APPENDIX I
(See Paragraph-6)
FORM 1M
Note : If space provided against any parameter is inadequate,Kindly upload supporting document under 'Additional Attachments if any'  at the last part of the Form 1M. Please note that all such Annexures must be part of single pdf document.
(I)Basic Informations
S.No.Item Details
(i).Name of the Mining Lease site KHAPRAJOLA STONE MINE
(ii).Location / site (GPS Co-ordinate) N 24 35 02.80 TO 24 35 55.00 & E 87 50 41.50 TO 87 50 31.10
Annexure-GPS file      
(iii).
Type of LeaseIndivisual Area
Size of the Mining Lease (in ha.)3.32 ha.
(iv).Capacity of the Mining Lease (TPA) 222345
(v).Period of Mining Lease 3
(vi).Expected cost of the Project 29.75
(vii).
Have you hired Consultant/Registered Qualified Person(RQP) for preparing document?Yes
Accreditation No.UDP/306/2006/A 
Name of Consultant/RQPAWADHESH KUMAR SINHA
Address B-31, VASHUNDHARA GARDEN, HARIHAR SINGH ROAD, BARIATU, RANCHI, JHARKHAND
Mobile No.9430361771
Landline No.06518775
Email Idsinhaawadhesh@gmail.com
(II) Environmental Sensitivity
S.No Areas Distance in kilometer / Details
1. (i).  Nearest rail or road bridge over the concerned river,rivulet,nallah etc. in kms.  13 km
2. (ii). Nearest Infrastructural along with distance in kms  4.65 km
(iii). Nearest Railway Line along with distance in kms  3.15 km
(iv). Nearest National Highway along with distance in kms  12.5 km
(v). Nearest State Highway along with distance in kms  6.7 km
(vi). Nearest Major District Road along with distance in kms 6.7 km
(vii). Nearest Any Other Road along with distance in kms  1 km
(viii). Nearest Electric transmission line pole or tower distance in kms  0 km
(ix). Nearest Canal or check dam or reservoirs or lake or ponds distance in kms  10 km
(x). Nearest In-take for drinking water pump house distance in kms  10 km
(xi). Nearest In-take for Irrigation canal pumps distance in kms  10 km
3. Areas protected under international conventions, national or local legislation for  their ecological, landscape, cultural or other related value
Not Applicable
4. Areas which are important or sensitive for ecological reasons - Wetlands, watercourses or other water bodies, coastal zone, biospheres, mountains, forests Ganga River-15 KM, Open Mixed Jungle-2.5 KM
5. Areas used by protected, important or sensitive species of flora or fauna for breeding, nesting, foraging, resting, over wintering, migration No such schedule I flora fauna are found in the project site.
6. Inland, coastal, marine or underground waters No Inland, coastal, marine or underground waters nearby the project site. ML area is not coming in these zones
7. State, National boundaries i)state Boundary with West Bengal-5.5Km East ii)National Boundary with Bangladesh-18.90 Km NE
8. Routes or facilities used by the public for access to recreation or other tourist,pilgrim areas No such Pilgrims are situated nearby the project area.
9. Defence installations No such defense area /installations are present.
10. Densely populated or built-up area, distance from nearest human habitation Pakpara-1.5, Malahari-0.85
11. Areas occupied by sensitive man-made land uses (hospitals, schools, places of worship,community facilities) i)Dr N C Dutta memorial hospital-50 Km south ii) Mohurapur High school- 10 Km south iii) KKM college- 5.5 Km north iv) Gawalpara Mosque- 4.50 Km north
12. Areas containing important, high quality or scarce resources.(ground water resources,surface resources,forestry,agriculture,fisheries,tourism,minerals) No such things present
13. Areas already subjected to pollution or environmental damage.(those where existing legal environmental standards are exceeded) No Such conditions are there for the proposed area
14. Areas susceptible to natural hazard which could cause the project to present environmental problems (earthquakes, subsidence, landslides, erosion, flooding or extreme or adverse climatic conditions) Area falls under Seismic Zone-III, i.e. moderately damage risk zone. Other natural hazard is also not expected because of the location of the project.
15.
Is proposed mining site located over or near fissure/fracture for ground water recharge?No
16.
Whether the proposal involves approval or clearance under the following Regulations or Acts namely?
(a).
The Forest (Conservation) Act,1980?No
(b).
The Wildlife (Protection) Act,1972?No
(c).
The Coastal Regulation Zone (C.R.Z) notification,2011?No
17.
Is forest land involved (ha)?No
18.
Whether there is any litigation pending against the project and/or land in which the project is proposed to be set up?No
19.
New/Expansion/ModernizationNew
Proposal NumberDIA/JH/MIN/14524/2018
File Number03/2018
Date of Apply EC13 Apr 2018
Details of State of the project
S.No. State Name District Name Tehsil Name
(1.)JharkhandPakaurPakaur
(III) EC Attachments
1 Uploaded PFR (Pre Feasibility Report) File Annexure-PFR file
2 Uploaded Approved Mining Plan File Annexure-Approved Mining Plan file
3 Uploaded District survey report Annexure-District Survey Report
4 Uploaded Cover Letter Annexure-Cover Letter
Uploaded Additional attachments, if any
S.No. Attached File Date of Submission
(1.)DRAWING13 Apr 2018
(IV) Undertaking
The aforesaid application and documents furnished here with are true to my knowledge.
(IV).(i)
NameSHYAM MANDHYAN
DesignationOWNER
Company SHYAM MANDHYAN
AddressVILL- KHAPRAJOLA, P.O.- PAKUR, P.S.- PAKUR
Print