BY SPEED POST

F. No. J-13011/34/2008-IA.II(T)

Government of India

Ministry of Environment & Forests

                                                                    

                   Paryavaran Bhawan

CGO Complex, Lodi Road

New Delhi-110 003

 

 Dated : 27   Feb, 2009     

To

M/s M.P. Power Generating Co. Ltd

Shed No. 1&2, Rampur

Jabalpur- 482 008

 

Subject: 2x250 MW Unit 10 & 11 Satpura Thermal Power Station at Sarni, District Betul, Madhya Pradesh by M/s MPPGCL- Environmental Clearance   regarding.

 Sir,         

The undersigned is directed to refer to your communication no.   07/01/STPS/Extn.II/7106/841 dt. 11.4.2008 regarding the subject mentioned above. Subsequent information furnished vide letters dt. 2.9.2008 17.12.200811.2.2009 have also been considered.

 

2.       It is noted that the proposal is for grant of environmental clearance for setting up of a 2x250 MW extension units 10 & 11 at Satpura Thermal Power Station, Sarni, District Betul, Madhya Pradesh.   The land requirement for the main plant and auxillary facilities is 57.86 ha, which is available within the existing plant boundary, however, 136 ha of land is to be acquired for the ash disposal area which includes 19 ha for alternate road in lieu of the existing roads to be included in the ash pond area. No forestland is involved in the land to be acquired for the proposed unit. Coal requirement will be 2.576 million metric tones per annum at 80% PLF. Water requirement is estimated as 1855 m3/hr, which will be met from Satpura Reservoir.   It was also stated that about Rs 1.0 crore per year will be spent on CSR activities.   Public hearing was held on 27.2.2008 . There will be 69 land oustees families due to this project extension. No National Park and Wildlife Sanctuary is located within 10 Km from project area. Total cost of the project is Rs.    2637.00 crores which includes Rs. 140.00 crores for  environmental protection measures.

 

3.       The proposal has been considered by the Expert Appraisal Committee for Thermal Power and Coal Mine projects  and Ministry of Environment & Forests hereby accords environmental clearance to     the said project under the provisions of Environment Impact Assessment Notification, 2006 subject to implementation of the following terms and conditions:-         

        

 (i)      The existing unit no. 1 ? 5 shall be de-commissioned within one year of the commissioning of the proposed units.  The ESPs relating to units no. 6 ? 9 shall also be renovated, so as to ensure       particulate emission from these units within 150 mg/Nm3.  A time bound action plan in this regard shall be prepared and submitted within 3 months from the issue of this letter. 

 

(ii)      The total land requirement for all the activities of the project shall not exceed 187.86 ha. 

 

(iii)       Sulphur and ash contents in the coal to be used in the project shall not exceed 0.56% and 44% respectively at any given time. In case of variation of coal quality at the time of issue of LOA, a fresh reference shall be made to MOEF for suitable amendments to environmental clearance conditions wherever necessary.

 

(iv)      A bi-flue stack of 275 m height shall be provided with continuous online monitoring equipments for Sox, NOx, Particulate matter and Hg. Exit velocity of flue gases shall not be less than 22 m/sec.

 

(v)        High efficiency Electrostatic Precipitator (ESP) shall be installed to ensure that particulate emission does not exceed 50 mg/Nm3.

 

 (vi)      Space provision shall be kept for retrofitting of FGD, if required at a later date.

 

(vii)      Adequate dust extraction system such as cyclones/ bag filters and water spray system in dusty areas such as in coal handling and ash handling points, transfer areas and other vulnerable dusty areas shall be   provided.

 

(viii)      Fly ash shall be collected in dry form and storage facility (silos) shall be provided.  The project authorities should adhere to the provision stipulated in the fly ash notification of September, 1999 and as amended in August, 2003 in regard to fly ash utilization.  Unutilized fly ash and bottom ash shall be disposed off in the ash pond. 

 

(ix)       Ash pond shall be lined with impervious lining. Adequate safety measures shall also be implemented to protect the ash   dyke from getting breached.

 

(x)        The old ash pond shall be rehabilitated.

 

(xi)     Closed cycle cooling system with Induced draft cooling towers shall be provided.  COC of at least 5 shall be adopted and the effluents shall be treated as per the prescribed norms.

 

(xii)     The treated effluents conforming to the prescribed standards shall be re-circulated and reused within the plant.  There shall be no discharge outside the plant boundary except during monsoon. Arrangements shall be made that effluents and storm water do not get mixed.

 

 (xiii)    A sewage treatment plant shall be provided and the treated sewage shall be used for raising greenbelt/plantation.

 

 (xiv)   Rain water harvesting should be adopted. Central Groundwater Authority/ Board shall be consulted for finalization of appropriate rain water harvesting   technology within a period of three months from the date of clearance and details shall be furnished.

 

 (xv)   Adequate safety measures shall be provided in the plant area to check/minimize spontaneous fires in coal yard, especially during summer season. Copy of the   these measures with full details along with  location plant layout shall be submitted to the Ministry as well as to the Regional Office of the Ministry at    Bhopal.

 

 (xvi)   Storage facilities for auxillary liquid fuel such as LDO and/ HFO/LSHS shall be made in the plant area where risk is minimum to the storage facilities.  Disaster Management Plan shall be prepared to meet any eventuality in case of an accident taking place. Mock drills shall be conducted regularly and based on the same, modifications required, if any shall be incorporated in the DMP. Sulphur content in the liquid fuel will not exceed 0.5%.

 

 (xvii)    Provision shall be made for the  housing of construction labour within the site  with all necessary infrastructure and facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking water, medical health care, crèche etc. The housing may be in the form of temporary structure to be removed after the completion of the project.

 

 (xviii)  Regular monitoring of ground water in and around the ash pond area   including heavy metals (Hg,Cr,As,Pb)  shall be carried out, records   maintained and six monthly reports shall be furnished to the Regional Office of this Ministry.

 

 (xix)    A green belt of adequate width and density shall be developed around the plant periphery covering 1/3 of total area   preferably with local species.

 

 (xx)   First aid and sanitation arrangements shall be made for the drivers and other contract workers during construction phase.

 

 (xxi)    Noise levels emanating from turbines shall be so controlled such that the noise in the work zone shall be limited to 75 dBA.   For people working in the high noise area, requisite personal protective equipment like earplugs/ear muffs etc. shall be provided. Workers engaged in noisy areas such as   turbine area, air compressors etc shall be periodically examined    to maintain audiometric record and for treatment for any hearing loss including shifting to non noisy/less noisy areas.

 

(xxii)     Regular monitoring of ground level concentration of SO2, NOx, Hg,SPM and RSPM shall be carried out in the impact zone and records maintained.  If at any stage these levels are found to exceed the prescribed limits, necessary        control measures shall be provided immediately.  The location of the monitoring stations and frequency of monitoring shall be decided in consultation with SPCB. Periodic reports shall be submitted to the Regional Office of this Ministry. The data so monitored shall also be put on the website of the company.

 

 (xxiii)  The project proponent shall advertise in at least two local newspapers widely  circulated in the region around the project, one of which shall be in the vernacular language of the locality, / office of Municipal  Corporation/Gram Panchayat  concerned and on the company?s web site  within seven days from the date of this clearance letter, informing that the project has been accorded environmental clearance and copies of clearance letter are available with the State Pollution Control Board/Committee and may also be seen at Website of the Ministry of Environment and Forests at http://envfor.nic.in.

 

(xxiv)   A separate environment management cell with qualified staff shall be set up   for implementation of the stipulated environmental safeguards.

 

(xxv)    Half yearly report on the status of implementation of the stipulated conditions and environmental safeguards shall be submitted to this Ministry/ Regional Office/CPCB/SPCB.

 

(xxvi)   Regional Office of the Ministry of Environment & Forests located at Bhopal will monitor the implementation of the stipulated conditions. A complete set of documents including Environmental Impact Assessment Report and Environment Management Plan along with the additional information submitted from time to time shall be forwarded to the Regional Office for their use during monitoring. Project proponent will up-load the compliance status in their website and up-date the same from time to time at least six monthly basis. Criteria pollutants levels (Stack & ambient levels of NOx) will be displayed at the main gate of the   power plant.

 

(xxvii) Separate funds shall be allocated for implementation of environmental protection measures along with item-wise break-up. These cost shall be included as part of the project cost. The funds earmarked for the environment protection measures shall not be diverted for other purposes and year-wise expenditure should be reported to the Ministry.

 

 (xxviii)  The project authorities shall inform the Regional Office as well as the Ministry regarding the date of financial closure and final approval of the project by the concerned authorities and the dates of start of land development work and commissioning of plant.

 

(xxix)   Full cooperation shall be extended to the Scientists/Officers from the Ministry / Regional Office of the Ministry at Bhopal /the CPCB/the SPCB who would be monitoring the compliance of environmental status.

 

 4.      The Ministry of Environment and Forests reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of the Ministry. MOEF may impose additional environmental conditions or modify the existing ones, if necessary.

 

 5.      The environmental clearance accorded shall be valid for a period of 5 years to   start of production operations by the power plant.

 

  6.     In case of any deviation or alteration in the project proposed from those submitted to this Ministry for clearance, a fresh reference should be made to the Ministry to assess the adequacy of the condition(s) imposed and to add additional environmental protection measures required, if any.

 

7.       The above stipulations would be enforced among others under the   Water(Prevention and Control of Pollution) Act,1974, the  Air(Prevention and Control of Pollution) Act,1981,the Environment (Protection) Act,1986 and rules there under, Hazardous Wastes (Management and Handling) Rules,1989 and its amendments, the Public Liability Insurance Act,1991 and its amendments .

 

 8.      Any appeal against this environmental clearance shall lie with the National Environment Appellate Authority, if preferred, within 30 days as prescribed under Section 11 of the National Environment Appellate Act, 1997.

 

 (LALIT KAPUR)

DIRECTOR

 

Copy to:-

 

1.            The Secretary, Ministry of Power, Shram Shakti Bhawan, Rafi Marg, New   Delhi-110 001.

2.        The Secretary (Environment), Government of Madhya Pradesh,   Bhopal-462 004.

3.            The Chairman, Central Electricity Authority, Sewa Bhawan,     R.K. Puram, New Delhi-110 066.

4.            The Chairman, Madhya Pradesh Pradushan Niwaran Mandal, Paryavaran Parisar, Sector E-5, Arera Colony, Bhopal-462 016 - with a request to display a copy of the clearance letter at the Regional Office, District Industries Centre and Collector?s office for 30 days.

5.            The Chairman, Central Pollution Control Board, Parivesh Bhawan, CBD-cum-Office Complex, East Arjun Nagar, Delhi-110 032.

6.       The Chief Conservator of Forests (C), Regional Office (WZ), Ministry of Environment & Forests, Kendriya Paryavaran   Bhawan, Link Road No.-3, E-5, Arera Colony, Bhopal - 462 016.

 7.      Director (EI), MOEF.         

 8.      Guard file.

 9.      Monitoring file.

                                                                                                                                                                                                                                   (LALIT KAPUR)                                                                                           DIRECTOR

 

 

 

 

Untitled Page