BY SPEED POST
No. J-13011/12/2008-IA.II(T)
Government of India
Ministry of Environment & Forests
Paryavaran Bhawan
CGO Complex, Lodi Road
New Delhi-110 003
Dated: 26th August, 2008
To
M/s R.K.M. Powergen Pvt. Ltd.
16,
First Canal Cross Road
Gandhinagar,
Adyar
Chennai
- 600 020.
Sub: 4x350 MW Thermal Power Project at
Uchpinda, Tehsil Dabar,
District Janjgir-Champa, Chhattisgarh of M/s R.K.M. Powergen
Pvt. Ltd - Environmental clearance regarding.
The undersigned is directed to refer
to your communication no. nil dated 8.5.2008 regarding the subject mentioned
above. Subsequent information furnished
vide letter No.RKMPL/MOEF/270608 dated 27.6.2008 has also been
considered.
2. It is noted that the proposal is for
grant of environmental clearance for setting up of a 4x350 MW thermal power
project at Uchpinda, Tehsil Dabar,
District Janjgir-Champa, Chhattisgarh.
The land requirement for the project is 900 acres. Water requirement is
122784 m3/day and will be sourced from Mahanadi River. Coal linkage is for 350 MW and coal from
captive coal block (Fatehpur east of SECL) is for 1000 MW. The coal will be
transported through rail to the coal yard and from coal yard to the plant
through conveyor. No ecologically
sensitive area is reported in 10 Km area of the project. The Bandhapali tank is at 2.8 km due south. Four families will be displaced and 660
will be land oustees. The public consultation was held on 30.4.2008. Total cost of the project is Rs 5950.00
crores, which includes Rs 250.00 crores for environmental protection measures.
3. The proposal has been considered and Ministry of Environment
& Forests hereby accords environmental clearance to the said project under
the provisions of Environment Impact Assessment Notification, 2006 subject to
implementation of the following terms and conditions:-
(i) No additional land in excess of 900 acres shall be acquired for
any activity/ facility of this project.
(ii) The confirmed coal
linkage / captive coal block to meet the requirement for requisite quantity of
coal for the ultimate capacity shall be obtained before commissioning the
project. Copy of the balance coal linkage shall be submitted to the Ministry.
(iii)
Sulphur and ash contents in the coal to be used in the project shall not
exceed 0.4% and 42% respectively at
any given time.
(iv) Two bi-flue stacks of 275 m height each shall be provided with
continuous online monitoring equipments for Sox, NOx and Particulate. Exit velocity of flue gases shall not be
less than 25 m/sec.
(v) High efficiency Electrostatic Precipitators (ESPs) shall be installed to ensure that particulate
emission does not exceed 50 mg/Nm3.
(vi) Space
provision shall be kept for retrofitting of FGD, if required at a later date.
(vii) Adequate dust extraction system such
as cyclones/ bag filters and water spray system
in dusty areas such as in coal handling and ash handling points, transfer areas and other vulnerable
dusty areas shall be provided.
(viii) Fly
ash shall be collected in dry form and storage facility (silos) shall be provided. 100% fly ash utilization shall be ensured from 5th
year onwards. Unutilized fly ash shall be disposed off in the ash pond in
the form of High Concentration
Slurry and the bottom ash in conventional slurry mode.
(ix)
Ash pond shall be
lined with impervious lining. Adequate safety measures shall also be
implemented to protect the ash dyke from getting breached.
(x)
Closed cycle cooling
system with cooling towers shall be provided.
COC of at least 4 shall be adopted and the effluents shall be treated as
per the prescribed norms.
(xi)
The treated effluents
conforming to the prescribed standards shall be re-circulated and reused within
the plant. There shall be no discharge
outside the plant boundary except during monsoon. Arrangements shall be made
that effluents and storm water do not get mixed.
(xii)
A sewage treatment
plant shall be provided and the treated sewage shall be used for raising
greenbelt/plantation.
(xiii)
Rainwater
harvesting should be adopted. Central
Groundwater Authority/ Board shall be consulted for finalization of appropriate
rainwater harvesting technology within
a period of three months from the date of clearance and details shall be
furnished.
(xiv)
Adequate safety
measures shall be provided in the plant area to check/minimize spontaneous
fires in coal yard, especially during summer season. Copy of the these measures with full details along with
location plant layout shall be submitted to the Ministry as well as to the
Regional Office of the Ministry at Chandigarh.
(xv)
Storage facilities for
auxillary liquid fuel such as LDO and/ HFO/LSHS shall be made in the plant area
where risk is minimum to the storage facilities. Disaster Management Plan shall be prepared to meet any
eventuality in case of an accident taking place. Mock drills shall be conducted regularly and based on the same,
modifications required, if any shall be incorporated in the DMP. Sulphur content in the liquid fuel will not
exceed 0.5%.
(xvi)
Regular monitoring of
ground water in and around the ash pond area shall be carried out, records
maintained and six monthly reports shall be furnished to the Regional Office of
this Ministry.
(xvii)
A
green belt of adequate width and density shall be developed around the plant
periphery covering an area of at least 300 acres preferably with local species.
(xviii)
Dense plantation
around Bandhapali Tank shall be done. Details of the same shall be submitted to
the Ministry.
(xix)
The PAP shall be
rehabilitated / compensation in accordance with the norms of the State
Government. Details of R&R plan
with compensation package shall be submitted to the Ministry/SPCB/regional
Office of the Ministry.
(xx)
Adequate funds shall
be allocated for undertaking CSR activities and in any case it shall not be
less than Rs 1.0 crore per annum. Details of activities shall also be
submitted to the Regional Office of the Ministry, SPCB and the Ministry.
(xxi)
First aid and
sanitation arrangements shall be made for the drivers and other contract
workers during construction phase.
(xxii)
Leq
of Noise levels emanating from turbines shall be limited to 75 dBA. For people
working in the high noise area, requisite personal protective equipment like
earplugs/ear muffs etc. shall be provided. Workers engaged in noisy areas such
as turbine area, air compressors etc shall be periodically examined to maintain
audiometric record and for treatment for any hearing loss including shifting to
non noisy/less noisy areas.
(xxiii)
Regular monitoring of
ground level concentration of SO2, NOx, SPM and RSPM shall be
carried out in the impact zone and records maintained. If at any stage these levels are found to
exceed the prescribed limits, necessary control measures shall be provided
immediately. The location of the
monitoring stations and frequency of monitoring shall be decided in
consultation with SPCB. Periodic reports shall be submitted to the Regional
Office of this Ministry.
(xxi) The project
proponent shall advertise in at least two local newspapers widely circulated in
the region around the project, one of which shall be in the vernacular language
of the locality concerned within seven days from the date of this clearance
letter, informing that the project has been accorded environmental clearance
and copies of clearance letter are available with the State Pollution Control
Board/Committee and may also be seen at Website of the Ministry of Environment
and Forests at http://envfor.nic.in.
(xxii) A separate
environment management cell with qualified staff shall be set up for implementation of the stipulated environmental safeguards.
(xxiii) Half yearly report on the status of
implementation of the stipulated conditions
and environmental safeguards shall be submitted to this Ministry/ Regional
Office/CPCB/SPCB.
(xxiv)
Regional
Office of the Ministry of Environment & Forests located at Chandigarh will
monitor the implementation of the stipulated conditions. A complete set of documents including
Environmental Impact Assessment Report and Environment Management Plan along
with the additional information submitted from time to time shall be forwarded
to the Regional Office for their use during monitoring.
(xxv)
Separate
funds shall be allocated for implementation of environmental protection
measures along with item-wise break-up. These cost shall be included as part of
the project cost. The funds earmarked for the environment protection measures
shall not be diverted for other purposes and year-wise expenditure should be reported
to the Ministry.
(xxvi)
The
project authorities shall inform the Regional Office as well as the Ministry
regarding the date of financial closure and final approval of the project by
the concerned authorities and the dates of start of land development work and
commissioning of plant.
(xxvii)
Full
cooperation shall be extended to the Scientists/Officers from the Ministry /
Regional Office of the Ministry at Chandigarh /the CPCB/the SPCB who would be
monitoring the compliance of environmental status.
4. The Ministry of Environment and Forests reserves the right to
revoke the clearance if conditions stipulated are not implemented to the
satisfaction of the Ministry. MOEF may impose additional environmental
conditions or modify the existing ones, if necessary.
5. The environmental clearance accorded shall be valid for a
period of 5 years to start of
production operations by the power plant.
6. In case of any deviation or alteration in the proposed project
from those submitted to this Ministry for clearance, a fresh reference should
be made to the Ministry to assess the adequacy of the condition(s) imposed and
to add additional environmental protection measures required, if any.
7. The above stipulations would be enforced among others under
the Water(Prevention and Control of
Pollution) Act,1974, the Air(Prevention
and Control of Pollution) Act,1981,the Environment (Protection) Act,1986 and
rules there under, Hazardous Wastes (Management and Handling) Rules,1989 and
its amendments, the Public Liability Insurance Act,1991 and its amendments .
8. Any appeal against this environmental clearance shall lie with
the National Environment Appellate Authority, if preferred, within 30 days as
prescribed under Section 11 of the National Environment Appellate Act, 1997.
(Dr.
S.K.AGGARWAL)
DIRECTOR
Copy
to:
1.
The Secretary,
Ministry of Power, Shram Shakti Bhawan, Rafi Marg, New Delhi -110 001.
2. The Secretary, Department of Environment, Dau Kalyan Singh Bhawan, Raipur-492001.
3.
The Chairman, Central
Electricity Authority, Sewa Bhawan, R.K. Puram, New Delhi-110 066.
4.
The Chairman, Chhattisgarh Environment Conservation Board,
Nanak Niwas, Civil Lines, Raipur - 492001 - with a request to display a copy of the clearance letter at the Regional
Office, District Industries Centre and Collector?s office for 30 days.
5.
The Chairman, Central
Pollution Control Board, Parivesh Bhawan, CBD-cum-Office Complex, East Arjun
Nagar, Delhi-110 032.
6.
The Chief Conservator
of Forests, Central Regional Office, Ministry of Environment & Forests, E-3/240, Arera Colony, Bhopal-462
016.
7.
Director (EI),
MOEF.
8.
Guard file.
9.
Monitoring file.
(Dr. S.K.AGGARWAL)
DIRECTOR