APPENDIX I | (See Paragraph-6) | FORM 1M | | Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any' at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document. | (I)Basic Informations | | (i). | Name of the Mining Lease site | Sri V R Parameswaran |
| (ii). | Location / site (GPS Co-ordinate) | N10degree24’15.308” to N10degree24’13.635”
E76degree21’14.486” to E76degree21’17.366”Annexure-GPS file |
| (iii). | |
Type of Lease | Indivisual Area | Size of the Mining Lease (in ha.) | 0.4734 ha. | | | (iv). | Capacity of the Mining Lease (TPA) | 22513 | | (v). | Period of Mining Lease | 4 | | (vi). | Expected cost of the Project | 29 | | (vii). | Have you hired Consultant/Registered Qualified Person(RQP) for preparing document? | Yes | Accreditation No. | 73 | Name of Consultant/RQP | cyriac Joseph, Global Environment & Mining Service | Address | HBR layout 5th block 5th main 1st cross 1st stage Bangalore | Mobile No. | 9880788836 | Landline No. | 25432447 | Email Id | gems.blr@globalmining.in | | | (II) | Environmental Sensitivity | S.No | Areas | Distance in kilometer / Details | | | 1. | (i). Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms. | 3 km |
| 2. | (ii). Nearest Infrastructural along with distance in kms | 25 km | | (iii). Nearest Railway Line along with distance in kms | 25 km | | (iv). Nearest National Highway along with distance in kms | 20 km | | (v). Nearest State Highway along with distance in kms | 10 km | | (vi). Nearest Major District Road along with distance in kms | 6 km | | (vii). Nearest Any Other Road along with distance in kms | 0.11 km | | (viii). Nearest Electric transmission line pole or tower distance in kms | 0.1 km | | (ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms | 6 km | | (x). Nearest In-take for drinking water pump house distance in kms | 10 km | | (xi). Nearest In-take for Irrigation canal pumps distance in kms | 40 km |
| 3. | Areas protected under international conventions, national or local legislation for their ecological, landscape, cultural or other related value | None within 5 Kms of the project site | 4. | Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests | Forest: Kanakamala forest 6 Km from project site
Pond: Panchayath pond- Uppuzhy, 4.00Km
River: Kurumalipuzha, 3.00Km | 5. | Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration | None within 5 Km of the project site | 6. | Inland, coastal, marine or underground waters | Kodungaloor Coast 40.0Km from the Project Site | 7. | State, National boundaries | Tamilnadu State boundary is about 50 Kms (E) from the project site. | 8. | Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas | National Highway: Thrissur-Ernakulam Road, (NH47), 20Km
State high way: Irinijalakuda Road, SH-61 , 10.00 Km | 9. | Defence installations | None within 5 Km of the project site | 10. | Densely populated or built-up area, distance from nearest human habitation | The nearest human settlements is at Nooluvally Village is located at 0.82 km away from the mine | 11. | Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) | Hospital: Govt Hospital ,Padichira – 4Kms
School : Mupliyam Govt High School,6.00Km
Church : Assumption Chruch, Mupliyam,1.50Km
Mosque : Juma Masjid,Varandarappilly 2.50Km
Temple : .Mathikunnu Temple, Thalore, 9.0Km | 12. | Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) | None within 5 Km of the project site | 13. | Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) | Not applicable, since this is Fresh proposal | 14. | Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) | No, Lease area is not susceptible to natural hazard, as there is no history of such incidents. | 15. | Is proposed mining site located over or near fissure/fracture for ground water recharge? | No |
| 16. | Whether the proposal involves approval or clearance under the following Regulations or Acts namely? | | (a). | The Forest (Conservation) Act,1980? | No | | | (b). | The Wildlife (Protection) Act,1972? | No | | | (c). | The Coastal Regulation Zone (C.R.Z) notification,2011? | No |
| | | | 17. | Is forest land involved (ha)? | No | |
| 18. | Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up? | No |
|
| 19. | New/Expansion/Modernization | New | Proposal Number | DIA/KL/MIN/15780/2018 | File Number | B1-9864/18 | Date of Apply EC | 12 Jun 2018 |
| |
|