MINUTES OF THE 10th MEETING OF RECONSTITUTED EXPERT APPRAISAL COMMITTEE ON ENVIRONMENTAL IMPACT ASSESSMENT OF THERMAL POWER AND COAL MINE PROJECTS

                                                                                              

The 10th Meeting of the reconstituted Expert Appraisal Committee (Thermal) was held during November 1-2, 2010 at Van Vigyan Bhawan, R.K. Puram, New Delhi. The Members present were:

         

1.           Shri V.P. Raja                                             -        Chairman

2.           Dr. C.R. Babu                                             -        Member

3.           Shri T.K. Dhar                                            -        Member

4.           Shri J.L. Mehta                                           -        Member

5.           Dr. G.S. Roonwal                                        -        Member

6.           Dr. S.D. Attri                                               -        Member

7.           Shri S. Seshadri                                         -        Member

8.           Dr. P.L. Ahujarai                                        -        Member Secretary

 

Dr. CBS Dutt, Member; Dr. K.K.S. Bhatia; Dr. V.B. Mathur, Member; and Member Secretary, CPCB could not attend due to their prior commitments.

 

In attendance:  Sh. W. Bharat Singh, Deputy Director, MoEF.

 

The deliberations held and the decisions taken are as under:

 

 

DATE: 01.11.2010.

 

Item No. 1. Confirmation of the Minutes of 8th Meeting.

 

The Committee could not deliberate on the minutes of the 8th meeting held during October 18-19, 2010 and therefore confirmation of the same was witheld.

 

 

ITEM NO. 2:          CONSIDERATION OF PROJECTS

 

2.1       Expansion of existing 106.617 MW and 112.45 MW Gas Based TPP by addition of 395 MW Gas Based TPPP of M/s Gujarat State Electricity Corporation Ltd. at village Dhuvaran, in Kahambat Taluk, in Anand Distt., in Gujarat      - reg. environmental clearance.

 

The proposal was placed for consideration for environmental clearance as per provisions of EIA notification 2006. The project proponent also gave a presentation along with its consultant M/s SENES Consultants India Pvt. Ltd. and provided the following information:

 

The proposal is for expansion of existing 106.617 MW and 112.45 MW Gas Based TPP by addition of 395 MW Gas Based TPPP at village Dhuvaran, in Kahambat Taluk, in Anand Distt., in Gujarat. Besides the above units other units which will be de-commissioned are 4x63.5 MW Oil Fired Plant; 2x27 MW Open Cycle Gas Turbine and 2x140 MW Open Cycle Gas Turbine. Land requirement will be 30 acres, which is available within the existing premises. The co-ordinates of the site are at Latitude 22014’03.76” N to 22014’09.95” N and Longitude 72045’30.39” E to 72045’30.75” E. Gas requirement will be 1.8 MMSCMD, which will be obtained from GAIL/GSPCL. Water requirement will be 13.8 MLD, which will be obtained from Mahi Canal and Reservoir at Kanbha village from existing pipeline. There are no national park, wild life sanctuary, biosphere/ tiger /elephant reserves, heritage sites etc within 10km of the project boundary. Public hearing was held on 29.09.2010. Cost of the project will be Rs. 1433.85 Crores.

 

The Committee noted that the area is water scarce area and also suggested that old cooling tower may be abandoned and the project proponent shall examine in detail the feasibility to use sea water for condenser cooling.

 

The Committee also discussed the issues raised in the public hearing and the responses made by the project proponent. The major issues raised were regarding employment of local people, training and benefit to Dhuvaran village; drinking water supply; depletion of ground water and measures to be taken etc. The project proponent also confirmed that no litigation is pending in any Courts pertaining to the project.

 

Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:

 

i)             Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.

ii)           No discharge shall be made into the estuary nor intake point shall be located in the estuary.

iii)          The project proponent shall provide space for FGD system for future installation as and when required.

iv)          It shall be ensured that the area drainage is not disturbed due to the proposed expansion.

v)            100 % fly ash disposal shall be ensured from 4th year of operation of the plant.

vi)          Height of stack shall be 70 m with flue gas velocity not less than 22 m/s.

vii)         Hydro geological study of the area shall be reviewed annually and report submitted to the Ministry.

viii)       Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.

ix)          Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible a 50 m width shall be raised and adequate justification shall be submitted to the Ministry.

x)            Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.

xi)          A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.    

xii)        Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB(A) should be provided.

xiii)       Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.

xiv)       Impact on fishery shall be studied in case sea water use is feasible and adopted. Accordingly a scheme for uplifting the livelihood of fishermen community shall be formulated and a separate Fishermen Welfare Fund created to enhance their quality of life through creation of facilities for fish landing platforms / fishing harbour / cold storage etc. and also to provide relief in case of emergency situations such as missing of fishermen on duty due to rough seas, tropical cyclones and storms etc. The fund shall be created not out of CSR budget.

xv)         An amount of Rs. 5.70 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs. 1.20 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities to be undertaken shall be submitted within six months to the Ministry.

xvi)       While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.

xvii)      It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.

xviii)    An Environmental Cell shall be created at the project site itself and shall be headed by qualified officer, who is well versed with the environmental aspects.  It shall be ensured that the Head of the Cell shall directly report to the head of the organization.

       

 

2.2   Expansion by addition of 800 MW Pragati-II Gas Based Combined Cycle Thermal Power Plant of M/s Pragati Power Corporation Ltd. at village Bamnauli, in South West Distt., in Delhi -  reg. Environmental Clearance.

 

The project proponent informed its inability to present their case due to unavoidable circumstances and therefore was deferred for re-consideration at a later stage.

 

 

2.3    2x10 MW Captive Coal Based Thermal Power Plant of M/s Usha Martin Ltd. at village Tatisilwai, in Ranchi Distt., in Jharkhand - reg.  Environmental Clearance.

 

The proposal is for consideration for environmental clearance. The project proponent made a presentation along with its consultant M/s Envirotech East Pvt. Ltd. and provided the following information:

 

The proposal is for setting up of 2x10 MW Captive Coal Based Thermal Power Plant at village Tatisilwai, in Ranchi Distt., in Jharkhand. Land requirement will be 12.278 acres, which is within the extended boundary of the existing Steel Wire Plant. The co-ordinates of the site are at Latitude 23021’56.07” N to 23022’28.79” N and Longitude 85025’14.29” E to 85026’03.60” E. Coal requirement will be 0.183 MTPA, which will be obtained from own captive operating mine at Kathautia near Daltonganj, in Jharkhand, which is about 200 Kms away. Ash and Sulphur contents in coal will be 41.70% and 0.3 to 0.5% respectively. About 0.0612 MTPA of Fly Ash will be generated, which will be supplied to cement manufacturer viz. M/s Holtec Cement Ltd. A stack of 61 m will be installed. Source of water requirement will be from Subarnarekha River which flows at a distance of 0.5 Km from the boundary of the project site. Air cooled condenser will be used for main condensate cooling. Make up water requirement will be 26 cum/hr. There are no national parks, wildlife sanctuaries, heritage sites, tiger/biosphere reserves etc. within 10 km of the site. Public hearing was conducted on 14.09.2010. Cost of the project will be Rs 97.0 Crores.

 

The project proponent requested the Committee that they be allowed to use coal through e-auction as the coal from their coal block is of high quality and it was felt unwise to use it for power generation. The Committee noted the request and informed that the issue can be taken up with the Ministry as these are matters that need to be in accordance with policy decision taken at the Ministry.

 

The project proponent also informed that they have not started any construction activity for the power project as alleged by some individual. It was further informed that the case filed in the High Court at Ranchi viz. W.P. No. 605/2010 is yet to be admitted.

 

The Committee noted that the plant is in the heart of the city and transportation of coal over a distance of 200 Kms by road is not an advisable option. The Committee therefore advised the project proponent that they shall firm up a concrete plan for taking up transportation of coal through railway. It was also noted that no firm agreement for fly ash utilization was in place and endorsement of the Ministry of Coal for utilizing the coal from the dedicated coal block for captive TPP need be furnished.

 

Before the end of the deliberation, the Committee further observed that the ambient air quality impact assessment was grossly erroneous and it was learnt that the project proponent have made the assessment based on better / best coal quality scenario. Not satisfied with the explanation offered by the consultant / project proponent the Committee suggested that the Ministry may like to seek explanation from the consultant seeking why action should not be taken against him for submission of false / erroneous data.

 

The Committee therefore decided that the project proponent shall first submit information on the following before their case is considered for environmental clearance:

 

i)             Point wise compliance of TORs prescribed shall be submitted;

ii)           Option for coal transportation by rail shall be considered.

iii)          In case rail transportation is not feasible and road transportation is the only option left, adequate justification shall be provided. In that case, impact on ambient air quality along the route of transportation with details of vehicular density along the route shall be submitted;

iv)          Ambient air quality data shall be re-assessed and cumulative impact of ambient air quality predictions accounting all possible sources of emissions shall be re-done using appropriate wind rose diagram;

v)            CSR action plan with time bound implementation schedule and budgetry allocation activity wise shall be submitted;

vi)          Proposal for fly ash utilization alongwith copy of agreements/MoUs firmed up with prospective fly ash users shall be submitted.

 

The Committee also decided that the above information / documents shall be submitted along with an undertaking in a notorised stamp paper of appropriate amount and duly signed by the Head of the Organisation or an officer of appropriate seniority (authorized to sign).

                                                                                                                 

Accordingly the proposal was deferred for reconsideration at a later stage.

 

 

2.4       Expansion of 1000 MW (4x250 MW) by addition of 4x600 MW (2400 MW) Coal Based Thermal Power Plant of M/s Jindal Power Ltd. at Tamnar, in Gharghoda Tehsil, in Raigarh District in Chhattisgarh.

                                                                                  

           

The Ministry  had earlier accorded environmental clearance to M/s Jindal Power Limited  in 2007 for 1000 MW Coal based thermal power plant at Tamnar in District Raigarh in Chhattisgarh.  The land required for this plant layout was 614 ha of which 360 ha for power plant and remaining for ash dyke colony, etc.  Subsequently, M/s Jindal Power Ltd. submitted an application for 2400 MW coal based power plant at Tamnar in District Raigarh with an area requirement was 1040 ha.  The Ministry prescribed TORs for the project in March 2009.  

2.       In the meantime, a complaint was received from the NGO with photographic evidence that the promoters have shifted site and have started construction activity.  A team was, therefore, deputed to verify the facts.  The team inspected the site in April 2010 and reported that the company has started construction for 2400 MW power plant at the site which has been acquired by them for 1000 MW power plant.  The Ministry also sought the facts from the proponent in this regard.  The proponent denied that they have started any construction activity for 2400 MW power plant.  The Chhattisgarh Environment Conservation Board (CECB) also verified the facts that the proponent has gone ahead with the construction activity even though no action was taken by the CECB under the provisions of Air & Water Acts.

3.       As per the inspection report, M/s JPL were planning to establish 2400 MW power plant in an area of 62 ha, which appears to be grossly inadequate.   The proponent did not inform the Ministry that they are planning to shift the plant area.

4.       In regard to public hearing, the company approached the CECB informing that they have changed the site for 2400 MW unit and it will now be set up in the land already acquired for 1000 MW plant.  The CECB, however, informed that the public hearing cannot be held due to change in the location as the draft EIA was prepared for the specific site.  The proponent then withdrew the letter of change of site and requested the CECB to hold the public hearing as per the original plant.  They further informed the CECB that they will obtain prior permission of the Ministry for changing the site.  However, Ministry was not informed in this regard.

5.       The Ministry noted the following:

 

a)            That M/s JPL have violated the provisions of EIA Notification 2006 requiring prior environmental clearance before construction work is to begin for a project;

b)           That M/s JPL have not informed the Ministry for any relocation / revised layout for 4x600 MW expansion plant for which TOR was prescribed on 31.03.2009.

c)            That setting up of 4x600 MW in an area of 62 Ha is not possible.

 

6.       The Ministry withdrew the TOR prescribed for 4x600 MW on 18.06.2010 and the project authorities were advised  to submit a clear proposal for the 4x600 MW plant and follow provisions of EIA Notification, 2006, in case they want  to pursue  this project. The Ministry also directed the State Govt. of Chhattisgarh on 18.06.2010 to take action under the provisions of Environment (Protection) Act, 1986 against M/s JPL for commencing work prior to obtaining environmental clearance.

7.       Based on the request of the project proponent, the proposal was placed before the Expert Appraisal Committee in its 3rd meeting held on 9th -10th August, 2010. M/s JPL made a presentation on the various issues leading to the withdrawal of TOR for 4x600 MW power plant.   M/s JPL requested the Committee for restoration of the TOR and subsequent appraisal of the proposed expansion project for environmental clearance.

 

8.       In that meeting the Committee recommended that the project may be appraised, based on its review of the matter, by following the original TORs along with additional information sought .

9.       In the 7th Meeting held on September 28, 2010, the reply submitted in response to the Ministry’s letter dated 27.08.2010 seeking information with regard to the discussion held in the 3rd meeting of the Committee during August 9th - 10th, 2010 was placed before the Committee.

10.     The information sought by the Committee were as under:

 

i)             Whether the conditions stipulated while according environmental clearance for 1000 MW Coal Based Power Plant have been complied?

ii)            The plant layout of 1000 MW power plant  indicating location of plant, green belt etc. while according environmental clearance and revised lay out due to 2400 MW power project and along with layout of 2400 MW plant detailing the location of the plant, ash dyke, green belt etc.

iii)          Whether there is a documentary evidence for firm coal linkage for 2400 MW power plant and water linkage for total capacity including 1000 MW and 2400 MW. 

iv)          What is the Cumulative environmental impact assessment and risk assessment due to 1000 MW and 2400 MW plants? 

v)            What is the total amount of ash to be generated from the 1000 MW and 2400 MW power plant and capacity of the ash dyke along with plan for utilization of fly ash?

 

11.     In the said meeting, M/s Jindal Power Ltd. (JPL) also made a presentation on the above information sought. The main highlights of the presentation made by M/s JPL included the following:

         

i)             Layout for the 1000 MW power plant and revised layout of 2400 MW along with green belt was submitted. As per the layout, the land use for 4x250 MW stage-I was 499 ha. As per the TORs awarded in March, 2009, the total area earmarked for 2400 MW was 1041 ha, of which 350 ha for the main plant area, 491 ha for ash dyke area, 100 ha for water reservoir and 100 ha for the staff colony.

ii)           After the optimization of plant area, the main plant area will be 115 ha instead of 350 ha as envisaged while awarding TORs for 2400 MW plant. The area for ash dyke will be 241 ha instead of 491 ha. An area of 100 ha will be for the water reservoir. There will be no staff colony after the land optimization for which 100 ha of area was earmarked at the time of awarding Terms of Reference.

iii)          Out of 614 ha of area for 1000 MW plant, about 499 ha of land has been used and remaining 115 ha of area now will be used for 2400 MW plant. The total land area optimized for the proposed expansion of 2400 MW power plant is 456 ha.

iv)          The total area for 3400 MW would be 955 ha (2395 acres). The land used is 0.70 acres /MW.

v)            Due to land optimization, some changes in the layout of 1000 MW power plant has been made. Revised layout for 2400 MW power plant was submitted.

vi)          The company has letter of assurance for confirmed coal linkage of 2x600 MW units from the Ministry of coal.

vii)         The water allocation of 54 MCM and 70 MCM is from Kurket Dam and Mahanadi River respectively.

viii)       The cumulative risk due to 1000 MW and 2400 MW would restricted with in the plant boundary.

ix)          As per the ash utilization plan from January, 2010 to July, 2010, for the 1000 MW TPP, total fly ash generated was 142482 tonnes, about 38% of the fly ash has been utilized. The maximum utilization of fly ash was due to mine back filling (47447 tonne) followed by low land filling (6820 tonne), brick plant (871 tonne) and batching plant (133 tonne).

x)            The cumulative ash generation/annum will be 9.2 MTPA due to 1000 MW power plant (4x250 MW, 4x150 MW and 4x600 MW power plant). Out of 9.2 MTPA, 2 MTPA of ash will be generated from the 1000 MW power plant which will be mixed with OB of Gare IV/2 & IV/3 mines. About 2.64 MTPA ash generated from the 4x150 MW will be mixed with OB of Gare IV/1 mines. The ash generated from 4x600 MW (4.56 MTPA) will be mixed with OB of Gare IV/2, IV/3 & IV/6 mines.

xi)          As per the cumulative ash plan presented before the Committee out of 9.2 MTPA ash generated, 7.36 MTPA of ash will be mixed with overburden and will be back filled with the captive coal mines.

xii)        The back filling of ash in the mined out area will be as per the DGMS guidelines.

xiii)       Out of 456 ha of land area for the 2400 MW power plant, green belt will be developed in 122 ha of area.

 

12.     In the 7th meeting, it was decided to constitute a sub-group who may study the issues involved and decide on the requirement of any information which are material to appraisal of the project. Accordingly, a group comprising Dr. C.R. Babu; Dr. S.D. Attri; Shri S. Seshadri; Dr. G.S. Roonwal, Shri M.S. Puri from Central Electricity Authority (CEA) and representatives of the Ministry met on 30.09.2010 and decided that clarification on the following be sought:

 

i)             The layout for 2400 MW power plant does not have provision for fabrication and storage area. The coal handling area will be near the steel plant at a distance of 30 km from the power plant. The details regarding area required for coal handling, corridor for pipe conveyor and status of land acquisition need to be furnished.

ii)           The layout of 1000 MW plant has been changed. The area which was meant for green belt has been encroached upon. The area of green belt for 1000 MW (Phase-I) has been reduced from 122 ha to 85 ha due to proposed facilities for 2400 MW Phase-II. The condition regarding 33% of plant area for the green belt in case of 1000 MW plant has not been complied;

iii)          The Chhattisgarh Mineral Development Corporation (CMDC) observed that the proposed site for 2400 MW is a coal bearing area. Whether concurrence of the Ministry of Coal has been obtained?

iv)          About 100 ha of area has been earmarked for water reservoir which is a large area. As per CEA guidelines, 80 acres of area is required for water reservoir for 2400 MW of plant;

v)            Detailed ash management plan for 100 % utilization from 4th year of operation excluding mine back filling;

vi)          Copy of permission given by DGMS for backfilling of mined out area; and

vii)         The report on the study regarding feasibility of dumping of fly ash in the mined out area as stipulated while according environmental clearance to Gare Palema mine in 2005

viii)       Action taken for implementation of plan for conservation of wildlife as stipulated in environmental clearance for Phase-I.

ix)          A detailed response to the issues raised during the public hearing and number of representations received regarding the project.

 

13.     The information by M/s JPL on the above was placed before the Committee again for its views. M/s JPL along with its consultant M/s EMTRC Consultant Pvt. Ltd. also made a presentation on the issues and gave point wise clarification. The following information was provided:

 

a)            That their parent company i.e. M/s JSPL have developed a fully automatic fabrication shop at Raigarh and is executing large fabrication orders for BHEL, reliance, L&T-MHI and JSPL’s captive power projects at Angul and Raigarh. That all major fabrication works for the proposed power project will be performed at this fabrication center at Raigarh and therefore no land provision for fabrication yard is kept at the plant site at Tamnar.

 

          That coal for the proposed plant (expansion) will be received by rail at Raigarh near its existing Steel Plant. JSPL has planned to construct the coal stock yard and handling facilities for coal to be received from Coal companies at the village prasada in close proximity of steel plant of JSPL at Raigarh. The land required for the said facility is about 250 acres. JSPL has already initiated acquisition of 250 acres of land at Parsada, out of which 180 acres has been acquired. Coal transportation shall be done through pipe coal conveyor from Prasada to JPL Tamnar and will be extended up to JSPL mines beyond JPL proposed 4X600MW plant area to bring coal from Gare pelma IV/1 for JSPL’s Steel plant. Right of way required for above installation of such pipe conveyor would be 7.5 meter wide corridor for the length of the conveyor.

 

b)           There is no change in the layout of the 1000 MW power plant and only the land use has been optimized. MoEF stipulated 33 % area of the main plant to be developed as green belt. That they had envisaged 360 Ha land to be utilized for setting up the main plant. However, finally the main plant could be setup over a land of 245 Ha due to optimization of the land. That the 1000 MW project was completed in 2008 and that the expansion project was conceived in 2007 (applied for grant of TOR in April 2007) i.e  well before the completion of the 1000 MW project . That the green belt had thus been planned keeping in view the total project. As the entire 3400 MW project has been proposed in the originally allocated 360 Ha, the consolidated green belt for 3400 MW has been proposed as 122 Ha which is meeting the MoEF requirement. That in their earlier submissions to the Expert Appraisal Committee stated that in addition to the greenery around the plant, they have carried out substantial greening. That plantation on the additional area, if the State Government can make available to M/s JPL adjacent to the plant or elsewhere around the plant will also be carried out. That already plantation of about 14.21 lakh trees on a area of 710 Ha has been undertaken.

 

c)             That in 1997 a letter from SECL was received stating that the 1000 MW proposed site is under the coal bearing areas. Accordingly, State Government helped the company in acquiring the necessary land for the 1000 MW power plant. In view of the clearance available to M/s Jindal Power Ltd. way back in 1997 for 2X250 MW, additional 2X250 MW in 2006 within the same 360 ha boundary and also due to the fact that the expansion project of 4X600 MW is being setup  within the same 360 ha of land area, which has already been approved long back by MoEF and the State Government, no need to obtain clearance from CMDC was felt, as prospecting license has been granted to CMDC only in 2009 i.e much later than the clearance granted to M/s JPL and 1000 MW power plant has been setup and is operational before the prospecting license was granted to CMDC.

 

          That as far as concurrence of Ministry of Coal is concerned, application for concurrence for setting up 2400 MW expansion project within same 360 Ha which was already approved by MoEF and the State Government in the year 1997, has been done. The same is under process in the MoC and it is expected to receive the  concurrence shortly. That concurrence of the State Government for setting up the expansion project of 2400 MW within the same 360 Ha is also under process and the same is expected to be received shortly.

 

d)           That an area of 100 ha was indicated for the water reservoir. In case the construction of the reservoir after detailed design is possible on the lesser area the balance area shall be converted into a green belt. During construction of the expansion project temporarily the area will be used for storage of material and for camping of the contactor’s labourers.

 

e)            That 100% ash utilization target after 4 years of operation (as per MoEF notification) does not stipulate 100 % ash utilization to be done without mine backfilling. Hence the request not to insist on 100 % Ash utilization without mine backfilling. However, as desired, plan for 100% ash utilization without mine backfilling has been prepared and the same has been submitted. 

 

f)             The DGMS approval for the 1000 MW plant’s ash backfilling in the mine is already available. Permission from DGMS for mine back filling with ash from expansion project will be applied after consent to establish etc are in place for the 4X600 MW expansion project.

 

g)            The geological report mentioning the type of rock formation in the mine area prepared by Geological Survey of India (GSI) has been also submitted. That IIT, Kharagpur has conducted a study and also done water samples testing after dumping of ash in the de-mined area and given results of the quality of underground water in the mines. A copy of study carried out by IIT, Kharagpur  has been submitted.

 

h)           As per the stipulation in the environmental clearance of 1000 MW plant, proposal for conservation of endangered wild life fauna was prepared in consultation with State Wild Life Department, and as per guidelines of the Wild Life (Protection) Act, 1972 had been submitted to the MoEF on 19.09.2006.

 

i)             That all point raised during the public hearing were duly replied during the public hearing and have been annexed to the final EIA report. And that no separate representation against our expansion project has been received.

 

j)             That regarding land acquisition, MoEF had cleared 56 Ha of land for the township for 1000 MW plant. The 33.984 Ha of land is part of the 56 Ha land approved by MoEF for construction of the colony. That MoEF had cleared 360 Ha of land for the main plant but it has been seen that the main plant could be set up within 245 Ha land. That 36.08 Ha as mentioned in MoEF letter is part of balance 115 Ha unacquired land remaining from 360 ha. That regarding 0.763 Ha as mentioned in MoEF letter for the pipe line conveyor belt, the land acquired was only for the footprint of the columns required for pipe conveyor.

 

14.     M/s JPL also informed that a coal gasification plant at Tamnar is also being proposed though the same is at a preliminary stage as of now. It was also informed that for their proposed Steel Plant in the area, public hearing is yet to be held.

 

15.     Further, regarding utilization of fly ash, M/s JPL also informed that they are proposing to have a Cement Plant in the area and that once the Cement Plant into operation, maximum fly ash will be utilized by the plant. However, it was also informed that a detailed fly ash utilization to cater 100% utilization from 4th year onwards has already been formulated and requisite documents will be submitted.

 

16.     The Committee deliberated on the explanation provided by M/s JPL and advised them that details associated with Coal Gasification Plant including its possible impact on environment shall be taken care while preparing the  EIA/EMP for the Steel plant. Further, impact of coal handing plant near the steel plant which is located at a distance of 30 Km should be brought to the notice of the public during the public hearing meeting. Cumulative impacts of the steel plant and coal handing plant should be assessed. All new activities like setting up a Coal Handling Plant and a Coal Gasification Plant which is now being proposed in the Steel Plant area should be clearly and specifically brought out in the Public Hearing Process for the Steel Plant.  M/s. JPL have a duty cast on them to ensure total transparency and to ensure that there is no information gap between what they are actually proposing to do and what the community/public perceive them to be doing.  The committee wishes to unequivocally advise M/s. JPL against playing a game of “Suppressio Veri – Suggestio Falsi” both at the time preparation of EIA/EMP for the proposed steel plant and at the time of Public Hearing for the same.  The full details of the activities being taken up for the power plant in the steel plant area should be brought to the notice of the public in a comprehensive and understandable fashion.

 

17.     Ms/ JPL was also informed that on the ground of optimizing land, the reduction in green belt area  is not  a wise decision, considering that the 33% area as interpreted by them seem to have considered only main plant area, whereas, thermal power plant in general comprises of main plant, ash dyke, coal handling area, water storage area, railway siding, township etc. etc. The Committee therefore emphasized that 33% green belt area shall be provided in all associated facilities / components of the power plant, in separate segments or otherwise, as the case may be.

 

18.     The Committee also noted that coal linkage for only 2x600 MW is available and therefore recommendation for environmental , if agreed, can only be made for 2x600 MW (out of 4x600 MW).

 

19.     Based on the information and clarifications provided, the Committee after prolonged deliberation recommended the project for environmental clearance for the expansion project by addition of 2x600 MW Coal Based Thermal Power Plant of M/s Jindal Power Ltd. at Tamnar, in Gharghoda Tehsil, in Raigarh District in Chhattisgarh subject to stipulation of the following specific conditions:

i)             Environmental clearance shall be applicable for 2x600 MW only. However at a later stage when firm coal linkage for the third and fourth unit of 600 MW are also available, the project proponent may request the Ministry for inclusion of 2x600 MW, which the Ministry may consider appropriately on merit.

ii)           As per the information provided by M/s JPL, it is noted that out of 360 ha of plant area, 245 ha is under 1000 MW capacity power plant. Out of remaining area of 115 ha, 53 ha is under the coal bearing area. As the project is located in the coal bearing area, M/s JPL shall obtain necessary permission from the Ministry of Coal.

iii)          Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.

iv)          Sulphur and ash contents in the coal to be used in the project shall not exceed 0.5 % and 34 % respectively at any given time.  In case of variation of coal quality at any point of time fresh reference shall be made to MOEF for suitable amendments to environmental clearance condition wherever necessary.

v)            Ash pond shall be lined with HDPE/LDPE lining or any other suitable impermeable media such that no leachate takes place at any point of time. Adequate safety measures shall also be implemented to protect the ash dyke from getting breached.

vi)          For disposal of Bottom Ash in abandoned mines (if proposed to be undertaken) shall be done only after detailed study of geology of the mine identified and after establishing that the process will not be detrimental to the ground water regime and geology of the area. The study report shall be first submitted to the Ministry and the State Pollution Control Board for examination before such a venture is proposed to be carried out. In such a case, it shall be ensured that the bottom and sides of the mined out areas are adequately lined with clay before Bottom Ash is filled up. The project proponent shall also inform the State Pollution Control Board well in advance before undertaking the activity.

vii)         100 % fly ash disposal shall be ensured from 4th year of operation of the plant. Detailed status for 100% utilization after the 4th year of operation of the plant shall be submitted every six months to the Ministry.

viii)       M/s JPL shall carry out a study to assess the impact on the ground water due to disposal of ash in  the mind out area

ix)          Height of stack shall be 275 m with flue gas velocity not less than 22 m/s.

x)            It shall be ensured that the area drainage is not disturbed due to the proposed power plant.

xi)          Source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season. The report shall be submitted to the Regional Office of the Ministry within six months.

xii)        Hydro geological study of the area shall be reviewed annually and report submitted to the Ministry.

xiii)       Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.

xiv)       Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible adequate width shall be raised and proper justification shall be submitted to the Ministry.

xv)         Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.

xvi)       A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.  

xvii)      Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB(A) should be provided.

xviii)    Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.

xix)       For the tribal families (if any) affected directly or indirectly by the proposed project, specific schemes for upliftment of their sustainable livelihood shall be prepared with time bound implementation and in-built monitoring programme. The status of implementation shall be submitted to the Regional Office of the Ministry from time to time.

xx)         The project proponent shall also adequately contribute in the development of the neighbouring villages. Special package with implementation schedule for free potable drinking water supply in the nearby villages and schools shall be undertaken in a time bound manner.

xxi)       An amount of Rs. 53.60 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs. 10.7 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities shall be submitted within six months to the Ministry.

xxii)     The project proponent shall also adequately contribute in the development of other neighbouring villages. Special package with implementation schedule for providing potable drinking water supply in the near by villages and schools shall be undertaken in a time bound manner.

xxiii)    While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.

xxiv)    It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.

xxv)      An Environmental Cell shall be created at the project site itself and shall be headed by an officer of appropriate seniority and qualification. It shall be ensured that the head of the Cell shall directly report to the head of the organization.

xxvi)  Information on all new activities like settling up of a Coal Handling Plant, a Coal Gasification Plant, Coal stock yard etc. proposed to be setup and the proposed pipe coal conveyer from Prasada to JPL Tamnar should be brought to the notice of the people both through EIA/EMP studies and at the time of the Public hearing for the proposed steel plant of JSPL in an explicit, comprehensive and understandable fashion.

 

20.     The recommendations of the committee are without any prejudice to the outcome of litigation filed by the Government of Chhattisgarh against M/s. JPL.

 

2.5       3X400 (1200) MW Gas Based Combined Cycle Power Plant of M/s Gujarat State Electricity Corporation Ltd. at village Maniyari, in Chanasma Taluk, in Patan  Distt., in Gujarat        -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Anand Consultant gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 3x400 MW Gas Based Combined Cycle Power Plant at Village Maniyari, in Chanasma Taluk, in Patan  Distt., in Gujarat. Land requirement will be 146 Acres, which is a waste land. The co-ordinates of the proposed site will be at Latitude 230 34’ 19” N and Longitude 720 4’ 7” E. Fuel requirement will be 4.69 MMSCMD, which will be sourced from GSPC network. Water requirement will be 42192 KLD, which will be met from Narmada Canal water, through a pipeline over a distance of 6 km from the project site. There are no National parks, Wildlife sanctuaries, Tiger/Biosphere reserves etc. within 10 km of the site. However there is a Sun Temple of Modhera at a distance of 9.0km from the project site.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Prior approval from ASI (as may be applicable) shall be obtained and a copy of the clearance submitted.

ii)           Vision document specifying prospective long term plan of the site shall be formulated and submitted.

iii)          Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iv)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

v)            The project proponent shall provide confirmed GPS readings of plant boundary.

vi)          No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

vii)         Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

viii)       Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

ix)          Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

x)            Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xi)          Land-use pattern in the study area shall be studied, which shall include identification of common property resources available for conversion into productive land. Action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project shall be prepared.

xii)        Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xiii)       CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xiv)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xv)         Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

xvi)       Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xvii)      Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xviii)        One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xix)            Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xx)         Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxi)       Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxii)     Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxiii)    Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxiv)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxv)      Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxvi)    Details of water balance taking into account reuse and re-circulation of effluents.

xxvii)   Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxviii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxix)    EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxx)      A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxi)    Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.

xxxii)  Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e019. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.6    Expansion by addition of 700 MW (Stage-II) Gas based Combined Cycle Power Project of M/s NTPC Ltd at National Capital Power Station Dadari, in  Dadri taluk, in Gautam Budh Nagar Distt., in Uttar Pradesh     -   reg. TOR .

 

The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent gave a presentation and provided the following information:

 

The proposal is for expansion of existing Gas based Combined Cycle Power Plant by addition of 700 MW (Stage-II) at National Capital Power Station Dadari, in Dadri taluk, in Gautam Budh Nagar Distt., in Uttar Pradesh. No additional land will be required for proposed expansion. The co-ordinates of the proposed site will be at Latitude 28034’20.93” to 28036’40.69” N and Longitude 77036’5.9” to 77037’37.63” E. Fuel Requirement will be 3.55 MMSCMD. Water requirement will be 15 cusecs, which will be obtained from Dehra Regulator located on Upper Ganga Canal system through a pipeline over a distance of 1.0 km from project site. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10km of the project boundary.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Status of compliance to the conditions stipulated in the environmental clearance for the existing units shall be submitted.

ii)           Vision document specifying prospective long term plan of the site shall be formulated and submitted.

iii)          Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iv)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

v)            The project proponent shall provide confirmed GPS readings of plant boundary.

vi)          No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

vii)         Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

viii)       Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

ix)          Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

x)            Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xi)          Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xii)        Land-use pattern in the study area shall be studied, which shall include identification of common property resources available for conversion into productive land. Action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project shall be prepared.

xiii)       Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xiv)       CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xv)         While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xvi)       Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xvii)      Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xviii)        One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xix)            Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xx)         Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxi)       Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxii)     Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxiii)    Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxiv)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxv)      Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxvi)    Details of water balance taking into account reuse and re-circulation of effluents.

xxvii)   Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxviii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxix)    EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxx)      A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxi)    Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.

xxxii)  Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)            All documents to be properly referenced with index, page numbers and continuous page numbering.

b)           Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)            Where the documents provided are in a language other than English, an English translation should be provided.

d)           The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e019. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.7       2X660 MW Coal Based Super Critical TPP of M/s NTPC Ltd. near village Selda, in Barwah Tehsil, in Khargone Distt., in Madhya Pradesh -  reg. TOR.

 

The proposal was earlier placed in the 1st Meeting of the Committee held during July 7-9, 2010 for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. In the said meeting the Committee had observed that in the absence of site details of alternative sites identified the proposal is pre-mature for consideration in its present form. The matter was accordingly deferred for re-consideration at a later stage. The project proponent gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 2x660 MW Coal Based TPP near village Selda, in Barwah Tehsil, in Khargone Distt., in Madhya Pradesh. Land requirement will be restricted to 1000 acres, which will be in Government barren land with some single crop private land. The co-ordinates of the proposed site will be at ratio of Latitude 22009’12” to 220 11’ N and Longitude 760 08’05” to 760 10’ 23” E. Coal requirement will be 7.5 MTPA. Coal will be obtained from North Karanpura/IB valley Coal Fields. Water requirement of 55 CUSECS will be met from Narmada River through a pipeline over a distance of 8 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.                                                                                                                                                                                                                                                                                                                                    

 

Based on the information provided and presentation made, the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

iv)          The project proponent shall provide confirmed GPS readings of plant boundary.

v)            No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

vi)          Detail information on water allocation by the Govt. of Madhya Pradesh for various purposes such as drinking, irrigation, industrial (including thermal power) shall be obtained and submitted.

vii)         Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

viii)       Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.

ix)          Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

x)            Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

xi)          Details of 100% fly ash utilization plan along with firm agreements / MoU with contracting parties shall be submitted. The plan shall also include disposal method / mechanism of bottom ash.

xii)        Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.

xiii)       Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xiv)       Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xv)         Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xvi)       Land-use pattern in the study area shall be studied, which shall include identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project shall be prepared.

xvii)      Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xviii)    CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xix)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xx)         Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xxi)       Location of intake and outfall points (with coordinates) should be given.

xxii)     Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xxiii)        One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM (PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xxiv)        Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xxv)      Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxvi)    Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxvii)   Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxviii) Source of water and its availability. Commitment regarding availability of requisite quantity of water from the Competent Authority shall be provided along with firm linkage.

xxix)    Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxx)      Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxxi)    Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxxii)  Details of water balance taking into account reuse and re-circulation of effluents.

xxxiii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxxiv) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxxv)   EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxvi) A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxvii)    Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xxxviii)  Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

 

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

  1. Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?
  2. If not, then by when is that expected?
  3. Has PDD (Project Design Document) been prepared?
  4. What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)
  5. Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.8       Expansion by addition of 2X500 MW Coal Based TPP and 2.0 MTPA Cement Grinding Unit of M/s Bina Power Supply Company Ltd. at village Jodh & Sirchopi, in Bina Tehsil, in Sagar Distt., in Madhya Pradesh  -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per the provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Vimta Labs Ltd gave a presentation and provided the following information:

                                                                                                        

The proposal is for expansion by addition of 2x500 MW Coal Based TPP and 2.0 MTPA Cement Grinding Unit at villages Jodh & Sirchopi, in Bina Tehsil, in Sagar Distt., in Madhya Pradesh. Stage-I 2x250 MW of the project is under implementation. Land requirement will be met from the existing 693.78 hectares which is already under possession. Cement grinding Unit will be accommodated within the existing land and will comprise of 20 acres area. The co-ordinates of the proposed site will be at Latitude 240 18’ 21” to 240 20’35” N and Longitude 780 07’27” to 780 10’ 07” E. Coal requirement will be 5.0 MTPA. Coal will be obtained from Domestic Coal block. No additional land is required for ash pond/dyke. Water requirement will be 108 MLD, which will be obtained from Betwa River through an Intake Well over a distance of 1.7 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.

 

The Committee noted that 2x500 MW Sub-Critical proposal is not very encouraging considering that the Govt. of India policy in power sector is promotion of energy efficient technology such as Super-Critical. The Committee therefore advised the project proponent to re-consider its proposal and explore the option of 2x660 MW Super-Critical technology. Accordingly the proposal was deferred for re-consideration at a later stage.

 

 

2.9    Expansion of 1000 MW by addition of 2X660 MW (Phase-III) Super-Critical Coal Based Power Plant of M/s Meenakshi Energy Pvt Ltd at Village Thamminapatnam, in Chillakur Mandal Taluk, in SPSR Nellore Distt., in Andhra Pradesh      -   reg. TOR .

 

The proposal was placed for consideration for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. A presentation was also made by the project proponent and its consultant M/s Grass Roots Research & Creation Pvt. Ltd & M/s Indomer Coastal Hydraulics Pvt. Ltd.  and provided the following information:

 

The proposal is for expansion by addition of 2x660 MW Super-Critical Coal Based TPP at village Thamminapatnam, in Chillakur Mandal Taluk, in SPSR Nellore Distt., in Andhra Pradesh. Phase-I 2x150 MW and Phase-II 2x350 MW are under active stage of implementation. Land requirement for expansion will be 533 acres, which is  a Govt. barren land. The co-ordinates of the proposed site will be at  Latitude 14012’11” N to 140  13’26” N and Longitude 80006’12” E to 80004’36.97” E. Coal Requirement will be 5.39 MTPA. Domestic and Imported coal in the ratio of 70:30 shall be used. Water requirement will be 348384 m3/day, which will be obtained from Kandaleru Creek near Krishnapatnam Port, through a pipeline over a distance of 800 m. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10 km of the project boundary.

 

The Committee advised the proponent to draw water from the Sea. The project proponent informed that it will be difficult to take water from Sea as the location of their plant is in between Port. However, it was also informed that they will explore the possibility. The project proponent also informed that no expansion beyond the present proposal is envisaged.

 

The Committee noted that a number of thermal power projects are proposed in the Nellore area. Therefore, the Committee suggested that a carrying capacity study shall be carried through the reputed institute.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          Status of compliance to conditions stipulated in the environmental clearances for the earlier phases shall be submitted.

iv)          CRZ line demarcation shall be obtained from an approved agency and submitted along with EIA/EMP report.

v)            The project proponent shall provide confirmed GPS readings of plant boundary.

vi)          No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.

vii)         Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

viii)       Study on the impact on river/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

ix)          The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

x)            Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

xi)          Details of 100% fly ash utilization plan along with firm agreements / MoU with contracting parties shall be submitted. The plan shall also include disposal method / mechanism of bottom ash.

xii)        Layout plan indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xiii)       Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for lying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xiv)       Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, mangroves, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xv)         A detailed plan for preservation and protection of mangroves in the area (as applicable) shall be submitted. The plan shall also include measures for regeneration of degraded mangroves (if any).

xvi)       Land-use pattern in the study area shall be studied which shall include identification of common property resources available for conversion into productive land. Accordingly action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project (as applicable) shall be prepared.

xvii)      Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xviii)    Impact on fishing and livelihood on fishing community shall be specifically undertaken from an institute of repute who has expertise in the area. A detailed report shall be submitted which shall spell out clearly alternative source of sustainable livelihood to address an adversity.

xix)       A detailed CSR plan shall be prepared. CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xx)         While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xxi)       Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xxii)          One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur

xxiii)    Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xxiv)    Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxv)      Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxvi)    Quantity of fuel required its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxvii)   Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

xxviii) Detail plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxix)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxx)      Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxxi)    Details of water balance taking into account reuse and re-circulation of effluents.

xxxii)  Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Detail of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxv)   A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxvi) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Further, the following shall be strictly followed (as applicable):

 

a)            No waste should be discharged into canal systems, backwaters, marshy areas and seas without treatment.

b)           To absorb the ground level pollutants, to act buffer against strong winds arising out of tropical cyclones/ storms, to reduce heat load and ameliorate environment, there is a need for shelterbelts / greenbelts / tree cover along the coastline, bunds around marshy areas, roadsides, around the project boundaries, around village boundaries, ash dykes, railway lines, around protected monuments, forts, waste places, School Campuses and other vacant lots. Coconut plantations can be developed along the coastline and near villages, Schools and forts. Stands of Casuariana should also be developed on some dunes and along coasts. Bamboos, neem and other native trees should be planted in and around at the villages.

c)            To meet the expenditure of these plantations and their management, a common Green Endowment Fund should be created by the project proponents out of EMP budgets. The interest earned out of it should be used for the development and management of green cover of the area.

d)           The villages bordering the sites may be predominantly inhabitated by fishermen and the TPSs have impacts on their livelihood, although most of the fishing activity is confined to deep seas. An endowment of Fishermen Welfare Fund should be created out of CSR grants not only to enhance their quality of life through creation of facilities for fish landing platforms / fishing harbour / cold storage, but also to provide relief in case of emergency situations such as missing of fishermen on duty due to rough seas, tropical cyclones and storms etc.

e)            The project specific recommendation should be made at the time of consideration of EIA.

f)             The project proponent should submit a detailed toposheet showing the locations of project site, Villages major canals, backwaters, low lying areas (marshy), coastline, sand dunes (bars), aquaculture ponds, creek, jetty and intake and outfall points. The distances from the project boundaries to the landscape features mentioned above should be marked.

g)            There should not be any contamination of soil, ground and surface waters (canals & village pond) with sea water in and around the project sites. In other wards necessary preventive measures for spillage from pipelines, such as lining of guard pond used for the treatment of outfall before discharging in to the sea and surface RCC channels along the pipelines of outfall and intake should be adopted. This is just because the areas around the projects boundaries is fertile agricultural land used for paddy cultivation.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)             If not, then reasons thereof?

ii)           If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues emerged during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.10    2x660 MW Coal Based Super Critical TPP of M/s India Power Corporation Ltd. at Village Indragachi (Bariaria), P.O. Dariyapur, in  Purba Champaran Distt., in Bihar -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Envirotech East Pvt. Ltd. gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 2x660 MW Coal Based TPP at village Indragachi (Bariaria), P.O. Dariyapur, in Purba Champaran Distt., in Bihar. Land requirement will be restricted to 900 acres, which comprises of single crop agricultural land. The co-ordinates of the proposed site will be at atitude 26029’45.81” N and Longitude 840 43’ 25.02” E. Coal requirement will be 6.75 MTPA. Coal will be obtained from domestic Coal from Eastern Coalfields Ltd. Water requirement will be 140000 KLD, which will be obtained from Gandak River through a pipeline over a distance of 4.5 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          The project proponent shall provide confirmed GPS readings of plant boundary.

iv)          No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.

v)            Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

vi)          Study on the impact on river/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

vii)         The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

viii)       Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

ix)          Details of 100% fly ash utilization plan along with firm agreements / MoU with contracting parties shall be submitted. The plan shall also include disposal method / mechanism of bottom ash.

x)            Layout plan indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xi)          Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for lying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xii)        Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, mangroves, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xiii)       Land-use pattern in the study area shall be studied which shall include identification of common property resources available for conversion into productive land. Accordingly action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project (as applicable) shall be prepared.

xiv)       Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xv)         A detailed CSR plan shall be prepared. CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xvi)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xvii)      Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xviii)        One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur

xix)       Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xx)         Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxi)       Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxii)     Quantity of fuel required its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxiii)    Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

xxiv)    Detail plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxv)      Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxvi)    Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxvii)   Details of water balance taking into account reuse and re-circulation of effluents.

xxviii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Detail of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxix)    Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxx)      EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxi)    A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxii)  Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)            If not, then reasons thereof?

ii)           If yes, then details under mentioned to be provided:

 

a)      Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)     If not, then by when is that expected?

c)      Has PDD (Project Design Document) been prepared?

d)     What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)

e)      Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues emerged during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.11    1300 MW Gas Based Combined Cycle Power plant of M/s Poena Power Company Ltd. at village Savaroli,  in Khalapur Tehsil, in Raigarh Distt., in Maharastra -  reg. TOR.

 

The proponent informed that they will not be able to attend the meeting. The proposal was accordingly deferred for re-consideration at a later stage.

 

 

2.12    1000 MW Gas Based Combined Cycle Power plant of M/s Poena Power Generation Ltd. at village Mahagaon, in Tala Tehsil, in Raigarh Distt., in Maharastra -  reg. TOR.

 

The proponent informed that they will not be able to attend the meeting. The proposal was accordingly deferred for re-consideration at a later stage.

 

 

2.13    2x600 MW Imported Coal Based TPP of M/s Chettinad Power Corporation Private Ltd. at villages Erukkattanchery, Kazhizppanallur and Manichkapangu, in Tarangambadi Taluk, in  Nagapattinam Distt., in Tamil Nadu -  reg. Environmental Clearance.

 

The proposal was placed for consideration of environmental clearance. The project proponent along with its consultant viz. M/s Vimta Labs Limited, Hyderabad gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 2x600 MW Imported Coal Based TPP at villages Erukkattanchery, Kazhizppanallur and Manichkapangu, in Tarangambadi Taluk, in Nagapattinam Distt., in Tamil Nadu. Land requirement will be 332.5 ha, out of which 252.15 ha is single crop agricultural land; 80.35 ha land is waste land (Government Temple & Porombokke land). The area was Tsunami affected area and the agricultural land has become saline and no more suitable for cultivation in its present state. The co-ordinates of the proposed plant will be at Latitude 11002’48.404” N to 11004’03.286” N and Longitude 79050’08.907” E to 79050’52.712” E and the co-ordinates of the ash pond will be at Latitude 11003’30.43” N to 11003’49.51” N and Longitude 79050’12.06” E to 79050’27.01” E . Coal requirement will be 3.4 MTPA. Coal will be imported from Indonesia. Coal will be transported through a captive jetty proposed near the power plant site. Water requirement will be 115.8 MCM/annum, which will be obtained from Sea water (Bay of Bengal) through a Pipeline over a distance of 1.25 Km from the project site. A desalination plant of 12 MLD is proposed to be set up. Closed cycle system with natural draft cooling tower is proposed. High concentration slurry disposal system is proposed. The treated waste water will be used in ash handling plant. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. However there is a Town Gateway situated at Tranquebar at a distance of 2 km. Public hearing was held on 21.05.2010. Cost of the project  will be Rs. 7216.40 Crores.

 

The Committee discussed the issue of setting up of Sub-Critical Technology power plant and sought clarification from the project proponent whether they can shift to 2x660 Super-Critical Technology. The project proponent informed that at this juncture it may not be possible. However, it was also agreed by the project proponent that FGD can be installed keeping to environmental concerns raised by the Committee.

 

The Committee also deliberated on the issues raised in the public hearing and the responses provided by the project proponent. The major issues raised were regarding likely impact on fishermen and agriculturists; adverse impact due to fly ash to be generated; cumulative impact of all power plants likely to come up in the region; employment of local people; civic amenities for villages such as roads, electricity; the area is located at tail end of Cauvery river; land sold were mostly uncultivable Tsunami affected land; impact on marine ecology due to hot water to be released from power plant etc. The project proponent also stated that no litigation in any court pertaining to the project is filed/pending.

 

The objections raised by an NGO viz. Coastal Action Network were also discussed. The issues raised were brought to notice of the Committee and noted valid points which was subsequently clarified by the project proponent such as location of archeological site of importance at 2.0 Km from the site; cumulative impact of power plants in the area; area being nesting ground of Olive Ridley Turtle etc.

 

Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:

 

i)             Environmental clearance is subject to obtaining CRZ clearance for permissible activities in CRZ area.

ii)           FGD shall be installed prior to commissioning of the plant.

iii)         The project proponent shall examine in detail the possibility to adopt NIOT technology of handling Brine through Low Temperature Thermal Desalination (LTTD) process. In case the same is not feasible detailed explanation shall be submitted.

iv)          The levelling in plant area should be minimum with no or minimal disturbance to the natural drainage of the area. If the minor canals (if any) have to be diverted, the design for diversion should be such that the diverted canals not only drains the plant area but also collect the volume of flood water from the surrounding areas and discharge the same into marshy areas/major canals that enter into creek/nallah etc. Major canals should not be altered but their bunds should be strengthened and desilted.

v)            Additional soil for levelling of the sites should be generated within the sites in a way that natural drainage system of the area is protected and improved.

vi)          The marshy areas in the vicinity (if any) which may hold large quantities of water shall not be disturbed.

vii)         To absorb the ground level pollutants, to act buffer against strong winds arising out of tropical cyclones/ storms, to reduce heat load and ameliorate environment, there is a need for shelterbelts / greenbelts / tree cover along the coastline, bunds around marshy areas, roadsides, around the project boundaries, around village boundaries, ash dykes, railway lines, around protected monuments, forts, waste places, School Campuses and other vacant lots. Coconut plantations can be developed along the coastline and near villages, Schools and forts. Stands of Casuariana should also be developed on some dunes and along coasts. Bamboos, neem and other native trees should be planted in and around at the villages.

viii)       To meet the expenditure of these plantations (stated above) and their management, a common Green Edowment Fund should be created by the project proponents out of EMP budgets. The interest earned out of it should be used for the development and management of green cover of the area.

ix)          Continuous monitoring of marine biology shall be undertaken by an institute of repute

x)            An endowment of Fishermen Welfare Fund should be created not only to enhance the quality of life of fishermen community through creation of facilities for fish landing platforms / fishing harbour / cold storage, but also to provide relief in case of emergency situations such as missing of fishermen on duty due to rough seas, tropical cyclones and storms etc.

xi)          There should not be any contamination of soil, ground and surface waters (canals & village pond) with sea water in and around the project sites. In other wards necessary preventive measures for spillage from pipelines, such as lining of guard pond used for the treatment of outfall before discharging in to the sea and surface RCC channels along the pipelines of outfall and intake should be adopted. This is just because in the areas around the projects boundaries there may be fertile agricultural land used for paddy or other crop cultivation

xii)        100 % fly ash disposal shall be ensured from 4th year of operation of the plant and action plan in this regard including the utilization of fly ash in the cement and brick manufacturing shall be submitted to the Ministry within six months.

xiii)       Possibility for using nearest Port shall be made for obtaining coal and report submitted within six months to the Ministry.

xiv)       It shall be ensured that natural drainage in the region is not disturbed due to activities associated with operation of the plant.

xv)         The project proponent shall regenerate any degraded water body located nearby within 5.0 km atleast.

xvi)       COC of 1.5 shall be adopted and report submitted within 3 months of operation of the plant.

xvii)      Stack of 275 m height with flue gas velocity of 22 m/s will be installed.

xviii)    Monitoring surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.

xix)       Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.

xx)         A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months. 

xxi)       Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB(A) should be provided.

xxii)     The emission of particulate matter from the proposed thermal power plant shall not exceed 50 mg/Nm3 by installation of ESP and along with bag filter.

xxiii)    Atleast three nearest village shall be adopted and basic amenities like development of roads, drinking water supply, primary health centre, primary school etc shall be developed in co-ordination with the district administration.

xxiv)    The project proponent shall also adequately contribute in the development of the neighbouring villages. Special package with implementation schedule for providing free potable drinking water supply in the near by villages and schools shall be undertaken in a time bound manner.

xxv)      An amount of Rs 28.90 Crores as one time investment shall be earmarked for activities to be taken up under CSR. Recurring expenditure for CSR shall be Rs 5.8 Crores.

xxvi)    While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poor section of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment and jobs shall be imparted to identified villagers free of cost.

xxvii)   It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from the nearest government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.

xxviii) An Environmental Cell shall be created at the project site itself and shall be headed by an officer of appropriate superiority and qualification. It shall be ensured that the head of the Cell shall directly report to the head of the organization.

 

 

2.14    600 MW (2x300 MW) Coal Based TPP of M/s TRN Energy Pvt. Ltd. at villages Bhengari, Nawpara, Katangdih, in Ghargoda Tehsil, in Raigarh Distt, in Chhattisgarh     -        reg. Environmental Clearance.

 

The proposal was placed for consideration of environmental clearance. The project proponent along with its consultant viz. M/s Crystal Consultants gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting up of 2x300 MW Imported Coal Based TPP at villages Bhengari, Nawpara, Katangdih, in Ghargoda Tehsil, in Raigarh Distt, in Chhattisgarh. Land requirement will be 548.0 acres, out of which 508 acres is waste land and 40 acres is single crop agricultural land. The co-ordinates of the proposed plant will be at Latitude 22007’30” N to 22009’22” N and Longitude 83014’02” E to 83016’58” E. Coal requirement will be 3.0 MTPA, which will be obtained from SECL. LoA from SECL has been obtained. Ash and sulphur contents in the coal will be 40-45% and 30 to 0.40 % respectively. Water requirement will be 19 MCM/annum, which will be obtained from River Kurket at distance of 3.0 from the project site. Water allocation letter from Water resources Dept., Govt. of Chhattisgarh has been obtained. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Public hearing was held on 14.07.2010. Cost of the project will be Rs. 2820.0 Crores.

 

The Committee observed that the flora and fauna list provided by the project proponent (authenticated by the DFO) seem to be highly erroneous and may be re-examined/re-validated. The project proponent was advised to submit a list of fauna from ZSI or University of the region. It was also noted that ground water and surface water quality test result data presented is highly erroneous and need to be re-checked. The ambient air quality analysis and predictions presented were also observed to be unacceptable. The predictions have been based on 0.3 % sulphur content of coal, whereas sulphur content in the coal can be as high as 0.6%. It was also noted that no concrete plan for Fly Ash utilization is in place and MoU / Agreement with prospective Fly Ash buyers have been submitted. In the area of CSR, the Committee also noted that details of compensation paid / proposed to be paid to land losers have not been furnished, nor action plan for CSR actives with budgetary allocation provided in detail.

 

The Committee also noted that the mine from where coal is to be sourced is at distance of about 14-19 Kms and alternative mode of transportation such as by rail shall be examined. The Committee further discussed the representation submitted by an NGO and decided that the project proponent shall submit detailed response / clarification to the representation.

 

In view of the shortcomings as noted above the Committee decided that the project proposal can be re-considered only after requisite information as noted above is provided. Accordingly the proposal was deferred.

 


2.15  2x660 MW Coal Based Supercritical TPP of M/s Lanco Vidarbha Thermal Power Ltd. at village Mandva, in Wardha Taluk & Distt., in Maharashtra - reg. Environmental Clearance.

 

The proposal was considered and  placed for environmental clearance. The project proponent along with its consultant viz. M/s Vimta Labs Ltd., Hyderabad gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting up of 2x660 MW Coal Based TPP at village Mandwa, in Wardha Taluk & Distt., in Maharastra. Land requirement will be  1195 acres, out of which 484.13 acres has been purchased and rest is under progress for acquisition. The co-ordinates of the proposed site will be at ratio of Latitude 20048’44.6” N to 20049’47.4” N and Longitude 78027’56.7” E to 78030’24.3” E. Coal requirement will be 7.5 MTPA. Coal will be obtained from domestic coal block and sourced from SECL mines. Coal linkage has been obtained. Ash and sulphur contents in coal will be 42% and 0.45 % respectively. Water requirement will be 3858m3/hr, which will be sourced from Lower Wardha Reservoir through a Pipeline over a distance of 30.0 km from the project site. Water allocation has been obtained from the State Govt. Lean concentration fly ash disposal system shall be adopted. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site. Public hearing was held on 19.09.2010. Cost of the project will be Rs. 6936.0 Crores.

 

The Committee noted that the distance from coal mine to the project site is about 600 Kms and therefore considering the environmental implications involved that may arise due to transportation of coal by road; the project proponent shall adopt rail transportation only till nearest possible destination to the project site. The Committee also suggested that coal washery at appropriate place at mine shall be explored  either by itself or tying up for supply of washed coal from the washery to be set up near the mining area. The Committee also noted that an area of 955 acres for the power plant is on the higher side which should be restricted to 900 acres by excluding the double crop area.

 

The Committee also discussed the representations received from various quarters and more particularly the Member of Parliament of the region. The Committee expressed its concern over the general pattern of regional imbalance in development of States and cautioned that project proponent shall ensure that land owners from whom land have been acquired are not deprived of sustainable livelihood or that they become non-eligible for gainful employment. The Committee taking note of the concerns expressed in the representations and the clarification provided, decided that the project proponent shall  undertake measures to provide opportunity for livelihood for the landless people. Public concerns are on land getting destroyed by fly ash and use of excessive water, affecting agriculture adversely.  These concerns must be addressed by the Project Proponents to the satisfaction of the people in the area through Education, Communication and mitigative measures.

 

The Committee further discussed the issues raised in the public hearing and the responses made by the project proponent. The major issues raised were the likely impacts due to fly ash generated on air, water and soil; allocation of water for the TPP and its impact on irrigation; justification for setting up TPP in Wardha which is already highly polluted; inadequate compensation for land acquired; NOC by Gram Panchayat is not  consent of villagers; justification for water from Lower Wardha Dam being diverted for the project etc. The project proponent also confirmed that no litigation is pending in any court pertaining to the proposed project.

 

Based on the information and clarifications provided, the Committee recommended the project for environmental clearance subject to stipulation of the following specific conditions:

 

i)             Vision document specifying prospective plan for the site shall be formulated and submitted to the Ministry within six months.

ii)           Land requirement shall be restricted to 900 acres and double crop agricultural land shall be excluded to the extent possible.

iii)          The project proponent shall provide space for FGD system for future installation as and when required.

iv)          Transportation of coal shall be through railways till the nearest possible destination.

v)            The proponent shall explore the possibility of tying up for supply of washed coal from the washery to be set up near the mining area.

vi)          DGMS permission shall be obtained for back filling of mined out area (if any proposed). In any case, mine back filling shall be carried out after detailed likely impact studies and adoption of adequate mitigation measures such as providing adequate layer of clay lining before filling.

vii)         100 % fly ash disposal shall be ensured from 4th year of operation of the plant.

viii)       Height of stack shall be 275 m each with flue gas velocity not less than 22 m/s.

ix)          It shall be ensured that the area drainage is not disturbed due to the proposed expansion.

x)            Water requirement shall be restricted to 35 cusecs.

xi)          Hydro geological study of the area shall be reviewed annually and report submitted to the Ministry.

xii)        Monitoring of surface water quantity and quality shall also be regularly conducted and records maintained. The monitored data shall be submitted to the Ministry regularly. Further, monitoring points shall be located between the plant and drainage in the direction of flow of ground water and records maintained. Monitoring for heavy metals in ground water shall be undertaken.

xiii)       Green Belt consisting of 3 tiers of plantations of native species around plant and at least 100 m width shall be raised. Wherever 100 m width is not feasible a 50 m width shall be raised and adequate justification shall be submitted to the Ministry.

xiv)       Waste water generated from the plant shall be treated before discharge to comply limits prescribed by the SPCB.

xv)         A well designed rain water harvesting system shall be put in place within six months, which shall comprise of rain water collection from the built up and open area in the plant premises. Action plan and road map for implementation shall be submitted to the Ministry within six months.   

xvi)       Well designed acoustic enclosures for the DG sets and noise emitting equipments to achieve the desirable insertion loss viz. 25 dB(A) should be provided.

xvii)      Additional soil for leveling of the sites should be generated within the site in a way that natural drainage system of the area is protected and improved.

xviii)    An amount of Rs. 27.80 Crores as one time investment should be earmarked for activities to be taken up under CSR by the above proponent. Recurring expenditure for CSR shall not be less than Rs. 5.60 Crores per annum till the operation of the plant. Detailed action plan with break-up of activities to be undertaken shall be submitted within six months to the Ministry.

xix)       While identifying CSR activities it shall be ensured that need based assessment for the nearby villages within study area shall be conducted to study economic measures with action plan which can help in upliftment of poorer sections of society. Income generating projects consistent with the traditional skills of the people shall be undertaken. Development of fodder farm, fruit bearing orchards, vocational training etc. can form a part of such programme. Company shall provide separate budget for community development activities and income generating programmes. Vocational training programme for possible self employment shall be imparted to pre identified villagers free of cost.

xx)         The project proponent shall ensure that land losers and other indirectly impacted by land acquired for the project are not deprived of sustainable livelihood.

xxi)       It shall be ensured that an in-built monitoring mechanism for the CSR schemes identified is in place and annual social audit shall be got done from a government institute of repute in the region. The project proponent shall also submit the status of implementation of the scheme from time to time.

xxii)     An Environmental Cell shall be created at the project site itself and shall be headed by qualified officer, who is well versed with the environmental aspects.  It shall be ensured that the Head of the Cell shall directly report to the head of the organization.

xxiii)    Continuous efforts must be made to optimise the use of water and recycle water wherever feasible.

 

2.16    2x660 MW Coal Based Captive TPP of M/s Jindal Steel & Power Ltd. at villages Nipania and Pankaghat, in Sunder Pahari Taluk, in Godda Distt., in Jharkhand -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006 in the 69th Meeting of the Committee held during April 30-May 01, 2010 but was deferred as the Committee desired that then project proponent shall look for alternative site. On submission proposal of alternate location the proposal was again placed for consideration. The project proponent along with its consultant viz. M/s EMTRC Consultant Pvt. Ltd, Delhi gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 2x660 MW Coal Based Captive TPP at villages Nipannia, Pankaghat, in Sunder Pahari Taluk, in Godda Distt., in Jharkhand. Land requirement will be 383 hectares, out of which 283.37 ha is single crop agricultural land; 99.63 ha is Government land. The co-ordinates of the proposed site will be at Latitude 24045’21.22” N to 24045’54.56” N and Longitude 87019’9.09” E to 87020’6.53” E. Ash Pond will be at Latitude 24046’12.80” N to 24047’3.48” N and Longitude 87018’52.94” E to 87019’53” E. Staff colony will be at Latitude 24047’33.70” N to 24048’12.0” N and Longitude 87018’15.20” E to 87018’49.90” E. Coal requirement will be 7.0 MTPA. Coal will be obtained from domestic coal block and sourced from captive coal block at Jitpur. Area requirement for ash pond/dyke will be 156 hectares. Water requirement will be 36 MCM, which will be obtained from Sunder River through a Pipeline over a distance of 27 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Geological / Mineral map of the plant area to ascertain the present of the mineral.

iii)          Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iv)          The project proponent shall provide confirmed GPS readings of plant boundary.

v)            No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.

vi)          Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

vii)         Study on the impact on river/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

viii)       The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

ix)          Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

x)            Details of 100% fly ash utilization plan along with firm agreements / MoU with contracting parties shall be submitted. The plan shall also include disposal method / mechanism of bottom ash.

xi)          Layout plan indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xii)        Land requirement for the project shall be optimized to 900 acres. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for lying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report.  The area for the ash dyke should be reduced to 250 acres.

xiii)       Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, mangroves, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xiv)       Land-use pattern in the study area shall be studied which shall include identification of common property resources available for conversion into productive land. Accordingly action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project (as applicable) shall be prepared.

xv)         Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xvi)       A detailed CSR plan and R&R plan (as applicable) shall be prepared. CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xvii)      While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xviii)    Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xix)            One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur

xx)         Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xxi)       Cumulative impact of various sources including the proposed project on the AAQ of the study area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxii)     Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxiii)    Quantity of fuel required its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxiv)    Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

xxv)      Detail plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxvi)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxvii)   Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxviii) Details of water balance taking into account reuse and re-circulation of effluents.

xxix)    Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Detail of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxx)      Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxxi)    EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxii)  A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxiii) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.17    1000 MW Gas Based Combined Cycle Power Project of M/s Hecate Power Systems Ltd. at village Khandpur, in Latur Taluk, in Latur  Distt., in Maharastra      -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA Notification, 2006. The project proponent along with its consultant viz. M/s GIS Enabled Environment & Neo-Graphic Centre, Ghaziabad gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 1000 MW Gas Based Power Project at village Khandpur, in Latur Taluk & Distt., in Maharashtra. Land requirement will be 50 acres, which is MIDC land. The co-ordinates of the proposed site will be at Latitude 18021’28.9” N and Longitude 76029’10.1” E. Natural Gas requirement will be 2.67 to 3.33 MMSCMD, which will be sourced from M/s GAIL. Water requirement will be 13.0 MCM, which will be obtained from Manjra River through a Pipeline over a distance of 12 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.

 

The Committee noted that the proposed area even though a notified industrial area, the environmental clearance for the said industrial estate seem to be not in place and hence exemption from public hearing cannot be given.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

iv)          The project proponent shall provide confirmed GPS readings of plant boundary.

v)            No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

vi)          Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

vii)         Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

viii)       Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

ix)          Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

x)            Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xi)          Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.

xii)        Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xiii)       CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xiv)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xv)         Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xvi)       Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xvii)          One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xviii)        Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xix)       Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xx)         Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxi)       Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxii)     Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxiii)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxiv)    Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxv)      Details of water balance taking into account reuse and re-circulation of effluents.

xxvi)    Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxvii)   Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxviii) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxix)    A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxx)      Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.

xxxi)    Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

                                    

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e019. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expect]

f)     {|ed to be reduced from the baseline data available on the CEA’s web-site (-*/)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.18    1350 MW Coal Based Mansa TPP of M/s Poena Power Development Ltd. at villages Gobindpura, Phullwall Dod, in Mansa Taluk, in Mansa Distt., in Punjab -  reg. TOR.

 

The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The proposal was earlier considered in the 5th Meeting held during September 6-7, 2010 and TOR was recommended for the proposal at a different site at villages Bhupal & Harsinghwala, in Taluk & Distt. Mansa, in Punjab. The project proponent have now requested for change of site and informed that the earlier TOR issued by the Ministry vide J-13012/132/2010-IA.II(T) dated 07.10.2010 may be cancelled. The project proponent along with its consultant viz. M/s GIS Enabled Environment & Neo-Graphic Centre, Ghaziabad gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 1350 MW Coal Based TPP at villages Gobindpura, Phullwall Dod, in Mansa Taluk, in Mansa Distt., in Punjab. Land requirement will be 1000 acres, which is agricultural land and barren land. The co-ordinates of the proposed site will be at Latitude 29052’17.5” N  and Longitude 75037’14” E. Coal requirement will be 7.2 MTPA. Coal will be obtained from domestic coal block and sourced from SECL/MCL mines.  Area requirement for Ash pond/dyke will be 200 acres. Water requirement will be 41 MCM, which will be obtained from Boha Distributary, Sirhind canal through a pipeline over a distance of 1.5 km from the project site. There are no National parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 10 km of the site.

 

The Committee decided that the TOR earlier prescribed shall be reiterated for the proposed site and the Ministry may accordingly do the needful.

 

 

2.19  Expansion of 10x 8.73 MW (94.80 MW) Gas Based Power Plant  by addition of 10x8.73 MW each & HRSG (6.0 MW) of M/s Arkay Energy (Rameswaram) Limited at village Valuthur, In Ramanathapuram Taluk, in Ramanathapuram Distt., in Tamil Nadu.-   reg. TOR .

 

The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent on the salient features and other details of the project and provided the following information: 

 

The proposal is for setting up for expansion of existing 94.80 MW Gas Based Power Plant by addition of 10x8.73 MW each & HRSG (6.0 MW) at village Valuthur, In Ramanathapuram Taluk, in Ramanathapuram Distt., in Tamil Nadu. The total capacity after addition will be 188.6 MW. Land requirement will be 13 acres, which will be within the existing plant. Natural Gas requirement will be 2,70,000 SCMD. Water requirement will be 20 m3/day, which will be obtained from desalinated water from M/s South Ganga water Technologies Pvt. Ltd. through tankers over a distance of 2.0 km. There are no national park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc. within 10km of the project boundary. However, Gulf of Mannar situated within 10.0km of the project site.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Status of compliance to the conditions stipulated for existing plant (as applicable) shall be submitted.

iii)          Copy of application to the Standing Committee of the National Board of Wildlife for clearance along with action plan and road map of conservation measures shall be submitted.

iv)          Authenticated map indicating location of Gulf of Mannar and the proposed power plant duly vetted by the concerned Office of the Chief Wildlife Warden shall be submitted.

v)            Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

vi)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

vii)         The project proponent shall provide confirmed GPS readings of plant boundary.

viii)       No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

ix)          Hydro-geological study (including sustainability study during lean season) of the area shall be conducted from an institute/ organisation of repute to assess impact of water regime in the area. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

x)            Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

xi)          Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xii)        Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xiii)       Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xiv)       Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.

xv)         Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xvi)       CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xvii)      While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xviii)    Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xix)       Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xx)              One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xxi)            Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xxii)     Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxiii)    Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxiv)    Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxv)      Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxvi)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxvii)   Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxviii) Details of water balance taking into account reuse and re-circulation of effluents.

xxix)    Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxx)      Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxxi)    EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxii)  A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxiii) Detailed plan for raising Green belt of 50 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.

xxxiv) Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

                                    

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e019. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.20    3X350 MW Coal Based Thermal Power Project of M/s Suryachakra Thermal Energy (Andhra) Pvt. Ltd. at Nakkapalli Mandal, in Visakhapatnam Distt., in Andhra Pradesh    - reg. TOR.

 

Neither the project proponent nor its representative was present in the meeting. The proposal was accordingly deferred for re-consideration at a later stage.

 

 

2.21    2X660 MW Coal Based Thermal Power Project of M/s Era Engineering Pvt. Ltd. at village Chichgohan/Attar, in Khandwa  Tehsil & Distt., in Madhya Pradesh          -  reg. TOR.

 

The proposal was earlier placed in the 62nd Meeting held during January 11-12, 2010 but was deferred as the Committee noted that the identified site may not be suitable and the project proponent was advised to come with alternative sites. The site chosen then was at village Jatwar in Umaria District. Later the matter was again placed in the 69th Meeting of the Committee held during April 30-May01, 2010 wherein the Committee noted that a clarification w.r.t. location of proposed site and vis-à-vis, the buffer (proposed) of Bandhavgar Tiger Reserve is required. The Committee therefore felt that the matter be referred to the National Tiger Conservation Authority for its views or alternatively the project proponent may provide a certificate from the Director, Bandhavgar Tiger Reserve that the proposed site does not fall  within the proposed buffer of the tiger reserve. Accordingly the matter was deferred for re-consideration at a later stage.

 

The project proponent chose to drop the site and have requested for a different site in a different Distt. The proposal was considered for determination of terms of reference for undertaking EIA/EMP study as per provisions of EIA notification 2006. The project proponent along with its consultant viz. M/s Vimta Labs Ltd. Hyderabad gave a presentation and provided the following information:

                                                                                                        

The proposal is for setting of 2X660 MW Coal Based Power Project at village Chichgohan/Attar, in Khandwa Tehsil & Distt., in Madhya Pradesh. Land requirement will be 900 acres, out of which 390 acres land will be for main plant; 150 acres for ash disposal; 270 acres for green belt; 50 acres for town ship; and 40 acres for service corridor. The co-ordinates of the proposed site will be Latitude 21058’53” N to 22000’03” N and Longitude 76010’4” E to 76011’36” E. Coal requirement will be 6.3 MTPA. Coal will be obtained from domestic coal block. Water requirement will be 4620 m3/hr, which will be obtained from Indira Sagar Reservoir through a pipeline over a distance of 47.5 km from the project site. There are no National Parks, Wildlife sanctuaries, Heritage sites, Tiger/Biosphere reserves etc. within 15 km of the site.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          The project proponent shall provide confirmed GPS readings of plant boundary.

iv)          No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah (if any) passing in and around the proposed site.

v)            Hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

vi)          Study on the impact on river/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

vii)         The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

viii)       Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

ix)          Details of 100% fly ash utilization plan along with firm agreements / MoU with contracting parties shall be submitted. The plan shall also include disposal method / mechanism of bottom ash.

x)            Layout plan indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xi)          Land requirement for the project shall be optimized and item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for lying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xii)        Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, mangroves, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xiii)       Land-use pattern in the study area shall be studied which shall include identification of common property resources available for conversion into productive land. Accordingly action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project (as applicable) shall be prepared.

xiv)       Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xv)         A detailed CSR plan and R&R plan (as applicable) shall be prepared. CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xvi)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xvii)      Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xviii)        One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur

xix)       Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xx)         Cumulative impact of various sources including the proposed project on the AAQ of the study area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxi)       Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxii)     Quantity of fuel required its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxiii)    Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

xxiv)    Detail plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxv)      Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxvi)    Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxvii)   Details of water balance taking into account reuse and re-circulation of effluents.

xxviii) Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Detail of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxix)    Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxx)      EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxi)    A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxii)  Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.22  Expansion by existing 4x50 MW (Phase-I) Liquid (Diesel) Fuel Based Power Plant by addition of 120 MW (Phase-II) Gas Based Combined Cycle Power Plant of M/s GMR Power Corporation Ltd. at village Basin Bridge, in Pullianthope Taluk, in Chennai Distt., in Tamil Nadu - reg. TOR.

and

 

2.23  Conversion of existing 4x50 MW (Phase-I) Liquid (Diesel) Fuel Based Power Plant to Gas Based of M/s GMR Power Corporation Ltd. at village Basin Bridge, in Pullianthope Taluk, in Chennai Distt., in Tamil Nadu - reg. TOR.

 

The above project were considered in sequel as the proposal is at the same premises belonging to the same party.

 

The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent gave a presentation and provided the following information:

 

The proposal for expansion is a ‘B’ category project since Purasawakkam-Perambur and Fort Tondiarpet (critically polluted area of Manali Industrial Area) is within 10.0 Km is considered at the centre as per general condition of EIA , 2006. The proposal is for conversion of existing 4x50 MW (Phase-I) Liquid Fuel Based Power Plant to Gas based and addition of 120 MW (Phase-II) Gas based Combined Cycle Power Plant at village Basin Bridge, in Pullianthope Taluk, in Chennai Distt., in Tamil Nadu. Phase-I is in operation since 1999. Land requirement for expansion will be 2.5 acres, which is within existing premises. The co-ordinates of the proposed site will be at Latitude 13006’08.33” N to 13006’29.14” N and Longitude 80016’01.70” E to 80016’08.20” E. Natural Gas requirement for expansion will be 0.60 MMSCMD, which will be obtained from Krishna-Godavari basin. Natural Gas required for conversion of existing Diesel Based plant will be 1.1 MMSCMD. Water requirement for expansion will be 3.48 MLD, which will be obtained from treated sewage water within the plant premises. Water required for conversion will be 4.80 MLD. There are no National park, wild life sanctuary, Biosphere/ tiger /Elephant reserves, Heritage sites etc within 10.0 Km of the project boundary.

 

i)             The project proponent shall examine the implications of running the plant with respect to the provisions enshrined in Chennai Master Plan. Relevant documents pertaining to running of power plant in Chennai Metropolitan Area and requirements thereof shall be submitted.

ii)           Vision document specifying prospective long term plan of the site shall be formulated and submitted.

iii)          Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iv)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

v)            The project proponent shall provide confirmed GPS readings of plant boundary.

vi)          Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated.

vii)         Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

viii)       Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for fuel transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

ix)          Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc (as applicable) in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

x)            Land-use pattern in the study area shall be studied, which shall include identification of common property resources available for conversion into productive land. Action plan for abatement and compensation for damage to agricultural land/ common property land (if any) due to proposed project shall be prepared.

xi)          Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xii)        CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poor section of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poor section of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xiii)       While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xiv)       Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xv)              One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include SPM, RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xvi)            Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xvii)      Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xviii)    Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xix)       Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xx)         Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxi)       Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxii)     Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxiii)    Details of water balance taking into account reuse and re-circulation of effluents.

xxiv)    Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxv)      Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxvi)    EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxvii)   A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxviii) Detailed plan for raising Green belt of 100 m width and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted. If the same is not feasible detailed justification shall be submitted.

xxix)    Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e019. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

                                         

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

2.24  Expansion of 1500 MW Indira Gandhi Super TPP by addition of  2X660 MW Stage – II Coal based TPP of M/s Aravali Power Company Pvt. Ltd. (A JV company of NTPC Ltd., HPGCL & IPGCL) near villages Jharli, Goria, Mohan Bari and Khanpur Khurd, in Jhajjar Distt., in Haryana -    reg. TOR .

 

The proposal was placed for consideration for environmental clearance. A presentation was also made by the project proponent gave a presentation and provided the following information:

 

The proposal is for setting up for expansion of Indira Gandhi  Super TPP from 1500 MW to 2850 MW near villages Jharli , Goria, Mohan Bari and Khanpur Khurd, in Jhajjar Distt., in Haryana. The co-ordinates of the proposed site will be at Latitude 28029’04” N and Longitude 76022’35” E. Coal Requirement will be 7.5 MTPA. Coal will be obtained from domestic coal block Mahanadi coal field. Water requirement will be 40 cusecs, which will be obtained from Jawahar Lal Nehru Feeder Canal through a pipeline over a distance of 15 km from the site. There are no National park, wild life sanctuary, Biosphere/ tiger/Elephant reserves, Heritage sites etc within 10km of the project boundary.

 

Based on the information provided and presentation made the Committee prescribed the following specific TORs for undertaking detailed EIA study and preparation of EMP.

 

i)             Vision document specifying prospective long term plan of the site shall be formulated and submitted.

ii)           Executive summary of the project indicating relevant details along with photograph of site shall be provided and issues raised in public hearing along with action plan to address the same shall be provided in tabular form including requisite allocation of funds.

iii)          Conformity of the site with the prescribed guidelines in terms of distance of 500 m from HFL of the river, highways, railway line shall be shown on the study area map. 

iv)          The project proponent shall provide confirmed GPS readings of plant boundary.

v)            No water body/nallah (if any) shall be touched. It shall also be ensured that atleast 100 m distance is kept away from the HFL of the nallah/ river (if any) passing in and around the proposed site.

vi)          Detailed hydro-geological study of the area shall be conducted from an institute/ organisation of repute to assess impact of on ground and surface water regime. Specific mitigation measures shall be spelt out and action plan for implementation of the same shall be provided.

vii)         Detailed source sustainability study of water requirement shall be carried out by an institute of repute. The study shall also specify the source of water for meeting the requirement during lean season and proposed plan of action.

viii)       Study on the impact on river/reservoir/marine ecology (as applicable) due to the proposed discharge of treated wastewater into the river/creek shall be carried out and submitted alongwith the EIA Report.

ix)          Transportation of coal shall be through rail to the nearest possible destination near power plant and detail initiated taken in the matter shall be submitted.

x)            Ash pond shall be shifted away as far as possible from any surface water source and its location shall be chosen taking into consideration the elevation and water drainage pattern in the area. The coordinates of the proposed site including location of ash pond shall be submitted along with topo sheet. 

xi)          Action plan for identification of local employable youth for training in skills relevant to the project for eventual employment in the project itself shall be formulated and details submitted along with EIA/EMP Report.

xii)        Layout of the plant indicating break-up of plant, green belt, infrastructure, roads etc. shall be provided.

xiii)       Land requirement for the project shall be optimized. Item wise break up of land requirement and its availability to be furnished. It should also include land to be acquired, if any, for coal transportation system as well as for laying of pipeline including ROW.  It may clearly be confirmed that the land including ROW is free of all encumbrances. The issues relating to land acquisition and R&R should be clearly discussed in the EIA report. 

xiv)       Land use based on satellite imagery or authenticated map indicating drainage, cropping pattern, water bodies (rivers, nallahs, ponds etc.), location of nearest villages, creeks, rivers, reservoirs, national parks, wildlife sanctuaries, tiger reserves, biosphere reserves, heritage sites etc in the study area shall be provided. Location of any National Park, Sanctuary, Elephant/Tiger Reserve (existing as well as proposed), migratory routes, if any, within 10 km of the project site shall be specified and marked on the map duly authenticated by the Chief Wildlife Warden. 

xv)         Study on land-use pattern in the study area shall be carried out, including identification of common property resources available for conversion into productive land and action plan for abatement and compensation for damage to agricultural land/ common property land (if any) in the nearby villages, due to proposed project shall be prepared.

xvi)       Detailed socio-economic study shall be carried out for the study area comprising of 10 km from the plant site.

xvii)      CSR component shall be prepared based on need based assessment study to be carried out in the study area.  Income generating measures which can help in upliftment of poorer sections of society which is consistent with the traditional skills of the people shall be identified. The programme can include activities such as development of fodder farm, fruit bearing orchards, vocational training etc.  In addition, vocational training for individuals shall be imparted so that poorer sections of society can take up self employment and jobs. Separate budget for community development activities and income generating programmes shall be specified. Financial allocation to be taken up under CSR shall be specified.

xviii)    While formulating CSR schemes it shall be ensured that an in-built monitoring mechanism for the schemes identified is in place and mechanism for conducting annual social audit from the nearest government institute of repute in the region shall be prepared. The project proponent shall also provide plan for the status of implementation of the scheme from time to time.

xix)       Possibility for adopting nearest three villages shall be explored and details of civic amenities such as roads, drinking water, power etc proposed to be provided at the company’s expenses shall be submitted.

xx)         Location of intake and outfall points (with coordinates) should be given. These locations should be selected based on detailed modeling studies.  Details of modeling and the results obtained there from should be furnished.  It may be kept in view that the intake and outfall points are away from the mangroves or other eco sensitive areas. A river/marine ecology study (as applicable) should also be done to assess impact on river/marine ecology. River/Marine impact of such activities should be clearly brought out in the EIA report.

xxi)       Topography of the area should be given clearly indicating whether the site requires any filling.  If so, details of filling, quantity of fill material required, its source, transportation etc. should be given. 

xxii)          One complete season AAQ data (except monsoon) to be given along with the dates of monitoring. The parameters to be covered shall include RSPM(PM10,PM2.5), SO2, NOx, Hg and Ozone (ground level). The location of the monitoring stations should be so decided so as to take into consideration the pre-dominant downwind direction, population zone and sensitive receptors including reserved forests. There should be at least one monitoring station each in the upwind and in the pre dominant downwind direction at a location where maximum ground level concentration is likely to occur.

xxiii)        Cumulative impact assessment on ambient air quality due to proposed plant and others (including existing as well as other proposed source of emission) shall be carried out and result submitted in the EIA Report. Mitigative measures as necessary shall be clearly spelt out.

xxiv)    Impact of the project on the AAQ of the area. Details of the model used and the input data used for modelling should also be provided. The air quality contours may be plotted on a location map showing the location of project site, habitation nearby, sensitive receptors, if any. The wind roses should also be shown on this map.

xxv)      Fuel analysis shall be provided. Details of auxillary fuel, if any including its quantity, quality, storage etc should also be given.

xxvi)    Quantity of fuel required, its source and transportation route and mode and a confirmed fuel linkage documents shall be provided.

xxvii)   Source of water and its availability. Commitment regarding availability of requisite quantity of water from the competent authority shall be provided along with firm linkage.

xxviii) Detailed plan for carrying out rainwater harvesting and proposed utilisation in the plant shall be provided.

xxix)    Feasibility of zero discharge shall be examined and detailed justification shall be submitted if in case the same is not possible. Proposed discharge (if any), its quantity, quality and point of discharge, users downstream etc. shall be provided.

xxx)      Optimization of COC for water conservation. Other water conservation measures proposed in the project should also be given. Quantity of water requirement for the project should be optimized. 

xxxi)    Details of water balance taking into account reuse and re-circulation of effluents.

xxxii)  Detailed plan for conducting monitoring of water quality regularly and mechanism for maintenance of records shall be formulated. Details of methodology and identification of monitoring points (between the plant and drainage in the direction of flow of surface / ground water) shall be submitted. It shall be ensured that parameter to be monitored also include heavy metals in surface and ground water.

xxxiii) Details regarding infrastructure facilities such as sanitation, fuel, restroom, medical facilities, safety during construction phase etc. to be provided to the labour force during construction as well as to the casual workers including truck drivers during operation phase.

xxxiv) EMP to mitigate the adverse impacts due to the project along with item wise cost of its implementation.

xxxv)   A Disaster Management Plan along with risk assessment study including fire and explosion issues due to storage and use of fuel should be carried out.  It should take into account the maximum inventory of storage at site at any point in time. The risk contours should be plotted on the plant layout map clearly showing which of the proposed activities would be affected in case of an accident taking place. Based on the same, proposed safeguard measures should be provided.  Measures to guard against fire hazards should also be provided.

xxxvi) Detailed plan for raising Green belt of 100 m width on the western side of the plant and 50m wide on the other sides and consisting of at least 3 tiers around plant boundary with tree density not less than 2500 trees per ha and survival rate atleast 75% shall be submitted.

xxxvii)                Details of litigation pending or otherwise with respect to project in any courts, tribunal etc. shall be provided.

 

Besides all the above, the following general points will be followed:-

 

a)    All documents to be properly referenced with index, page numbers and continuous page numbering.

b)   Where data is presented in the report especially in table, the period in which the data was collected and the source should invariably be indicated. 

c)    Where the documents provided are in a language other than English, an English translation should be provided.

d)   The Questionnaire for environmental appraisal of thermal power projects as devised earlier by the Ministry shall also be filled and submitted.

 

In addition, information on the following may also be incorporated in the EIA report.

 

1).      Is the project intended to have CDM-intent?

 

i)     If not, then reasons thereof?

ii)   If yes, then details under mentioned to be provided:

 

a)    Has PIN (Project Idea Note) {or PCN (Project Concept Note)} been submitted to the NCA? (National CDM Authority) in the MoEF?

b)   If not, then by when is that expected?

c)    Has PDD (Project Design Document) been prepared?

d)   What is the Carbon intensity from your electricity generation projected (i.e. CO2  Tons/MWH or Kg/KWH)

e)    Amount of CO2 in Tons/year expected to be reduced from the baseline data available on the CEA’s web-site (www.cea.nic.in)

 

2.       Notwithstanding 1(i) above, data on (d) & (e) above to be worked out and reported.

 

The Committee informed the project proponent that after preparing the draft EIA (as per the generic structure prescribed in Appendix-III of the EIA Notification, 2006) covering the above mentioned issues, the same shall be submitted to the SPCB for conducting the public hearing as per procedure of EIA notification 2006. The issues which emerge during public hearing shall be further incorporated in the Draft EIA/EMP report. The final EIA/EMP report along with public hearing report and the requisite documents (including written objections, if any) shall be submitted to the Ministry for appraisal by the Expert Appraisal Committee for consideration of awarding environmental clearance under the provisions of Environmental Impact Assessment notification dated September 14, 2006.

 

 

3.0    ANY OTHER ITEM WITH THE PERMISSION OF THE CHAIR

 

3.1    2X250 MW Thermal Power Plant of M/s Bina Power Supply Company Ltd. at Bina, in Madhya Pradesh  - reg. Stack Height.

 

M/s Jaiprakash Power Venture Ltd. (A Jaypee Group company) have informed that they have acquired 100 % share holding of M/s Bina Power Supply Company Ltd. (An Aditya Birla Group company) in May, 2008. That M/s Bina Power Supply Company Ltd. was accorded environmental clearance for the 2x250 MW Coal Based TPPP, at Bina, in Madhya Pradesh on 23.04.21996. 

 

That on perusal of the stipulations in the environmental clearance, it was observed that no stipulation for stack height was mentioned.  M/s Bina Power Supply Company Ltd now request that they may be allowed to construct 200 m Stack Height.

 

The matter was taken up for discussion. The Committee however decided that Dr. S.D. Atri, Member and Sh. Seshadri, Member may in consultation with CPCB and MoEF examine the matter and submit a report. Accordingly the matter was deferred.

 

3.2    2x35 MW Captive Imported Coal Based Thermal Power Plant of M/s Tulsyan NEC Ltd. at village Sinthoornatham, in Gummidipoondi Taluk, in Thiruvallur Distt., in Tamil Nadu -reg. Environmental Clearance.

 

The above proposal was considered in the 8th meeting held during 18th - 19th October, 2010 for environmental clearance.

 

During the meeting, the Committee noted that certain requisite details pertaining to wind rose diagram based on which the ambient air quality impact assessment /prediction has been calculated and other were erroneous.

 

Subsequently, the proponent submitted the revised information as desired by the Committee which was placed before it for consideration. The Committee found that the information provided is acceptable and recommended the project for environmental clearance subject to stipulation of standard safeguards.

 

There being no agenda item left the meeting ended with thanks to the Chair. It was also decided that the next meeting of the Committee will be held on 6th - 7th December, 2010.

 

-------------

 

Untitled Page