BY SPEED POST
No.
J-13011/24/2008-IA.II(T)
Government of India
Ministry of Environment
& Forests
Paryavaran Bhawan
CGO Complex, Lodi Road
New Delhi-110 003
Dated : 11th July, 2008
To
M/s Talwandi Sabo Power Limited
PSEB Building, The Mall
Patiala - 147 001
Sub: 2000 MW (4x500 MW) Talwandi Sabo Thermal
Power Project near Banawala,
District Mansa, Punjab by M/s Talwandi Sabo Power Ltd - Environmental Clearance regarding.
**********
Sir,
The
undersigned is directed to refer to your communication no. 65 dated 11th March,
2008 regarding the subject mentioned above. Subsequent information furnished
vide letter dt. 9.5. 2008 has also been considered.
2. It is
noted that the proposal is for grant of environmental clearance for setting up
of a 2000 MW (4x500 MW) thermal power project near village Banawala, District
Mansa, Punjab. The units will be of 500
MW each based on sub critical technology. Coordinates of the site are 290
53’ 31” to 290 56’ 10” N and 750 12’ 53” to 750
15’ 11” E. The land requirement is
2105 acres including water reservoir, CHP area and greenbelt area. Coal
requirement is estimated as 8.7 million TPA, which will be obtained from MCL
mines in Ib Valley. Coal will be
transported by rail. Water requirement
is estimated as 7100 m3/hr, which will be obtained from Bheni sub-branch of
Kotla canal branch at a distance of 20 km.
Auxiliary fuel i.e. LDO and HFO/LSHS will be required for start up and flame
stabilization purpose. Ground water
level in the area varies from 2.92 mbgl to 12.77 mbgl. Orchards are reported in the vicinity of the
area. There will be 10440 PAPs of 1746
households due to this project. The
public hearing for the project has been held on 29.1.2008. No ecologically sensitive area is located
within a radius of 10 km from the plant boundary. Total cost of project is Rs
8000.00 crores, which includes Rs. 461.00 crores for environmental protection
measures.
3. The
proposal has been considered by the Expert Appraisal Committee for Thermal
Power and Coal Mine projects and Ministry of Environment & Forests hereby
accords environmental clearance to the said project under the provisions of
Environment Impact Assessment Notification, 2006 subject to implementation of
the following terms and conditions:-
(i) The total land requirement for the
project shall be restricted to 2105
acres.
(ii)
Requisite quantity of coal for
the ultimate capacity shall be obtained before commissioning the project.
(iii) Sulphur and ash contents in the coal to
be used in the project shall not exceed
0.5% and 34% respectively.
(iv) A bi-flue stack of 275 m
height shall be provided with continuous online monitoring equipments for Sox,
NOx and Particulate. Exit velocity of flue gases shall not be less than 25
m/sec.
(v) High efficiency Electrostatic Precipitator
(ESP) shall
be installed to ensure that particulate emission does not exceed 50 mg/Nm3.
(vi) Space provision shall be kept for retrofitting of
FGD, if required at a later date.
(vii) Adequate dust extraction system such
as cyclones/ bag filters and water spray system in dusty areas such as in coal
handling and ash handling points, transfer areas and other vulnerable dusty
areas shall be provided.
(viii) Fly ash shall be collected in dry form and
storage facility (silos) shall be provided.
Fly ash shall be used in a phased manner as per provisions of the
notification on Fly Ash Utilization issued by the Ministry in September, 1999 and its amendment. By
the end of 9th year full fly ash utilization should be ensured.
Unutilized fly ash shall be disposed off in the ash pond in the form of High Concentration Slurry and the
bottom ash in conventional slurry mode.
(ix)
Ash pond shall be lined with HDPE lining. Adequate safety measures shall
also be implemented to protect the ash dyke from getting breached.
(x)
Closed cycle cooling system with cooling towers shall be provided. COC of at least 5 shall be adopted and the
effluents shall be treated as per the prescribed norms.
(xi)
The treated effluents conforming to the prescribed standards shall be
re-circulated and reused within the plant.
There shall be no discharge outside the plant boundary except during
monsoon. Arrangements shall be made that effluents and storm water do not get
mixed.
(xii)
A sewage treatment plant shall be provided and the treated sewage shall
be used for raising greenbelt/plantation.
(xiii)
Rain water harvesting should be adopted. Central Groundwater
Authority/ Board shall be consulted for finalization of appropriate rain water
harvesting technology within a period
of three months from the date of clearance and details shall be furnished.
(xiv)
Adequate safety measures shall be provided in the plant area to
check/minimize spontaneous fires in coal yard, especially during summer season.
Copy of the these measures with full
details along with location plant
layout shall be submitted to the Ministry as well as to the Regional Office of
the Ministry at Chandigarh.
(xv)
Storage facilities for liquid fuel such as LDO and/ HFO/LSHS shall be
made in the plant area where risk is minimum to the storage facilities. Disaster Management Plan shall be prepared to meet any eventuality in
case of an accident taking place. Mock drills
shall be conducted regularly and based on the same, modifications required, if
any shall be incorporated in the DMP.
(xvi)
Regular monitoring of ground water in and around the ash pond area shall
be carried out, records maintained and
six monthly reports shall be furnished to the Regional Office of this Ministry.
(xvii) A green belt of adequate width and density
shall be developed around the plant periphery covering about 1/3 of the project
area preferably with local species.
(xviii) Activities under CSR shall be enhanced with proper financial
allocation. Details of these activities shall also be submitted to the Regional
Office of the Ministry, SPCB and the Ministry.
(xix)
First aid and sanitation arrangements shall be made for the drivers and
other contract workers during construction phase.
(xx)
Leq of Noise
levels emanating from turbines shall
be limited to 75 dBA. For people working in the high noise area, requisite personal protective equipment like
earplugs/ear muffs etc. shall be provided. Workers engaged in noisy areas such
as turbine area, air compressors etc
shall be periodically examined to
maintain audiometric record and for treatment for any hearing loss including
shifting to non noisy/less noisy areas.
(xxi)
Regular monitoring of ground level concentration of SO2, NOx,
SPM and RSPM shall be carried out in the impact zone and records
maintained. If at any stage these
levels are found to exceed the prescribed limits, necessary control measures
shall be provided immediately. The
location of the monitoring stations and frequency of monitoring shall be
decided in consultation with SPCB. Periodic reports shall be submitted to the
Regional Office of this Ministry.
(xxi) The
project proponent shall advertise in at least two local newspapers widely
circulated in the region around the project, one of which shall be in the
vernacular language of the locality concerned within seven days from the date of this clearance letter, informing
that the project has been accorded environmental clearance and copies of
clearance letter are available with the State Pollution Control Board/Committee
and may also be seen at Website of the Ministry of Environment and Forests at http://envfor.nic.in.
(xxii) A separate environment management cell with
qualified staff shall be set up
for implementation of the
stipulated environmental safeguards.
(xxiii) Half yearly report on the status of
implementation of the stipulated conditions
and environmental safeguards shall be
submitted to this Ministry/ Regional Office/CPCB/SPCB.
(xxiv) Regional
Office of the Ministry of Environment & Forests located at Chandigarh will
monitor the implementation of the stipulated conditions. A complete set of
documents including Environmental Impact Assessment Report and Environment
Management Plan along with the additional information submitted from time to
time shall be forwarded to the Regional Office for their use during monitoring.
(xxv) Separate
funds shall be allocated for implementation of environmental protection
measures along with item-wise break-up. These cost shall be included as part of
the project cost. The funds earmarked for the environment protection measures
shall not be diverted for other purposes and year-wise expenditure should be
reported to the Ministry.
(xxvi) The
project authorities shall inform the Regional Office as well as the Ministry
regarding the date of financial closure and final approval of the project by
the concerned authorities and the dates of start of land development work and
commissioning of plant.
(xxvii) Full
cooperation shall be extended to the Scientists/Officers from the Ministry /
Regional Office of the Ministry at Chandigarh /the CPCB/the SPCB who would be
monitoring the compliance of environmental status.
4. The Ministry of Environment and Forests
reserves the right to revoke the clearance if conditions stipulated are not
implemented to the satisfaction of the Ministry. MOEF may impose additional
environmental conditions or modify the existing ones, if necessary.
5. The
environmental clearance accorded shall be valid for a period of 5 years to start of production operations by the power
plant.
6. In case of any deviation or alteration in
the project proposed from those submitted to this Ministry for clearance, a
fresh reference should be made to the Ministry to assess the adequacy of the
condition(s) imposed and to add additional environmental protection measures
required, if any.
7. The
above stipulations would be enforced among others under the Water (Prevention
and Control of Pollution) Act, 1974, the Air (Prevention and Control of
Pollution) Act, 1981, the Environment (Protection) Act, 1986 and rules there
under, Hazardous Wastes (Management and Handling) Rules, 1989 and its
amendments, the Public Liability Insurance Act, 1991 and its amendments.
8. Any appeal against this environmental
clearance shall lie with the National Environment Appellate Authority, if
preferred, within 30 days as prescribed under Section 11 of the National
Environment Appellate Act, 1997.
(Dr. S. BHOWMIK)
ADDITIONAL DIRECTOR
Copy to:-
1. The
Secretary, Ministry of Power, Shram Shakti Bhawan, Rafi Marg, New Delhi - 110001.
2. The Secretary, Science, Technolgy & Environment Deptt., Government of Punjab,
Punjab Civil Secretariat,
Chandigarh.
3. The
Chairman, Central Electricity Authority, Sewa Bhawan, R.K. Puram, New Delhi-110066.
4. The Chairman, Punjab Pollution Control Board, Vata Varan
Bhawan,Nabha Road, Patiala, Punjab-147 001
- with a request to display a copy of the clearance letter at the Regional
Office, District Industries Centre and Collector’s office for 30 days.
5. The Chairman, Central Pollution Control
Board, Parivesh Bhawan, CBD-
cum-Office
Complex, East Arjun Nagar, Delhi-110032.
6. The Chief Conservator of Forests, Northern Regional Office,
Ministry of Environment & Forests, SCO 132-133, Sector 34-A,
Chandigarh-160022.
7. The Director (EI), MOEF.
8.
Guard file.
9.
Monitoring file.
(Dr. S.
BHOWMIK)
ADDITIONAL DIRECTOR