Form-4
APPLICATION FOR AMENDMENT IN ENVIRONMENTAL CLEARANCE
(To be filled up by User Agency)
Proposal No. : IA/MP/THE/105718/2019
(a) Name of the project : Gadarwara Super Thermal Power Project, Stage-I (2x800 MW)
(b) Name of Company / Organisation. : NTPC Limited
(c) Registered Address. : NTPC Engineering Office Complex Sector-24, Noida
(d) Legal Status of the Company. : Central PSU
(e) Joint Venture (Yes/No) : No | 2. | Address for the Correspondence |
(a) Name of Applicant. : Vijay
(b) Designation (Owner/Partner/CEO) : Head of Deptt Env Engg
(c) Address :- NTPC Engineering Office Complex
Sector-24, Noida
State : Uttar Pradesh
District : Gautam Buddha Nagar
Town / Village : Noida
(d) Pin Code : 201301
(e) Email : environment.ntpc@gmail.com
(f) Telephone no : 2410331
(g) Fax no : 24105060
(h) Mobile no : 9650991509
(i) Contact Person. : Vijay
(j) Website (if any) : No | 3. | Category of the Project/Activity as per Schedule of EIA Notification,2006 |
(a). Major Activity. : 1(d) Thermal Power Plants
Minor Activity : No
Major Sub Activity. : No
Minor Sub Activity : No
(b). Category : A
Reason for applicant at central level/state level(in case of B1 and B2 projects): No
(a) Plot No/Survey No/Khasra No : Plot No. 257, 258, 259, 271, 272, 265, 238
(b) Village : Gangai & Umariya
(c) Tehsil : Gadarwara
(d) District : Narsimhapur
(e) State : Madhya Pradesh
(f) Pin Code : 487770
(g) Bounded Latitudes (North) : Yes
From : Degree:22, Minutes : 51, Second :06
To : Degree:22, Minutes : 52, Second :30
(h) Bounded Longitudes (East) : Yes
From : Degree:78, Minutes : 51, Second :24
To : Degree:78, Minutes : 52, Second :42
(i) Survey of India Topo Sheet No : 55 J/13 | 5 | Details of Environment Clearance |
(a) Project Name : Gadarwara Super Thermal Power Project, Stage-I (2x800 MW)
(b) MoEF&CC / SEIAA File No : J-13012/125/2009-IA.II(T)
(c) Date of issue of EC : 22/03/2013 (d) Uploaded EC letter (PDF Only):
| 6 | Details of Consent to Operate |
(i) Whether Consent to operate obtained (Yes/No) ? : Yes (ii) Uploaded copies of all Consent to operate obtained since inception:
(iii)Date of issue : 30/01/2019
(iv)Valid Upto: 31/12/2019
(v)File No : No
(vi)Application No : No (vii)Uploaded copy of Consent to operate valid as on Date:
Amendment in Configuration/ Amendments in Clearance condition/ Other (specify) : No amendment in configuration is envisaged.
As such there is not any condition w.r.t CSR-CD in CT | 8 | Details of Product (as per the approved EC) |
| Details of Products |
|---|
| S.no | Product / Activity (Capacity/ Area). | Quantity | Unit | Mode of Transport/ Transmission of Product |
|---|
| 1 | Electricity Generation | 1600 | MW | BY PGCIL TRANSMISSION LINES |
| 9 | Details of Configuration (Multiple Entries Allowed) |
| Details of Configurations |
|---|
| S.no | Plant/ Equipment/ Facility | Existing Configuration | Proposed Configuration | Final configuration after Amendment | Remarks if Any |
|---|
| 1 | Thermal Power Plant | 2x800 MW | 2x800 MW | 2x800 MW | Nil |
Reason for Amendment : Reason for EC amendment is detailed in the Application letter dated 17.05.2019 along with its Annexures. | 11 | Any Other Amendment required |
| Any Other Amendment Required |
|---|
| S.no | Reference of Approved EC | Description as per Approved EC | Description as per Proposal. | Remarks |
|---|
| 1 | EC Specific Condition No. (xiii) | An amount of Rs. 45.60 Crores as one time investm | The current proposal is for seeking amendment in E | EC amendment for Specific Condition No. (xiii) is |
| 12 | Details of EIA Consultant |
Have you hired Consultant for preparing document (Yes/No) ? : No
(i)Reason for not engaging the Consultant : As the current proposal is only for seeking amendment in Environment Clearance (EC) condition regarding provision for recurring annual fixed expenditures towards CSR activities throughout life of the project. Therefore, requirement of consultant is not envisaged. | 13. | Document to be Attached |
(a) Uploaded addendum to EIA/EMP Report : No Data
(b) Uploaded Copy of revised -Feasibility Report /Detailed Project Report (DPR) / Detailed Engineering Report / Detailed Conceptual Plan / Approved Mining Plan (in case of mining proposals) : No Data
(c) Upload Copy of final Layout Plan : No Data (d)Uploaded Cover Letter duly signed by the project proponent or authorized person:
(e)Uploaded a copy of authorization duly signed by the project proponent in support of the person making this application on behalf of the User Agency:
(f)Uploaded Additional File, If any : No Data
(g)Uploaded Proposal Presentation : No Data | Details of State of the project |
|---|
| S.no. | EDS Sought Date | EDS Sought | Letter |
|---|
| NIL |
| Additional Detail Sought |
|---|
| S.no. | Ads Letter | Remarks | Date of Submission |
|---|
| 1. | Additional Information | Please provide the information as per attached letter. | 17 Jan 2020 |
| 2. | Additional Information | The updated details of expenditure incurred for implementation of CSR-CD activities for Gadarwara STPP, Stage-I is herewith attached. | 31 Jan 2020 |
(a): I hereby give undertaking that the data and information given in the application and enclosures are true to be best of my knowledge and belief and I am aware that if any part of the data and information found to be false or misleading at any stage, The project will be rejected and clearance given, If any to the project will be revoked at our risk and cost. In addition to above, I hereby give undertaking that no activity / construction / expansion has since been taken up. (b)Name : Vijay Prakash (c)Designation: Head of Deptt Env Engg (d)Company: NTPC Limited (e)Address: NTPC Engineering Office Complex Sector-24, Noida