Compliance report (Six monthly) of Durgapur Steel Thermal Power Station, DVC against MoEF upto 31.05.10

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DAMODAR VALLEY CORPORATION

OFFICE OF THE CE (CONSTN.) & PROJECT HEAD

DURGAPUR STEEL THERMAL POWER STATION

ANDAL-713321

 

 

 

 

To

The Director(S)

Ministry of Environment & Forests

Eastern Region Office,

A/3 Chandrasekharpur, Bhubaneswar-751023

 

         Sub: Compliance of the conditions of environmental clearance issued by Govt.

                 Of India, Ministry of  Environment & Forest, New Delhi.

       

        

Dear Sir,

 

            Enclosed please find herewith above compliance report (six monthly) upto 31.05.10 with relevant information related to environmental aspect of DSTPS.

 

Thanking you,

 

 

 

 

                                                                                                 Yours faithfully,

 

Enclo: As above along with soft copy.

 

 

                                                                            Chief Engineer (Const) & Project head

                                                                                                  DSTPS, DVC

                                                                                                         

 

 

 

 

Copy to:

The Chief Environment Officer (EM &PC), Kolkata-700 054

 

 

 

 

 

 

Compliance of the conditions of environmental clearance issued by Govt. Of India, Ministry of Environment & Forest, New Delhi.

 

 

Sl. no.

Stipulation as per Environment

Compliance

Remarks

1

R & R policy 2007

The project affected has been categorized into 5 classes namely A, B, C, D and E. Further it is to mention here that DVC spends 2 % of its profit each year in different social integration programmes undertaken in adjoining areas normally within 10 km radius of the project. In this project the affected peoples under category A, B & C only exist and compensation will be made after categorization of the PAP’s by engaging a suitable consultant for the purpose.

Acquisition of land is under process

2

Ash utilization plan

Already agreement with M/S Durga Hightech Cement, M/S Ultratech Cement Ltd, M/S Emami Cement Ltd & M/S Jagadamba Fiscal Services has been done. Two nos brick plants have been commissioned inside the plant premises. At present as the units are under construction we don’t provide ash for running the Brick plants. However, we have arranged necessary requirement of ash from MTPS, DVC. Approx. 30,000 nos bricks per day are being produced and the same is being utilized for Boundary wall works & other areas.

 

 

3

Rain water harvesting

A detailed scheme for rain water harvesting to recharge the ground water aquifers shall be prepared in consultation with Central Ground Water Authority/ State Ground Water Board and a copy of the same shall be submitted after completion of the same. Already the matter has been taken up with State Ground Water Board. The representative of State Ground Water Board visited the plant. Various data as required by them is being collected. Some building drawings are yet to receive.

 

4

Greenbelt area

Management plan for Green belt area has been prepared in consultation with local DFO which will be executed through Forest Deptt, Govt. of West Bengal. Management plan has been placed before Board of Directors, DVC. Main thrust has been given to raise the plant on indigenous species. Few thousand of seedling has been planted around the project area through Forest Deptt, Govt. of West Bengal. Plantation created during 2009 will be maintained during this year with additional planting (gap filling), if required. We have observed 38th World Environment day on 5th June,2010 and planted some seedlings (Photo enclosed) and send messages to the local people towards awareness of environment.

 

5

Project Status report

Progress upto May,10 is enclosed.

 

6

Environmental budget

Total environmental budget is around 70 crores including cost of land but excluding cost of pollution control device like ESP, ETP, Water recycling plant etc. Total Project expenditure incurred upto May, 2010 is Rs. 3205.87 crores (approx). Expenditure towards environment management plans is yet to be taken up other than payment towards cost of land for creation of Green belt.

 

7

Data Sheet furnished by Regional Office, Bhubaneshwar, Ministry of Environment & Forest,

Enclosed as Annexure-A

 

 

ANNEXURE-A

 

Ministry of Environment & Forests

Regional Office

BHUBANESWAR

 

PART-I

DATA SHEET

1.         Project type                                                     : Thermal Power Station

 

2.         Name of the Project                                        : 2X 500 MW Durgapur Steel

                                                                                      Thermal Power Station

3.         Clearance/Approval letter(s) no. & date         : F.No. J-13011/16/2006-IA.II(T)

                                                                                      dt. 27.11.2006

4.         Locations

            a.         District(s)                                            : Bardhaman

           

            b.         State(s)                                                : West Bengal

 

            c.         Latitudes/Longitudes                          : 23˚34’30" N Latitude and

                                                                                      87˚12’ E Longitude

 

5.         Address of Correspondence

            a.         Address of concerned Head of          : Secretary, DVC Towers, DVC,

                        Organization (with pin code and          VIP Road, Kolkata-700054

                        Telephone/telex/fax numbers)   Ph. No. 033-23559940

                                                                                      Fax No. 033-23550585

 

            b.         Address of Head of Project                : Shri P.S. Singh

                        (With pin code and Telephone/             Chief Engineer (Construction)

                        telex/fax numbers)                                Durgapur Steel Thermal Power

                                                                                       Station

                                                                                       Ph. No. 0341 2374 553

                                                                                       Fax no. 0341 2374 338

6.         Salient features

            a.         Of the project                                      : Coal based Thermal Power

                                                                                      Plant

 

            b.         Of the Environment management       : Electrostatic precipitator (ESP),

                        plans                                                      Effluent treatment plant (ETP),

                                                                                      Fly ash utilization, Aforestation,                                                                                Green belt development, Water                                                                                  Recycling plant, Water

                                                                                      Harvesting structure, Coal slurry

                                                                                      Settling pond, Dust extraction

                                                                                      system in CHP by spraying

                                                                                      water, Mines filling.

 

 

 

7.         Break of the project areas (in ha)

 

            a.         Forest area                                           :  0.37 % of study area

 

            b.         Non Forest area                                   : 99.63 % of study area

                                    Total                                        : 1006 Acres

 

8.         Break up of Project affected population

            with enumeration of those losing houses/

            dwelling units only, agricultural land

            and land less labourers/artisians

 

            a.         SC,ST/Adivasis/                                  : (32.0 + 2.79) % of overall                                                                                            population

 

            b.         Others                                                 : 65.21 % of overall population

 

            c.         SC.ST/Adivasis/others                        :

 

9.         Financial Details        

                                                                                  

            a.         Project cost as originally planned       : Rs. 5120.95 Crores (Revised)

                        and subsequent revised estimates        

                        and the years of price reference            

 

            b.         Allocation made for environmental    : Included in the total Project cost

                        Management plans, with item wise       (Total environmental budget is

                        & year wise break up                            around Rs. 70 crores including

                                                                                      cost of land but excluding cost

                                                                                      of pollution control device like

                                                                                      ESP, ETP, Water recycling

                                                                                      plant etc.)                                 

 

            c.         Benefit cost ratio/ internal rate of       : Will be submitted with next                         return & year of assessment                     compliance report.

 

            d.         Whether (c) includes the cost of         : Will be submitted with next

                        Environmental management as             compliance report.

                        Shown in (b) above

 

            e.         Actual expenditure incurred on          : Till May, 2010 is Rs. 3205.87                       the project so far                                   crores

 

            f.          Actual expenditure incurred on          : Yet to be taken up.

                        Environment management plans

                        so far

 

 

 

 

10.       Forest land requirement

 

            a.         The status of approval for a                : NA

                        diversion of forest land for non

                        forestry use

 

            b.         The status of compensatory                : NA

 

            c.         The status of clear filling                    :

 

            d.         Comments on the viability &              : NA

                        Sustainability of compensatory

                        aforestation programme in the

                        light of actual field experience

                        so far

 

11.       The status of clear felling in non forest          : Filling of the required land is

            areas ( such as sub- mergence area of               under progress

            Reservoir, approach roads), if any,

            with quantitive information

           

 

12.       Status of construction

 

            a.         Date of commencement                      : LOA placed to BHEL on

                        (proposal/actual)                                  22.07.08 for main plant package

 

            b.         Date of completion                             : Unit # 1: on Aug’ 2010

                        (proposal/actual)                                    (Commercial operation

                                                                                      Declaration)

                                                                                      Unit # 2: on Nov’ 2010

                                                                                      (Commercial Operation

                                                                                      Declaration)

                                                                                      Water system package- 02.12.09

                                                                                      Coal handling package- U#1-

                                                                                       26.06.10

                                                                                      U#2- 26.09.10

13.       Reasons for delay if the project is                  : Not Applicable

            yet to start

 

                       

 

 

 

 

 

 

 