PARIVESH Portal shall be corrected by project proponent.
· Permission for Stage-I Forest Clearance for forest land of 349.705 involved in the project.
- Project proponent shall provide year wise production and OB removal plan along with details of land reclaimed and restored. The plan shall contain the year-wise details of land disturbed on account of excavation, internal and external dumping, and land reclaimed and restored.
· Mine Closure plan should be as per Ministry of Coal latest guidelines of 2019
· Drainage map of the area shall be shown in topo sheet and further zero liquid discharge with water balance should be presented
· PP shall study the impact Assessment on the proposed road route on receptors for environment parameters of PM10, PM2.5, SOX and NOX
· Permission of extraction of ground water from Central Ground Water Authority
· Clarification from District Forest Officer (DFO) regarding no presence of schedule I species in the project area and buffer zone shall be submitted. Distance from Wildlife/National Sanctuary should be substantiated by DFO.
· Provision of alternate grazing land shall be proposed by project proponent
· Quantitative Conclusion / Impact / Mitigation measures should be clearly presented of Carrying capacity study.
· Heavy metals shall be analyzed in surface water
In view of above the proposal was deferred for compliance of above points | 14 Sep 2020 | 5. | ADS Reply Letter | The reply to the Additional Details Sought (ADS) by the Member Secretary on 23/09/2019 is hereby attached. | 10 Jul 2020 | 6. | NA | The EAC, after
deliberations and especially in view of the project site in Ib Valley (having
CEPI score 66.35) covered under the said orders of NGT, preferred not to take
the proposal forward for the present, but to seek advice of the Ministry for
appropriate course of action in such cases. The Committee also opined that in
case, such proposals are to be considered on merits, environmental conditions
and other stringent measures would have to be looked into comprehensively in complete
perspective and in consultation with | 23 Sep 2019 | |
| Undertaking |
| I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief. And I am aware that if any part of the data and information found to be false or misleading at any stage, the project will be rejected and clearance given, if any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity/ construction/ expansion has since been taken up. |
| Name of Applicant | Satish Chandra Tripathi | Designation | Project Officer, Basundhara-Garjanbahal Area, MCL | Name of Company (Applicant Name should not be given here) | A.K.Singh | Address | Mahanadi Coalfields Limited
Office of the General Manager, B-G Area
P.O. Basundhara
Dist: Sunderg |
|