Minutes
of the 17th Meeting of the Expert Appraisal Committee-1 (Industry) held
during 13th
& 14th
December, 2010 at
Scope Complex, Core 6, 5th Floor, IOCL Conference Room, Ministry of Petroleum and Natural Gas, Lodhi
Road, New Delhi 110 003
17.0 Opening Remarks of the Chairman
At the outset, Chairman welcomed the members of the
Expert Appraisal Committee-1(Industry). Thereafter, agenda items were taken up
for discussion.
17.1 Confirmation of the Minutes of the 16th
Meeting of the Expert Appraisal Committee (Industry-1) held on 22nd,
23rd & 24th November, 2010
Minutes of
the last meeting held during 22nd -24th November, 2010
were confirmed.
17.2.0 Consideration of the Projects
13th December, 2010
Proposals
for Environmental clearance
17.2.1 Expansion of Integrated Steel Plant (from
10.0 MTPA to 16.0 MTPA) along with Captive Power Plant (415 MW) near Village
Tornagallu, District Bellary in Karnataka by M/s JSW Steel Limited – ( Environmental Clearance)
The project authorities and their consultant,
M/s MECON Ltd., Ranchi gave a detailed presentation
on the salient features of the project and proposed environmental protection
measures to be undertaken as per Terms of Reference (TORs) awarded during the 3rd
Meeting of the Expert Appraisal Committee-1 (Industry) held during 23rd
– 24th September, 2009 for preparation of EIA/EMP. All the Integrated Steel plants are
listed at S.No. 3(a) under category ‘A’ of the Schedule of EIA Notification,
2006 and appraised at the Central level.
M/s JSW Steel Ltd. have
proposed for the expansion
of the Integrated Steel Plant (from 10.0 MTPA to 16.0 MTPA) along with Captive
Power Plant (600 MW) near Village Tornagallu, District Bellary, Karnataka. M/s JSW Steel
Ltd. is presently operating 7 MTPA Steel Plant and will be commissioning 10
MTPA units in March 2011. Environmental Clearance for 10 MTPA was accorded on 7th
May 2007. Boundary of Daroji Bear
Sanctuary is located at a distance of about
5 Km from the Plant boundary and the Notification of Bear Sanctuary was
done after notification of Steel Plant. About 700 acres of land is required for the proposed expansion
which is within the existing plant area. No additional land is required. Total project
area including township is 7,761 acres and 33 % of the total area will be
covered as green belt. Total Cost of the project is Rs 16,000 Crores. Rs 800
Crores and Rs 107.56 Crores/Annum will be earmarked
towards capital cost and recurring cost for environmental pollution control
measures
The following
is the plant configuration and capacity:
S. No. |
Details |
Plant Configuration |
Installation Capacity in MTPA |
1.
|
Pellet
plant |
1
unit of 464 m2 grate area |
4.2 |
2 |
DR Plant |
1 unit of 150 tph |
1.2 |
3 |
Coke Oven Battery |
4 x 69 ovens x
7.0 m tall |
3.06 |
4 |
Sinter Plant |
1 unit of 700 m2 grate
area |
7.2 |
5 |
Blast Furnace |
2 units of 4,019 m3 inner
volume |
6.23 |
6 |
Steel Melting Shop - HMDS -BOF
Converter - Ladle
furnace (LF) -RHOB |
6.187 mtpa liquid steel capacity
with 2X 180 t 4 x 180 t 4 x 180 t 2 x 180 t |
6.187 |
7 |
Continuous casting -
Blank Caster -
Bloom
Caster -
Billet Caster |
6.0 mtpa of
crude steel 2 x 3 strand –
2.2 Mtpa 2 x 6 strand
– 2.2 Mtpa 2 x 6 strand – 1.9 Mtpa |
6.0 |
8 |
Finishing Mills -
Wire
Rod Mill -
SQB
Mill(Special Quality Bar Mill) -
Medium
Section Mills
- Universal Beam Mills |
2 x 0.5 Mtpa 1X 0.8 Mtpa 2.1 Mtpa 2.1 Mtpa |
6.0 |
9 |
Lime kilns |
8 units of 300 tpd |
2,400 tpd |
10 |
Beneficiation Plant |
4 units of x 500 t/h |
10.3 |
11 |
Pig Casting machine |
1 unit |
3,600 tpd |
12 |
Power plant |
2 units of 300 MW Gas/Coal |
600 MW |
13 |
Incinerator |
1 unit |
250 kg/h |
14 |
Slag grinding plant |
1 unit |
2 mtpa |
15 |
Oxygen plant |
2 units of 1,800 tpd |
3,600 tpd |
16 |
Residential township |
1 unit |
5,000 houses |
Iron Ore fines, Coking Coal, Non Coking coal, lime stone, dolomite, quartize,
Betonites, Ferro alloys, Coal are the raw materials used. Products are saleable
steel products like Billets, Blooms, Sections, Rebar, Wire & Rods. Coking
coal is being imported from Australia.
All the Air pollution Control
equipments are designed for emission norms of 50 mg / Nm3. Bag
filter based dust extraction system in BF with gas cleaning plant and Bag
filter based dust extraction system for ground based pushing emission control
in Coke Oven battery shall be provided. Dry fog type dust suppression system will
be provided for material handling junction points and Fume Extraction system will
be provided for BOF & LF along with gas cleaning plant. Dust extraction
system in Sinter Plant and Dedusting System in lime & dolo plant will be
provided. Monitoring of ambient air quality will be done through online AAQ
monitoring system at two locations.
Total water requirement of 5,578
m3/h (29.5 MGD) is met within the existing allocation of 72.8 MGD.
No impact on ground water is envisaged since no ground water will be drawn by
the expansion plant. The present water
consumption is 2.4 m3 per ton of steel which is the best in the
world. Blow down water from power plant will be reused for Pig Casting Machines
and Quenching in Coke ovens. Blow down water from BOF re-circulation system
will be reused in SMS slag yards for spraying on hot slag. Blown down water
from Blast Furnace re-circulation system will be reused in Slag Granulation
Plant as make-up water to SGP re-circulation Water System. In addition, rain
water harvesting schemes are envisaged for the proposed project.
About 98% of Iron Making slag is
granulated & sold to Cement plants and 2% is treated in dry pits and used
for land fill. BOF slag from Steel
making slag is granulated, metalics separated and used in construction. Iron
making sludge will be used in Pellet plant after dewatering and Steel making
sludge is used in Sinter plants after dewatering. Mill scales, Flue dust from
Blast furnace, Dust from bag filter and Lime / Dolo dusts will be used in
Sinter plants. Fly ash from boilers will be sold to Cement Plants and used for
manufacturing fly ash bricks. Misc wastes & debris will be reused &
sent for landfill.
Total
power requirement of 415 MW will be sourced from captive power plant of 2
X 300 MW of 2 units of 300 MW Gas/Coal
Public hearing/Public consultation
meeting was conducted by the Karnataka State Pollution Control Board on 5th
October, 2010. The main issues raised in the public hearing meeting were w.r.t.
provision of employment and education for locals,
pollution control measures, green belt development, drinking water etc.
and have been included in the EIA/EMP.
After detailed deliberations, the
Committee sought the following information for reconsideration and deferred the
project.
·
Detailed
plan of housing for construction workers.
·
An
authenticated map showing the location of the project and Daroji Bear Sanctuary
along with his comments or recommendation.
·
A
copy of application submitted to the National Board for wild life.
·
Exact
source and Trace Element analysis of Raw Materials.
·
A
copy of coal linkage document
·
Management
plan for SMS slag.
·
Trace
Element analysis of ground water and fluoride concentration.
·
Detailed
Risk analysis &Disaster Management plan.
·
Bar/line
diagrams of the EMP (including OHS etc.) for the last 10 to 15 years
·
Revised
green belt Development plan with an average minimum width of 20 m.
·
Detailed
CSR plan for 5% of the project cost.
The
Committee also decided that a Sub-Committee shall visit the plant site to see the implementation of pollution control and environmental
conservation measures taken on receipt of additional information.
17.2.2
Ferro Alloys Plant (2x6
MVA, 18,000 TPA, Fe-Mn & Si-Mn) at Plot No. 213, Growth Centre, Mandal
Bobbili, District Vizianagaram, Andhra Pradesh by M/s Gee Bee Ferro &
Power Private Limited – (Environmental Clearance)
The project authorities and their consultant,
M/s Sri Sai Manasa Nature Tech Pvt. Ltd., Hyderabad gave a detailed presentation on the salient features of the project and
proposed environmental protection measures to be undertaken as per Terms of
Reference (TORs) awarded during the 10th Meeting
of the Expert Appraisal Committee-1 (Industry) held during 17th – 18th
May, 2010 for preparation of EIA/EMP. All the Ferro Alloy
Plants are listed at S.No. 3(a) in Primary Metallurgical Industries under
Category ‘A’ of the Schedule of EIA Notification, 2006 and appraised at
the Central level.
M/s Gee Bee Ferro &
Power Private Ltd. have proposed for the Ferro Alloy Plant (2x6 MVA, 18,000
TPA, Fe-Mn & Si-Mn) at Growth Centre, Mandal Bobbili, District
Vizianagaram, Andhra Pradesh. Total land
acquired is 4.0 acres and green belt will be developed in 1.35 acres. Mettavalasa village is at
Manganese ore, coal, coke, dolomite, quartz and carbon paste will be used as
raw materials. Coke will be used as one of the raw material and not as fuel in
the Ferro Alloy plant. Mixture of ore, coke, coal and briquettes will be
smelted in electric submerged arc furnace through electro-thermic process. The metal will be tapped at regular intervals
in pans/moulds.
The furnace will be provided with a
dust extraction system comprising of hood to collect the smoke and will
discharge filtered smoke to the chimney. The furnace stack will be maintained
as per CPCB standards. Pulse jet bag filters will be provided to control down
pollution.
Total ground water
requirement from bore wells will be 80 m3/day will be met from the
APIIC. Treated wastewater will be used for cooling purpose. Cooling water will be passed through heat
exchangers and collected in sump or holding tank. Screens and recirculation tanks will be
provided to recycle/reuse treated waste water. The treated effluent will be
used for ash conditioning, dust suppression and green belt development. Fines
generated during breaking and sizing of the finished metal will be sent to
jigging machine and cleaned in flow of water.
The wastewater from jigging machine will be recycled/reused. Service
water will be passed through oil separator to remove oil content in the
effluent. Domestic effluent will be treated in septic tank followed by
soak pit. No effluent will be discharged outside the premises and ‘Zero’
discharge will be adopted.
Ferro-Manganese slag will be reused
in the manufacture of Silico-Manganese. Silico-Manganese slag will be used for
construction works. Bag filter dust will be provided to brick manufacturing
units. The finer collected in pollution control equipments will be taken back
to raw material processing area and mixed with the ore and charged in the
furnace. Waste oil and used batteries will be sold to authorized recyclers
/ re-processors.
Equipment of less noise generation
will be used. Total power requirement will be 33 KVA increased to 132
KVA. HSD will be used as fuel.
It is noted that no public hearing/consultation is
required due to project being located in
notified Industrial area as per
Section (iii), Stage (3), Para (i) (b) of EIA Notification 2006.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other environmental conditions:
7. The total water requirement shall not
exceed 80 m3/day. ‘Zero’ effluent
discharge shall be strictly followed and no wastewater should be discharged
outside the premises.
13. At least 5 % of the total
cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan (need
based) should be prepared and submitted to the Ministry’s Regional Office at
Bangalore. Implementation of such program shall be ensured accordingly in a
time bound manner.
17.2.3
Ferro-Alloy Plant (Ferro-Silicon-2,000
TPA) at Sy. no. 376, Village & Mandal Parigi, District Ananthapur in Andhra
Pradesh by M/s Vee Six Alloys Pvt. Limited – (Environmental Clearance)
The project authorities and their consultant,
M/s Richardson
and Cruddas (1972) Ltd., Chennai gave a
detailed presentation on the salient features of the project and proposed
environmental protection measures to be undertaken as per Terms of Reference
(TORs) awarded during the 10th Meeting of the Expert Appraisal
Committee-1 (Industry) held during 17th – 18th May, 2010 for preparation of EIA/EMP. All the Ferro Alloy
Plants are listed at S.No. 3(a) in Primary Metallurgical Industries under
Category ‘A’ of the Schedule of EIA Notification, 2006 and appraised at
the Central level.
M/s Vee Six Alloys Pvt.
Ltd. have
proposed to install a Ferrosilicon plant of 2,000 TPA at Parigi (V), Parigi (M), Ananthapur (Dist.)
Andhra Pradesh. The total area of the plant is 3.0 Acres and green belt will be
developed in 33.3 % of the total area of the plant. There are no national
parks/wild life sanctuary/reserved forest within 10 km radius of the proposed
industry. The nearest human habitation is Parigi Village, which is at a
distance of 0.8 km. The Jayamangal river is at a distance of 0.85 km from the
proposed industry. The total cost of the project is 6.07 crores. About 5 % of
total cost of the project (Rs.30.35 lakhs) is earmarked towards the corporate
social responsibility in the adjoining villages.
Ferrosilicon will be manufactured in a
submerged Electric Arc Furnace
(2.50 MVA) using main raw materials such as Quartz (3,600 TPA), Coke (2,200
TPA), M.S. scrap (401 TPA) and electrode paste (121 TPA) etc. The manufacturing
process consists of: (a) blending of raw materials, (b) charging and smelting in
the submerged electric arc furnace (SEAF), (c) tapping and cooling of molten material,
(d) breaking, cleaning and packing.
Air pollution management will be accomplished
by providing bag house filters with a capacity of 6,310 Nm3/Hr for
ferrosilicon plant to treat the furnace gases. The gas from furnace top is
picked up by an air cooled swivel hood which can be removed as required during
operation. The gas is then conveyed by air cooled ducting to a heat exchanger
to strip off the heat in the gas. Thereafter, the gas is sucked by a forced
–draft pan to a positive pressure spark–arrester with cyclone and bag filters
having reverse flow arrangement to clean the bags automatically. The bag
filters house consists of 16 No. of bags (dia-150mm and height 3,660 mm of each
bag). Particulate Emissions will be restricted to less than 50 mg/Nm3.Whenever
air pollution control system fails, the production will be stopped till that
air pollution control system is rectified. Fugitive emissions will be
controlled by providing water sprinkler at raw material transfer points.
Greenbelt will be developed along the periphery of the boundary wall, on either
side of the roads and around the buildings to an extent of 33.3 % of the total
area of the plant.
The total quantity of water required is 15 m3/day
which will be drawn from ground water source within the plant premises for
cooling of SEAF, drinking and sanitation. The cooling water will be recycled to
the maximum possible extent. No treated waste
water will be discharged outside the plant. Domestic sewage will be treated in
septic tank and diverted to soak pit.
Solid waste management practices include: 1)
Temporarily solid waste dumping area will be provided with a garland drain, 2)
Alloy melting slag will be sold to cast iron foundries, 3) Lead acid batteries
will be sold to approved vendors by APPCB and 4) Dust from the air pollution
control equipment will be partly utilized in production process and rest will
be sold to brick manufactures/admixture in concrete works. Cleaning process
residues will be 100 % recycled into production process.
Noise pollution control measures include: 1) plantation
of suitable species near sensitive areas will result in partial noise
attenuation, 2) acoustic enclosures will be provided in D.G. set and noise
generation machineries like compressor and 3) ear plugs will be provided to all
employees who will work in the noise prone areas. Occupational health hazards
control and safety measures will be enforced strictly in the work zone areas.
The total power requirement is 2,174 KVA,
which will be supplied by APTRANSCO. A 125 KVA D.G. set is provided to various
critical areas like cooling water pump, crane and lighting to take care of on
process work during main supply failure. The proposed industry provides an
employment of 42 people directly and about 60 people indirectly.
Public hearing/Public consultation
meeting was conducted by the Andhra Pradesh Pollution Control Board on 15th
September, 2010. The issues raised in the public hearing meeting were regarding
provision of employment for locals, pollution
control measures, green belt development, rain water harvesting etc. and
have been included in the EIA/EMP.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other environmental conditions:
7.
The
total water requirement shall not exceed 15 m3/day. ‘Zero’ effluent discharge shall be strictly followed and no
wastewater should be discharged outside the premises. Since the project
area is a dry area, within 5 years, no ground water shall be used and rain
water shall only be used by means of rain water harvesting.
13. At least 5 % of the total
cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan (need
based) should be prepared and submitted to the Ministry’s Regional Office at
Bangalore. Implementation of such program shall be ensured accordingly in a
time bound manner.
17.2.4
Asbestos Fiber Cement Sheet Plant (1,20,000 TPA) at Plot No. A1, Industrial
Area, Village & Taluk Bihiya, District Bhojpur, Bihar by M/s Ramco Industries
Limited – (Environmental Clearance)
The project authorities and
their consultant M/s Vimta Labs, Hyderabad gave a detailed presentation on
the salient features of the project and proposed environmental protection
measures to be undertaken as per Terms of References (TORs) awarded
during the 10th Meeting of the Expert Appraisal Committee
(Industry-1) held during 17th & 18th May, 2010 for
preparation of EIA/EMP Report. All the Asbestos Fibre Sheet Manufacturing
Cement Plants have been listed at Sl. No. 4(c) of Schedule of EIA Notification,
2006 as Category ‘A’ and have to be appraised by the Central Govt.
M/s Ramco Industries Ltd. have
proposed for the Asbestos Fibre Cement Sheet Plant (1,20,000 TPA) at Industrial
Area, Plot No. A-1, Bihiya, Dist. Bhojpur, Bihar. Total land available is 20.0
acres allotted by Bihar Industrial Area Development Authority (BIADA), Patna. Out of
20 acres of total land, green belt will be developed in 8 acres i.e. 40 % of
total area. No rehabilitation and resettlement is involved. No national
parks/wild life sanctuary/reserve forests are located within
Raw asbestos fiber (10,200 TPA),
Cement (54,000 TPA), Fly Ash (31,800 TPA) and Paper pulp (600 TPA) will be used
as raw materials. Raw material will be transported by covered trucks.
Chrysotile Asbestos fibre received in
the polythene bags is mechanically opened in a bag opening device and fed into
edge runner mill to mill the fibre where water will be added to suppress dust.
The milled fibre will be stored in silo and required quantity of fibre in
drums. Ordinary portland cement will be
stored in cement silo and conveyed to slurry mixer. Fly ash will also be added to slurry mixer.
The slurry so formed will be pumped to the agitator and water of the slurry
filters through sieve depositing a fine film of asbestos cement on the
surface. The films of asbestos cement
are picked up by an endless belt through rubber rolls. Due to movement of felt forward, asbestos
cement layer is dewatered by vacuum and transferred to conveyer belt. The
sheets are corrugated and stacked.
Sheets harden in 8 h and cured by spray of water.
Total
water requirement of 80 m3/day will be sourced from own bore wells. Project
Authorities have obtained Clearance for ground water withdrawal of 80 m3/day
from Directorate, Ground Water Resources, Bihar, Patna. No wastewater will be
generated in the process. The settling
solids in slurry form from the recuperating tank will be collected in a
clarifier and reused in the process. Service water will be passed through
oil separator to remove oil content in the effluent. Domestic effluent
will be treated in septic tank followed by dispersion in underground strata
through dispersion trenches. No effluent will be discharged outside the
premises and ‘Zero’ discharge will be adopted.
All the solid waste generated will be
recycled in the manufacturing process. HDPE
fiber bags will be shredded in the shredder unit attached to the bag opening
device and sent along with the fiber into fiber mill through conveyor.
Acoustic enclosures will be provided
to D.G. sets. 750 KVA of Power will be required for the project and sourced by
BSEB Grid. However, to meet the emergency power requirement during the grid
failure, a diesel generator with capacity of 750 KVA will be installed.
Public hearing/Public consultation
meeting was conducted by the Bihar State Pollution Control Board on 22nd
November 2010. The Committee deliberated upon the issues raised during
the public hearing including, Implementation of Rain Water Harvesting for
recharging the ground water, Implementation of Pollution Control Systems, employment
to locals, waste disposal, Noise Pollution Control Measures & Details of
Plantation, effective air pollution control measures, development activities,
100 % solid waste utilization etc. and have satisfactorily been incorporated in
the final EIA/EMP report.
The Ministry took note of the
complaint dated 16.11.2010 received from an NGO regarding completion of 75 %
construction activity of the project before the public hearing. The Member
Secretary, BSPCB, vide his letter, dated 07.12.2010 informed that the project
site was inspected on 02.12.2010 by BSPCB and was found that “The boundary wall
was constructed all along the proposed site. There were partially constructed
guard room and plantation work has been taken up at some places”.
After detailed deliberations, the
Committee recommended the proposal for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
i.
The project proponent shall adhere to the prescribed BIS standards
and laws regarding use and handling of asbestos, safety of employees etc. Raw
materials like asbestos fibre and cement shall be transported in closed
containers. Asbestos fibre shall be brought in pelletized form in impermeable bags
and under compressed condition.
ii.
Only Chrysotile white asbestos fibre shall be used. Blue asbestos
shall not be utilized as raw material in the manufacturing process.
iii.
There shall be no manual handling/opening of asbestos fiber bags.
The company shall install fully automatic asbestos fiber debagging system
before commissioning the unit.
iv.
Fugitive emissions shall be controlled by bringing cement in
closed tankers, fly ash in covered trucks and asbestos in impervious bags
opening inside a closed mixer. Dust collectors shall be provided to Fibre mill,
Bag opening device (BOD), Cement and Fly ash silos to control emissions. Bag filters followed by wet washer
shall be provided at automatic bag opening machine, bag shredder, fibre mill
and to cement silo to collect the dust and recycle it into the process.
Fugitive emissions generated from hopper of Jaw crusher and Pulverizer shall be
channelized through hood with proper suction arrangement, bag filter and stack.
v.
The Company shall comply with total dust emission limit of 2 mg/Nm3 as notified under the Environment
(Protection) Act, 1986. Adequate measures shall be adopted to control the
process emission and ensure that the stack emission of asbestos fibre shall not
exceed the emission limit of 0.2 fiber/cc. Asbestos fibre in work zone
environment shall be maintained within 0.1 fibre/cc.
vi.
Bags containing asbestos fibre shall be stored in enclosed area to
avoid fugitive emissions of asbestos fibre from damaged bags, if any.
vii.
Proper house keeping shall be maintained within the plant
premises. Process machinery, exhaust and ventilation systems shall be laid in
accordance with Factories Act. Better house keeping practices shall be adopted
for improvement of the environment within the work environment also. These include:
(a) All monitoring transfer points
shall be connected to dust extraction system.
(b) Leakages or dust from machines and
ducts shall be plugged.
(c) Floor
shall be cleaned by vacuum cleaner only.
(d) Enclosed
belt conveyer shall be used instead of manual transportation of asbestos
within the premises.
viii.
Quarterly monitoring of pollutant (PM10, asbestos fibre
count) in the work zone area and stack(s) shall be undertaken by the Project
proponents. In addition, the asbestos fibre count in the work zone area shall
be monitored by an Independent monitoring agency like NIOH / ITRC / NCB or any
other approved agency and reports submitted to the Ministry’s Regional Office
at Bhubaneswar, SPCB and CPCB.
ix.
Total water requirement from ground water shall not exceed 80 m3/day. All the
recommendations of the State Ground Water Department, Govt. of Bihar shall be
implemented in time bound manner.
x.
After
the operation of plant no ground water shall be used and rain water shall only
be used to meet he water requirement.
xi.
As reflected in the Environmental Management Plan, all the treated
effluent shall be recycled and reused in the manufacturing process. No process
water shall be discharged outside the premises and ‘zero’ discharge shall be
maintained. All the domestic wastewater shall be treated in septic tank
followed by soak pit and used for green belt development.
xii.
The Company shall ensure that the entire solid waste generated
including process rejects, cement, fly ash, dust from bag filters and empty
asbestos bag shall be recycled back in the manufacturing process. Process
sludge shall be 100% recycled and reused in the process. Hazardous waste shall be ground in
dust proof pulverizer with integrated bag filter and recycled back to the
process. Asbestos fibres which can not be further recycled due to contamination
of iron dust shall be stored in HDPE lined secured landfill. The disposal
facilities for asbestos waste shall be in accordance with the Bureau of Indian
Standard Code.
xiii.
The cut and damaged fibre bags shall immediately be repaired.
Empty fibre bags will be shredded into fine particles in a bag shredder and
recycled into the process. Piling of AC sheets shall be done in wet condition
only.
xiv.
The Company shall obtain a certificate from the supplier of
Chrysotile fibre that it does not contain any toxic or trace metals. A copy of
certificate shall be submitted to the Ministry of Environment and Forests.
xv.
Regular medical examination of the workers and health monitoring
of all the employees shall be carried out and if cases of asbestosis are
detected, necessary compensation shall be arranged under the existing laws. A
competent occupational health physician shall be appointed to carry out medical
surveillance. Occupational health of all the workers shall be monitored for
lung function test, chest x-ray, sputum for acid-fast-bacilli (AFC) and
asbestos body (AB), urine for sugar and albumen, bloat tests for TLC, DLC, ESR,
Hb and records maintained for at least 40 years from the beginning of the
employment or 15 years after the retirement or cessation of employment
whichever is later. Occupational Health Surveillance shall be carried out as
per the directives of the Hon’ble Supreme Court.
xvi.
To educate the workers, all the work places where asbestos dust
may cause a hazard shall be clearly indicated as a dust exposure area through
the use of display signs which
identifies the hazard and the associated health effects.
xvii.
The company shall also undertake rain water harvesting measures
and plan of action shall be submitted to the Ministry of Environment and
Forests within three months.
xviii.
All the commitments made to the public during the Public Hearing /
Public Consultation meeting held on 22nd
November 2010 shall be satisfactorily implemented and
a separate budget for implementing the same should be allocated and information
submitted to the Ministry’s Regional Office at Bhubaneswar.
xix.
Green
belt shall be developed in at least 33 % of plant area as per the CPCB
guidelines in consultation with the DFO.
xx.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details along with time bound
action plan should be prepared and submitted to the Ministry’s Regional Office
at Bhubaneswar. Implementation of such program should be ensured accordingly in
a time bound manner.
17.2.5
Expansion
of Sponge Iron Plant (100 TPD to 200 TPD) and installation of Steel melting
shop (330 TPD) and Captive Power Plant (12 MW- 4 MW-WHRB & 8 MW AFBC) at 3rd Phase Extension, Adityapur
Industrial Area, P.O. Adityapur, District Saraikela- Kharsawan in Jharkhand by M/s Bimaldeep Steel Private Limited – (Environmental
Clearance)
The project authorities and their consultant, M/s Eco Care, Asansol, West Bengal, gave a detailed presentation
on the salient features of the project and proposed environmental protection
measures to be undertaken as per Terms of Reference (TORs) awarded during the 6th Meeting of the Expert Appraisal
Committee (Industry-1) held during 22nd – 23rd December
2009 for preparation of EIA/EMP. All
the Integrated steel plants are listed at S. No. 3 (a)
under Category “A” of the Schedule of EIA Notification 2006 and appraised at
the Central level.
M/s Bimaldeep Steel Private Limited have proposed for expansion of Sponge Iron Plant (from 100
TPD to 200 TPD) and installation of Steel melting shop (330 TPD) and Captive
Power Plant (12 MW- 4 MW-WHRB & 8 MW AFBC)
at 3rd Phase Extension, Adityapur Industrial Area, P.O.
Adityapur, District Saraikela- Kharsawan in Jharkhand. Total project area is 20.20 acres of
which green belt
will be developed in 33% area. No R & R is involved. No wild life sanctuary/national park is within
10 km radius of the unit. Rivers in the vicinity is
Karkari River at 2 Km from
the proposed site. Total cost of the project is Rs. 160.09 Crores. Rs. 3.11
Crores and Rs. 45.40 Lacs will be earmarked towards total capital cost and
recurring cost/annum for environmental pollution control measures.
Iron ore, non-coking coal, coking coal,
dolomite, iron ore fines, Manganese ore, limestone, bauxite and quartzite will
be used as raw materials. Coal will be sourced from the CCL mines. Water will
be used in process will be kept in closed circuit. Sponge iron will be
manufacture in DR plant. Sponge iron
produced in rotary kiln will be charged to induction furnace for steel making
and if required sold to outside parties. Steel making and continuous casting
shop are envisaged to produce 1,08,000 TPA of liquid steel. Captive power plant
(12 MW) will be installed. Billets
manufactured will be sold to rolling mills.
PRODUCTION FACILITY |
TECHNOLOGY |
CAPACITY PER DAY |
CAPACITY ANNUAL |
SPONGE IRON |
Coal based rotary kiln Direct Reduction |
Existing - 100 TPD Expansion
- 100 TPD Total – 200 TPD |
60,000 TPA |
STEEL MELTING |
Induction
Furnace (Steel) – CCM - LRF |
Steel Melting Shop – 330 TPD (Phase I – 2x 10 T Induction Furnace &
6/11 m CCM Phase – II – 1x 10T Induction Furnace , 1x 10 T LRF) |
1,08,000 TPA |
CAPTIVE POWER |
Based on steam from WHRB & AFBC |
12 MW ( 4 MW WHRB + 8MW AFBC) |
Electrostatic precipitator (ESP),
bag filters, dust collectors will be provided for air pollution control. Pulse
jet bag filters will be provided to steel melting shop (SMS) and ferro alloy
plant. ESP will be provided to captive power plant and Sponge iron plant. Bag
filters will be provided in coal crushing and coal handling area of FBC based
power plant as well as blast furnace raw material handling area. Dust
extraction system and water sprinklers will be done in sponge iron plant. Dust
extraction system such as dust cyclones, bag filters etc. will be provided at
all raw material handling areas, transfer points, conveyor points, crushing and
screening units, storage building etc.
Make up
water requirement from Sitarampur Dam will be 1,050 KLD. Permission for drawl of 1,000 m3/d from Sitarampur Dam has been granted by Sub-divisional officer, Drinking Water and
Sanitation Sub-Division Adityapur vide letter No. 429 dated 01.08.2009. Closed circuit recycling system will be
adopted in the proposed plant. The waste water generated from the power plant
will be used for ash quenching, sprinkling in the coal yard and dust
suppression. Treated wastewater from SMS, CCM will be recycled for washings and
dust suppression etc. Guard pond will
be provided for aeration and dosing of pH corrective. Neutralizing pit for the
treatment of DM Plant will be provided. The treated water will be recycled for
plant use and horticulture. Domestic effluent will be routed to a septic tank
and soak pit and the treated effluent will be used for green belt development.
No effluent will be discharged and zero discharge will be adopted.
Solid wastes
generated in the form of Char/dolochar will be used as fuel in FBC boilers for
power generation. Flue dust from sponge iron plant will be used for
manufacturing fly ash bricks. Fly ash will be used for cement making as well as
brick manufacturing. Kiln accretions will be used as sub-base material for road
construction or landfill. Return scrap will be used in SMS. Dust from air
pollution control equipments will be recycled in the process.
Total power
requirement of 14.5 MW will be met from captive power plant of 12 MW and
remaining from JSEB.
It is noted that no public hearing/consultation is
required due to project being located in
notified Industrial area as per Section
(iii), Stage (3), Para (i) (b) of EIA Notification 2006.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other environmental conditions:
i.
Efforts
shall be made to reduce RSPM levels in the ambient air and a time
bound action plan shall be submitted. On-line ambient air quality monitoring
and continuous stack monitoring facilities for all the stacks shall be provided
and sufficient air pollution control devices viz. Electrostatic precipitator
(ESP), gas cleaning plant, venturi scrubber, bag
filters etc. shall be provided to keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
ii.
As
proposed, Electrostatic precipitator (ESP) shall be provided to WHRB, CFBC and
DRI plants to control SPM levels within 50 mg/Nm3. Fume extraction
system shall be provided to induction furnaces to control the emissions within
the prescribed standards.
iii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iv.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed. New
standards for the sponge iron
plant issued by the Ministry vide
G.S.R. 414(E) dated 30th May, 2008 should be followed.
v.
Hot
gases from DRI kiln shall be passed through Dust Settling Chamber (DSC) to
remove coarse solids and After Burning Chamber (ABC) to burn CO completely and
used in waste heat recovery boiler (WHRB). The gas then shall be cleaned in ESP
before leaving out into the atmosphere through ID fan and stack.
vi.
Total
water requirement shall not exceed 1,050 KLD. Efforts shall further be made to
use maximum water from the rain water harvesting sources. Use of air cooled condensers shall be
explored and closed circuit cooling system shall be provided to reduce water
consumption and water requirement shall be modified accordingly. All the
effluent should be treated and used for ash handling, dust suppression and
green belt development. No
effluent shall be discharged and ‘zero’ discharge shall be adopted. Sanitary
sewage should be treated in septic tank followed by soak pit.
vii.
Efforts shall be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement shall be met
from other sources.
viii.
Regular monitoring of influent and effluent
surface, sub-surface and ground water (including chromite) should be ensured
and treated wastewater should meet the norms prescribed by the State Pollution
Control Board or described under the E(P) Act whichever are more stringent.
Leachate study for the effluent generated and analysis shall also be regularly
carried out and report submitted to the Ministry’s Regional Office at Bhubaneswar, SPCB and CPCB.
ix.
The water consumption shall not
exceed as per the standard prescribed for the steel plants.
x.
All the coal fines, char
from DRI plant shall be utilized in AFBC boiler of
power plant and no char shall be used for briquette making or disposed off
anywhere else. AFBC boiler shall be installed simultaneously along with the DRI
plant to ensure full utilization of char from the beginning.
Scrap shall be used in steel melting shop (SMS) and SMS slag and kiln
accretions shall be properly utilized. All the
other solid waste including broken
refractory mass shall be properly disposed off in
environment-friendly manner.
xi.
Proper utilization of fly ash shall
be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003.
xii.
Vehicular pollution due to
transportation of raw material and finished products shall be
controlled. Proper arrangements shall also be made to control dust
emissions during loading and unloading of the raw material and finished
product.
xiii.
All internal roads shall be black
topped. The roads shall be regularly cleaned with mechanical sweepers. A 3-tier
avenue plantation using native species shall be developed along the roads.
Facilities for parking of trucks carrying raw coal from the linked coalmines
shall be created within the Unit.
xiv.
Proper handling, storage,
utilization and disposal of all the solid waste shall be ensured and regular
report regarding toxic metal content in the waste material and its composition,
end use of solid/hazardous waste should be submitted to the Ministry’s Regional Office at Bhubaneswar, SPCB and CPCB.
xv.
A time bound action plan shall be
submitted to reduce solid waste, its proper utilization and disposal.
xvi.
Risk and Disaster Management Plan along with
the mitigation measures shall be prepared and a copy submitted to the Ministry’s
Regional Office at Bhubaneswar,
SPCB and CPCB within 3 months of issue of environment clearance letter.
xvii.
As proposed, green
belt shall be developed in 33 % of plant area as per the CPCB guidelines in
consultation with the DFO.
xviii.
All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the
Steel Plants should be implemented.
xix.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details along with time bound action plan should be prepared and
submitted to the Ministry’s Regional Office at Bhubaneswar.
Implementation of such program should be ensured accordingly in a time bound
manner.
xx.
The company shall provide housing
for construction labour within the site with all necessary infrastructure and
facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking
water, medical health care, crèche etc. The housing may be in the form of
temporary structures to be removed after the completion of the project.
17.2.6
Expansion
of the Cement Plant (Cement from 550 TPD PPC to 1,100 TPD PSC & PPC) and
Clinker from 400 TPD to 700 TPD at Village Sarutari, Tehsil Sonapur, Byrnihat,
District Kamrup in Assam by M/s
Purbanchal Cement Limited – (Environmental Clearance)
The project authorities and their consultant, M/s En-vision Enviro Engineers Pvt. Ltd., Gujarat gave a detailed presentation on the salient features of the
project and proposed environmental protection measures to be undertaken as per
Terms of Reference (TORs) awarded during the 7th Meeting of the Expert Appraisal
Committee (Industry-1) held during 2nd – 3rd February,
2010 for preparation of EIA/EMP. All the Cement plants (less than 1.0 MTPA) are listed at S.No.
3(b) under Category ‘B’ and proposed cement plant is appraised at the Central level
due to absence of SEIAA/SEAC
in Assam.
M/s Purbanchal Cement Ltd. have proposed for the expansion of the
Cement Plant (Cement 550 TPD PPC to 1,100 TPD PSC & PPC) and
Clinker (400 TPD to 700 TPD; 2,31,000 TPA) at Village Sarutari, Tehsil Sonapur,
Byrnihat, District Kamrup, Assam. The existing project area is 17.56 acres and
6.11 acres of additional land is required for the proposed expansion. Green
belt will be developed in 33 % of area. No R & R is involved.
Gorbhanga R.F. is located at 12 km, South West. No national parks/wild
life sanctuary/reserve forests are located within 10 km radius. Plant
is located in Seismic Zone V and necessary precautions will be adopted due to
possibility of damages like floods, earthquakes and
landslides. Meghalaya State boundary is at 1 km. Total cost of
the project is Rs. 26.51 Crore. Rs 120.0 Lakhs and Rs 5.0 Lakhs are earmarked
towards capital cost and recurring cost/annum respectively for environmental
pollution control measures.
Following will be manufactured:
Particulars |
Present
Capacity |
Proposed
Capacity |
Clinker
Manufacturing |
400
TPD |
700
TPD |
Cement
mill (OPC, PPC, PSC) |
550
TPD |
1,100
TPD |
Limestone (910 TPD), clay / shale (190 TPD), Iron dust (15 TPD),
clinker (100 TPD), gypsum (22 TPD), fly ash (277 TPD), coal (50 TPD) and slag (100
TPD) will be used as raw materials.
PAs
informed to the Committee that expansion of the production (400 to 700 TPD
clinker; 2,31,000 TPA) will be carried out in the same kiln which was underutilized
due to power shortage and now will be utilized at full capacity. No new kiln
will be added. ‘Consent to Establish’ for the existing plant is accorded by the
Assam SPCB vide letter dated WB/KAM/T-91/04-05/144/500 dated 29th May,
2004. Clinker manufacturing will involve raw material crushing, raw material
grinding, blending of raw meal, pyro-processing (clinkerization), clinker
cooling and storage. Cement manufacturing will involve clinker, fly ash &
gypsum proportioning & grinding in ball mills, cement storage in silos, packing
and dispatch.
The major pollutant is particulate
matter from the proposed cement plant. The unit will install bag filters to
control air pollutants. Adequate height shall be provided to stacks attached to
the air pollution control equipments to disperse the air pollutants to the
satisfactory levels. Dust emission due to
vehicular movement will be controlled by water sprinkling system.
Total water requirement after expansion from bore wells and River
Digaru will be 40 m3/day. ‘Permission’ for the drawl of 40 m3/day
water from Digaru River has been obtained. Service water will be passed through
oil separator to remove oil content in the effluent. Domestic effluent (3
m3/day) will be treated in septic tank followed by soak pit and used
for green belt development. No effluent will be discharged outside the premises
and ‘Zero’ discharge will be adopted.
All
the dust from de-dusting equipments will be recycled back to the process.
Waste/used/spent oil and used batteries will be sold to authorized recyclers/reprocessors.
Power (7,500
KVA) will be sourced from ASEB. D.G. set (2x1,250 KVA) is existing
and 2x1,500 KVA is proposed. Coal (146 TPD) will be used as fuel for the kiln
and for drying slag as secondary fuel. No litigation/court case is in pending
against the proposal.
Public hearing / Public consultation
meeting was conducted by the Assam State Pollution Control Board on 1st
November 2010. The Committee deliberated the issues raised during
the public hearing including, continuation of the CSR activities etc.
being done, provision of employment to locals, air pollution control measures, dispensary,
development of roads etc. and have
satisfactorily been incorporated in the final EIA/EMP report.
After detailed deliberations, the
Committee recommended the proposal for environmental clearance subject to
stipulation of following specific conditions along with other environmental
conditions:
i.
Continuous stack monitoring facilities to monitor gaseous
emissions from all the stacks shall be provided. After expansion particulate emission shall
be controlled within 50 mg/Nm3 by
installing adequate air pollution control system. Electrostatic precipitators to clinker
cooler, bag house to raw mill/kiln and bag
filters to coal mill and cement mill. Low NOX burners should be provided to control
NOX emissions.
ii.
Possibilities shall be explored for the proper and full
utilization of gases generated from the kiln in waste heat recovery boiler
(WHRB) and a feasibility report shall be prepared and submitted to the Ministry
and its Regional Office at Shillong within 3 months from the date of issue of
the letter.
iv.
Secondary fugitive emissions shall be controlled and shall be
within the prescribed limits and regularly monitored. Guidelines / Code of
Practice issued by the CPCB in this regard should be followed.
v.
Efforts shall be made to reduce impact of the transport of the raw
materials and end products on the surrounding environment including
agricultural land. All the raw materials including fly ash should be
transported in the closed containers only and shall not be overloaded. The
company shall have separate truck parking area. Vehicular emissions should be
regularly monitored.
vi.
Total water requirement
for cement plant shall not exceed 40 m3/day. All the treated wastewater shall
be recycled and reused in the process and/or for dust suppression and green belt development and other plant related
activities etc. No process wastewater shall be discharged outside the factory
premises and ‘zero’ discharge should be adopted.
ix.
All the bag filter dust, raw mill dust, coal dust, clinker dust
and cement dust from pollution control devices should be recycled and reused in
the process and used for cement manufacturing. Spent oil and batteries shall be
sold to authorized recyclers / reprocessors only.
x.
All the fly ash shall be utilized as per Fly ash Notification,
1999 subsequently amended in 2003. Efforts should be made to use fly ash
maximum in making Pozollona Portland Cement (PPC).
xi.
Efforts shall be made to use low-grade lime, more fly ash and
solid waste in the cement manufacturing.
xii.
An effort shall be made to use of high calorific hazardous waste
in the cement kiln and necessary provision should be made accordingly.
xiii.
As proposed, green belt shall be developed in at least 33 % area in and around the cement plant as
per the CPCB guidelines to mitigate the effects of air emissions in
consultation with local DFO.
xiv.
All the recommendations made in the Charter on Corporate Responsibility
for Environment Protection (CREP) for the Cement plants should be implemented.
xv.
All the commitments made to the public during the Public Hearing /
Public Consultation meeting held on 1st
November 2010 shall be satisfactorily implemented and
a separate budget for implementing the same shall be allocated and information
submitted to the Ministry’s Regional Office at Bangalore.
xvi.
At least 5 % of the total cost of the project shall be earmarked
towards the corporate social responsibility and item-wise details along with
time bound action plan shall be prepared and submitted to the Ministry’s
Regional Office at Shillong. Implementation of such program shall be ensured
accordingly in a time bound manner.
Any
Other Items
17.2.7 Steel Plant [Sponge Iron Plant (2,16,000 TPA),
Induction Furnace, Ingots / Billets, 2,59,200 TPA), Rolling Mill (2,88,000 TPA,
M.S. structures/bars)] along with Captive Power Plant (24 MW) at Sy. No. 7, 8,
13 & 72 Village Ravulapally, Mandal Pargi, District Ranga Reddy, Andhra
Pradesh by M/s T.M. Ispat (India) Limited.
(EC-Reconsideration)
Proposal of M/s T.M.
Ispat (India) Limited for Steel Plant [Sponge Iron Plant (2,16,000 TPA),
Induction Furnace, Ingots / Billets, 2,59,200 TPA), Rolling Mill (2,88,000 TPA,
M.S. structures/bars)] along with Captive Power Plant (24 MW) at Sy. No. 7, 8,
13 & 72 Village Ravulapally, Mandal Pargi, District Ranga Reddy, Andhra
Pradesh was considered and discussed in the 11th and 13th Expert Appraisal Committee-1 (Industry)
meeting held during 24th – 26th June, 2010 and 26th
– 28th August, 2010.
In the 13th EAC-1
meeting, Committee decided that the effluent characteristics data should be
sought and the Ministry may write to MS, APPCB to provide reply within one
month w.r.t the minutes of the Public Hearing. If no response is received,
within specified time, it will be presumed that MS, APPCB has nothing to say in
the matter. The Committee will take decision on the project.
There was no response from the MS, APPCB w.r.t
the minutes of the Public Hearing.
After detailed deliberations, the Committee recommended that the Project Proponent
shall obtain a certificate/undertaking from the gram panchayat regarding how
many of the people who opposed the project are within and out of 5 km radius of
the project site.
17.2.8 Expansion of
Sponge Iron Plant (0.75 MMTPA to 1.75 MMTPA) with integrated facility of Pellet
plant (4.0 MMTPA), Steel Plant (1.5 MMTPA), Captive Power Plant (330 MW) at
Village Salav, P.O. Revdanda, District Raigad, Maharashtra by M/s Welspun Max
Steel Ltd. (Formerly known as M/s Vikram Sponge Iron Limited) - (EC-Reconsideration)
Proposal of M/s Welspun Max Steel Ltd. for expansion of Sponge Iron Plant (0.75 MMTPA to 1.75
MMTPA) with integrated facility of Pellet plant (4.0 MMTPA), Steel Plant (1.5
MMTPA), Captive
Power Plant (330 MW) at Village Salav, P.O. Revdanda, District Raigad,
Maharashtra was considered
and discussed in the 12th Expert
Appraisal Committee-1 (Industry) meeting held during 26th – 28th
July, 2010. The Committee
after detailed deliberations sought the following additional information for
reconsideration of the project:
i.
A map indicating the location of the
project and Phansad wild life sanctuary shall be authenticated by the Chief
Wildlife Warden along with his comments / recommendations.
ii.
A copy of application submitted to
the National Board for Wildlife.
iii.
Demarcation
of CRZ lines from an approved agency shall be submitted along with CRZ
clearance for permissible activities (as applicable).
iv.
Location
of intake and outfall points (with coordinates) should be given. These
locations should be selected based on detailed modeling studies. Details of modeling and the results obtained
there from should be furnished. It may
be kept in view that the intake and outfall points are away from the mangroves.
v.
Details regarding the number of land oustees
and mode of compensation.
vi.
Trace metal analysis of raw material and certificate from
the supplier that the raw material is non toxic and non hazardous.
vii.
SO2 emissions are high. Modeling needs to be
redone (input & output is not matching) and better emission control
measures needs to be provided
viii.
Alternate option of fuel/producer gas in place of natural
gas for the sponge iron plant has to be explored.
The information sought was furnished by the project proponent to
MoEF vide their letter dated
16.11.2010 and the PP also made a presentation before the Committee. The information submitted/presented is as follows
i.
The
project proponent has obtained the location map over satellite imagery
demarcating the location of the project (with coordinates) and Phansad Wild
life Sanctuary(PWS). The map is duly signed by the Project Proponent, DFO –
Wildlife, Thane and Chief Wild Life Warden of Maharashtra. As directed by CWW-
Maharashtra, the project proponent has engaged Bombay Natural History Society
(BNHS), Mumbai to carry out the Bio-Diversity Impact Assessment Study of the
project area including PWS and to develop a conservation Plan. The DCF, Wild
Life – Thane has accorded his permission to the project proponent to get the
field survey done through BNHS for the study. Above facts are verified by Chief
Wildlife Warden of Maharashtra, in his letter no. Desk-23(2)/Survey/2322/
2010-11 dated 16th November 2010.
ii.
The project proponent has applied to National Board of Wild
Life. A copy of the application was submitted.
iii.
The project proponent has approached National Institute of
Oceanography, Goa to demarcate the HTL of the coast of Kundalika as per CRZ Notification
1991 report states that “Based on the
demarcation of relevant HTL and set back line of 150 m measured from HTL, it is
concluded that the proposed development site does not fall within Coastal
Regulation Zone except conveyor, jetty, transmission line, intake pipeline and
discharge water pipeline”. The project proponent is moving separately to CRZ
committee for the approval of the same.
iv.
The project proponent through M/s Green Circle Inc., have
carried out Hydrodynamic modeling to determine to determine the outfall
discharge point. MCZMA has recommended
the project.
v.
Total no. of land oustees is 400. Compensation will be made
in terms of direct payment for land and supported by other CSR activities.
vi.
Trace metal analysis from the coal supplier and their certificate
that the coal will not be toxic/hazardous was submitted.
vii.
As per the air dispersion modeling study shows that
incremental SO2 concentration varies from 7.31 ug/m3 to 18.12 ug/m3.
viii.
A letter from GAIL dated 16.08.2010 expressing their
interest to supply RLNG to M/s Welspun on a long term basis was submitted.
After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other
environmental conditions:
1. Compliance
to all the specific and general conditions stipulated for the existing plant by
the Central/State Govt. should be ensured and regular reports submitted to the
Ministry and its Regional Office at Bhopal.
2. Environmental clearance is subject to
obtaining CRZ clearance
3. Environmental clearance is subject to
obtaining clearance from the National Board of wildlife under the Wild Life
(Protection) Act 1972.
4. A wildlife conservation plan shall be
prepared in consultation with the Office of the Chief Wildlife Warden concerned
and reputed wildlife expert / institute and submitted to the Ministry within
six months along with a road map for implementation. The plan shall specify
budget earmarked for activities to be undertaken.
5. Efforts should be made to reduce RSPM levels in the ambient air and a
time bound action plan should be submitted. Continuous stack monitoring facilities for all the stacks should
be provided and sufficient air pollution control devices viz. Electrostatic
precipitator (ESP), bag house, bag
filters etc. should be provided to keep the emission levels below 50
mg/Nm3 and installing energy efficient technology. No charcoal should be used as raw
material.
7. Gaseous emission levels including secondary fugitive emissions from all
the sources should be controlled within the latest permissible limits issued by
the Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB should be followed. New standards for
the sponge iron plant issued by the
Ministry vide G.S.R. 414(E) dated 30th May, 2008 should be
followed.
8. Vehicular
pollution due to transportation of raw material and finished product should be controlled. Proper arrangements should also be made to
control dust emissions during loading and unloading of the raw material and
finished product.
9. Prior ‘permission’ for the drawl of 86 MLD of water and rain water
harvesting pond from the concerned department shall be obtained.
12. The water consumption should not
exceed 16 m3/Ton of Steel as per prescribed standard.
13. SMS slag should also be properly utilized. All
the other solid waste including broken
refractory mass should be properly disposed off in environment-friendly
manner.
17. A time bound action plan should be
submitted to reduce solid waste, its proper utilization and disposal.
18. A Disaster Management Plan should be
prepared and a copy submitted to the Ministry’s Regional Office at Bhopal, MPCB and CPCB within 3 months
of issue of environment clearance letter.
19. As proposed, green belt should be developed in 33 % area.
20. All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the Steel Plants should be
implemented.
21. All the commitments made to the public
during the Public Hearing / Public Consultation meeting held on 5th
March, 2010 should be satisfactorily implemented and a separate budget for implementing the same should be allocated and
information submitted to the Ministry’s Regional Office at Bhopal.
22. At least 5 %
of the total cost of the project should be earmarked towards the corporate
social responsibility and item-wise details along with time bound action plan
should be prepared and submitted to the Ministry’s Regional Office at Bhopal. Implementation of such program should be
ensured accordingly in a time bound manner.
17.2.9 Integrated Steel Plant
(0.14 MTPA) along with Captive Power Plant (22 MW) at Jamadoba, Post Bankati,
PS Kansa, District Burdwan, West Bengal
by M/s. Jagdamba Fiscal Services Limited- (EC-Reconsideration)
Proposal of M/s.
Jagdamba Fiscal Services Limited for Integrated Steel Plant (0.14 MTPA) along
with Captive Power Plant (22 MW) at Jamadoba, Post Bankati, PS Kansa, District
Burdwan, West Bengal was considered
and discussed in the 11th Expert
Appraisal Committee-1 (Industry) meeting held during 24th – 26th
June, 2010. The Committee
after detailed deliberations sought the following additional information for
reconsideration of the project without
calling the project proponent:
·
Permission from Irrigation Department for water supply
·
Site
specific meteorological data (hourly) at least for one season and AAQ modeling
shall be based on hourly data.
·
Cumulative
impact on the AAQ due to the proposed project and other industries in the
vicinity of the project.
·
Impact
of the ground water due to the proposed project and ground water management
plan.
·
5
% of the total cost shall be earmarked for CSR activities and detailed action
plan in this regard shall be submitted to the Ministry.
The above sought information was submitted by the project
proponent to MoEF vide their letter dated 01.11.2010. After detailed deliberations, the
Committee recommended the project for environmental clearance subject to
following specific conditions along with other
environmental conditions:
i.
Efforts
shall be made to reduce RSPM levels in the ambient air and a time
bound action plan shall be submitted. On-line ambient air quality monitoring
and continuous stack monitoring facilities for all the stacks shall be provided
and sufficient air pollution control devices viz. Electrostatic precipitator
(ESP), gas cleaning plant, venturi scrubber, bag
filters etc. shall be provided to keep the emission levels below 50 mg/Nm3 by installing energy efficient
technology.
ii.
As
proposed, Electrostatic precipitator (ESP) shall be provided to WHRB, CFBC and
DRI plants to control SPM levels within 50 mg/Nm3. Fume extraction
system shall be provided to induction furnaces to control the emissions within
the prescribed standards.
iii.
The
National Ambient Air Quality Standards issued by the Ministry vide G.S.R. No.
826(E) dated 16th November, 2009 shall be followed.
iv.
Gaseous
emission levels including secondary
fugitive emissions from all the
sources shall be controlled within the latest permissible limits issued by the
Ministry and regularly monitored. Guidelines/Code of Practice issued by the
CPCB shall be followed. New
standards for the sponge iron
plant issued by the Ministry vide
G.S.R. 414(E) dated 30th May, 2008 should be followed.
v.
Hot
gases from DRI kiln shall be passed through Dust Settling Chamber (DSC) to
remove coarse solids and After Burning Chamber (ABC) to burn CO completely and
used in waste heat recovery boiler (WHRB). The gas then shall be cleaned in ESP
before leaving out into the atmosphere through ID fan and stack.
vi.
Total
water requirement shall not exceed 2,110 KLD. Efforts shall further be made to
use maximum water from the rain water harvesting sources. Use of air cooled condensers shall be
explored and closed circuit cooling system shall be provided to reduce water
consumption and water requirement shall be modified accordingly. All the
effluent should be treated and used for ash handling, dust suppression and
green belt development. No
effluent shall be discharged and ‘zero’ discharge shall be adopted. Sanitary
sewage should be treated in septic tank followed by soak pit.
vii.
Efforts shall be made to make use of rain
water harvested. If needed, capacity of the reservoir should be enhanced to
meet the maximum water requirement. Only balance water requirement shall be met
from other sources.
viii.
Regular monitoring of influent and effluent
surface, sub-surface and ground water (including chromite) should be ensured
and treated wastewater should meet the norms prescribed by the State Pollution
Control Board or described under the E(P) Act whichever are more stringent.
Leachate study for the effluent generated and analysis shall also be regularly
carried out and report submitted to the Ministry’s Regional Office at Bhubaneswar, SPCB and CPCB.
ix.
The water consumption shall not
exceed as per the standard prescribed for the steel plants.
x.
All the coal fines, char
from DRI plant shall be utilized in AFBC boiler of
power plant and no char shall be used for briquette making or disposed off
anywhere else. AFBC boiler shall be installed simultaneously along with the DRI
plant to ensure full utilization of char from the beginning.
Scrap shall be used in steel melting shop (SMS) and SMS slag and kiln
accretions shall be properly utilized. All the
other solid waste including broken
refractory mass shall be properly disposed off in
environment-friendly manner.
xi.
Proper utilization of fly ash shall
be ensured as per Fly Ash Notification, 1999 and subsequent amendment in 2003.
xii.
Vehicular pollution due to
transportation of raw material and finished products shall be
controlled. Proper arrangements shall also be made to control dust
emissions during loading and unloading of the raw material and finished
product.
xiii.
All internal roads shall be black
topped. The roads shall be regularly cleaned with mechanical sweepers. A 3-tier
avenue plantation using native species shall be developed along the roads.
Facilities for parking of trucks carrying raw coal from the linked coalmines
shall be created within the Unit.
xiv.
Proper handling, storage,
utilization and disposal of all the solid waste shall be ensured and regular
report regarding toxic metal content in the waste material and its composition,
end use of solid/hazardous waste should be submitted to the Ministry’s Regional
Office at Bhubaneswar,
SPCB and CPCB.
xv.
A time bound action plan shall be
submitted to reduce solid waste, its proper utilization and disposal.
xvi.
Risk and Disaster Management Plan
along with the mitigation measures shall be prepared and a copy submitted to
the Ministry’s Regional Office at Bhubaneswar,
SPCB and CPCB within 3 months of issue of environment clearance letter.
xvii.
As proposed, green
belt shall be developed in 33 % of plant area as per the CPCB guidelines in
consultation with the DFO.
xviii.
All the recommendations made in the
Charter on Corporate Responsibility for Environment Protection (CREP) for the
Steel Plants should be implemented.
xix.
All the commitments made to the
public during the Public Hearing / Public Consultation meeting held on 18th August, 2009 should be
satisfactorily implemented and a
separate budget for implementing the same should be allocated and information
submitted to the Ministry’s Regional Office at Bhubaneswar.
xx.
At least 5 % of the total cost of
the project should be earmarked towards the corporate social responsibility and
item-wise details along with time bound action plan should be prepared and
submitted to the Ministry’s Regional Office at Bhubaneswar.
Implementation of such program should be ensured accordingly in a time bound
manner.
xxi.
Rehabilitation and Resettlement Plan for
the project affected population including tribals, if any shall be implemented
as per the policy of the State Govt. in consultation with the State Govt. of West
Bengal. Compensation paid in any case should not be less than the norms
prescribed under the National Resettlement and
Rehabilitation Policy, 2007.
xxii.
The company shall provide housing
for construction labour within the site with all necessary infrastructure and
facilities such as fuel for cooking, mobile toilets, mobile STP, safe drinking
water, medical health care, crèche etc. The housing may be in the form of
temporary structures to be removed after the completion of the project.
17.2.10
Enhancement
in Cement production (from 3.9 MTPA to 4.48 MTPA) at Awarpur Cement Works,
Taluka Korpana, District Chandrapur, Maharashtra by M/s Ultra Tech Cement
Limited – (Amendment in Environmental Clearance)
Environmental
Clearance to M/s Ultra Tech Cement Limited for the Enhancement in Cement
production (3.9 MTPA to 4.48 MTPA) at Awarpur Cement Works, Taluka Korpana,
District Chandrapur, Maharashtra
was accorded on 02.08.2010.
The project proponent vide their letter dated 26.10.2010
informed MoEF that in the Specific Condition No. 2 of the EC letter, it was
asked to maintain the particulate emissions below 50 mg/Nm3. The permissible
limit for particulate matter emissions for the existing production capacity has
been granted as 150 mg/Nm3 (as per Consent to Operate issued by MPCB
vide letter no. BO/PCI-II/EIC No. CH-121-09/R/CC-371, dated 11.08.2009). Being
an existing unit designed to maintain emissions below 150 mg/Nm3, it
is not possible for them to keep the emissions below 50 mg/Nm3.
However, adequate mitigation measures are being taken to maintain the emissions
below 100 mg/Nm3. Hence, an amendment in this regard was requested.
The Committee after
detailed discussion decided that the company shall make an effort to mitigate
the dust level within 50 mg/Nm3 by installing the pollution control equipment.
17.2.11
Integrated
Steel Plant (1.9 MTPA) at Village Jharbandh, Galapada and Tarakabeda, District
Dhenkanal in Orissa by M/s Rungta Mines
Limited – (Amendment in Environmental Clearance)
Environmental
Clearance to M/s Rungta Mines Limited for Integrated Steel Plant (1.9
MTPA) at Village Jharbandh, Galapada and Tarakabeda, District Dhenkanal in
Orissa was accorded on 02.08.2010. The project proponent vide their letter dated
25.09.2010 informed the following to MoEF:
“In the course of technical
discussions with our consultants M/s MECON, Ranchi and prospective vendors, we
have been advised that in addition to the facilities as approved in the EC, it
is desirable to have additional facilities such as vacuum degassing unit and
auxiliary facilities like limestone and dolomite calcination plant and oxygen
plant.
For production of quality steel with
lower gas content, vacuum degassing unit is a technological necessity in phase-I
and phase-II for production of steel grades such as electrode quality, cold
heading quality, spring steel, bearing steel and free cutting steel. To improve
the lining life of the electric arc furnace (EAF) and for desulphurization and
dephosphorisation, dolomite and limestone is added as a flux in electric arc
furnace. Similarly oxygen is required to decarburize the steel in electric arc
furnace.
Hence, installation of limestone &
dolomite calcination plant and oxygen plant is a technological necessity for
producing good quality steel through EAF route with following capacities:
S.
No. |
Particulars |
Total
Capacity |
1 |
Lime plant |
1x300 TPD |
2 |
Dolo Plant |
1x300 TPD |
3 |
Oxygen Plant |
1x200 TPD |
4 |
Vacuum Degassing unit |
1x70 TPD |
Above proposed additional units are non-pollutant and
non-hazardous and help us in reducing Sulphur and Phosphorous in final product.”
Therefore, an amendment to the EC dated 02.08.2010
was requested so as to include the above additional and auxiliary facilities.
After detailed deliberations, the
Committee recommended for amendment in Environmental Clearance dated 02.08.2010
with the following additional Specific Condition:
“The existing pollution load shall not increase and the
individual components should be environmentally compliant”.
Proposals
for TORs
17.2.12 Proposed 0.25 MTPA Steel Plant along
with 28 MW Captive Power Plant at Village Karanda, Tehsil Hindol, District
Dhenkanal in Odisha by M/s Tecton Ispat
Pvt. Limited- (TORs)
The
project authorities and their consultant
M/s Visiontek Consultancy Services Pvt. Ltd., Bhubaneswar gave a detailed
presentation on the salient features of the project and proposed environmental
protection measures to be undertaken along with the draft TORs for preparation
of EIA/EMP. All the Steel Plants
are listed at S.No. 3(a) in Primary Metallurgical Industries under category ‘A’
of the Schedule of EIA Notification, 2006 and
appraised at the Central level.
M/s Tecton Ispat Pvt. Limited have
proposed for 0.25 MTPA Steel Plant along with 28 MW Captive Power Plant at
Village Karanda, Tehsil Hindol, District Dhenkanal in Odisha. No national Park/wild life sanctuary is
located within 10 km radius of the project site. Total proposed
project area is of 128.0 acres and Green belt will be
developed in 33 % of the total plant area. Total proposed project area is of 128.0 acres.
Total cost of the project is Rs. 694.00 Crores. Rs. 38 Crores and Rs. 7.6
Crores will be earmarked towards capital cost and recurring cost for
environmental pollution control measures. Following are the details of the
proposed plants:
Sl. No. |
Products |
Plant Facilities |
Quantity in TPA |
1. |
Sponge Iron |
DRI (2 x 350 TPD ) |
2,10,000 |
2. |
Pig Iron/ Hot Metal |
MBF (1x125 m3) |
75,000 |
3. |
SMS |
1 x 30T EAF + 1 x 15T IF, 1 x 30T +1 x 35T LRF, Billet Caster 2
x 3 Strand (6/11 meter) with Continuous casting machine. |
2,50,000 |
4. |
Power |
28 MW (14
MW WHRB + 14 MW AFBC) |
28 MW |
Iron Ore, Dolomite, Coal,
Coke, Limestone, Ferro Alloys and Scrap are the major raw materials used in the
plant process. The unit’s saleable product will be Steel Billets and Power.
Gaseous emission will be
controlled by installing air pollution control equipments. Dust suppression
will be done by water sprinkling to control fugitive emissions due to
transportation activities. Fume extraction system with bag filters will be
provided to DRI plant. MBF will be equipped with bag filter and ventury scrubbers.
Spark arrester and bag filter will be provided to SMS plant. Air pollution from
CPP will be controlled by ESP and ash conditioning and moistening system. Water sprinkling will be done along the haul
roads to control dust arising from vehicular movement.
Total water
requirement for the proposed project is of 295 m3/hr. Settling
tank will be installed for the treatment of wastewater and the treated water
will be used for dust suppression, plantation etc. Cooling Blow down from Power
Plant will be routed to Common Basin.
The treated water from Common Basin will be re-used for dust
suppression, ash handling and green belt development. Domestic wastewater will
be treated in septic tank and discharged to soak pit. Zero discharge norms will
be maintained in the proposed plant.
Solid waste i.e.
char generated from DRI production unit will be reused in Power Plant and dust
will be disposed in ash mound. Slag from
MBF and SMS plant will be used for land filling and road construction. Ash from power plant will be sold to fly ash
brick and cement manufacturers.
Ear muffs/ear plugs will
be provided to workers working in high noise prone areas.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the site
3.
Detailed
fluoride assessment survey & management plan
4.
Coal
linkage documents
5.
Revised and Detailed lay out
plan
6.
Storage
of Ground water in 40 acres of land.
7.
Cumulative
impacts of the nearby industries shall be estimated.
8.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper longitude/latitude/heights
with min. 100/200 m. contours should be included. 3-D view i.e. DEM (Digital
Elevation Model) for the area in 10 km radius from the proposal site. Present
land use should be prepared based on satellite imagery. High-resolution satellite
image data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10 Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
9.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
10. Location of national
parks / wildlife sanctuary / reserve forests within 10 km. radius should
specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
11. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
12.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
13. Details and
classification of total land (identified and acquired) shall be included.
14. A list of industries
containing name and type in 10 km radius shall be incorporated.
15. Residential colony
shall be located in upwind direction.
16. List of raw material required,
analysis of all the raw materials and source along with mode of transportation
should be included. All the trucks for raw material and finished product
transportation must be “Environmentally Compliant”.
17. Action plan for
excavation and muck disposal during construction phase.
18. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
19. Manufacturing process
details for all the plants shall be included.
20. Mass balance for the
raw material and products shall be included.
21. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
22. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
23. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
24.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account the
pre-dominant wind direction, population zone and sensitive receptors including
reserved forests.
25. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
26. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
27. Determination of atmospheric
inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
28. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
29. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
30.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
31.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
32. A plan for the
utilization of waste/fuel gases in the WHRB for generating power have to be set
out.
33. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
34. One season data for
gaseous emissions other than monsoon season is necessary.
35. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
36. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
37. Source of surface/ground
water level, site (GPS), cation, anion (Ion Chromatograph), metal trace element
(as above) chemical analysis for water to be used. If surface water is used
from river, rainfall, discharge rate, quantity, drainage and distance from
project site should also be included. Information regarding surface hydrology
and water regime should be included.
38. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
39. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
40. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
41. A note on the impact
of drawl of water on the nearby River during lean season.
42. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
43. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
44. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
45. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
46. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
47. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
48. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
49. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
50. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
51. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
52. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
53. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
54. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
55. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
56. Details regarding
expected Occupational & Safety Hazards. Protective measures for
Occupational Safety & Health hazards so that such exposure can be kept
within permissible exposure level so as to protect health of workers. Health of
the workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far &
Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations and
plan of monthly and yearly report of the health status of workers with
special reference to Occupational Health and Safety.
57. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
58. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
59. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
60. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
61. A note on
identification and implementation of Carbon Credit project should be included.
62. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Orissa State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The TORs prescribed shall be valid
for a period of two years for submission of the EIA/EMP reports, after public
consultation.
17.2.13 Proposed 100 MVA (1,65,000 MTPA)
capacity High Carbon Ferro Chrome Plant at Village Kolathapangi, PS-
Gurudijhatia, Tehsil Athagarh, District Cuttack in Orissa by M/s Cronimet Alloys India Limited- (TORs)
The
project authorities and their consultant
M/s ERS (I) Pvt. Ltd., Bhubaneswar gave a detailed presentation on the salient
features of the project and proposed environmental protection measures to be
undertaken along with the draft TORs for preparation of EIA/EMP. All the Ferro
Alloy Plants are listed
at S.No. 3(a) in Primary Metallurgical Industries under category ‘A’ of the
Schedule of EIA Notification, 2006 and appraised at
the Central level.
M/s Cronimet Alloys India Limited have
proposed for 100 MVA (1,65,000 MTPA) capacity High Carbon Ferro Chrome Plant at
Village Kolathapangi, PS- Gurudijhatia, Tehsil Athagarh, District Cuttack in
Orissa. No national Park/wild life sanctuary is located within 10
km radius of the project site. Out of the total project area of 51 Acres,
41 Acres is in possession and balance 10 Acres of land is under process of
acquisition. Around 33% (17.0
Acres) of the total land will be developed as green belt. Total cost of the project is Rs. 330
Crores. Rs. 18.0 Crores and Rs. 1.8 Crores will be earmarked towards capital
cost and recurring cost/annum for environmental pollution control
measures.
A 100
MVA (6 X 16.5 MVA) Sub Merged Arc Furnace with a production capacity of
1,65,000 MTPA of High carbon Ferro Chrome along with a Beneficiation Plant (1,00,000
MTPA), Briquetting Plant (4,50,000 MTPA) and a Metal Recovery Plant (16,500 MTPA)
would be installed.
Water sprinklers will
be used to suppress dust emission during raw material handling and black topping of internal roads would be done to avoid particulate matter
emissions due to plying of
trucks.
Dry
Fog dust suppression system and bag filters will be used to control dust emission
during the briquetting process.
Bag
filters will
be used to control gaseous fumes and dust emission from the submerged arc furnace
and Suction Hood followed by bag filters will
be used to control air pollution from tapping process.
The total requirement of water will
be 100 m3/day. Ground water available at site will be used during
construction stage with prior permission from the Central Ground Water
Authority. Efforts shall be made to reuse the effluent generated
after
adequate treatment. Effluent from the tailing pond and thickener will be treated in
a chemical dosing tank followed by settling tank. Runoff water from the storage yard will be collected in drains and
treated along with tailing pond effluent.
Sewage generated due to domestic activities will be treated in a septic tank followed by soak pit. Rainwater harvesting pit
are
envisaged to recharge ground water.
Dust from Bag Filter of Submerged
arc furnace and tapping process will be collected, stored in storage yards and
used in briquetting process. Slag generated will be dumped in the secured landfill
within the plant premises. Used oil will be disposed to authorized reprocessing
units having valid authorization from Orissa State Pollution Control Board.
1.
Executive summary of the project.
2.
Photographs of plant area.
3.
A
line diagram/flow sheet for the process and EMP
4.
A copy of coal linkage documents
5.
Proposal
should be submitted to the Ministry for environment clearance only after acquiring
total land. Necessary documents indicating acquisition of land should be
included.
6.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in
7.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
8.
Location
of national parks / wildlife sanctuary / reserve forests within
9.
A
list of industries within 10 km radius of the plant area.
10.
Details
and classification of total land (identified and acquired) should be included.
11.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within
12.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
13.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
14.
Mass
balance for the raw material and products should be included.
15.
Energy
balance data for all the components of ferro alloy plant should be
incorporated.
16.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
17.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
18.
Ambient
air quality at 8 locations within the study area of
19.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
20.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
21.
Air
quality modeling for ferro alloy plant for specific pollutants needs to be
done. APCS for the control of emissions
should also be included to control emissions within 50 mg/Nm3.
22.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
23.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
24.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
25.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
26.
Presence
of aquifer/aquifers within
27.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
28.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
29.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
30.
A
note on the impact of drawl of water on the nearby River during lean season.
31.
Action
plan for rainwater harvesting measures.
32.
Surface
water quality of nearby River (
33.
If
the site is within
34.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
35.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
36.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
37.
Identification
and details of land to be used for all type of slag disposal in the secured
land fill as per CPCB guidelines should be included.
38.
End
use of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
39.
Provision
of Toxic Chemical Leachability Potential (TCLP) test for the slag and its end
use should be included.
40.
Action plan for chrome recovery and its solid waste
management plan.
41.
Action
plan for the green belt development plan in 33 % area should be included.
42.
Chrome
water treatment/management plan
43.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
44.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
45.
Details
regarding expected Occupational & Safety Hazards. Protective measures for
Occupational Safety & Health hazards so that such exposure can be kept
within permissible exposure level so as to protect health of workers. Health of
the workers with special reference to Occupational Health. Plan of exposure
specific health status evaluation of workers; pre placement and periodical
health status of workers; plan of evaluation of health of workers by pre
designed format, chest x ray, Audiometry, Spirometry Vision testing (Far &
Near vision, colour vision and any other ocular defect) ECG, during pre
placement and periodical examinations and
plan of monthly and yearly report of the health status of workers with
special reference to Occupational Health and Safety.
46.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details along with time bound
action plan should be included. Socio-economic development activities need to
be elaborated upon.
47.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
48.
Public
hearing issues raised and commitments made by the project proponent on the same
should be included separately in EIA/EMP Report in the form of tabular chart
with financial budget for complying with the commitments made.
49.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed by the
Expert Appraisal Committee-1 (Industry)
should be considered for preparation of
EIA / EMP report for the above mentioned project in addition to all the
relevant information as per the ‘Generic Structure of EIA’ given in Appendix
III and IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be
submitted to the Orissa State Pollution Control Board for public hearing. The
issues emerged and response to the issues shall be incorporated in the EIA report.
The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP along with Public hearing
proceedings.
17.2.14 Expansion of existing DRI plant
(66,000 TPA) by installation of 0.85 MTPA Iron Ore Beneficiation Plant, 0.6
MTPA Pellet Plant & 10 MW Captive Power Plant at Village Tumkela, Tehsil
Bonai, District Sundargarh in Orissa by M/s
Vikram Pvt. Limited- (TORs)
The
project authorities and their consultant
M/s Sun Consultancy and Services, Bhubaneswar gave a detailed presentation on
the salient features of the project and proposed environmental protection
measures to be undertaken along with the draft TORs for preparation of EIA/EMP.
All the Steel Plants are listed
at S.No. 3(a) in Primary Metallurgical Industries under category ‘A’ of the
Schedule of EIA Notification, 2006 and appraised at
the Central level.
M/s Vikram Pvt. Limited have proposed
for expansion of existing DRI plant (66,000 TPA) by installation of 0.85 MTPA
Iron Ore Beneficiation Plant, 0.6 MTPA Pellet Plant & 10 MW Captive Power
Plant at Village Tumkela, Tehsil Bonai, District Sundargarh in Orissa. No
national Park/wild life sanctuary is located within 10 km radius of
the project site. Total project area is 82.0 acres of which 27
acres area has been earmarked for green belt development. Total cost of the project is Rs. 276.19
Crores. Rs. 13.81 Crores and Rs. 0.27 Crores will be earmarked towards capital
cost and recurring cost/annum for environmental pollution control measures.
Iron Ore Fines (8,57,494 TPA), Coke Fines (12,000
TPA), Limestone (12,000 TPA), Bentonite (4,200 TPA) and Coal Fines (62,117 TPA) are the rawmaterials that will be used. Following are the existing and proposed
facilities:
Unit |
Product |
Existing |
Proposed |
Total |
DRI Plant |
Sponge Iron |
66,000 TPA |
- |
2 × 100 TPD (66,000 TPA) |
Beneficiation Plant |
Concentrate |
- |
6,60,000 TPA [Throughput :8,50,000 TPA] |
6,60,000 TPA [Throughput :8,50,000 TPA] |
Pelletisation Plant |
Pellet |
- |
6,00,000 TPA |
6,00,000 TPA |
Captive Power Plant WHRB AFBC |
Power |
- |
2 X 10 tph 1 X 40 tph |
10 MW |
There will be emissions during handling of raw materials and
products, which will be controlled by dust suppression system. The emissions from
the production process will be passed through Scrubber and Bag filters / ESP to
retain flue dust particles and then it will be released through high stack. The
PM level will be maintained below 100 mg/Nm3.
Total
water requirement will be 3,132 m3/day which will be sourced from
bore wells. There will be no effluent
generation from the plant. The waste water generated from the plant shall be
recycled & utilized in beneficiation plant, dust suppression &
gardening. As such the plant will work on zero discharge basis.
Solid
waste generated from beneficiation plant shall be dumped in the waste disposal
yard. Bottom ash shall be used for low land filling & road construction.
Fly Ash shall be used for brick manufacturing, construction of road and stored
in ash mound for subsequent use.
Total
power requirement will be about 10.8 MW out of which 10 MW will be met through
captive generation and 0.8 MW will be drawn from the State grid. The
consumption of furnace oil will be about 12,000 KL per annum where as LDO
consumption will be around 200 KL per annum.
After detailed deliberations, the Committee prescribed
following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the existing and proposed plant area.
3.
Compliance to the
conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
4.
A
line diagram/flow sheet for the process and EMP
5.
Coal
linkage documents
6.
Detailed
lay out plan
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. Present land use should be prepared based on satellite
imagery. High-resolution satellite image data having 1m-5m spatial resolution
like quickbird, Ikonos, IRS P-6 pan sharpened etc. for the 10 Km radius area
from proposed site. The same should be used for land used/land-cover mapping of
the area.
8.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
9.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
10. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
11.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
12. Details and
classification of total land (identified and acquired) shall be included.
13. A list of industries
containing name and type in 10 km radius shall be incorporated.
14. Residential colony
shall be located in upwind direction.
15. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
16. Action plan for
excavation and muck disposal during construction phase.
17. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
18. Manufacturing process
details for all the plants shall be included.
19. Mass balance for the
raw material and products shall be included.
20. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
21. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
22. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
23.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors including
reserved forests.
24. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
25. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
26. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
27. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
28. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
29.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
30.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
31. A plan for the
utilization of waste/fuel gases in the WHRB for generating power have to be set
out.
32. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
33. One season data for
gaseous emissions other than monsoon season is necessary.
34. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
35. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
36. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
37. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
38. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest rainwater
from the roof tops and storm water drains to recharge the ground water and also
to use for the various activities at the project site to conserve fresh water
and reduce the water requirement from other sources. Rain water harvesting and groundwater recharge
structures may also be constructed outside the plant premises in consultation
with local Gram Panchayat and Village Heads to augment the ground water level.
Incorporation of water harvesting plan for the project is necessary, if source
of water is bore well.
39. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
40. A note on the impact
of drawl of water on the nearby River during lean season.
41. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
42. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
43. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
44. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
45. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
46. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
47. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
48. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
49. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
50. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
51. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
52. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
53. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
54. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
55. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
56. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
57. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
58. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
59. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
60. A note on
identification and implementation of Carbon Credit project should be included.
61. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It was decided that ‘TORs’
prescribed by the Expert Appraisal
Committee-1 (Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to Orissa State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. The final EIA report shall be submitted to the Ministry for
obtaining environmental clearance.
The TORs prescribed shall be valid
for a period of two years for submission of the EIA/EMP reports, after public
consultation.
17.2.15 Proposed expansion of Cement Grinding
Unit (from 200 TPD to 325 TPD) at 15th Mile, GS Road, N.H. No.-40,
Village Byrnihat, Taluk Sonapur, District Kamrup (M), Assam by M/s Mahashakti Cements – (TORs)
The
project authorities and their consultant
M/s M/s En-vision Enviro Engineers Ltd., Surat gave a detailed presentation on
the salient features of the project and proposed environmental protection
measures to be undertaken along with the draft TORs for preparation of EIA/EMP.
All stand alone cement grinding
units are covered under Category ‘B’ as per para 3(b) of the Schedule of the
EIA notification 2006, but due to absence of SEIAA for Assam, the proposal is appraised
at central level.
M/s Mahashakti Cements have proposed for expansion of Cement
Grinding Unit (from 200 TPD to 325 TPD) at 15th Mile, GS Road, N.H.
No.-40, Village Byrnihat, Taluk Sonapur, District Kamrup (M), Assam. The total
land requirement for the proposed plant is 8,640 sq.m which is already in the
possession of the project proponent. About 2,851.2 sq m of plant area will be developed
under green belt. No forest land is involved. The Umtru River flows at a
distance of 100 m from the project site. Site is in Zone-V category of earth
quake. The total cost of the project will be Rs. 382 Lakhs. Rs.80 Lakhs and
Rs.12 Lakhs will be earmarked towards total capital cost and recurring
cost/annum for environmental pollution control measures.
The manufacturing process of cement
consists of mixing, drying and grinding of clinker, gypsum & fly ash.
The raw materials required for the proposed plant will be Clinker (Existing-
130 TPD, Proposed- 211), Gypsum (Existing - 10 TPD to Proposed- 16 TPD) and fly
ash (Existing - 60 TPD to Proposed -98). Raw materials will be procured from
various places and transported by road through trucks.
Source of air pollution from the
proposed plant will be Cement Mill and packing plant. For control of air
pollution, twin cyclone separator followed by reverse pulse jet type bag filter
will be provided.
The total existing water requirement
is 3 KLD and for proposed expansion, water requirement will be 1 KLD which
shall be met through ground water using Bore Well. There is no wastewater
generation due to the process. Domestic wastewater will be generated which will
be discharge through septic tank and soak pit. The waste collected in control
equipments will be recycled in the process and the spent lube oil will be given
to registered recyclers.
In existing plant, the total power
requirement is 600 KW, After proposed expansion, total power requirement will
be 800 KW which will be sourced from the Assam State Electricity Board. A DG set of 750
KVA will be installed to meet the emergency power requirement.
After detailed deliberations, the Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1. Executive summary of
the project.
2. Photographs of the
existing and proposed plant area.
3. Compliance to the conditions stipulated in the Environmental
Clearance / NOC granted by the SPCB.
4. Coal linkage documents
5. A line diagram/flow
sheet for the process and EMP
6.
Proposal
should be submitted to the Ministry for environment clearance only after
acquiring total land. Necessary documents indicating acquisition of land should
be included.
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site.
8.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
9.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing landuse/landcover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
10.
A
list of industries within 10 km radius of the plant area.
11.
Details
and classification of total land (identified and acquired) should be included.
12.
Project
site layout plan showing raw materials and other storage plans, bore well or
water storage, aquifers (within 1 km.) dumping, waste disposal, green areas,
water bodies, rivers/drainage passing through the project site should be
included.
13.
List
of raw material required and source along with mode of transportation should be
included. All the trucks for raw material and finished product transportation
must be “Environmentally Compliant”.
14.
Quantification
& Characterization of solid /hazardous waste & its action plan for
management should be included.
15.
Mass
balance for the raw material and products should be included.
16.
Energy
balance data for all the components of plant should be incorporated.
17.
Design
details of Ferro Alloy Plant and manufacturing process details should be
included.
18.
Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall is necessary.
19.
Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
20.
The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of RSPM and incorporating of RSPM data.
21.
Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
22.
Air
quality modeling for specific pollutants needs to be done. APCS for the control of emissions should also
be included to control emissions within 50 mg/Nm3.
23.
Ambient
air quality as per National Ambient Air Quality Emission Standards issued by
the Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should
be included.
24.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
25.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
26.
An
action plan to control and monitor secondary fugitive emissions from all the
sources as per the latest permissible limits issued by the Ministry vide G.S.R.
414(E) dated 30th May, 2008.
27.
Presence
of aquifer/aquifers within 1 km of the project boundaries and management plan
for recharging the aquifer should be included.
28.
Source
of surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
29.
Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
30.
‘Permission’ for the drawl of water should be
obtained. Water balance data must be provided.
31.
A
note on the impact of drawl of water on the nearby River during lean season.
32.
Action
plan for rainwater harvesting measures.
33.
Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
34.
If
the site is within 10 km radius of any major river, Flood Hazard Zonation
Mapping is required at 1:5000 to 1;10,000 scale indicating the peak and lean
river discharge as well as flood occurrence frequency.
35.
Pretreatment
of raw water, treatment plant for waste water should be described in detail.
Design specifications may be included.
36.
Ground
water monitoring minimum at 8 locations and near solid waste dump zone,
Geological features and Geo-hydrological status of the study area are essential
as also. Ecological status (Terrestrial
and Aquatic) is vital.
37.
Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources should also be included.
38.
Acton
plan for the green belt development plan in 33 % area should be included.
39.
Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
40.
Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
41.
Occupational
health:
a) Details of existing Occupational &
Safety Hazards. What are the exposure levels of above mentioned hazards and
whether they are within Permissible Exposure level (PEL). If these are not
within PEL, what measures the company has adopted to keep them within PEL so
that health of the workers can be preserved,
b) Details of exposure specific health
status evaluation of worker. If the
workers’ health is being evaluated by pre designed format, chest x rays,
Audiometry, Spirometry, Vision testing (Far & Near vision, colour vision
and any other ocular defect) ECG, during pre placement and periodical
examinations give the details of the same. Details regarding last month
analyzed data of abovementioned parameters as per age, sex, duration of
exposure and department wise.
c) Annual report of heath status of
workers with special reference to Occupational Health and Safety.
42.
At
least 5 % of the total cost of the project should be earmarked towards the
corporate social responsibility and item-wise details along with time bound action
plan should be included. Socio-economic development activities need to be
elaborated upon.
43.
Total
capital cost and recurring cost/annum for environmental pollution control
measures should also be included.
44.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
The
Expert Committee (Industry) decided that PAs may be communicated the above
‘TORs’ for the preparation of EIA/EMP. As soon as the EIA/EMP report is prepared,
the same may be submitted by the PAs to the MOEF for obtaining environmental
clearance. The
proposal is exempted from public hearing by
categorizing in B-2 category due to use of energy efficient technology, no
clinker manufacturing at the proposed site, no sensitive area within 10 km.
radius, ‘zero’ effluent discharge, utilization of all the solid waste in the
process itself including utilization of fly ash etc.
The
TORs prescribed shall be valid for a period of two years for submission of the EIA/EMP
report.
17.2.16 Expansion of Billet plant ( from 90,000
TPA to 1,80,000 TPA) and installation of 2x350 TPD Sponge Iron, 16 MW WHRB and
8 MW AFBC at Industrial Growth Centre Borai, Village Rasmada, District Durg,
Chhattisgarh by M/s Brahaspati Iron
& Steel Co. Pvt. Limited- (TORs)
The
project authorities and their consultant
M/s J.M. EnviroNet Pvt. Ltd., Gurgaon gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft TORs for preparation of EIA/EMP report. All the Steel Plants are listed at S.No.
3(a) under Primary Metallurgical Industries under category ‘A’ of the Schedule
of EIA Notification, 2006 and appraised at the Central level.
M/s Brahaspati Iron & Steel Co.
Pvt. Limited have proposed for expansion of Billet plant from 90,000 TPA to
1,80,000 TPA and installation of 2x350 TPD Sponge Iron, 16 MW WHRB and 8 MW
AFBC at Industrial Growth Centre Borai, Village Rasmada, District Durg,
Chhattisgarh. No national Park/wild life
sanctuary is located within 10 km radius of the project site. Total
land available for the project activity is 17.14 ha. and no additional land is required for Proposed Project
Expansion. Green belt will be developed in 5.7 ha. Total cost of the project is
Rs. 163.7 Crores. Rs. 4.17 Crores and Rs. 0.5 Crores will be earmarked towards
capital cost and recurring cost/annum for environmental pollution control
measures.
Production capacities of different units of
the Project are as follows:-
S.
No. |
Details |
Existing
Capacity |
Proposed
Expansion/ Additional Capacity |
After
Expansion |
1. |
Billet
Plant |
90,000
TPA |
90,000
TPA |
1,80,000
TPA |
2. |
Sponge
Iron Plant |
---- |
2,00,000
TPA |
2,00,000
TPA |
3. |
Captive
power Plant |
---- |
24
MW •
WHRB:
16 MW & •
AFBC
: 8MW |
24
MW •
WHRB
: 16 MW & •
AFBC
: 8MW |
Covered
conveyor belt will be used for transfer of materials. Raw material will be
stored in covered Silos. Stack emission will be maintained below 50 mg/Nm3.
CPCB guidelines for control of fugitive emissions will be followed. All the
roads inside the plant will be black topped to reduce fugitive emissions. The
sprinkling of water will
be done along
the haul roads in the
plant premises to control the
dust arising due to
the movement of
vehicular traffic.
Total Water requirement {Existing (30 KLPD)
+Proposed (3,000 KLPD)} of the Project will be around 3,030 KLPD which will be sourced from Chhattisgarh Industrial Developmental
Corporation (CSIDC), Permission for the same is under process. There will
be zero discharge from the project. The water will be mainly used to control
the temperature of the product & flue gases by indirect cooling & direct
cooling. The process is based on closed circuit system, hence there will be
only evaporation losses. Water will be treated in primary & secondary
settling tank and will be recycled back for further use in process.
Dolo Char
(50,000 TPA) will be utilized partly in FBC boiler and remaining will be
supplied to brick manufacturers. Bag filter Dust & Ash generated from ESP
of FBC Boiler (1,62,000 TPA) will be given to cement plants/brick manufacturers
in the nearby area.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the existing and proposed plant area.
3.
Compliance to the
conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
4.
A
line diagram/flow sheet for the process and EMP
5.
Coal
linkage documents
6.
Detailed
lay out plan
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000
scale on an A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10
kms and further 10 kms on A3/A2 sheets with proper longitude/latitude/heights
with min. 100/200 m. contours should be included. 3-D view i.e. DEM (Digital
Elevation Model) for the area in 10 km radius from the proposal site. Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from proposed site. The
same should be used for land used/land-cover mapping of the area.
8.
Topography
of the area should be given clearly indicating whether the site requires any
filling. If so, details of filling, quantity of fill material required, its
source, transportation etc. should be given.
9.
Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
10. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
11.
Coordinates
of the plant site as well as ash pond with topo sheet shall be included.
12. Details and
classification of total land (identified and acquired) shall be included.
13. A list of industries
containing name and type in 10 km radius shall be incorporated.
14. Residential colony
shall be located in upwind direction.
15. List of raw material
required, analysis of all the raw materials and source along with mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
16. Action plan for
excavation and muck disposal during construction phase.
17. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
18. Manufacturing process
details for all the plants shall be included.
19. Mass balance for the
raw material and products shall be included.
20. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
21. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
22. Data generated in the
last three years i.e. air, water, raw material properties and analysis (major,
trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
23.
One
season site-specific micro-meteorological data using temperature, relative
humidity, hourly wind speed and direction and rainfall and AAQ data (except
monsoon) should be collected. The monitoring stations should take into account
the pre-dominant wind direction, population zone and sensitive receptors
including reserved forests.
24. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
25. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical characterization of RSPM and
incorporating of RSPM data.
26. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
27. Air quality modelling
for steel plant for specific pollutants needs to be done. APCS for the control of emissions from the
kiln and WHRB should also be included to control emissions within 50 mg/Nm3.
Existing stack emission data.
28. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
29.
Air
Quality Impact Predication Modelling based on ISCST-3 or the latest models.
30.
Impact
of the transport of the raw materials and end products on the surrounding
environment should be assessed and provided.
31. A plan for the
utilization of waste/fuel gases in the WHRB for generating power have to be set
out.
32. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided. The alternate method of raw material and end
product transportation should also be studied and details included.
33. One season data for
gaseous emissions other than monsoon season is necessary.
34. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
35. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
36. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
37. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
38. Action plan for
rainwater harvesting measures at plant site shall be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
39. Permission for the
drawl of water from the water source from the concerned authority and water
balance data including quantity of effluent generated, recycled and reused and
discharged is to be provided. Methods adopted/to be adopted for the water
conservation should be included.
40. A note on the impact
of drawl of water on the nearby River during lean season.
41. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
42. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
43. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
44. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
45. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
46. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
47. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
48. Action plan for
solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
49. Details of evacuation
of ash, details regarding ash pond impermeability and whether it would be
lined, if so a detail of the lining etc. needs to be addressed.
50. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
51. Action plan for the
green belt development plan in 33 % area i.e. land with not less than 1,500
trees per ha. giving details of species, width of plantation, planning schedule
etc. should be included. The green belt should be around the project boundary
and a scheme for greening of the travelling roads should also be incorporated.
All rooftops/terraces should have some green cover.
52. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
53. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details alongwith time bound action plan should be
included. Socio-economic development activities need to be elaborated upon.
54. Disaster Management
Plan including risk assessment and damage control needs to be addressed and
included.
55. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
56. Details regarding
infrastructure facilities such as sanitation, fuel, restroom etc. to be
provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
57. Impact of the project
on local infrastructure of the area such as road network and whether any
additional infrastructure needs to be constructed and the agency responsible
for the same with time frame.
58. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
59. Plan for the
implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
60. A note on
identification and implementation of Carbon Credit project should be included.
61. Any litigation
pending against the project and/or any direction/order passed by any Court of
Law against the project, if so, details thereof should also be included.
It
was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be submitted
to Chhattisgarh Environment Conservation Board for public hearing. The issues
emerged and response to the issues shall be incorporated in the EIA report. Public Hearing will not be required as per Section (iii), Stage (3), Para (i)(b)
of EIA Notification 2006 only if the Gazette Notification is submitted.
The final EIA report shall be submitted to the Ministry for obtaining
environmental clearance.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports, after public consultation.
17.2.17 Proposed 1.0 MTPA Cement Grinding Unit
at Village Chojudwar, District Cuttack in Odisha by M/s Toshali Cement Pvt. Limited – (TORs)
The Committee noted that all stand alone cement grinding units are covered under Category ‘B’ as per para 3(b) of the Schedule of the EIA notification 2006 and hence shall be transferred to SEIAA, Odisha.
17.2.18 Proposed Cement Grinding Unit (300
TPD) at Changmaji Pather Kissam, Mouza Jamunamukh, District Nagaon, Assam by M/s Laxmi Cement Industries - regarding
TORs
The project proponents did not
attend the meeting and hence the proposal was deferred till further request
from the project proponent.
17.2.19 Expansion of Sponge Iron Plant (1X350
TPD) into Integrated Steel Plant at Village Godwali & Bastali Biran, Tehsil
Devassar & Chitarangi, District Singrauli, Madhya Pradesh by M/s Trimula Industries Limited – (TORs)
The project authorities and their consultant
M/s Insitu Envirocare Pvt. Ltd., Bhopal gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft Term of References for the preparation of
EIA/EMP. All the integrated steel plants have been kept at S.No. 3(a) under
primary metallurgical industry under category- A of the Schedule of the EIA notification 2006 and
appraised at Central level.
M/s Trimula Industries Limited have proposed
for expansion of Sponge Iron Plant (1X350 TPD) into Integrated Steel Plant at
Village Godwali & Bastali Biran, Tehsil Devassar & Chitarangi, District
Singrauli, Madhya Pradesh. PAs have
confirmed that proposed project is not located within 10 km of Critically
Polluted Area. No National Park /
Wildlife Sanctuary / Reserve Forest is located within 10 km. Total land
acquired for the proposed project is 61.61 Ha and Green belt will be developed
in 33% area of the total area. Nearest village is Godwali at 2.0 km. from the proposed site. No litigation
or court case is pending against the project and/or land. Bijul river is situated at 10.0 km. Total cost of the project is Rs. 410.0
Crores.
Following are
the proposed production capacities:
Details |
|
Annual
Production |
SPONGE IRON |
: |
1,10,000
Tons/ Year |
MS
Billets |
: |
3,28,500
Tons/ Year |
TMT/ STRUCTURE |
: |
3,00,000
Tons/ Year |
|
|
|
Following
units will be installed:
Unit |
|
Capacity |
DRI
with Auxilliary |
: |
1X350 TPD |
SMS with Auxilliary |
: |
6 x 15 MT |
ROLLING MILL with Auxilliary |
: |
2 x 500 MT |
60
MW POWER PLANT |
: |
|
WHRB 2 Nos. |
: |
16MW |
AFBC |
: |
44 MW |
Sponge Iron
(1,10,000 TPA) will manufactured from Iron Ore (3,52,000 TPA) and Coal (3,08,000
TPA) in 350 TPD Kiln. The sponge
produced will be the raw material for SMS and waste gases so produced will be
the utilized to generate power of 8 MW through Waste Heat Recovery Boiler. Sponge
Iron (3,30,000 TPA), Scrap (1,04,039 TPA), Ferro Alloys (1,380 TPA) will be
used as raw material in Steel Melting Shop to produce MS Billets. Billets will be manufactured by
melting in Induction furnace and casting in continuous casting machine. 16 MW
power will be produced from Waste Heat Recovery Boiler (WHRB) and Balance 44 MW
so produced will be from Atmospheric Fluidized Bed Combustion (AFBC) Boiler.
This AFBC boiler utilizes coal (2,85,809 TPA) and Char (5,500TPA). The char is
by-product of DRI.
Bag filters
will be installed at various places like day bin, Product Separation Circuit,
Cooler Discharge, IBIN and Ground Hopper for Coal Ckt and Iron Ore Ckt to
control fugitive emission. The waste gas of kiln will be utilized to generate
power in WHRB and also char which is generated will be fed to AFBC boiler to
generate power. Fume extraction system with bag filters will be provided to
control emissions from SMS unit and rolling Mill. The cleaned gases will be
vented to atmosphere through a stack of adequate height. Dust suppression
system will be provided in loading and unloading areas. Dust extraction system
with bag filters to control fugitive emissions from raw material handling
areas.
Total water
requirement for the proposed expansion will be 1,835 m3/day, which
will be met from the Bilul River and will be stored in plant reservoir. Only
waste water generated will be sanitary wastewater, which will be treated in
septic tank followed by soak pit. The wastewater generated from DM plant and
Boiler Blow down will be treated in ETP and can be utilized in green belt.
SMS slag from Induction Furnace will be used
for road making and land filling. Bottom Ash and fly Ash generated in the power plant
can easily be sold to nearby cement Plant. Also there is a provision for ash
pond of 1.07 Ha for storage.
DG set (1,250
KVA) will be operated only in case of grid breakdown.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive
summary of the project
2.
Photographs
of the existing and proposed plant area.
3.
Compliance to the
conditions stipulated in the Environmental Clearance / NOC granted by the SPCB.
4.
A
line diagram/flow sheet for the process and EMP
5.
Coal
linkage documents
6.
A
map indicating distance between project site and critically/severely polluted
area and a certificate from the CPCB/SPCB certifying the same.
7.
A
site location map on Indian map of 1:10, 00,000 scale followed by
1:50,000/1:25,000 scale on an A3/A2 sheet with at least next 10 Kms of terrains
i.e. circle of 10 kms and further 10 kms on A3/A2 sheets with proper
longitude/latitude/heights with min. 100/200 m. contours should be included.
3-D view i.e. DEM (Digital Elevation Model) for the area in 10 km radius from
the proposal site. A photograph of the site should also be included.
8.
Present
land use should be prepared based on satellite imagery. High-resolution
satellite image data having 1m-5m spatial resolution like quickbird, Ikonos,
IRS P-6 pan sharpened etc. for the 10 Km radius area from
proposed site. The same should be used for land used/land-cover mapping of the
area.
9.
Topography of the area should be given clearly indicating whether
the site requires any filling. If so, details of filling, quantity of fill
material required, its source, transportation etc. should be given.
10. Location
of national parks / wildlife sanctuary / reserve forests within 10 km. radius
should specifically be mentioned. A map showing land use / land cover, reserved
forests, wildlife sanctuaries, national parks, tiger reserve etc in 10 km of
the project site.
11. Project
site layout plan showing raw materials, fly ash and other storage plans, bore
well or water storage, aquifers (within 1 km.) dumping, waste disposal, green
areas, water bodies, rivers/drainage passing through the project site should be
included.
12.
Coordinates of the plant site as well as ash pond with topo sheet
co-ordinates of the plant site as well as ash pond with topo sheet should also
be included.
13. Details
and classification of total land (identified and acquired) should be
included.
14. Permission and
approval for the use of forest land, if any, and recommendations of the State
Forest Department regarding impact of proposed expansion on the surrounding
reserve forests.
15. A list of industries
containing name and type in 10 km radius should be incorporated.
16. Residential colony
should be located in upwind direction.
17. List of raw material
required, analysis of all the raw materials and source alongwith mode of
transportation should be included. All the trucks for raw material and finished
product transportation must be “Environmentally Compliant”.
18. Action plan for
excavation and muck disposal during construction phase.
19. Studies for fly ash,
muck, slurry, sludge material disposal and solid waste generated, if the raw
materials used has trace elements and a management plan should also be
included.
20. Manufacturing process
details for all the plants should be included.
21. Mass balance for the
raw material and products should be included.
22. Energy balance data
for all the components of steel plant including proposed power plant should be
incorporated.
23. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
24. Data generated in the last three years i.e.
air, water, raw material properties and analysis (major, trace and heavy metals), ground water table, seismic history, flood hazard
history etc.
25.
One season site-specific micro-meteorological data using temperature,
relative humidity, hourly wind speed and direction and rainfall and AAQ data
(except monsoon) should be collected. The monitoring stations should take into
account the pre-dominant wind direction, population zone and sensitive
receptors including reserved forests.
26. Ambient
air quality at 8 locations within the study area of 10 km., aerial coverage
from project site with one AAQMS in downwind direction should be carried out.
27. The
suspended particulate matter present in the ambient air must be analyzed for
the presence of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble
fraction. Chemical characterization of
RSPM and incorporating of RSPM data.
28. Determination
of atmospheric inversion level at the project site and assessment of ground
level concentration of pollutants from the stack emission based on
site-specific meteorological features.
29. Air
quality modelling for steel plant for specific pollutants needs to be
done. APCS for the control of emissions
from the kiln and WHRB should also be included to control emissions within 50
mg/Nm3.
30. Action
plan to follow National Ambient Air Quality Emission Standards issued by the
Ministry vide G.S.R. No. 826(E) dated 16th November, 2009 should be
included.
31.
Air Quality Impact Predication Modelling based on ISCST-3 or the latest models.
32.
Impact of the transport of the raw materials and end products on
the surrounding environment should be assessed and provided.
33. A plan
for the utilization of waste/fuel gases in the WHRB for generating power have
to be set out.
34. Impact of
the transport of the raw materials and end products on the surrounding
environment should be assessed and provided. The alternate method of raw
material and end product transportation should also be studied and details
included.
35. One
season data for gaseous emissions other than monsoon season is necessary.
36. An action
plan to control and monitor secondary fugitive emissions from all the sources
as per the latest permissible limits issued by the Ministry vide G.S.R. 414(E)
dated 30th May, 2008.
37. Presence
of aquifer(s) within 1 km of the project boundaries and management plan for
recharging the aquifer should be included.
38. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included. Information regarding
surface hydrology and water regime should be included.
39. Ground
water analysis with bore well data, litho-logs, drawdown and recovery tests to
quantify the area and volume of aquifer and its management.
40. Action
plan for rainwater harvesting measures at plant site should be submitted to
harvest rainwater from the roof tops and storm water drains to recharge the
ground water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
41. Permission
for the drawl of water from the surface water body from the State Irrigation Department concerned authority and water balance data
including quantity of effluent generated, recycled and reused and discharged is
to be provided. Methods adopted/to be adopted for the water conservation should
be included.
42. A note on
the impact of drawl of water on the nearby River during lean season.
43. Surface
water quality of nearby River (60 m upstream and downstream) and other surface
drains at eight locations must be ascertained.
44. If the
site is within 10 km radius of any major river, Flood Hazard Zonation Mapping
is required at 1:5000 to 1;10,000 scale indicating the peak and lean river
discharge as well as flood occurrence frequency.
45. A note on
treatment of wastewater from different plants, recycle and reuse for different
purposes should be included.
46. Provision
of traps and treatment plants are to be made, if water is getting mixed with
oil, grease and cleaning agents.
47. If the
water is mixed with solid particulates, proposal for sediment pond before
further transport should be included. The sediment pond capacity should be 100
times the transport capacity.
48. Wastewater
characteristics (heavy metals, anions and cations, trace metals, PAH) from
washed / beneficiated plants / washery or any other source should be included.
49. The
pathways for pollution via seepages, evaporation, residual remains are to be
studied for surface water (drainage, rivers, ponds, lakes), sub-surface and
ground water with a monitoring and management plans.
50. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
51. Action
plan for solid/hazardous waste generation, storage, utilization and disposal
particularly slag from all the sources, char and fly ash. Copies of MOU
regarding utilization of ash should also be included.
52. Details
of evacuation of ash, details regarding ash pond impermeability and whether it
would be lined, if so details of the lining etc. needs to be addressed.
53. A note on
the treatment, storage and disposal of all type of slag should be included.
Identification and details of land to be used for SMS slag disposal should be
included. Details of secured land fill as per CPCB guidelines should also be
included.
54. End use
of solid waste and its composition should be covered. Toxic metal content in the waste material and
its composition should also be incorporated particularly of slag.
55. All stock
piles will have to be on top of a stable liner to avoid leaching of materials
to ground water.
56. Acton
plan for the green belt development plan in 33 % area i.e. land with not less
than 1,500 trees per ha. giving details of species, width of plantation, planning
schedule etc. should be included. The green belt should be around the project
boundary and a scheme for greening of the travelling roads should also be
incorporated. All rooftops/terraces should have some green cover.
57. Detailed
description of the flora and fauna (terrestrial and aquatic) should be given
with special reference to rare, endemic and endangered species.
58. At least
5 % of the total cost of the project should be earmarked towards the corporate
social responsibility and item-wise details along with time bound action plan
should be included. Socio-economic development activities need to be elaborated
upon.
59. Disaster
Management Plan including risk assessment and damage control needs to be
addressed and included.
60. Details
regarding expected Occupational & Safety Hazards. Protective measures
for Occupational Safety & Health
hazards so that such exposure can be kept within permissible exposure level so
as to protect health of workers. Health of the workers with special reference
to Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
61. Details
regarding infrastructure facilities such as sanitation, fuel, restroom etc. to
be provided to the labour force during construction as well as to the casual
workers including truck drivers during operation phase.
62. Impact of
the project on local infrastructure of the area such as road network and
whether any additional infrastructure needs to be constructed and the agency
responsible for the same with time frame.
63. Environment
Management Plan (EMP) to mitigate the adverse impacts due to the project along
with item wise cost of its implementation. Total capital cost and recurring
cost/annum for environmental pollution control measures should be included.
64. Plan for
the implementation of the recommendations made for the steel plants in the CREP
guidelines must be prepared.
65. A note on
identification and implementation of Carbon Credit project should be included.
66. Any
litigation pending against the project and/or any direction/order passed by any
Court of Law against the project, if so, details thereof should also be
included.
It
was decided that ‘TORs’ prescribed by the Expert Appraisal Committee-1 (Industry) should be
considered for preparation of EIA / EMP
report for the above mentioned project in addition to all the relevant
information as per the ‘Generic Structure of EIA’ given in Appendix III and
IIIA in the EIA Notification, 2006. The draft EIA/EMP report shall be submitted
to Madhya Pradesh Pollution Control
Board for public hearing. The issues emerged and response to the issues
shall be incorporated in the EIA report. The final EIA report shall be
submitted to the Ministry for obtaining environmental clearance.
The
TORs prescribed shall be valid for a period of two years for submission of the
EIA/EMP reports, after public consultation.
17.2.20 Proposed Clinker Grinding Unit of 2.0
MTPA capacity, along with Captive Power Plant of 15 MW at Industrial Growth
Centre, Village Kahalgaon, District Bhagalpur in Bihar by M/s Amrit Cement Private Limited
– (TORs)
The
project authorities and their consultant
M/s B.S Envi Tech (p) Ltd., Hyderabad gave a detailed presentation on the
salient features of the project and proposed environmental protection measures
to be undertaken along with the draft TORs for preparation of EIA/EMP. All stand alone clinker grinding units are
covered under Category ‘B’ as per para 3(b) of the Schedule of the EIA
notification 2006, but due to absence of SEIAA/SEAC for Bihar, the proposal is
appraised at central level.
M/s Amrit Cement Private Limited. have
proposed for the greenfield Clinker Grinding Unit with Captive Power Plant for
production of 2.0 million tonnes per annum of Cement and 15 MW of Thermal Power
at Kahalgaon village, Bhagalpur District, Bihar. Total Project area for Cement
plant is 12 Ha and is proposed to come up in Kahalgaon Industrial Growth
Centre, Kahalgaon in two phases. Out of 12 Ha of land, about 33% area will be
earmarked for Green belt development. The total project cost is Rs.275 Crores
and Rs. 10 Crores are earmarked towards Capital Cost for pollution control
measures. Nearest Place is Kahalgaon at 5.2 km, the river Ganges at 1.9 km in
Western Direction and Vikramshila
Gangetic Dolphin Sanctuary is located at a distance of 7.3 Km south west of the site.
The major raw materials for the
grinding unit are Clinker, Gypsum, and Fly ash. The storage will be in Covered
Sheds for all the Raw Material. The Clinker will be transported from Meghalaya
and is crushed in ball mill with Gypsum. The raw materials requirement of plant
along with source is
Raw Material |
Quantity (MTPA) |
Source |
Clinker |
0.65 |
Own Cement plant located at
Meghalaya or from outside |
Flyash |
1.05 |
Nearby power plants and captive
power plant |
Gypsum |
0.05 |
Rajasthan , Sindhri |
Coal |
0.10 |
Local market |
The Thermal power plant will be coal
based and will meet the power requirement of the plant. Air cooled condensers will be installed. Bag
Filters will be provided for the Cement mill and all transfer points .The
emissions from all the Pollution Control Equipment is restricted to less than
50 mg/nM3.
The
water requirement of 300 m3/day will be sourced from the ground
water and necessary permission will be obtained. No wastewater will be
generated from process. The wastewater coming out of power plant will be used
for green belt development and dust suppression measures.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1. Executive summary of the project
2. Photographs of the proposed plant area.
3.A line diagram/flow
sheet for the process and EMP
4. Coal linkage documents
5.
A map duly
authenticated by the Chief Wild Life Warden showing the location of wildlife
sanctuary vis-à-vis the project location and the recommendations or comments of
Chief Wild Life Warden.
6. A
copy of application submitted to the National Board for Wildlife.
7. Active flood plan zonation map especially w.r.t River Ganges
8. Detailed hydro geological study and aquifer study (min 5 to 6 bore wells)
9. The earlier questionnaire for industry sector should be submitted while
submitting EIA/EMP.
10. A site location map
on Indian map of 1:10, 00,000 scale followed by 1:50,000/1:25,000 scale on an
A3/A2 sheet with at least next 10 Kms of terrains i.e. circle of 10 kms and
further 10 kms on A3/A2 sheets with proper longitude/latitude/heights with min.
100/200 m. contours should be included. 3-D view i.e. DEM (Digital Elevation
Model) for the area in 10 km radius from the proposal site.
11. Present land use
should be prepared based on satellite imagery. High-resolution satellite image
data having 1m-5m spatial resolution like quickbird, Ikonos, IRS P-6 pan
sharpened etc. for the 10Km radius area from proposed site. The same should be
used for land used/land-cover mapping of the area.
12. Location of national
parks / wildlife sanctuary / reserve forests within 10 km. radius should
specifically be mentioned. A map showing landuse / landcover, reserved forests,
wildlife sanctuaries, national parks, tiger reserve etc. in 10 km of the
project site. A map duly authenticated by the Chief Wild Life Warden showing
the location of wildlife sanctuaries vis-à-vis the project location including
the cement plant and the recommendations or comments of Chief Wild Life Warden.
13. Project site layout
plan showing raw materials, fly ash and other storage plans, bore well or water
storage, aquifers (within 1 km.) dumping, waste disposal, green areas, water
bodies, rivers/drainage passing through the project site should be included.
14. Details and
classification of total land (identified and acquired) should be included.
15. Proposal should be
submitted to the Ministry for environment clearance only after acquiring total
land. Necessary documents indicating acquisition of land should be included.
16. Rehabilitation &
Resettlement (R & R) should be as per policy of the State Govt. and a
detailed action plan should be included.
17. Permission and
approval for the use of forest land and recommendations of the State Forest
Department regarding impact of proposed expansion on the surrounding reserve
forests, if applicable, should be included.
18. A list of industries
containing name and type in 10 km radius shall be incorporated.
19. Residential colony
should be located in upwind direction.
20. List of raw material
required and source along with mode of transportation should be included. All
the trucks for raw material and finished product transportation must be
“Environmentally Compliant”.
21. Petrological and
Chemical analysis and other chemical properties of raw materials used (with GPS
location of source of raw material) i.e. ores, minerals, rock, soil, coal,
iron, dolomite quartz etc. using high definition and precision instruments
mentioning their detection range and methodology such Digital Analyzers, AAS
with Graphite furnace, ICPMS, MICRO-WDXRF, EPMA, XRD, Nano studies or at least
as per I30-10500 and WHO norms. These analysis should include trace element and
metal studies like Cr (vi) Ni, Fe, As, Pb, Zn, Hg, Se, S etc. Presence of
radioactive elements (U, Th etc.).
22. Petrography, grain
size analysis and Major element analysis of raw material and soil from project
site and raw material should be done on the same parameters along with analysis
for SiO2, Al2O3, MgO, MnO, K2O,
CaO, FeO, Fe2O3, P2O5, H2O,
CO2.
23. If the rocks, ores,
raw material has trace elements their petrography, ore microscopy, XRD,
elemental mapping EPMA, XRF is required to quantify the amount present in it
and hence future risk involved while using it and management plan.
24. Studies for fly ash,
muck disposal, slurry, sludge material and solid waste generated should also be
included, if the raw materials used has trace elements and a management plan.
25. Manufacturing process
details should be included.
26. Possibility of
installation of WHRB will be explored and details included
27. Mass balance for the
raw material and products should be included.
28. Energy balance data
for all the components including proposed power plant should be incorporated.
29. Site-specific
micro-meteorological data using temperature, relative humidity, hourly wind
speed and direction and rainfall should be collected.
30. Sources of secondary
emissions, its control and monitoring as per the CPCB guidelines should be
included. A full chapter on fugitive emissions and control technologies should
be provided.
31. An action plan to
control and monitor secondary fugitive emissions from all the sources as per
the latest permissible limits issued by the Ministry vide G.S.R. 414(E) dated
30th May, 2008.
32. Vehicular pollution
control and its management plan should be submitted.
33. A write up on use of
high calorific hazardous wastes from all the sources in kiln and commitment
regarding use of hazardous waste should be included.
34. Ambient air quality
at 8 locations within the study area of 10 km., aerial coverage from project
site with one AAQMS in downwind direction should be carried out.
35. The suspended
particulate matter present in the ambient air must be analyzed for the presence
of poly-aromatic hydrocarbons (PAH), i.e. Benzene soluble fraction. Chemical
characterization of RSPM and incorporating of RSPM data.
36. Determination of
atmospheric inversion level at the project site and assessment of ground level
concentration of pollutants from the stack emission based on site-specific
meteorological features.
37. Air quality modelling
for all the plants proposed including mine for specific pollutants needs to be
done. APCS for the control of emissions within 50 mg/Nm3 should be
included. Cumulative impacts of cement plant, Captive Power Plant and mines
located at a distance of 2.0 km on the
ambient air quality shall be assessed.
38. Action plan to follow
National Ambient Air Quality Emission Standards issued by the Ministry vide
G.S.R. No. 826(E) dated 16th November, 2009 should be included.
39.
Ambient
air quality monitoring modeling alongwith cumulative impact should be included
for the day (24 hrs) for maximum GLC alongwith following :
i) Emissions (g/second) with and without
the air pollution control measures
ii) Meteorological inputs (wind speed,
m/s), wind direction, ambient air temperature, cloud cover, relative humidity
& mixing height) on hourly basis
iii) Model input options for terrain, plume
rise, deposition etc.
iv) Print-out of model input and output on
hourly and daily average basis
v) A graph of daily averaged
concentration (MGLC scenario) with downwind distance at every 500 m interval
covering the exact location of GLC.
vi) Details of air pollution control
methods used with percentage efficiency that are used for emission rate
estimation with respect to each pollutant
vii) Applicable air quality standards as
per LULC covered in the study area and % contribution of the proposed plant to
the applicable Air quality standard. In case of expansion project, the
contribution should be inclusive of both existing and expanded capacity.
viii) No. I-VII are to be repeated for
fugitive emissions and any other source type relevant and used for industry
ix) Graphs of monthly average daily
concentration with down-wind distance
x) Specify when and where the ambient air
quality standards are exceeded either due to the proposed plant alone or when
the plant contribution is added to the background air quality.
xi) Fugitive dust protection or dust
reduction technology for workers within 30 m of the plant active areas.
40. Impact of the
transport of the raw materials and end products on the surrounding environment
should be assessed and provided.
41. One season data for
gaseous emissions other than monsoon season is necessary.
42. Presence of
aquifer(s) within 1 km of the project boundaries and management plan for recharging
the aquifer should be included.
43. Source of
surface/ground water level, site (GPS), cation, anion (Ion Chromatograph),
metal trace element (as above) chemical analysis for water to be used. If
surface water is used from river, rainfall, discharge rate, quantity, drainage
and distance from project site should also be included.
44. Ground water analysis
with bore well data, litho-logs, drawdown and recovery tests to quantify the
area and volume of aquifer and its management.
45. Ground water
modelling showing the pathways of the pollutants should be included
46. Column leachate study
for all types of stockpiles or waste disposal sites, at 20oC-50oC
should be conducted and included.
47. Action plan for
rainwater harvesting measures at plant site should be submitted to harvest
rainwater from the roof tops and storm water drains to recharge the ground
water and also to use for the various activities at the project site to
conserve fresh water and reduce the water requirement from other sources. Rain water harvesting and groundwater
recharge structures may also be constructed outside the plant premises in
consultation with local Gram Panchayat and Village Heads to augment the ground
water level. Incorporation of water harvesting plan for the project is
necessary, if source of water is bore well.
48. Permission for the
drawl of water from the concerned authority and water balance data including
quantity of effluent generated, recycled and reused and discharged is to be
provided. Methods adopted/to be adopted for the water conservation should be
included.
49. A note on the impact
of drawl of water on the nearby River during lean season.
50. Surface water quality
of nearby River (60 m upstream and downstream) and other surface drains at
eight locations must be ascertained.
51. If the site is within
10 km radius of any major river, Flood Hazard Zonation Mapping is required at
1:5000 to 1;10,000 scale indicating the peak and lean river discharge as well
as flood occurrence frequency.
52. A note on treatment
of wastewater from different plants, recycle and reuse for different purposes
should be included.
53. Provision of traps
and treatment plants are to be made, if water is getting mixed with oil, grease
and cleaning agents.
54. If the water is mixed
with solid particulates, proposal for sediment pond before further transport
should be included. The sediment pond capacity should be 100 times the
transport capacity.
55. The pathways for
pollution via seepages, evaporation, residual remains are to be studied for
surface water (drainage, rivers, ponds, lakes), sub-surface and ground water
with a monitoring and management plans.
56. Ground water
monitoring minimum at 8 locations and near solid waste dump zone, Geological
features and Geo-hydrological status of the study area are essential as
also. Ecological status (Terrestrial and
Aquatic) is vital.
57. Geo-technical data by
a bore hole of upto 40 mts. in every One sq. km area such as ground water
level, SPTN values, soil fineness, geology, shear wave velocity etc. for
liquefaction studies and to assess future Seismic Hazard and Earthquake Risk
Management in the area and impacts due to land slides.
58. Action plan for
solid/hazardous waste generation, storage, utilization and disposal. A note on
the treatment, storage and disposal of all type of solid waste should be
included. End use of solid waste viz. fly ash etc. and its composition should
be covered.
59. All stock piles will
have to be on top of a stable liner to avoid leaching of materials to ground
water.
60.
Action
plan for the green belt development plan in 33 % area should be included. The
green belt should be around the project boundary and a scheme for greening of
the travelling roads should also be incorporated. All rooftops/terraces should
have some green cover.
61.
A
scheme for rainwater harvesting has to be put in place. Incorporation of water
harvesting plan for the project is necessary, if source of water is bore well.
Efforts should be made to make use of rain water harvested. If needed, capacity
of the reservoir should be enhanced to meet the maximum water requirement. Only
balance water requirement should be met from other sources.
62. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
63. Action plan for the
green belt development plan in 33 % area should be included. The green belt
should be around the project boundary and a scheme for greening of the
traveling roads should also be incorporated. All rooftops/terraces should have
some green cover.
64. Detailed description
of the flora and fauna (terrestrial and aquatic) should be given with special
reference to rare, endemic and endangered species.
65. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan should
be included. Socio-economic development activities need to be elaborated upon.
66. Disaster Management
Plan including risk assessment & damage control needs to be addressed and
included. Landslide hazard map and mitigation plan, Earthquake history and
management plan should be submitted.
67. Details regarding
expected Occupational & Safety Hazards. Protective measures for Occupational Safety & Health hazards so
that such exposure can be kept within permissible exposure level so as to
protect health of workers. Health of the workers with special reference to
Occupational Health. Plan of exposure specific health status evaluation of
workers; pre placement and periodical health status of workers; plan of
evaluation of health of workers by pre designed format, chest x ray,
Audiometry, Spirometry Vision testing (Far & Near vision, colour vision and
any other ocular defect) ECG, during pre placement and periodical examinations
and plan of monthly and yearly report of
the health status of workers with special reference to Occupational Health and
Safety.
68. Plan for the
implementation of the recommendations made for the cement plant in the CREP
guidelines must be prepared.
69. At least 5 % of the
total cost of the project should be earmarked towards the corporate social
responsibility and item-wise details along with time bound action plan should
be prepared and incorporated.
70. A note on
identification and implementation of Carbon Credit project should be included.
71. Total capital cost
and recurring cost/annum for environmental pollution control measures.
72. Public hearing issues
raised and commitments made by the project proponent on the same should be
included separately in EIA/EMP Report in the form of tabular chart.
73.
Any
litigation pending against the project and / or any direction / order passed by
any Court of Law against the project, if so, details thereof.
It was decided that ‘TORs’ prescribed
by the Expert Appraisal Committee-1
(Industry) should be considered for
preparation of EIA / EMP report for the above mentioned project in
addition to all the relevant information as per the ‘Generic Structure of EIA’
given in Appendix III and IIIA in the EIA Notification, 2006. The draft EIA/EMP
report shall be submitted to the Bihar State Pollution Control Board for public
hearing. The issues emerged and response to the issues shall be incorporated in
the EIA report. Public Hearing will not
be required as per Section (iii), Stage
(3), Para (i)(b) of EIA Notification 2006 only if the Gazette
Notification is submitted. The final EIA report shall be submitted to the
Ministry for obtaining environmental clearance.
The TORs prescribed shall be valid for
a period of two years for submission of the EIA/EMP reports, after public
consultation
17.2.21 Proposed Ferro Alloy Plant
(installation of 3x7 MVA Submerged Arc Furnace & 50 MW Captive Power Plant
at Sy. No. 7/B1, 7/A2, 7/A3, 7/B3, 7/C3, 7/2/A, Village Hattighat, Gimma
Grampanchayat, Mandal & District Jainath in Andhra Pradesh by M/s G.S. Biotech Limited - regarding TORs
The project proponents have
requested to consider their proposal in the next meeting and hence the proposal
is deferred for next meeting.
17.2.22 Value addition to existing Pig Iron
Plant (1,20,000 TPA) by installation of Ductile Iron Pipe Plant (1,20,000 TPA) at
Village Halkote, Post Hatcholi, Taluk- Sirugupp, District Bellary in Karnataka
by M/s Shri Ram Electro Cast Pvt.
Limited – (TORs)
The project
authorities and their consultant M/s Environmental Health
& Safety Consultant Private Limited, Bangalore gave a detailed presentation
on the salient features of the project and proposed environmental protection
measures to be undertaken along with the draft Term of References for the preparation of EIA/EMP. All the Ductile Iron Pipe Plants are listed at S.No. 3(a) under
Primary Metallurgy Industry under Category A and appraised at the Central
level.
M/s Shri Ram Electro Cast Pvt. Limited have proposed for value addition of existing
Pig Iron Plant (1,20,000
TPA) by installation of Ductile Iron Pipe Plant (1,20,000 TPA) at
Village Halkote, Post Hatcholi, Taluk- Sirugupp, District Bellary in Karnataka. No national Park/wild life sanctuary is located
within 10 km radius of the project site. The land available with SREPL is about 114.97 acres.
38 acres of this land is utilized for existing pig iron plant. PAs
informed that there are no reserve forests within 10 km however state
plantations can be seen. Total cost of
the project is Rs. 156.0 Crores.
Existing unit is having Pig iron plant of 1,20,000
TPA and Captive Power Plant of 2.5 MW Capacity. Environmental Clearance was
obtained for the same vide Letter No J.11011/321/2007-IA II(I) dated 30-09-2009.Total power requirement will be met from captive generation.
Total water requirement for the DIP
plant is 800 m3/d (for the existing unit, 2400 m3/d was allotted
out of which 1,157 m3/d of water is being used). The source of water
is Tungabhadra River.
Fly ash will be kept in ash mound and subsequently used for fly
ash brick making. Iron ore fines will be
sold to Cement Industry, Slag will be disposed to Cement Industry, Used oil
will be sold to authorized reprocessors.
PH is exempted because of no increase
in the production capacity and pollution load.
After detailed deliberations, the
Committee prescribed following TORs for undertaking detailed EIA/EMP study:
1.
Executive summary of the project.
2. Photographs of the existing and proposed plant area.